CN110994510A - Electric power erection device for bridge road - Google Patents
Electric power erection device for bridge road Download PDFInfo
- Publication number
- CN110994510A CN110994510A CN201911321652.4A CN201911321652A CN110994510A CN 110994510 A CN110994510 A CN 110994510A CN 201911321652 A CN201911321652 A CN 201911321652A CN 110994510 A CN110994510 A CN 110994510A
- Authority
- CN
- China
- Prior art keywords
- electric power
- installation
- bridge
- mounting
- power erection
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F21—LIGHTING
- F21V—FUNCTIONAL FEATURES OR DETAILS OF LIGHTING DEVICES OR SYSTEMS THEREOF; STRUCTURAL COMBINATIONS OF LIGHTING DEVICES WITH OTHER ARTICLES, NOT OTHERWISE PROVIDED FOR
- F21V21/00—Supporting, suspending, or attaching arrangements for lighting devices; Hand grips
- F21V21/10—Pendants, arms, or standards; Fixing lighting devices to pendants, arms, or standards
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F21—LIGHTING
- F21V—FUNCTIONAL FEATURES OR DETAILS OF LIGHTING DEVICES OR SYSTEMS THEREOF; STRUCTURAL COMBINATIONS OF LIGHTING DEVICES WITH OTHER ARTICLES, NOT OTHERWISE PROVIDED FOR
- F21V33/00—Structural combinations of lighting devices with other articles, not otherwise provided for
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
- H02G7/05—Suspension arrangements or devices for electric cables or lines
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
- H02G7/05—Suspension arrangements or devices for electric cables or lines
- H02G7/053—Suspension clamps and clips for electric overhead lines not suspended to a supporting wire
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
- H02G7/20—Spatial arrangements or dispositions of lines or cables on poles, posts or towers
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J7/00—Circuit arrangements for charging or depolarising batteries or for supplying loads from batteries
- H02J7/34—Parallel operation in networks using both storage and other dc sources, e.g. providing buffering
- H02J7/35—Parallel operation in networks using both storage and other dc sources, e.g. providing buffering with light sensitive cells
Abstract
The invention discloses a power erection device for a bridge road, relates to the field of bridge power erection, and mainly solves the problem that the potential safety hazard of the conventional bridge power erection device is large; the device comprises a base, wherein the base is fixedly connected with a concrete pavement through a fixing bolt, a hollow mounting column is fixedly connected onto the base, a stand column is sleeved in the mounting column, an adjusting sleeve is mounted on the stand column, a mounting cross rod is fixedly connected to the top end of the stand column, a cavity is formed in the mounting cross rod, the stand column is provided with a cavity of the same type as the mounting cross rod, a connecting rod is mounted in the mounting cross rod and penetrates through the mounting column and the cavity in the stand column, a sliding groove is formed in the right side of the mounting cross rod, a connecting device is uniformly arranged in the sliding groove, and a sealing ring is arranged on the right side of the sliding groove.
Description
Technical Field
The invention relates to the field of electric power erection equipment, in particular to an electric power erection device for a bridge road.
Background
When the bridge road is constructed, electric wires need to be erected in the air, and the purpose of safely transmitting electric power is achieved.
The existing bridge electric power erection device is simple and crude, various problems are easily generated in the bridge construction process although the cable outer layer contains an insulating skin, the cable outer layer is damaged, the potential safety hazard is high, and great threats are generated to the safety of bridge construction workers.
Disclosure of Invention
An embodiment of the present invention provides an electric power erection device for a bridge road to solve the problems in the background art.
In order to achieve the above purpose, the embodiments of the present invention provide the following technical solutions:
a power erection device for bridge roads comprises a base, wherein the base is fixedly connected with a concrete pavement through a fixing bolt, a hollow mounting post is fixedly connected to the base, a stand column is sleeved in the mounting post, an adjusting sleeve is installed on the stand column, a mounting cross rod is fixedly connected to the top end of the stand column, a cavity is formed in the mounting cross rod, the stand column is provided with a cavity of the same type as the mounting cross rod, a connecting rod is installed in the mounting cross rod and penetrates through the cavity in the mounting post and the stand column, a sliding groove is formed in the right side of the mounting cross rod, connecting devices are uniformly arranged in the sliding groove and comprise a sliding block, the sliding block is connected with a mounting block through a threaded rod, a locking bolt is installed on the threaded rod, clamping blocks are symmetrically installed on the mounting block and are rotationally connected with the mounting block through a rotating shaft and a connecting ring, the bottoms of the two symmetrically-arranged clamping blocks are fixedly connected through connecting bolts, and a cable is arranged in the middle of each clamping block.
As a further scheme of the embodiment of the invention: the upright post is provided with an adjusting sleeve, the adjusting sleeve is provided with a supporting rod, and the supporting rod is rotatably connected with a connecting flange on the left side of the mounting cross rod.
As a further scheme of the embodiment of the invention: the utility model discloses a solar energy storage lamp, including stand, stand top is provided with lighting device, lighting device include with stand fixed connection's lamp pole, the light is installed on the top of lamp pole, be provided with solar panel on the installation horizontal pole, solar panel's bottom is provided with the battery, battery and light electric connection.
As a further scheme of the embodiment of the invention: the connecting device is provided with three groups.
As a further scheme of the embodiment of the invention: ribbed plates are arranged between the base and the mounting columns, and the number of the ribbed plates is four.
As a further scheme of the embodiment of the invention: and a locking washer is arranged between the locking bolt and the mounting block.
As a further scheme of the embodiment of the invention: and a sealing ring is arranged on the right side of the sliding groove.
As a further scheme of the embodiment of the invention: and a rubber gasket is arranged between the clamping block and the cable.
Compared with the prior art, the embodiment of the invention has the beneficial effects that: the bridge electric power erection device realizes electric power erection on a bridge road through the mounting columns, the vertical columns, the mounting cross rods and the connecting device, realizes reliable fixation of the mounting cross rods through the connecting rods, the supporting rods and the adjusting sleeves, adjusts the fixed position of the cable through the sliding blocks and the locking bolts, realizes erection and installation of the cable through the connecting bolts and effectively ensures the safety of electric power erection of the bridge.
Drawings
Fig. 1 is a schematic structural view of an electric power erection device for a bridge road.
Fig. 2 is a schematic structural view of a connecting device in the electric power erection device for a bridge road.
Fig. 3 is a schematic structural view of a clamping block in the electric power erection device for bridge roads.
Fig. 4 is a schematic structural view of a base in the electric power erection device for a bridge road.
Fig. 5 is a schematic structural view of an electric power erection device for bridge roads, which comprises an electric power box.
In the figure: 1-base, 2-fixing bolt, 3-ribbed plate, 4-mounting column, 5-upright column, 50-cable hole, 6-adjusting sleeve, 7-supporting rod, 8-connecting flange, 9-mounting cross rod, 10-connecting rod, 11-solar panel, 12-storage battery, 13-lamp column, 14-lighting lamp, 15-sliding chute, 16-sliding block, 161-threaded rod, 162-mounting block, 17-locking bolt, 18-locking washer, 19-connecting ring, 190-rotating shaft, 20-clamping block, 21-rubber washer, 22-connecting bolt, 23-cable, 24-sealing ring and 25-power box.
Detailed Description
In the description of the present invention, it is to be understood that the terms "upper", "lower", "top", "bottom", "inner", "outer", and the like, indicate orientations or positional relationships based on those shown in the drawings, and are used only for convenience in describing the present invention and for simplicity in description, and do not indicate or imply that the referenced devices or elements must have a particular orientation, be constructed and operated in a particular orientation, and thus, are not to be construed as limiting the present invention.
In the present invention, unless otherwise expressly stated or limited, the terms "mounted," "connected," "secured," and the like are to be construed broadly and can, for example, be fixedly connected, detachably connected, or integrally formed; can be mechanically or electrically connected; either directly or indirectly through intervening media, either internally or in any other relationship. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
The technical solution of the present patent will be described in further detail with reference to the following embodiments.
Example 1:
as shown in fig. 1-4, an electric power erection device for bridge roads comprises a base 1, wherein the base 1 is fixedly connected with a concrete pavement through a fixing bolt 2, a hollow installation column 4 is fixedly connected to the base 1, an upright column 5 is sleeved in the installation column 4, an adjusting sleeve 6 is installed on the upright column 5, an installation cross rod 9 is fixedly connected to the top end of the upright column 5, a cavity is formed in the installation cross rod 9, the upright column 5 is provided with a cavity of the same type as the installation cross rod 9, a connecting rod 10 is installed in the installation cross rod 9, the connecting rod 10 penetrates through the installation column 4 and the cavity inside the upright column 5, a chute 15 is formed in the right side of the installation cross rod 9, connecting devices are uniformly arranged in the chute 15, each connecting device comprises a sliding block 16, and each sliding block 16 is connected with an installation block 162 through a threaded rod 161, the threaded rod 161 is provided with a locking bolt 17, the mounting block 162 is symmetrically provided with clamping blocks 20, the clamping blocks 20 are rotatably connected with the mounting block 162 through a rotating shaft 190 and a connecting ring 19, the bottoms of the symmetrically mounted clamping blocks 20 are fixedly connected through connecting bolts 22, and a cable 23 is mounted in the middle of the clamping blocks 20.
Specifically, at the concrete of bridge subaerial pre-buried construction bolt, speech base 1 is fixed subaerial through this bolt, is connected with erection column 4 on the base 1, and this erection column 4 is the cavity setting, and base 1 can be the welding with the fixed connection of erection column 4, also can be base 1 and erection column 4 integrated into one piece.
More specifically, the connection mode of the upright post 5 and the installation cross bar 9 is that a cavity is arranged on the upright post 5, and similarly, the installation cross bar 9 is provided with the same type of cavity, the installation cross bar 9 is lifted until the installation cross bar 9 is matched with the cavity on the upright post 5, and a connecting rod 10 is inserted into the cavity to fix the position of the installation cross bar 9 on the upright post 5.
More specifically, the right side of the mounting rail 9 is provided with a sliding groove 15, the cable 23 is mounted through the sliding groove 15, the connecting device is slidably mounted in the sliding groove 15, and the cable 23 is erected by combining the sliding block 16, the lock nut, the mounting block 162, the clamping block 20 and the connecting bolt 22.
Further, the connecting device is provided with three groups.
Furthermore, ribbed plates 3 are arranged between the base 1 and the mounting column 4, and the number of the ribbed plates 3 is four.
Specifically, the arrangement of the rib plate 3 can ensure the installation reliability of the base 1.
Further, a lock washer 18 is disposed between the lock bolt 17 and the mounting block 162.
Further, a sealing ring 24 is arranged on the right side of the sliding groove 15.
Specifically, place rainwater through sealing washer 24 and get into in the spout 15 of installation horizontal pole 9, cause rusty in the spout 15, influence the dismantlement in later stage.
Further, a rubber gasket 21 is arranged between the clamping block 20 and the cable 23.
In particular, the rubber gasket 21 may protect the skin of the cable 23.
As shown in fig. 5, in a state where the power erection device for bridge roads is at the power erection end, the cable 23 is inserted into the column 5 through the cable 23 hole 50 by providing the column 5 with the cable 23 hole 50, and the power box 25 is provided at the middle lower portion of the column 5, thereby preventing the cable 23 from being manually touched, protecting the cable 23, and preventing the cable 23 from being damaged.
Example 2:
this embodiment is a further improvement and a limitation of embodiment 1 on the basis of embodiment 1.
An electric power erection device for bridge roads, comprising all the components of embodiment 1, further comprising:
furthermore, the upright post 5 is provided with an adjusting sleeve 6, the adjusting sleeve 6 is provided with a supporting rod 7, and the supporting rod 7 is rotatably connected with a connecting flange 8 on the left side of the mounting cross rod 9.
Specifically, the installation cross rod 9 is fixed on the upright post 5 through the connecting rod 10, and for protecting the reliable installation of the installation cross rod 9, the left side of the installation cross rod 9 is fixedly provided with the connecting flange 8, the upright post 5 is slidably provided with the adjusting sleeve 6, the installation supporting rod 7 is rotated between the connecting flange 8 and the adjusting sleeve 6, and the supporting effect is further enhanced.
Further, 5 tops of stand columns are provided with lighting device, lighting device include with 5 fixed connection's of stand columns lamp pole 13, light 14 is installed on the top of lamp pole 13, be provided with solar panel 11 on the installation horizontal pole 9, solar panel 11's bottom is provided with battery 12, battery 12 and light 14 electric connection.
Specifically, the solar panel 11 and the storage battery 12 are arranged on the mounting cross bar 9, and the solar panel 11 is used for realizing lighting and power supply at night.
The working principle of the embodiment of the invention is as follows:
as shown in fig. 1 to 5, the base 1 is fixedly mounted on a hard floor such as concrete by means of the mounting posts 4.
With stand 5 hoist and mount in erection column 4, adjust the position of installation horizontal pole 9 on stand 5 for cavity on the installation horizontal pole 9 is identical with the cavity on stand 5, inserts installation horizontal pole 9 with connecting rod 10 through the left side of installation horizontal pole 9 afterwards inside, and preliminary fixed mounting horizontal pole 9 is in the position on stand 5, installs connecting device in the spout 15 of installation horizontal pole 9 afterwards, through lock nut fixed connection device.
Subsequently, an adjusting sleeve 6 is mounted on the upright 5, and a support rod 7 is connected between the adjusting sleeve 6 and a connecting flange 8, further fixing a mounting cross rod 9.
A cable 23 is installed between the clamp blocks 20 of the connecting device, and the cable 23 is fixed by a connecting bolt 22.
The bridge road electric power erection device is completely erected.
It should be noted that: the bridge electric power erection device has the advantages that electric power erection of a bridge road is realized through the mounting columns, the vertical columns, the mounting cross rods and the connecting devices, the mounting cross rods are reliably fixed through the connecting rods, the supporting rods and the adjusting sleeves, the fixing positions of cables are adjusted through the sliding blocks and the locking bolts, the cables are erected and installed through the connecting bolts through the clamping blocks, and safety of bridge electric power erection is effectively guaranteed.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.
Claims (8)
1. The utility model provides a bridge road power erection device, includes base (1), base (1) is through fixing bolt (2) and concrete road surface fixed connection, its characterized in that, fixedly connected with hollow erection column (4) on base (1), stand (5) have cup jointed in erection column (4), install adjusting sleeve (6) on stand (5), the top fixedly connected with installation horizontal pole (9) of stand (5), be provided with the cavity on installation horizontal pole (9), be provided with the cavity with installation horizontal pole (9) the same model on stand (5), install connecting rod (10) in installation horizontal pole (9), connecting rod (10) run through the cavity of connecting erection column (4) and stand (5) inside, the right side of installation horizontal pole (9) is provided with spout (15), evenly be provided with connecting device in spout (15), connecting device includes slider (16), slider (16) link to each other with installation piece (162) through threaded rod (161), install locking bolt (17) on threaded rod (161), clamp splice (20) are installed to the symmetry on installation piece (162), clamp splice (20) are rotated with installation piece (162) through pivot (190) and go-between (19) and are connected two clamp splice (20) bottom of symmetry installation is through connecting bolt (22) fixed connection, install cable (23) in the middle of clamp splice (20).
2. The electric power erection device for bridge and road of claim 1, wherein an adjusting sleeve (6) is arranged on the upright post (5), a support rod (7) is arranged on the adjusting sleeve (6), and the support rod (7) is rotatably connected with a connecting flange (8) at the left side of the mounting cross rod (9).
3. The electric power erection device for bridge and road of claim 2, wherein a lighting device is arranged at the top end of the upright post (5), the lighting device comprises a lamp post (13) fixedly connected with the upright post (5), a lighting lamp (14) is installed at the top end of the lamp post (13), a solar panel (11) is arranged on the installation cross rod (9), a storage battery (12) is arranged at the bottom end of the solar panel (11), and the storage battery (12) is electrically connected with the lighting lamp (14).
4. The electric power erection device for bridge road of claim 1, wherein said connection means is provided in three groups.
5. The electric power erection device for bridge road of claim 1, wherein a number of ribbed plates (3) is four, and ribbed plates (3) are arranged between the base (1) and the mounting post (4).
6. The electric power erection device for bridge road of claim 1, wherein a lock washer (18) is disposed between the lock bolt (17) and the mounting block (162).
7. The electric power erection device for bridge road of claim 1, wherein a sealing ring (24) is disposed at the right side of the chute (15).
8. The electric power erection device for bridge road of claim 1, wherein a rubber gasket (21) is arranged between the clamping block (20) and the cable (23).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911321652.4A CN110994510A (en) | 2019-12-20 | 2019-12-20 | Electric power erection device for bridge road |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911321652.4A CN110994510A (en) | 2019-12-20 | 2019-12-20 | Electric power erection device for bridge road |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110994510A true CN110994510A (en) | 2020-04-10 |
Family
ID=70065703
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911321652.4A Pending CN110994510A (en) | 2019-12-20 | 2019-12-20 | Electric power erection device for bridge road |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110994510A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111769501A (en) * | 2020-06-30 | 2020-10-13 | 菏泽成科企业管理有限公司 | Strain-resistant transmission tower |
CN114482682A (en) * | 2022-03-18 | 2022-05-13 | 河南省泰贸照明科技工程有限公司 | Street lamp adjusting and mounting equipment |
CN117039773A (en) * | 2023-10-08 | 2023-11-10 | 国网山东省电力公司阳信县供电公司 | Displacement adjusting bracket for cable construction |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2116422C1 (en) * | 1996-04-18 | 1998-07-27 | Григорий Иванович Чубыкин | Installation for mounting and dismounting of hoist support and design of hoist |
CN206908248U (en) * | 2017-07-06 | 2018-01-19 | 浙江侨泰电力设备有限公司 | High-tension cable fixing clamper |
CN207705693U (en) * | 2018-01-25 | 2018-08-07 | 泰州敬道电力工程有限公司 | Electric system cable fixture |
CN208112164U (en) * | 2018-04-26 | 2018-11-16 | 吴国军 | A kind of video line support of pipelines |
CN108933420A (en) * | 2017-05-26 | 2018-12-04 | 蒙小东 | A kind of power Transmission bracket of mini zone scarer |
CN208548681U (en) * | 2018-07-27 | 2019-02-26 | 温州承玥机械设备有限公司 | A kind of power cord suspended and fixed device |
CN208674827U (en) * | 2018-07-04 | 2019-03-29 | 荔浦县东方水泥制品有限公司 | A kind of component of the fixed cable of electric force pole tower |
CN209232139U (en) * | 2018-09-10 | 2019-08-09 | 武汉鑫弘凯交通科技有限公司 | A kind of intelligent bayonet system |
CN209339734U (en) * | 2018-12-31 | 2019-09-03 | 季亚婷 | A kind of environmental protection greenbelt fence |
-
2019
- 2019-12-20 CN CN201911321652.4A patent/CN110994510A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2116422C1 (en) * | 1996-04-18 | 1998-07-27 | Григорий Иванович Чубыкин | Installation for mounting and dismounting of hoist support and design of hoist |
CN108933420A (en) * | 2017-05-26 | 2018-12-04 | 蒙小东 | A kind of power Transmission bracket of mini zone scarer |
CN206908248U (en) * | 2017-07-06 | 2018-01-19 | 浙江侨泰电力设备有限公司 | High-tension cable fixing clamper |
CN207705693U (en) * | 2018-01-25 | 2018-08-07 | 泰州敬道电力工程有限公司 | Electric system cable fixture |
CN208112164U (en) * | 2018-04-26 | 2018-11-16 | 吴国军 | A kind of video line support of pipelines |
CN208674827U (en) * | 2018-07-04 | 2019-03-29 | 荔浦县东方水泥制品有限公司 | A kind of component of the fixed cable of electric force pole tower |
CN208548681U (en) * | 2018-07-27 | 2019-02-26 | 温州承玥机械设备有限公司 | A kind of power cord suspended and fixed device |
CN209232139U (en) * | 2018-09-10 | 2019-08-09 | 武汉鑫弘凯交通科技有限公司 | A kind of intelligent bayonet system |
CN209339734U (en) * | 2018-12-31 | 2019-09-03 | 季亚婷 | A kind of environmental protection greenbelt fence |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111769501A (en) * | 2020-06-30 | 2020-10-13 | 菏泽成科企业管理有限公司 | Strain-resistant transmission tower |
CN114482682A (en) * | 2022-03-18 | 2022-05-13 | 河南省泰贸照明科技工程有限公司 | Street lamp adjusting and mounting equipment |
CN114482682B (en) * | 2022-03-18 | 2023-11-10 | 河南省泰贸照明科技工程有限公司 | Street lamp adjusting and installing equipment |
CN117039773A (en) * | 2023-10-08 | 2023-11-10 | 国网山东省电力公司阳信县供电公司 | Displacement adjusting bracket for cable construction |
CN117039773B (en) * | 2023-10-08 | 2024-02-02 | 国网山东省电力公司阳信县供电公司 | Displacement adjusting bracket for cable construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110994510A (en) | Electric power erection device for bridge road | |
US4295308A (en) | Pole base assembly, bolt circle adaptor | |
CN207339082U (en) | A kind of vehicle moving crossing frame | |
CN205428231U (en) | Interim traffic pilot lamp of municipal administration | |
CN204517238U (en) | A kind of insulated isolated device | |
KR102144466B1 (en) | Posts for explosion proof lamp | |
CN210315220U (en) | Municipal administration bridge is with adjustable rail guard | |
CN216109881U (en) | High-voltage line protection device | |
CN210088655U (en) | Intelligence view garden street lamp | |
CN214890069U (en) | Fixing device for traffic monitoring camera | |
CN207062738U (en) | A kind of bridge of fast demountable | |
CN112324989B (en) | Pipeline laying device for municipal construction | |
CN212803478U (en) | Frock of driftage calliper | |
CN212719530U (en) | Solar street lamp convenient to remove equipment | |
CN213013934U (en) | Modular strutting arrangement that bridge construction of quick concatenation was used | |
CN210223059U (en) | Temporary traffic light supporting device | |
CN210639879U (en) | Electric power engineering is with preventing empting warning sign | |
KR100843058B1 (en) | High Voltage Cable Supporter | |
WO2021237631A1 (en) | Isolation protection device for road bridge construction | |
CN206971933U (en) | A kind of municipal works temporary construction guardrail | |
CN217950251U (en) | Plug-and-play type single-post insulator climbing auxiliary device | |
CN108128740B (en) | Transformer yoke gantry area bulk migration device and method | |
CN207602806U (en) | A kind of adjustable auxiliary earthing apparatus of substation | |
KR20110013832A (en) | A post for a rode-lamp exchange equipments | |
CN204782190U (en) | On --spot interim power consumption assembled of construction supports switching device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200410 |