CN110878529A - Construction device and construction method for stay cable bridge - Google Patents

Construction device and construction method for stay cable bridge Download PDF

Info

Publication number
CN110878529A
CN110878529A CN201911349035.5A CN201911349035A CN110878529A CN 110878529 A CN110878529 A CN 110878529A CN 201911349035 A CN201911349035 A CN 201911349035A CN 110878529 A CN110878529 A CN 110878529A
Authority
CN
China
Prior art keywords
bridge
construction method
temporary
sections
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911349035.5A
Other languages
Chinese (zh)
Other versions
CN110878529B (en
Inventor
张祥祺
贾宝荣
储慧斌
王子堃
郑祥杰
孙阳
顾伟虬
潘家杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Group Co Ltd filed Critical Shanghai Mechanized Construction Group Co Ltd
Priority to CN201911349035.5A priority Critical patent/CN110878529B/en
Publication of CN110878529A publication Critical patent/CN110878529A/en
Application granted granted Critical
Publication of CN110878529B publication Critical patent/CN110878529B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/04Cable-stayed bridges

Abstract

The invention provides a bridge construction method, which is characterized in that a construction method of 'beam first and cable last' is optimized, and a lower structure of a bridge is constructed while a bridge section is hoisted, so that the bridge construction time is reduced, the bridge construction progress is improved, and the bridge construction closure time is shortened.

Description

Construction device and construction method for stay cable bridge
Technical Field
The invention relates to the technical field of municipal bridge engineering construction, in particular to a bridge construction method.
Background
The bridge is generally a building erected on rivers, lakes and seas to enable vehicles, pedestrians and the like to smoothly pass through, and is also extended to be a building which is erected to span mountain stream, unfavorable geology or meet other traffic needs to enable the bridge to pass through more conveniently in order to adapt to the modern high-speed developed traffic industry. In the bridge construction process, especially in the construction process of a large-span steel structure bridge, the most outstanding contradiction is how to meet the requirements of construction safety, quality and progress on a shipping trunk road with busy traffic and not to influence the normal navigation of the navigation road. In the prior art, the construction of the bridge substructure is generally carried out firstly, the maintenance of the bridge substructure is completed, and then the bridge sections are installed.
Disclosure of Invention
The invention aims to provide a bridge construction method which can reduce the bridge construction time, accelerate the construction progress and further reduce the navigation sealing time of a navigation channel.
In order to achieve the above objects and other related objects, the present invention provides a bridge construction method, comprising the steps of:
s1, constructing the steel pipe pile of the bridge lower structure;
s2, constructing a foundation bearing platform of the bridge lower structure, and erecting at least two temporary supports;
s3, after the temporary support is completely erected, carrying out midspan sectional hoisting on the bridge, wherein the midspan sections are bridge sections except bridge sections at two ends of the outermost side of the bridge;
s4, maintaining the foundation bearing platform of the lower structure of the bridge, and butt-welding the hoisted midspan sections;
and S5, hoisting and welding the rest bridge sections.
Further, the temporary supports comprise temporary supports on shore and temporary supports on water.
Further, the temporary shore support comprises steel box girders for pressure transfer members, steel columns for vertical support, short columns for supporting bridge segments, and angle irons for diagonal support.
Furthermore, a roadbed box for temporary support is arranged between the shore temporary support and the bottom surface.
Further, the temporary support on water includes steel truss struts for vertical support, an operation platform for constructor construction, stairs for constructor to move up and down, and short columns for supporting bridge segments.
Furthermore, a flood prevention wall is arranged between the shore temporary support and the river.
Further, in the step S3, a floating crane ship is used to hoist the midspan section of the bridge.
Furthermore, the bridge cable towers are positioned on bridge sections at two ends of the outermost side of the bridge, and the inclined stay cables are installed after the bridge sections at two ends of the outermost side of the bridge are hoisted.
Further, in the step S3, the midspan section includes at least 3 bridge sections, and the hoisting sequence is performed from the middle of the bridge to both sides of the bridge.
Furthermore, the number of the temporary supports is N, the number of the bridge segments is N +1, and N is more than or equal to 3.
In conclusion, the bridge construction method provided by the invention optimizes the construction method of 'beam first and cable last', and constructs the lower structure of the bridge while hoisting the bridge sections, so that the bridge construction time is reduced, the bridge construction progress is improved, and the bridge construction closure time is shortened.
Drawings
FIG. 1 is a flow chart of a bridge construction method according to an embodiment of the present invention;
FIG. 2 is a structural view of a bridge in the bridge construction method shown in FIG. 1;
FIG. 3 is a side view of an onshore temporary support of the bridge of FIG. 2;
FIG. 4 is an elevation view of an onshore temporary support of the bridge of FIG. 2;
FIG. 5 is a side view of the temporary aquatic support of the bridge of FIG. 2;
FIG. 6 is an elevation view of a temporary underwater support of the bridge of FIG. 2;
the construction method comprises the following steps of 1-a first bridge section, 2-a second bridge section, 3-a third bridge section, 4-a fourth bridge section, 5-a fifth bridge section, 6-stay cables, 7-temporary shore supports, 8-temporary marine supports, 9-flood walls, 10-steel pipe piles, 11-foundation bearing platforms, 12-steel box girders, 13-steel upright columns, 14-angle steels, 15-roadbed boxes, 16-short columns, 17-short columns, 18-operation platforms, 19-stairs and 20-steel truss struts.
Detailed Description
The bridge construction method provided by the invention is further described in detail below with reference to the accompanying drawings and specific embodiments. Advantages and features of the present invention will become apparent from the following description and from the claims. It is to be noted that the drawings are in a very simplified form and are not to precise scale, which is merely for the purpose of facilitating and distinctly claiming the embodiments of the present invention.
In the description of the present invention, it is to be understood that the terms "center", "upper", "lower", "left", "right", and the like indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience in describing the present invention and simplifying the description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention.
As shown in fig. 1, an embodiment of the present invention provides a bridge construction method, including the following steps:
s1, constructing the steel pipe pile of the bridge lower structure;
s2, constructing a foundation bearing platform of the bridge lower structure, and erecting at least two temporary supports;
s3, after the temporary support is completely erected, carrying out midspan sectional hoisting on the bridge, wherein the midspan sections are bridge sections except bridge sections at two ends of the outermost side of the bridge;
s4, maintaining the foundation bearing platform of the lower structure of the bridge, and butt-welding the hoisted midspan sections;
and S5, hoisting and welding the rest bridge sections.
The substructure includes a bridge steel pipe pile and a foundation cap.
The bridge in the embodiment is a semi-self-anchored stayed cable bridge, and the specific structure of the bridge is shown in fig. 2. It can be seen that the bridge construction phase is divided into 5 bridge segments, namely, a first bridge segment 1, a second bridge segment 2, a third bridge segment 3, a fourth bridge segment 4 and a fifth bridge segment 5, wherein the second bridge segment 2, the third bridge segment 3 and the fourth bridge segment 4 are midspan segments, and the first bridge segment 1 and the fifth bridge segment 5 respectively include a pylon. The bridge also includes 4 temporary supports for supporting each bridge segment. Therefore, when the number of the temporary supports is N, the number of the bridge segments is N +1, wherein N is larger than or equal to 3, and constructors can set the number of the bridge segments according to actual requirements.
As can be seen in fig. 2, the temporary supports include an onshore temporary support 7 and an aquatic temporary support 8.
As shown in fig. 3 and 4, the onshore temporary support 7 comprises steel box girders 12 for pressure transfer members, steel columns 13 for vertical support, short columns 16 for supporting bridge segments, and angle irons 14 for diagonal support.
In order to improve the stability of the temporary shore support 7, a roadbed box 15 for temporary support is arranged between the temporary shore support and the bottom surface for pressure diffusion.
As shown in fig. 5 and 6, the marine temporary support 8 includes a steel truss strut 20 for vertical support, an operation platform 18 for construction of a constructor, a staircase 19 for up and down movement of the constructor, and a stub 16 for supporting a bridge segment.
In actual construction, the difficulty of machining the foundation cap 11 of the substructure is great, and the machining period is long, so in construction, after the steel pipe pile 10 is completely constructed in the step S1, the construction of the foundation cap 11 is started until the step S4 is completed, and the construction of the foundation cap 11 can be performed in this period of time, so as to shorten the construction time.
Meanwhile, in order to reduce the influence on the construction of the foundation cap 11, in the step S3, the midspan section includes 3 bridge sections, and the hoisting sequence is performed from the middle of the bridge to two sides of the bridge.
In the construction process, a flood prevention wall 9 is arranged between the shore temporary support 7 and the river to enhance the safety of the shore temporary support 7.
Of course, in the step S3, the floating crane is used to hoist the midspan section of the bridge, and the hoisting sequence is performed from the middle to both sides.
In addition, as the bridge cable tower is positioned on the bridge segments at the two ends of the outermost side of the bridge, after the bridge segments at the two ends of the outermost side of the bridge are hoisted, the stay cables 6 can be installed.
It should be noted that the bridge construction method of the present invention can also be used for ground anchored cable-stayed bridges and self-anchored cable-stayed bridges.
In conclusion, in the bridge construction method, the construction of the substructure and the bridge segment is carried out simultaneously in the construction process, so that the construction time of the bridge is greatly shortened, the construction progress is improved, and the river closure time is reduced.
Finally, it should be noted that the above embodiments are only for illustrating the technical solutions of the present invention and not for limiting, and although the present invention is described in detail with reference to the preferred embodiments, it should be understood by those skilled in the art that modifications or equivalent substitutions may be made on the technical solutions of the present invention without departing from the spirit and scope of the technical solutions of the present invention.

Claims (10)

1. A bridge construction method is characterized by comprising the following steps:
s1, constructing the steel pipe pile of the bridge lower structure;
s2, constructing a foundation bearing platform of the bridge lower structure, and erecting at least two temporary supports;
s3, after the temporary support is completely erected, carrying out midspan sectional hoisting on the bridge, wherein the midspan sections are bridge sections except bridge sections at two ends of the outermost side of the bridge;
s4, maintaining the foundation bearing platform of the lower structure of the bridge, and butt-welding the hoisted midspan sections;
and S5, hoisting and welding the rest bridge sections.
2. The bridge construction method according to claim 1, wherein the temporary supports include an onshore temporary support and an offshore temporary support.
3. The bridge construction method according to claim 2, wherein the onshore temporary support comprises a steel box girder for the pressure transfer member, a steel column for vertical support, a short column for supporting the bridge segment, and an angle iron for diagonal support.
4. The bridge construction method according to claim 2, wherein a roadbed box for temporary support is provided between the shore temporary support and the bottom surface.
5. The bridge construction method of claim 2, wherein the above-water temporary supports include steel truss struts for vertical support, an operation platform for construction of constructors, stairs for the constructors to move up and down, and a short column for supporting bridge segments.
6. The bridge construction method according to claim 1, wherein a flood wall is provided between the onshore temporary support and the river.
7. The bridge construction method according to claim 1, wherein in the step S3, a floating crane is used to hoist the midspan section of the bridge.
8. The bridge construction method according to claim 1, wherein the bridge cable towers are positioned on the bridge segments at the two outermost ends of the bridge, and the stay cables are installed after the bridge segments at the two outermost ends of the bridge are hoisted.
9. The bridge construction method according to claim 1, wherein in the step S3, the midspan section comprises at least 3 bridge sections, and the hoisting sequence is performed from the middle of the bridge to two sides of the bridge.
10. The bridge construction method according to claim 1, wherein the number of the temporary supports is N, the number of the bridge segments is N +1, wherein N is more than or equal to 3.
CN201911349035.5A 2019-12-24 2019-12-24 Construction device and construction method for stay cable bridge Active CN110878529B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911349035.5A CN110878529B (en) 2019-12-24 2019-12-24 Construction device and construction method for stay cable bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911349035.5A CN110878529B (en) 2019-12-24 2019-12-24 Construction device and construction method for stay cable bridge

Publications (2)

Publication Number Publication Date
CN110878529A true CN110878529A (en) 2020-03-13
CN110878529B CN110878529B (en) 2021-11-19

Family

ID=69731140

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911349035.5A Active CN110878529B (en) 2019-12-24 2019-12-24 Construction device and construction method for stay cable bridge

Country Status (1)

Country Link
CN (1) CN110878529B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106012797A (en) * 2016-07-25 2016-10-12 同济大学 All-ground-anchor type single-tower double-span cable-stayed bridge structure and construction method thereof
CN106498837A (en) * 2016-11-02 2017-03-15 西南交通大学 A kind of novel bridge and its construction method
CN207244425U (en) * 2017-06-13 2018-04-17 同济大学 Part earth anchored suspension bridge
CN108978499A (en) * 2018-06-12 2018-12-11 中铁大桥勘测设计院集团有限公司 A kind of oblique pull suspension cable co-operative system bridge erection method
CN110258315A (en) * 2019-04-17 2019-09-20 中国公路工程咨询集团有限公司 Antidetonation bridge and its method of construction across active breaking belt
CN110306442A (en) * 2019-07-23 2019-10-08 安徽省路港工程有限责任公司 A kind of few fulcrum pushing tow is floating to drag method bridge falsework erection method
KR102035492B1 (en) * 2019-03-12 2019-10-23 에스오씨기술지주 주식회사 Semi cable stayed bridge structure
CN209652741U (en) * 2018-10-26 2019-11-19 中铁武汉勘察设计研究院有限公司 Across the rail yard large span overpass of one kind

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106012797A (en) * 2016-07-25 2016-10-12 同济大学 All-ground-anchor type single-tower double-span cable-stayed bridge structure and construction method thereof
CN106498837A (en) * 2016-11-02 2017-03-15 西南交通大学 A kind of novel bridge and its construction method
CN207244425U (en) * 2017-06-13 2018-04-17 同济大学 Part earth anchored suspension bridge
CN108978499A (en) * 2018-06-12 2018-12-11 中铁大桥勘测设计院集团有限公司 A kind of oblique pull suspension cable co-operative system bridge erection method
CN209652741U (en) * 2018-10-26 2019-11-19 中铁武汉勘察设计研究院有限公司 Across the rail yard large span overpass of one kind
KR102035492B1 (en) * 2019-03-12 2019-10-23 에스오씨기술지주 주식회사 Semi cable stayed bridge structure
CN110258315A (en) * 2019-04-17 2019-09-20 中国公路工程咨询集团有限公司 Antidetonation bridge and its method of construction across active breaking belt
CN110306442A (en) * 2019-07-23 2019-10-08 安徽省路港工程有限责任公司 A kind of few fulcrum pushing tow is floating to drag method bridge falsework erection method

Also Published As

Publication number Publication date
CN110878529B (en) 2021-11-19

Similar Documents

Publication Publication Date Title
Mangus et al. Orthotopic Deck Bridges
CN101418543A (en) Self-anchored rope-suspension bridge inclined drawing construction method
Troitsky Planning and design of bridges
CN112342917A (en) Combined construction method for pushing beam first and then lifting arch of large-span tied arch bridge
Chen et al. Construction and maintenance
WO1985004437A1 (en) Offshore multi-stay platform structure
CN110878529B (en) Construction device and construction method for stay cable bridge
CN113802461B (en) Steel box girder erection method
CN115748413A (en) Continuous steel truss web-plate truss double-layer combined swivel bridge structure
CN112523097A (en) Large-span bridge gantry crane and construction method thereof
CN211340438U (en) Steel bridge pushing and pulling system in navigation water area
CN214401420U (en) Construction structure of large-span tied arch bridge
Brown et al. Peace Bridge, Londonderry: design and construction
Han et al. Bridging the Hudson
Gimsing Construction Technology of Long Span Bridges
CN209779429U (en) Landscape walking bridge applying cable tower structure
Jakobsen et al. Concept development of a Sognefjord floating bridge crossing
Xiang et al. 70 Years of China’s Bridges
Bakhoum -Bridge Engineering in Egypt
Radić et al. Bridge Engineering in Croatia
Valenchon Offshore Application of High Performance Concrete Space Frame
Xiang et al. Making Technological Breakthrough and Becoming a World Power in Bridge Technology
Xiang et al. Rapidly Developing and Becoming a World Power in the Number of Bridges
MARKELJ ДГКМ MASE
Zhai Introduction to Bridge Construction in a Mountainous City

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant