CN110928273A - Automatic testing method for automatic power generation control function test of photovoltaic power station - Google Patents

Automatic testing method for automatic power generation control function test of photovoltaic power station Download PDF

Info

Publication number
CN110928273A
CN110928273A CN201911246310.0A CN201911246310A CN110928273A CN 110928273 A CN110928273 A CN 110928273A CN 201911246310 A CN201911246310 A CN 201911246310A CN 110928273 A CN110928273 A CN 110928273A
Authority
CN
China
Prior art keywords
test
photovoltaic power
power station
automatic
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911246310.0A
Other languages
Chinese (zh)
Other versions
CN110928273B (en
Inventor
周策
尹旭佳
白志刚
郝丽花
闫俊
付文华
张屹峰
杜鸿飞
张志刚
温武
贾峰生
刘建辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Research Institute of State Grid Shanxi Electric Power Co Ltd
Original Assignee
Electric Power Research Institute of State Grid Shanxi Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of State Grid Shanxi Electric Power Co Ltd filed Critical Electric Power Research Institute of State Grid Shanxi Electric Power Co Ltd
Priority to CN201911246310.0A priority Critical patent/CN110928273B/en
Publication of CN110928273A publication Critical patent/CN110928273A/en
Application granted granted Critical
Publication of CN110928273B publication Critical patent/CN110928273B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B23/00Testing or monitoring of control systems or parts thereof
    • G05B23/02Electric testing or monitoring
    • G05B23/0205Electric testing or monitoring by means of a monitoring system capable of detecting and responding to faults
    • G05B23/0208Electric testing or monitoring by means of a monitoring system capable of detecting and responding to faults characterized by the configuration of the monitoring system
    • G05B23/0213Modular or universal configuration of the monitoring system, e.g. monitoring system having modules that may be combined to build monitoring program; monitoring system that can be applied to legacy systems; adaptable monitoring system; using different communication protocols
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/20Pc systems
    • G05B2219/24Pc safety
    • G05B2219/24065Real time diagnostics
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy
    • Y02E10/56Power conversion systems, e.g. maximum power point trackers

Abstract

The invention discloses an automatic test method for an automatic power generation control function test of a photovoltaic power station, which realizes automatic instruction issuing, test data acquisition and performance index calculation during an AGC (automatic gain control) test of the photovoltaic power station, automatically judges whether a test condition is met or not according to a weather condition under the condition of no need of manual intervention, and completes a complete test process. Establishing an automatic test system, wherein the test system starts to acquire data such as actual power, predicted power and the like of the photovoltaic power station in real time, the test system calculates and judges whether a test starting condition is met or not in real time, if so, the test system starts to automatically test according to test steps, sequentially sends step change AGC commands to the photovoltaic power station according to a preset output curve, and acquires data such as actual power, target commands and the like required by the test; judging whether the test is interrupted or not, and calculating various test indexes according to the collected test data; the experimental data is displayed in the form of an image and provides a derivation function. The universality is strong, and the application range is wide.

Description

Automatic testing method for automatic power generation control function test of photovoltaic power station
Technical Field
The invention relates to a testing device for an automatic power generation control function test of a photovoltaic power station, in particular to an automatic testing device and a testing method for the automatic power generation control function test of the photovoltaic power station.
Background
In recent years, photovoltaic power stations are built on a large scale, the photovoltaic grid-connected capacity is increased rapidly, and the influence of randomness and volatility on the safe operation of a power grid is increased along with the continuous improvement of photovoltaic permeability; in order to ensure the stable operation of the power grid, the standards of GB/T19964-2012 'technical Specification for photovoltaic power station access to electric power system', DL/T1870-; when the photovoltaic power station is connected to the grid, an AGC test is carried out on the photovoltaic power station, and the AGC test is an important means for judging whether the automatic generation control function (AGC) control performance of the photovoltaic power station meets the standard requirements, the test process comprises the steps that a dispatching mechanism issues a power station load change instruction to the photovoltaic power station, the set value of the power station load instruction is changed, a photovoltaic inverter is controlled to track the change of the load instruction, and the active power control of the photovoltaic power station in the full load range is realized within the rated power and zero output range of the photovoltaic power station.
At present, most of testing devices used for carrying out photovoltaic power station AGC tests on site are data acquisition devices, and only have a basic test data collection function, and testers derive data from the data acquisition devices after completing the tests, although the test mode is widely adopted, the testing devices inevitably have the following problems in the practical application process: (1) the AGC test of the photovoltaic power station is limited in time, namely, the AGC test of the photovoltaic power station needs to be completed within a scheduling and approving construction period according to a plan, as the influence of weather factors on photovoltaic power generation is large, most of the existing test methods are manual field tests, and the situation that the test cannot be completed on schedule often occurs in practical application, so that the photovoltaic power station is subjected to power grid check and the benefit of the power station is influenced; (2) most of the existing testing devices can only collect test data, cannot automatically judge test conditions according to weather conditions, does not have the functions of automatically issuing instructions, calculating performance indexes and the like, still needs testers or a dispatching master station to manually set AGC instructions, and needs to wait on site all the time when the weather conditions are not met, so that the technical strength waste and high labor cost of the testers are caused, and the working efficiency is low; (3) in the existing testing device and method, whether the performed test is effective or not cannot be automatically judged after the test is interrupted due to weather reasons in the testing period, and whether the whole-process test is performed again or only the test in the incomplete test stage is performed after the weather is improved, so that a large amount of manual calculation is needed, and the test fails.
Disclosure of Invention
The invention provides an automatic test method for an automatic power generation control function test of a photovoltaic power station, which realizes automatic instruction issuing, test data acquisition and performance index calculation during an AGC (automatic gain control) test of the photovoltaic power station, automatically judges whether a test condition is met or not according to a weather condition under the condition of no need of manual intervention, and completes a complete test process.
The invention solves the technical problems by the following technical scheme:
an automatic test method for an automatic power generation control function test of a photovoltaic power station comprises the following steps:
firstly, establishing an automatic test system: the device comprises a data acquisition unit, a logic control unit, an instruction output unit, a calculation storage unit and a result display unit, wherein the data acquisition unit is used for acquiring data of the photovoltaic power station in real time, preprocessing the data and transmitting the preprocessed data to the logic control unit, and the logic control unit is used for calculating an active power target instruction of the AGC test process of the photovoltaic power station and transmitting an instruction signal to the instruction output unit; the instruction output unit is used for receiving the active power target instruction signal transmitted by the logic control unit and transmitting an active power target instruction in an AGC test process to the photovoltaic power station; the calculation storage unit is used for storing and calculating data of the AGC test of the photovoltaic power station to obtain various performance indexes of the AGC test; the result display unit is used for displaying data of the photovoltaic power station AGC test in an image form;
secondly, the test system starts to collect data such as actual power, predicted power and the like of the photovoltaic power station in real time;
thirdly, the test system calculates and judges whether the test starting condition is met or not in real time, if yes, automatic test is started according to the test steps, step change AGC commands are sequentially issued to the photovoltaic power station according to a preset output curve, and data such as actual power, target commands and the like required by the test are collected;
step four, judging whether the test is interrupted, if the interruption time exceeds the preset time, returning to the step two, and if the test is not interrupted or the interruption time is less than the preset time, performing the next step;
fifthly, continuing to perform unfinished tests;
sixthly, completing the test, and calculating various test indexes according to the collected test data;
and step seven, displaying the test data in the form of images and providing a derivation function.
The data acquisition unit also comprises a communication protocol conversion module and an analog input and output module, wherein the communication protocol conversion module can enable the automatic test device to be connected with a photovoltaic power station AGC system, a photovoltaic power prediction system and a booster station monitoring system through different interface types; the data acquired by the data acquisition unit comprise active power of grid-connected power points of the photovoltaic power station, active power target instructions, active power of a collection line, active power of a sample plate inverter and ultra-short-term power prediction data of 16 points in 4 hours in the future; the instruction output unit is provided with a communication interface and a communication protocol which are consistent with those of the dispatching system, and can communicate with the AGC system of the photovoltaic power station according to the grid-connected dispatching information exchange specification and send an active power target instruction; the logic control unit can automatically judge whether a test condition is met or not through calculation based on the data acquired by the data acquisition unit, if so, an active power target instruction is sent to the photovoltaic power station according to a preset instruction curve, the test condition refers to that the illumination condition of the photovoltaic power station meets the active power output range required by the test, the duration time is longer than the shortest time required by the test, and the judgment is specifically carried out according to the active power of a grid-connected point of the photovoltaic power station and the ultra-short-term predicted power; the AGC test performance indexes obtained by calculation of the calculation storage unit comprise response time, overshoot, regulation rate and regulation precision.
The response time refers to the time for reliably spanning a response dead zone consistent with the instruction direction on the basis of the current active power by the output of the photovoltaic power station after the automatic testing device sends an instruction; the overshoot refers to the deviation of the active power of the photovoltaic power station from the maximum value of an AGC instruction; the adjusting speed is the speed of the photovoltaic power station in the AGC instruction direction, wherein the output force exceeds the response dead zone to enter the adjusting dead zone; the adjusting precision refers to a difference value between actual output and set point output in a period from the photovoltaic power station entering an adjusting dead zone to the beginning of a next instruction.
If the test condition does not meet the test requirement of the subsequent stage in the process of carrying out automatic test, the automatic test device waits for the interruption of the test, stops issuing instructions to the photovoltaic power station, and calculates the subsequent test condition according to the completed test condition, wherein the subsequent test condition means that the current actual active power of the photovoltaic power station is not less than the maximum output value required by the test of the incomplete stage, and the time for predicting and maintaining the output is not less than the minimum time required for completing the test of the subsequent stage;
if the required test conditions are restored within a certain time (which can be manually configured), continuing the test from the previously interrupted test phase; if the interruption time exceeds the preset time and the test condition is not met, the test device judges the test starting condition again, and complete test is carried out again after the test starting condition is met.
The automatic testing method for the AGC test of the photovoltaic power station can realize automatic judgment of test conditions, automatic instruction issuing, test data acquisition and performance index calculation in the AGC test of the photovoltaic power station, has high automation degree, can improve the completion efficiency of the test, avoids the photovoltaic power station from being checked by more power grid departments, effectively reduces the labor intensity and workload of testing personnel, and reduces the labor cost; whether the weather condition meets the test condition can be automatically judged according to the data of the photovoltaic power station, the interference of external factors such as cloud layer shielding or rain shower on the test in the test process can be effectively avoided, manual intervention is not needed in the whole process, and a complete test is automatically completed; the data transmission with the photovoltaic power station can be realized through two modes of a communication protocol and an analog quantity signal, the photovoltaic power station can be used after a small amount of configuration is modified and connection is established with the photovoltaic power station, and the photovoltaic power station has strong universality and wide application range.
Drawings
FIG. 1 is a flow diagram of an automatic test system of the present invention;
FIG. 2 is a block diagram of the automatic test system of the present invention.
Detailed Description
The invention is described in detail below with reference to the accompanying drawings:
an automatic test method for an automatic power generation control function test of a photovoltaic power station comprises the following steps:
firstly, establishing an automatic test system: the device comprises a data acquisition unit, a logic control unit, an instruction output unit, a calculation storage unit and a result display unit, wherein the data acquisition unit is used for acquiring data of the photovoltaic power station in real time, preprocessing the data and transmitting the preprocessed data to the logic control unit, and the logic control unit is used for calculating an active power target instruction of the AGC test process of the photovoltaic power station and transmitting an instruction signal to the instruction output unit; the instruction output unit is used for receiving the active power target instruction signal transmitted by the logic control unit and transmitting an active power target instruction in an AGC test process to the photovoltaic power station; the calculation storage unit is used for storing and calculating data of the AGC test of the photovoltaic power station to obtain various performance indexes of the AGC test; the result display unit is used for displaying data of the photovoltaic power station AGC test in an image form;
secondly, the test system starts to collect data such as actual power, predicted power and the like of the photovoltaic power station in real time;
thirdly, the test system calculates and judges whether the test starting condition is met or not in real time, if yes, automatic test is started according to the test steps, step change AGC commands are sequentially issued to the photovoltaic power station according to a preset output curve, and data such as actual power, target commands and the like required by the test are collected;
step four, judging whether the test is interrupted, if the interruption time exceeds the preset time, returning to the step two, and if the test is not interrupted or the interruption time is less than the preset time, performing the next step;
fifthly, continuing to perform unfinished tests;
sixthly, completing the test, and calculating various test indexes according to the collected test data;
and step seven, displaying the test data in the form of images and providing a derivation function.
The data acquisition unit also comprises a communication protocol conversion module and an analog input and output module, wherein the communication protocol conversion module can enable the automatic test device to be connected with a photovoltaic power station AGC system, a photovoltaic power prediction system and a booster station monitoring system through different interface types; the data acquired by the data acquisition unit comprise active power of grid-connected power points of the photovoltaic power station, active power target instructions, active power of a collection line, active power of a sample plate inverter and ultra-short-term power prediction data of 16 points in 4 hours in the future; the instruction output unit is provided with a communication interface and a communication protocol which are consistent with those of the dispatching system, and can communicate with the AGC system of the photovoltaic power station according to the grid-connected dispatching information exchange specification and send an active power target instruction; the logic control unit can automatically judge whether a test condition is met or not through calculation based on the data acquired by the data acquisition unit, if so, an active power target instruction is sent to the photovoltaic power station according to a preset instruction curve, the test condition refers to that the illumination condition of the photovoltaic power station meets the active power output range required by the test, the duration time is longer than the shortest time required by the test, and the judgment is specifically carried out according to the active power of a grid-connected point of the photovoltaic power station and the ultra-short-term predicted power; the AGC test performance indexes obtained by calculation of the calculation storage unit comprise response time, overshoot, regulation rate and regulation precision.
The response time refers to the time for reliably spanning a response dead zone consistent with the instruction direction on the basis of the current active power by the output of the photovoltaic power station after the automatic testing device sends an instruction; the overshoot refers to the deviation of the active power of the photovoltaic power station from the maximum value of an AGC instruction; the adjusting speed is the speed of the photovoltaic power station in the AGC instruction direction, wherein the output force exceeds the response dead zone to enter the adjusting dead zone; the adjusting precision refers to a difference value between actual output and set point output in a period from the photovoltaic power station entering an adjusting dead zone to the beginning of a next instruction.
If the test condition does not meet the test requirement of the subsequent stage in the process of carrying out automatic test, the automatic test device waits for the interruption of the test, stops issuing instructions to the photovoltaic power station, and calculates the subsequent test condition according to the completed test condition, wherein the subsequent test condition means that the current actual active power of the photovoltaic power station is not less than the maximum output value required by the test of the incomplete stage, and the time for predicting and maintaining the output is not less than the minimum time required for completing the test of the subsequent stage;
if the required test conditions are restored within a certain time (which can be manually configured), continuing the test from the previously interrupted test phase; if the interruption time exceeds the preset time and the test condition is not met, the test device judges the test starting condition again, and complete test is carried out again after the test starting condition is met.
The automatic testing device is used for the AGC test of the photovoltaic power station, and has two modes of manual test and automatic test; in the automatic test mode, whether the required test conditions are met can be automatically judged through calculation; in the automatic test process, when the test is interrupted due to weather and other reasons, the device can automatically wait for the recovery of the test condition and judge to continue the unfinished test or restart a new test according to the condition; the system can be connected with the photovoltaic power station in two modes of communication protocol and analog quantity hard wiring, and the communication mode is flexible.

Claims (4)

1. An automatic test method for an automatic power generation control function test of a photovoltaic power station comprises the following steps:
firstly, establishing an automatic test system: the device comprises a data acquisition unit, a logic control unit, an instruction output unit, a calculation storage unit and a result display unit, wherein the data acquisition unit is used for acquiring data of the photovoltaic power station in real time, preprocessing the data and transmitting the preprocessed data to the logic control unit, and the logic control unit is used for calculating an active power target instruction of the AGC test process of the photovoltaic power station and transmitting an instruction signal to the instruction output unit; the instruction output unit is used for receiving the active power target instruction signal transmitted by the logic control unit and transmitting an active power target instruction in an AGC test process to the photovoltaic power station; the calculation storage unit is used for storing and calculating data of the AGC test of the photovoltaic power station to obtain various performance indexes of the AGC test; the result display unit is used for displaying data of the photovoltaic power station AGC test in an image form;
secondly, the test system starts to collect data such as actual power, predicted power and the like of the photovoltaic power station in real time;
thirdly, the test system calculates and judges whether the test starting condition is met or not in real time, if yes, automatic test is started according to the test steps, step change AGC commands are sequentially issued to the photovoltaic power station according to a preset output curve, and data such as actual power, target commands and the like required by the test are collected;
step four, judging whether the test is interrupted, if the interruption time exceeds the preset time, returning to the step two, and if the test is not interrupted or the interruption time is less than the preset time, performing the next step;
fifthly, continuing to perform unfinished tests;
sixthly, completing the test, and calculating various test indexes according to the collected test data;
and step seven, displaying the test data in the form of images and providing a derivation function.
2. The automatic test method for the automatic power generation control function test of the photovoltaic power station as claimed in claim 1, wherein the data acquisition unit further comprises a communication protocol conversion module and an analog input and output module, the communication protocol conversion module enables the automatic test device to be connected with an AGC system of the photovoltaic power station, a photovoltaic power prediction system and a booster station monitoring system through different interface types; the data acquired by the data acquisition unit comprise active power of grid-connected power points of the photovoltaic power station, active power target instructions, active power of a collection line, active power of a sample plate inverter and ultra-short-term power prediction data of 16 points in 4 hours in the future; the instruction output unit is provided with a communication interface and a communication protocol which are consistent with those of the dispatching system, and can communicate with the AGC system of the photovoltaic power station according to the grid-connected dispatching information exchange specification and send an active power target instruction; the logic control unit can automatically judge whether a test condition is met or not through calculation based on the data acquired by the data acquisition unit, if so, an active power target instruction is sent to the photovoltaic power station according to a preset instruction curve, the test condition refers to that the illumination condition of the photovoltaic power station meets the active power output range required by the test, the duration time is longer than the shortest time required by the test, and the judgment is specifically carried out according to the active power of a grid-connected point of the photovoltaic power station and the ultra-short-term predicted power; the AGC test performance indexes obtained by calculation of the calculation storage unit comprise response time, overshoot, regulation rate and regulation precision.
3. The automatic test method for the automatic power generation control function test of the photovoltaic power station as claimed in claim 2, wherein the response time is a time taken for the photovoltaic power station to reliably span a response dead zone having a direction consistent with a command direction on the basis of the current active power after the automatic test device sends the command; the overshoot refers to the deviation of the active power of the photovoltaic power station from the maximum value of an AGC instruction; the adjusting speed is the speed of the photovoltaic power station in the AGC instruction direction, wherein the output force exceeds the response dead zone to enter the adjusting dead zone; the adjusting precision refers to a difference value between actual output and set point output in a period from the photovoltaic power station entering an adjusting dead zone to the beginning of a next instruction.
4. The automatic test method for the automatic power generation control function test of the photovoltaic power station as claimed in claim 1, wherein if the test condition does not meet the test requirement of the subsequent stage in the automatic test process, the automatic test device waits, interrupts the test, suspends the issue of the instruction to the photovoltaic power station, and calculates the subsequent test condition according to the completed test condition, wherein the subsequent test condition means that the current actual active power of the photovoltaic power station is not less than the maximum output value required by the test of the unfinished stage, and the time for maintaining the output is not less than the minimum time required for completing the test of the subsequent stage;
if the required test conditions are restored within a certain time (which can be manually configured), continuing the test from the previously interrupted test phase; if the interruption time exceeds the preset time and the test condition is not met, the test device judges the test starting condition again, and complete test is carried out again after the test starting condition is met.
CN201911246310.0A 2019-12-08 2019-12-08 Automatic testing method for automatic power generation control function test of photovoltaic power station Active CN110928273B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911246310.0A CN110928273B (en) 2019-12-08 2019-12-08 Automatic testing method for automatic power generation control function test of photovoltaic power station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911246310.0A CN110928273B (en) 2019-12-08 2019-12-08 Automatic testing method for automatic power generation control function test of photovoltaic power station

Publications (2)

Publication Number Publication Date
CN110928273A true CN110928273A (en) 2020-03-27
CN110928273B CN110928273B (en) 2022-09-02

Family

ID=69858272

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911246310.0A Active CN110928273B (en) 2019-12-08 2019-12-08 Automatic testing method for automatic power generation control function test of photovoltaic power station

Country Status (1)

Country Link
CN (1) CN110928273B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112505451A (en) * 2020-11-23 2021-03-16 广东电网有限责任公司电力科学研究院 Mobile AGC (automatic gain control) and AVC (automatic Voltage control) function test system for offshore wind farm
CN113189893A (en) * 2021-04-09 2021-07-30 国网上海市电力公司 Real-time simulation-based controller grid-connected test system and method

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1901677A (en) * 2006-07-25 2007-01-24 北京中星微电子有限公司 Decoding error restoring method for MPEG4 decoder
US20100321148A1 (en) * 2009-06-18 2010-12-23 Peter Gevorkian Wireless intelligent solar power reader (wispr) structure and process
CN101996107A (en) * 2009-08-31 2011-03-30 中国工商银行股份有限公司 Operation interruption automatic recovering system and method
CN102566435A (en) * 2012-02-17 2012-07-11 冶金自动化研究设计院 Performance prediction and fault alarm method for photovoltaic power station
CN103217595A (en) * 2013-02-18 2013-07-24 华为技术有限公司 Detection method, equipment and system of one-phase island of three-phase grid-connected inverter
CN103812133A (en) * 2014-02-08 2014-05-21 振发新能源科技有限公司 Grid-connected photovoltaic power station power control system and remote control method thereof
CN106296038A (en) * 2016-08-26 2017-01-04 隆鑫通用动力股份有限公司 Test assignment triggering method
CN106597165A (en) * 2016-12-19 2017-04-26 国网甘肃省电力公司电力科学研究院 Photovoltaic power station grid-connected remote test method and system based on Internet
CN106980762A (en) * 2017-03-29 2017-07-25 河海大学 Photovoltaic electric station grid connection active power reference value quick calculation method
CN108199420A (en) * 2017-12-31 2018-06-22 北京金风科创风电设备有限公司 Photovoltaic power plant and secondary frequency modulation control method thereof
CN108206536A (en) * 2016-12-20 2018-06-26 中国电力科学研究院 A kind of active power control method of photovoltaic power station and device
CN108375422A (en) * 2018-01-29 2018-08-07 中国第汽车股份有限公司 A kind of control method, control device and system that electromagnet temperature liter is tested automatically

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1901677A (en) * 2006-07-25 2007-01-24 北京中星微电子有限公司 Decoding error restoring method for MPEG4 decoder
US20100321148A1 (en) * 2009-06-18 2010-12-23 Peter Gevorkian Wireless intelligent solar power reader (wispr) structure and process
CN101996107A (en) * 2009-08-31 2011-03-30 中国工商银行股份有限公司 Operation interruption automatic recovering system and method
CN102566435A (en) * 2012-02-17 2012-07-11 冶金自动化研究设计院 Performance prediction and fault alarm method for photovoltaic power station
CN103217595A (en) * 2013-02-18 2013-07-24 华为技术有限公司 Detection method, equipment and system of one-phase island of three-phase grid-connected inverter
CN103812133A (en) * 2014-02-08 2014-05-21 振发新能源科技有限公司 Grid-connected photovoltaic power station power control system and remote control method thereof
CN106296038A (en) * 2016-08-26 2017-01-04 隆鑫通用动力股份有限公司 Test assignment triggering method
CN106597165A (en) * 2016-12-19 2017-04-26 国网甘肃省电力公司电力科学研究院 Photovoltaic power station grid-connected remote test method and system based on Internet
CN108206536A (en) * 2016-12-20 2018-06-26 中国电力科学研究院 A kind of active power control method of photovoltaic power station and device
CN106980762A (en) * 2017-03-29 2017-07-25 河海大学 Photovoltaic electric station grid connection active power reference value quick calculation method
CN108199420A (en) * 2017-12-31 2018-06-22 北京金风科创风电设备有限公司 Photovoltaic power plant and secondary frequency modulation control method thereof
CN108375422A (en) * 2018-01-29 2018-08-07 中国第汽车股份有限公司 A kind of control method, control device and system that electromagnet temperature liter is tested automatically

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
华光辉: "光伏电站快速频率响应技术研究及应用", 《电网与清洁能源》 *
王小平: "基于 AGC 的光伏电站一次调频控制", 《电力大数据》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112505451A (en) * 2020-11-23 2021-03-16 广东电网有限责任公司电力科学研究院 Mobile AGC (automatic gain control) and AVC (automatic Voltage control) function test system for offshore wind farm
CN113189893A (en) * 2021-04-09 2021-07-30 国网上海市电力公司 Real-time simulation-based controller grid-connected test system and method

Also Published As

Publication number Publication date
CN110928273B (en) 2022-09-02

Similar Documents

Publication Publication Date Title
CN108767851B (en) Intelligent operation command method and system for operation and maintenance of transformer substation
CN100588070C (en) System for controlling and managing micro power network
CN110020967B (en) Information processing method and device for intelligent alarm of power grid dispatching end transformer substation
CN110928273B (en) Automatic testing method for automatic power generation control function test of photovoltaic power station
HUE035925T2 (en) Hybrid electric generating power plant that uses a combination of real-time generation facilities and energy storage system
CN108681830B (en) Substation patrol intelligent operation dynamic command method and system
CN110401692B (en) Integrated automatic checking and accepting system and method for monitoring information of transformer substation
CN111179457A (en) Inspection system and inspection method for industrial equipment
CN102393726B (en) Method for evaluating performance of AGC (automatic gain control) controller of thermal power unit
CN109301935B (en) Monitoring method and system for power quality operation decision support
CN108267670B (en) Distribution network fault study and judgment early warning system and implementation method thereof
CN106532806B (en) Intelligent battery replacement control method and system for electric vehicle battery charging and replacement station
CN111105049A (en) Distribution network emergency repair system and method based on intelligent Internet of things
CN111950197A (en) Distribution network attack and fault acquisition and analysis system based on artificial intelligence semantics
CN112290886A (en) Fault detection method and device and photovoltaic power generation system
CN212623717U (en) Remote energy consumption monitoring system based on raspberry group
CN219247485U (en) Pressure regulating system of electric drive fracturing equipment and electric drive fracturing equipment
CN206331274U (en) A kind of equipment long-distance service system
CN103281371A (en) System and method for controlling pumping unit in long distance based on 4G mobile network
CN114741447A (en) Distributed energy station data processing method and device
CN115759599A (en) Power supply guarantee method and device, electronic equipment and storage medium
CN104963514A (en) Control system with a plurality of prestress intelligent tensioning devices
CN210515359U (en) Transformer substation secondary equipment fault monitoring system based on edge calculation
CN114357762A (en) Wisdom power equipment high in clouds control automatic system
CN111351988A (en) Intelligent tower grounding resistance measuring system and method based on mobile internet

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant