Process for rotating-spraying composite piles Download PDF

Info

Publication number
CN1109128A
CN1109128A CN 94105409 CN94105409A CN1109128A CN 1109128 A CN1109128 A CN 1109128A CN 94105409 CN94105409 CN 94105409 CN 94105409 A CN94105409 A CN 94105409A CN 1109128 A CN1109128 A CN 1109128A
Authority
CN
China
Prior art keywords
stake
pile
reinforcement
churning
slurry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 94105409
Other languages
Chinese (zh)
Other versions
CN1043068C (en
Inventor
王光明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ling Guangrong
Wang Enyuan
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 94105409 priority Critical patent/CN1043068C/en
Publication of CN1109128A publication Critical patent/CN1109128A/en
Application granted granted Critical
Publication of CN1043068C publication Critical patent/CN1043068C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The construction method for reinforcing foundation based on chemical churning pile features that concrete grout is sprayed into loose pile foundation and prefabricated reinforced concrete pile in the form of bamboo joints or screw is put in it after mixing to form a composite pile. Its advantages include high bearing power and drawing-out resistance, and less consumption of steel and concrete.

Description

Process for rotating-spraying composite piles
The present invention relates to method for processing foundation, particularly a kind of job practices of churning pile consolidated subsoil.
In capital construction, in order to reinforce soft foundation, improve its supporting capacity, in recent years on the basis of boring slip casting with consolidated subsoil, formed the churning "forming column, promptly the churning equipment that revolves hole stirring-head and shotcrete pipe with band unscrews the earth at pile place on pending ground, the slurry of spray simultaneously, make slurry and the earth mix that unscrews, treat to become after it solidifies the higher rotary churning pile of intensity.This rotary churning pile can only limited ground consolidated subsoil.In order further to improve the intensity of rotary churning pile, strengthen its supporting capacity, the disclosed churning "forming column of Chinese patent CN1071724 " method for processing foundation " is to unscrew earth in the hole with churning equipment, while next isolated tube in the stake hole, the churning sandstone that loosens the soil outside isolated tube then, the air placed concrete slurry is mentioned isolated tube then in isolated tube, after treating concrete setting, promptly be formed with the rotary churning pile that concrete is strengthened the stake heart.But construction results shows thisly have the bearing capacity of the rotary churning pile of a heart, uplift resistance still lower, and pile strength is also not high.
The purpose of this invention is to provide a kind of job practices with pile strength height, rotary jet grouting pile in foundation stabilization that supporting capacity is bigger.
To be the churning equipment that revolves hole stirring-head and shotcrete pipe with band on the soil base unscrew the earth at pile place to foundation reinforcement method of the present invention, while air placed concrete slurry, make concrete slurry and the earth mix that unscrews, before the concrete slurry solidifies, prefabricated steel concrete is strengthened stake and inserts, treat slurry solidify after with it one become composite pile.
Foundation reinforcement method of the present invention is easy to use, and can improve the pile strength of rotary churning pile and the vertical plane bearing capacity of stake greatly.Compare with all steel rib concrete pile of identical vertical plane bearing capacity, can save various soils bases such as steel and concrete, and suitable sandy soil, loam and clay greatly.
For ease of the soil that unscrews that solidifies preceding concrete slurry and mix is inserted in steel concrete reinforcement stake, steel concrete reinforcement stake can be prefabricated into cone or cross section is triangle, the square and polygonal cone more than four limits.
Strengthen the adhesive power and the uplift resistance of stake for improving steel concrete, also steel concrete reinforcement stake can be prefabricated into to have on the conical surface has the stake of the screw type of Luo Xuan fin or groove on the stake of the slub type of ansa or annular groove or the conical surface.
Below in conjunction with drawings and Examples the present invention is described.
Fig. 1 is the churning composite pile schematic diagram that forms with method for processing foundation construction of the present invention.
Fig. 2 is that churning composite pile embodiment side cone slub type steel concrete is strengthened the stake schematic diagram among the present invention.
Fig. 3 is the vertical view of Fig. 2.
Fig. 4 is that screw type steel concrete is strengthened the stake schematic diagram.
Fig. 5 is the vertical view of Fig. 4.
Embodiment, with reference to Fig. 1, the stake position of selecting on the mollisol ground 3 that needs reinforcement unscrews the earth in the stake hole 4 with churning equipment, simultaneously the earth mix pile soil 2 in air placed concrete slurry and the stake hole 4.Exert pressure with vibration then and prefabricated steel concrete is strengthened stake 1 insert in the stake soil 2 of ot-yet-hardened, treat that promptly strengthening stake 1 with steel concrete after stake soil 2 solidifies becomes one and become and revolve compound spray stake.
With reference to Fig. 2, Fig. 3, it can be the cone that ansa 5 is arranged on its conical surface 6 that the steel concrete of inserting in the churning composite pile is strengthened stake 1, and its cross section is a quadrangular section 7, and concrete strengthens in the stake 1 reinforcing cage 8 being arranged.
With reference to Fig. 4, Fig. 5, it can be the screw type stake that Luo Xuan groove 9 is arranged on its conical surface 6 that the steel concrete of inserting in the churning composite pile is strengthened stake 1, and its cross section is a circular cross-section 10, and it is reinforcing cage 8 that concrete is strengthened in the stake 1.

Claims (5)

1, a kind of foundation reinforcement method promptly revolves the hole with churning machinery on the soil base and the churning slurry solidifies pile, thereby the job practices of consolidated subsoil is characterized in that:
The slurry of a, said churning is the concrete slurry,
B, before inward turning whitewashing material in stake hole solidifies, prefabricated reinforcement is inserted, treat slurry solidify after with it one become composite pile.
2, foundation reinforcement method according to claim 1 is characterized in that the prefabricated reinforcement stake of using in the said reinforcement means is the cone reinforced concrete pile.
3, foundation reinforcement method according to claim 1 is characterized in that the prefabricated reinforcement stake of using in the said reinforcement means is that cross section is polygonal cone reinforced concrete pile.
4,, it is characterized in that the cone reinforced concrete pile that uses in the said reinforcement means is the slub type stake that ansa is arranged on the conical surface according to claim 2 or 3 described foundation reinforcement methods.
5,, it is characterized in that the cone reinforced concrete pile that uses in the said reinforcement means is the screw type stake that the Luo Xuan groove is arranged on the conical surface according to claim 2 or 3 described foundation reinforcement methods.
CN 94105409 1994-05-12 1994-05-12 Process for rotating-spraying composite piles Expired - Fee Related CN1043068C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 94105409 CN1043068C (en) 1994-05-12 1994-05-12 Process for rotating-spraying composite piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 94105409 CN1043068C (en) 1994-05-12 1994-05-12 Process for rotating-spraying composite piles

Publications (2)

Publication Number Publication Date
CN1109128A true CN1109128A (en) 1995-09-27
CN1043068C CN1043068C (en) 1999-04-21

Family

ID=5032045

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 94105409 Expired - Fee Related CN1043068C (en) 1994-05-12 1994-05-12 Process for rotating-spraying composite piles

Country Status (1)

Country Link
CN (1) CN1043068C (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100371545C (en) * 2005-12-16 2008-02-27 张国梁 Reversed construction method for building
CN111809611A (en) * 2020-08-24 2020-10-23 黑龙江辰午建筑工程有限公司 Construction method of jet grouting prefabricated composite pile
CN112227360A (en) * 2020-09-25 2021-01-15 福建新华夏建工有限公司 High-pulling-resistance-strength foundation reinforcing device for rotary jet drilling machine
CN112726568A (en) * 2020-12-29 2021-04-30 中铁四局集团有限公司 Method for reinforcing silt sand layer

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100371545C (en) * 2005-12-16 2008-02-27 张国梁 Reversed construction method for building
CN111809611A (en) * 2020-08-24 2020-10-23 黑龙江辰午建筑工程有限公司 Construction method of jet grouting prefabricated composite pile
CN112227360A (en) * 2020-09-25 2021-01-15 福建新华夏建工有限公司 High-pulling-resistance-strength foundation reinforcing device for rotary jet drilling machine
CN112227360B (en) * 2020-09-25 2021-10-29 福建新华夏建工有限公司 High-pulling-resistance-strength foundation reinforcing device for rotary jet drilling machine
CN112726568A (en) * 2020-12-29 2021-04-30 中铁四局集团有限公司 Method for reinforcing silt sand layer
CN112726568B (en) * 2020-12-29 2022-04-19 中铁四局集团有限公司 Method for reinforcing silt sand layer

Also Published As

Publication number Publication date
CN1043068C (en) 1999-04-21

Similar Documents

Publication Publication Date Title
CN206956714U (en) Down-the-hole impacts rotating spraying mixture pile construction equipment
CN101608448B (en) Pile-forming method for cement paste spraying multi-directional core entraining mixing pile
CN103993611A (en) Anti-floating piled raft structure combining deep-layer jet-grouting cement-soil board and anchor and construction method
CN1710213A (en) Construction method of synchronous combined pile with high-pressure rotary-spraying pile tip
CN205907679U (en) Cast -in -place strength core stirring stake
CN106593467A (en) Supporting method for underground soft rock roadway of coal mine
CN204780874U (en) Insert many drilling rods cement mixing method of prefabricated section bar
CN1043068C (en) Process for rotating-spraying composite piles
CN105002895B (en) More drilling rod cement mixing methods inserted with prefabricated shaped-section
CN203866852U (en) Anti-floating pile structure composited by deep spiral-spraying cement soil plate and anchor rod
CN207260138U (en) High-pressure rotary-spray stirs the drilling rod of bearing pile and has its device
CN103953053B (en) Plant-growing type eco-concrete anti-overflow device and construction method are built in inclined-plane
CN107740419A (en) Foundation pit supporting method and raked pile
CN104746512B (en) A kind of soil cement stiff composite pile and its pile making method
CN1260425A (en) Making method for reinforced concrete stiff-core cement soil composite pile and its pile and construction equipment
CN217270125U (en) Ultrahigh-pressure soil body jet cutting grouting device
CN1259604A (en) Cement earth reinforced composite piling method
CN100374657C (en) Construction method employing threaded stirring shaft to decrease ambient foundation deformation
CN2231275Y (en) Reinforced pile with rotary spray composite pile
CN107620309A (en) Foundation pit supporting method
CN107366290A (en) Foundation pit supporting method and raked pile
CN207193988U (en) Raked pile
CN1891913A (en) Counterweight punching-expanding replacement method
CN105019440A (en) Control tower pile used for manufacturing high-strength cemented soil mixing pile
CN110158584A (en) Four limbs bilayer drill configurations

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C14 Grant of patent or utility model
GR01 Patent grant
C53 Correction of patent for invention or patent application
COR Change of bibliographic data

Free format text: CORRECT: CO-PATENTEE TO: LING GUANGRONG; WANG ENYUAN

CP01 Change in the name or title of a patent holder

Co-patentee after: Ling Guangrong

Co-patentee after: Wang Enyuan

C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee