CN110908347B - Intelligent power plant management and control system based on Internet of things - Google Patents

Intelligent power plant management and control system based on Internet of things Download PDF

Info

Publication number
CN110908347B
CN110908347B CN201911111656.XA CN201911111656A CN110908347B CN 110908347 B CN110908347 B CN 110908347B CN 201911111656 A CN201911111656 A CN 201911111656A CN 110908347 B CN110908347 B CN 110908347B
Authority
CN
China
Prior art keywords
intelligent
management
equipment
control
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201911111656.XA
Other languages
Chinese (zh)
Other versions
CN110908347A (en
Inventor
王英敏
王鹤麒
宋寅
王然
万逵芳
武永鑫
孙志鹏
叶翔
邱桂芝
王伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Thermal Power Generation Technology Research Institute of China Datang Corporation Science and Technology Research Institute Co Ltd
Original Assignee
Thermal Power Generation Technology Research Institute of China Datang Corporation Science and Technology Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Thermal Power Generation Technology Research Institute of China Datang Corporation Science and Technology Research Institute Co Ltd filed Critical Thermal Power Generation Technology Research Institute of China Datang Corporation Science and Technology Research Institute Co Ltd
Priority to CN201911111656.XA priority Critical patent/CN110908347B/en
Publication of CN110908347A publication Critical patent/CN110908347A/en
Application granted granted Critical
Publication of CN110908347B publication Critical patent/CN110908347B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM]
    • G05B19/4185Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM] characterised by the network communication
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/30Nc systems
    • G05B2219/31From computer integrated manufacturing till monitoring
    • G05B2219/31088Network communication between supervisor and cell, machine group
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Abstract

The invention relates to an intelligent power plant management and control system based on the Internet of things, which comprises a unit operation management and control system, an equipment maintenance management and control system, an intelligent security system and an operation management system; the unit operation control system comprises an intelligent inspection module and an intelligent control module; the equipment maintenance management and control system comprises an intelligent equipment management module, an intelligent fault diagnosis module and an intelligent maintenance management module; the intelligent security system includes: the electronic fence system is used for personnel positioning and virtual electronic fence management and control; the plant intelligent monitoring system is used for intelligently monitoring a plant; the intelligent access control system is used for access control management; the protection system is used for perimeter protection and alarm of important areas; the operation management system includes: the performance management module is used for performing performance management; the intelligent material management module is used for managing materials; the intelligent security system shares resources with the intelligent construction site to acquire and store the data information of the infrastructure stage. The intelligent management system realizes the centralized management and control of intelligent unit operation, intelligent equipment maintenance, intelligent safety prevention and control and intelligent operation management.

Description

Intelligent power plant management and control system based on Internet of things
Technical Field
The invention belongs to the technical field of power plant management and control, and particularly relates to an intelligent power plant management and control system based on the Internet of things.
Background
In a traditional power plant, commonly used control and processing data information systems include a DCS (distributed control system), an SIS (plant-level monitoring information system) and an MIS (management information system), and the DCS system focuses on real-time monitoring and accurate control, focuses on process control, and aims at stable operation. The SIS is used for realizing real-time command and scheduling of production operation of the whole plant through real-time analysis of monitoring data of the power plant. The MIS is mainly responsible for information processing, task transfer and working coordination, provides required information for production management and administrative management personnel of the whole plant, and completes equipment and maintenance management until production management, financial management and office automation.
Therefore, in the traditional power plant, DCS, SIS and MIS systems are independent and crossed mutually, face different levels, have different targets and have different functions. Because DCS, SIS and MIS systems have definite functional partitions and certain flow direction exists between data and information, the functions are single, and centralized control of all aspects of a power plant cannot be realized.
Disclosure of Invention
The invention aims to provide an intelligent power plant management and control system based on the Internet of things, which realizes intelligent unit operation management and control, intelligent equipment maintenance management and control, intelligent safety prevention and control and intelligent operation management through a power plant intelligent management and control integrated platform.
The invention provides an intelligent power plant management and control system based on the Internet of things, which comprises a unit operation management and control system, an equipment maintenance management and control system, an intelligent security and protection system and an operation management system;
the unit operation management and control system comprises:
the intelligent inspection module is used for monitoring the equipment state based on machine vision;
the intelligent control module is used for performing APS automatic start-stop control, combustion online optimization and operation intelligent optimization;
the equipment maintenance management and control system comprises:
the intelligent equipment management module is used for three-dimensional visual management of the power plant and full life cycle management of equipment;
the intelligent fault diagnosis module is used for diagnosing the vibration of the spindle machine;
the intelligent overhaul management module is used for intelligent defect management, two-ticket management and intelligent overhaul scheduling and comprises an intelligent defect management system and a two-ticket system;
the intelligent security system includes:
the electronic fence system is used for personnel positioning and virtual electronic fence management and control;
the system comprises a factory intelligent monitoring system, a factory monitoring system and a monitoring system, wherein the factory intelligent monitoring system is used for intelligently monitoring a factory based on image identification;
the intelligent access control system is used for access control management;
the protection system is used for perimeter protection and alarm of important areas;
the operation management system includes:
the performance management module is used for performing performance management;
the intelligent material management module is used for managing materials; the intelligent security system shares resources with the intelligent construction site to acquire and store the data information of the construction stage.
Further, the wisdom building site includes building site three-dimensional visual module, capital construction information sign and trail management module, building site wisdom security module with intelligent security system communication realizes the resource sharing.
Further, the device full lifecycle management comprises:
and establishing a coding system which runs through the whole life cycle of the equipment, forming three codes of unified material codes, fixed asset codes and equipment codes, and using the three codes as equipment codes of an equipment identification system, so as to establish the relation among the material, spare parts and the equipment and form a linkage relation.
Further, the intelligent defect management and two-ticket system, the intelligent security system and the equipment identification system form a linkage relation:
when the equipment has defects, the defect management system sends an alarm and generates a billing suggestion, after a work ticket is issued, the permission time and the ending time of the work ticket are used as time elements, the equipment information of the work ticket, namely the process position of the equipment, is used as a space element, and related operation information is automatically sent to an electronic fence system or a factory intelligent monitoring system to control the working state of a working member and the intrusion of a non-working member in real time; and meanwhile, sending information to the two-ticket system by scanning the equipment code of the equipment identification system so as to confirm the working condition of the working ticket.
Borrow by above-mentioned scheme, through the wisdom power plant management and control system based on the thing networking, established power plant wisdom management and control integration platform, realized the concentrated management and control of wisdom unit operation, wisdom equipment maintenance, wisdom safety prevention and control, wisdom operation management.
The foregoing description is only an overview of the technical solutions of the present invention, and in order to make the technical solutions of the present invention more clearly understood and to make the technical solutions of the present invention practical in accordance with the contents of the specification, the following detailed description is given of preferred embodiments of the present invention with reference to the accompanying drawings.
Drawings
Fig. 1 is a block diagram of an intelligent management and control system of an intelligent power plant according to the present invention.
Detailed Description
The following detailed description of embodiments of the present invention is provided in connection with the accompanying drawings and examples. The following examples are intended to illustrate the invention but are not intended to limit the scope of the invention.
Referring to fig. 1, the embodiment provides an intelligent power plant management and control system based on the internet of things, which includes a unit operation management and control system, an equipment maintenance management and control system, an intelligent security system, and an operation management system;
the unit operation management and control system comprises:
the intelligent inspection module is used for monitoring the equipment state based on machine vision;
the intelligent control module is used for performing APS automatic start-stop control, combustion online optimization and operation intelligent optimization;
the equipment maintenance management and control system comprises:
the intelligent equipment management module is used for three-dimensional visual management of the power plant and full life cycle management of equipment;
the intelligent fault diagnosis module is used for diagnosing the vibration of the spindle machine;
the intelligent overhaul management module is used for intelligent defect management, two-ticket management and intelligent overhaul scheduling and comprises an intelligent defect management system and a two-ticket system;
the intelligent security system includes:
the electronic fence system is used for personnel positioning and virtual electronic fence management and control;
the system comprises a factory intelligent monitoring system, a factory monitoring system and a monitoring system, wherein the factory intelligent monitoring system is used for intelligently monitoring a factory based on image identification;
the intelligent access control system is used for access control management;
the protection system is used for perimeter protection and alarm of important areas;
the operation management system includes:
the performance management module is used for performing performance management;
the intelligent material management module is used for managing materials;
the intelligent security system shares resources with the intelligent construction site to acquire and store the data information of the construction stage.
This wisdom power plant management and control system based on thing networking has established power plant wisdom management and control integration platform, has realized the concentrated management and control of wisdom unit operation, wisdom equipment maintenance, wisdom safety prevention and control, wisdom operation management.
In this embodiment, the wisdom building site includes building site three-dimensional visual module (like underground pipe network three-dimensional visual), capital construction information sign and tracking management module, building site wisdom security module with the communication of intelligence security system realizes the resource sharing.
The construction management demand of wisdom building site towards the capital construction stage realizes the digitization of capital construction information simultaneously, provides good basis for the realization of wisdom power plant function. The intelligent construction site comprises the functions of construction site three-dimensional visualization, infrastructure information identification and tracking management, intelligent security and the like. The intelligent construction site function can be established on an intelligent power plant management and control system (platform) or a data interface is made with the platform, so that the data information of the basic construction stage is completely and comprehensively reserved. Building site wisdom security protection and wisdom power plant intelligence security protection system realize effectively linking up and resource reasonable multiplexing, avoid repeated construction and waste.
In this embodiment, the device full lifecycle management comprises:
and establishing a coding system which runs through the whole life cycle of the equipment, forming three codes of unified material codes, fixed asset codes and equipment codes, and using the three codes as equipment codes of an equipment identification system, so as to establish the relation among the material, spare parts and the equipment and form a linkage relation.
In this embodiment, the intelligent defect management and two-ticket system forms a linkage relationship with the intelligent security system and the device identification system:
when the equipment has defects, the defect management system sends an alarm and generates a billing suggestion, after a work ticket is issued, the permission time and the ending time of the work ticket are used as time elements, the equipment information of the work ticket, namely the process position of the equipment, is used as a space element, and related operation information is automatically sent to an electronic fence system or a factory intelligent monitoring system to control the working state of a working member and the intrusion of a non-working member in real time; and meanwhile, sending information to the two-ticket system by scanning the equipment code of the equipment identification system so as to confirm the working condition of the working ticket.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, it should be noted that, for those skilled in the art, many modifications and variations can be made without departing from the technical principle of the present invention, and these modifications and variations should also be regarded as the protection scope of the present invention.

Claims (1)

1. An intelligent power plant management and control system based on the Internet of things is characterized by comprising a unit operation management and control system, an equipment maintenance management and control system, an intelligent security system and an operation management system;
the unit operation management and control system comprises:
the intelligent inspection module is used for monitoring the equipment state based on machine vision;
the intelligent control module is used for performing APS automatic start-stop control, combustion online optimization and operation intelligent optimization;
the equipment maintenance management and control system comprises:
the intelligent equipment management module is used for three-dimensional visual management of the power plant and full life cycle management of equipment;
the intelligent fault diagnosis module is used for diagnosing the vibration of the spindle machine;
the intelligent overhaul management module is used for intelligent defect management, two-ticket management and intelligent overhaul scheduling and comprises an intelligent defect management system and a two-ticket system;
the intelligent security system includes:
the electronic fence system is used for personnel positioning and virtual electronic fence management and control;
the system comprises a factory intelligent monitoring system, a factory monitoring system and a monitoring system, wherein the factory intelligent monitoring system is used for intelligently monitoring a factory based on image identification;
the intelligent access control system is used for access control management;
the protection system is used for perimeter protection and alarm of important areas;
the operation management system includes:
the performance management module is used for performing performance management;
the intelligent material management module is used for managing materials; the intelligent security system shares resources with the intelligent construction site and is used for acquiring and storing data information of the infrastructure stage;
the intelligent construction site comprises a construction site three-dimensional visualization module, a capital construction information identification and tracking management module and a construction site intelligent security module, and the construction site intelligent security module is communicated with the intelligent security system to realize resource sharing;
the device full lifecycle management comprises:
establishing a coding system which runs through the whole life cycle of the equipment, forming a three-code unification of material codes, fixed asset codes and equipment codes, and taking the three-code unification as an equipment code of an equipment identification system so as to establish the relation among the materials, spare parts and the equipment and form a linkage relation;
the intelligent defect management and two-ticket system forms a linkage relation with the intelligent security system and the equipment identification system:
when the equipment has a defect, the defect management system sends an alarm and generates an invoicing suggestion, after the work order is invoiced, the permission time and the ending time of the work order are used as time elements, equipment information of the work order, namely the process position of the equipment, is used as a space element, and related operation information is automatically sent to an electronic fence system or a factory intelligent monitoring system to control the working state of a working member and the intrusion of a non-working member in real time; and meanwhile, sending information to the two-ticket system by scanning the equipment code of the equipment identification system so as to confirm the working condition of the working ticket.
CN201911111656.XA 2019-11-14 2019-11-14 Intelligent power plant management and control system based on Internet of things Active CN110908347B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911111656.XA CN110908347B (en) 2019-11-14 2019-11-14 Intelligent power plant management and control system based on Internet of things

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911111656.XA CN110908347B (en) 2019-11-14 2019-11-14 Intelligent power plant management and control system based on Internet of things

Publications (2)

Publication Number Publication Date
CN110908347A CN110908347A (en) 2020-03-24
CN110908347B true CN110908347B (en) 2022-06-14

Family

ID=69817565

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911111656.XA Active CN110908347B (en) 2019-11-14 2019-11-14 Intelligent power plant management and control system based on Internet of things

Country Status (1)

Country Link
CN (1) CN110908347B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113982851B (en) * 2021-09-30 2024-03-01 国家能源集团新能源技术研究院有限公司 Intelligent wind power system
CN114764641B (en) * 2022-04-29 2023-11-14 中国能源建设集团广东省电力设计研究院有限公司 Two-ticket management method, system, computer equipment and medium based on security verification

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106570641A (en) * 2016-11-07 2017-04-19 成都科曦科技有限公司 Intelligent hotel management system based on Internet of everything
CN207216378U (en) * 2017-08-17 2018-04-10 中国电力工程顾问集团西北电力设计院有限公司 A kind of wisdom plant area of thermal power plant managing and control system of three-dimensional visualization
WO2018139043A1 (en) * 2017-01-30 2018-08-02 株式会社日立製作所 Distribution control system, distribution control method, power-system distribution control system, and power resource control method
CN108762224A (en) * 2018-08-23 2018-11-06 中国电力工程顾问集团西南电力设计院有限公司 A kind of wisdom power plant comprehensive monitoring management system
CN109283897A (en) * 2018-08-23 2019-01-29 中国电力工程顾问集团西南电力设计院有限公司 A kind of wisdom power plant comprehensively monitoring center intelligent monitoring implementation method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106570641A (en) * 2016-11-07 2017-04-19 成都科曦科技有限公司 Intelligent hotel management system based on Internet of everything
WO2018139043A1 (en) * 2017-01-30 2018-08-02 株式会社日立製作所 Distribution control system, distribution control method, power-system distribution control system, and power resource control method
CN207216378U (en) * 2017-08-17 2018-04-10 中国电力工程顾问集团西北电力设计院有限公司 A kind of wisdom plant area of thermal power plant managing and control system of three-dimensional visualization
CN108762224A (en) * 2018-08-23 2018-11-06 中国电力工程顾问集团西南电力设计院有限公司 A kind of wisdom power plant comprehensive monitoring management system
CN109283897A (en) * 2018-08-23 2019-01-29 中国电力工程顾问集团西南电力设计院有限公司 A kind of wisdom power plant comprehensively monitoring center intelligent monitoring implementation method

Also Published As

Publication number Publication date
CN110908347A (en) 2020-03-24

Similar Documents

Publication Publication Date Title
CN111142414B (en) Intelligent power plant management and control system based on edge cloud cooperation
CN113112086B (en) Intelligent production system based on edge calculation and identification analysis
US10860006B2 (en) Device and system including multiple devices for supervision and control of machines in industrial installation
CN109313423B (en) Device for supervising and controlling machines in an industrial installation and system comprising a plurality of devices
KR101768810B1 (en) Wind farm supervision monitoring system
US10313281B2 (en) Delivery of automated notifications by an industrial asset
KR101789923B1 (en) Wind farm supervision monitoring method
CN103283208B (en) Based on the remote real-time monitoring system of cloud computing
US20130211546A1 (en) Smart device for industrial automation
CN201163361Y (en) Control system used for industry assembly line
CN110908347B (en) Intelligent power plant management and control system based on Internet of things
CN105809575A (en) Mobile operation system and method for water and electricity production management
CN203241783U (en) Cathodic protection remote management system
CN102801805A (en) Field data acquisition system and method based on mobile internet technology
CN102404401A (en) WSN (Wireless Sensor Network) based cluster state monitoring system and method
CN108319638B (en) Dangerous goods production and manufacturing execution system applying handheld inspection equipment
CN102880146B (en) Profibus device monitoring and managing system
CN109976270A (en) Municipal sewage treatment cloud management platform
CN111127245A (en) Wisdom power plant wisdom management and control system
CN105956118B (en) A method of realizing real time information quality stamp distribution global data base
CN110888406A (en) Intelligent control implementation method for intelligent power plant
CN112445169A (en) Energy power equipment management system and method based on industrial Internet of things cloud platform
Platenius-Mohr et al. An analysis of use cases for the asset administration shell in the context of edge computing
CN202334597U (en) Cluster state monitoring system based on WSN (Wireless Sensor Network)
CN105467969A (en) Manufacturing execution system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant