CN110872813A - Precast concrete guardrail connecting structure and assembling method - Google Patents

Precast concrete guardrail connecting structure and assembling method Download PDF

Info

Publication number
CN110872813A
CN110872813A CN201911321889.2A CN201911321889A CN110872813A CN 110872813 A CN110872813 A CN 110872813A CN 201911321889 A CN201911321889 A CN 201911321889A CN 110872813 A CN110872813 A CN 110872813A
Authority
CN
China
Prior art keywords
guardrail
flange plate
precast concrete
concrete guardrail
reserved
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911321889.2A
Other languages
Chinese (zh)
Inventor
姚晓飞
霍龙飞
贾伟红
来猛刚
李刚
姚文奇
李超
刘浩
孙文杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Consultants Co Ltd
Original Assignee
CCCC First Highway Consultants Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Consultants Co Ltd filed Critical CCCC First Highway Consultants Co Ltd
Priority to CN201911321889.2A priority Critical patent/CN110872813A/en
Publication of CN110872813A publication Critical patent/CN110872813A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • E01D19/103Parapets, railings ; Guard barriers or road-bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

本发明涉及预制混凝土护栏连接构造及拼装方法,所述连接构造包括主梁翼缘板及其横向外侧竖直的预制混凝土护栏;主梁翼缘板端部分别设置有主梁翼缘板内侧预留短钢筋和主梁翼缘板外侧预留长钢筋,竖向伸出主梁翼缘板表面;预制混凝土护栏的内侧面设置有预埋钢板,与主梁翼缘板内侧预留短钢筋焊接固定;预制混凝土护栏外侧设置有竖向的护栏预留锚固孔道,主梁翼缘板外侧预留长钢筋插入护栏预留锚固孔道并通过灌浆实现固定。本发明中,采用焊接基础钢筋+锚栓连接,操作简单,连接方便快捷,连接容差大。且其受力性能较好,吊装、运输方便,耐久性好,施工风险小,适用性强。由于预制节段两端设有加劲段,可直接用传力杆连接,且操作简单,易于实现。

Figure 201911321889

The invention relates to a prefabricated concrete guardrail connection structure and an assembling method. The connection structure comprises a main girder flange plate and a vertical prefabricated concrete guardrail on the lateral outer side thereof; the ends of the main girder flange plate are respectively provided with short steel bars reserved inside the main girder flange plate and a main girder flange. Long steel bars are reserved on the outside of the plate, which extend vertically from the surface of the main girder flange plate; the inner side of the prefabricated concrete guardrail is provided with a pre-embedded steel plate, which is welded and fixed with the short steel bars reserved on the inner side of the main beam flange plate; the outside of the prefabricated concrete guardrail is provided with a vertical guardrail Anchoring holes are reserved, and long steel bars are reserved on the outside of the main girder flange plate and inserted into the guardrail to reserve anchoring holes and fix them by grouting. In the present invention, the welded basic steel bar and the anchor bolt are used for connection, the operation is simple, the connection is convenient and fast, and the connection tolerance is large. And its mechanical performance is good, hoisting, transportation is convenient, durability is good, construction risk is small, and applicability is strong. Since the two ends of the prefabricated segment are provided with stiffening segments, they can be directly connected with dowel rods, and the operation is simple and easy to implement.

Figure 201911321889

Description

预制混凝土护栏连接构造及拼装方法Precast concrete guardrail connection structure and assembly method

技术领域technical field

本发明涉及预制混凝土护栏技术领域,具体涉及一种预制混凝土护栏连接构造及拼装方法。The invention relates to the technical field of prefabricated concrete guardrails, in particular to a connection structure and an assembling method of a prefabricated concrete guardrail.

背景技术Background technique

预制装配式护栏具有工厂化制造、标准化施工、快速化安装等传统施工工艺不可比拟的优势,可有效解决施工中对交通、环境、施工周期等的要求。采用装配式防撞护栏具有以下优势:①工厂化预制,有比较稳定的作业人员和配套的加工设备,受外界干扰因素小,加工精度和外观质量明显提高;②将大量高噪声、高污染、高风险的“湿作业”搬到工厂中进行,减少建筑垃圾80%,更大大减少了现场浇捣施工对周边噪音、粉尘等影响;③现浇需要3~5天的时间,预制拼装施工1天即可完,更将大部分的工作转移至工厂,大大减少作业人员现场高空作业风险;④预制防撞墙可将路灯管线、灯杆预埋件、栏杆预埋件,通信管线、电箱等埋设其中,提高质量和精度,缩短工期。Prefabricated guardrails have the incomparable advantages of traditional construction techniques such as factory manufacturing, standardized construction, and rapid installation, which can effectively solve the requirements for traffic, environment, and construction period during construction. The use of prefabricated anti-collision guardrails has the following advantages: ① factory prefabricated, with relatively stable operators and supporting processing equipment, less external interference factors, and significantly improved processing accuracy and appearance quality; ② a large number of high-noise, high-pollution, High-risk "wet operations" are moved to the factory, reducing construction waste by 80%, and greatly reducing the impact of on-site pouring and tamping on surrounding noise and dust; ③ It takes 3 to 5 days for in-situ pouring, and prefabricated assembly construction 1 It can be completed in a day, and most of the work is transferred to the factory, which greatly reduces the risk of operators working at heights on site; ④The prefabricated anti-collision wall can be used for street lamp pipelines, lamp pole embedded parts, railing embedded parts, communication pipelines, electrical boxes. It can be buried in it to improve the quality and accuracy and shorten the construction period.

发明内容SUMMARY OF THE INVENTION

本发明的目的是提供一种预制混凝土护栏连接构造及拼装方法,降低施工风险,加快施工效率。The purpose of the present invention is to provide a connection structure and an assembling method of a prefabricated concrete guardrail, which can reduce the construction risk and speed up the construction efficiency.

本发明所采用的技术方案为:The technical scheme adopted in the present invention is:

预制混凝土护栏连接构造,其特征在于:The connection structure of precast concrete guardrail is characterized by:

所述连接构造包括主梁翼缘板及其横向外侧竖直的预制混凝土护栏;The connecting structure includes a main girder flange plate and its laterally outer vertical precast concrete guardrail;

主梁翼缘板端部分别设置有主梁翼缘板内侧预留短钢筋和主梁翼缘板外侧预留长钢筋,竖向伸出主梁翼缘板表面;The ends of the main beam flange plates are respectively provided with short steel bars reserved on the inner side of the main beam flange plates and long steel bars reserved on the outside of the main beam flange plates, which extend vertically from the surface of the main beam flange plates;

预制混凝土护栏的内侧面设置有预埋钢板,与主梁翼缘板内侧预留短钢筋焊接固定;预制混凝土护栏外侧设置有竖向的护栏预留锚固孔道,主梁翼缘板外侧预留长钢筋插入护栏预留锚固孔道并通过灌浆实现固定。The inner side of the precast concrete guardrail is provided with a pre-embedded steel plate, which is welded and fixed with the short steel bars reserved on the inner side of the main girder flange plate; the outer side of the precast concrete guardrail is provided with a vertical guardrail reserved for anchoring holes, and the long steel bars reserved on the outer side of the main beam flange plate are inserted into the guardrail. Anchoring holes are left and fixed by grouting.

预制混凝土护栏内设置有钢板锚固钢筋,预埋钢板焊接于钢板锚固钢筋并被锚于预制混凝土护栏内部。A steel plate anchoring steel bar is arranged in the precast concrete guardrail, and the embedded steel plate is welded to the steel plate anchoring steel bar and anchored inside the precast concrete guardrail.

主梁翼缘板上方设置桥面板,桥面板外端与预制混凝土护栏的内侧面之间留有纵向的间隙,浇筑混凝土形成后浇带。A bridge deck is arranged above the flange plate of the main girder, and a longitudinal gap is left between the outer end of the bridge deck and the inner side of the precast concrete guardrail, and the concrete is poured to form a post-pouring zone.

预制混凝土护栏纵向分节段预制,每一节段包括纵向两端的加劲部和中间的标准部;标准部设置有纵向的花槽;加劲部开设有减重孔。The prefabricated concrete guardrail is prefabricated in longitudinal sections, and each section includes stiffening parts at both ends of the longitudinal direction and a standard part in the middle; the standard part is provided with a longitudinal flower groove; the stiffening part is provided with a weight reduction hole.

预制混凝土护栏每一节段的加劲部均设置有纵向开孔,相邻节段之间通过开孔位置设置的传力杆实现纵向连接;The stiffening part of each segment of the precast concrete guardrail is provided with longitudinal openings, and the longitudinal connection between adjacent segments is realized by dowel rods arranged at the opening positions;

传力杆为不锈钢螺杆,端部通过螺母固定。The dowel rod is a stainless steel screw, and the end is fixed by a nut.

预制混凝土护栏底面外侧设置有向下延伸的限位部,限位部内侧面紧靠主梁翼缘板的外端面。The outer side of the bottom surface of the precast concrete guardrail is provided with a limiting portion extending downward, and the inner side surface of the limiting portion is close to the outer end face of the flange plate of the main beam.

预制混凝土护栏底面与主梁翼缘板表面之间设置有砂浆垫层。A mortar cushion is arranged between the bottom surface of the precast concrete guardrail and the surface of the main beam flange plate.

护栏预留锚固孔道内壁设置有波纹管。A corrugated pipe is arranged on the inner wall of the anchoring hole reserved for the guardrail.

预制混凝土护栏连接构造的拼装方法,其特征在于:The assembling method of the connection structure of the precast concrete guardrail is characterized in that:

所述方法包括以下步骤:The method includes the following steps:

步骤一:分节段预制混凝土护栏,在预制混凝土护栏外侧预设竖向的护栏预留锚固孔道,内侧面预设预埋钢板;Step 1: Precast concrete guardrails in sections, preset vertical guardrails on the outside of the precast concrete guardrail to reserve anchoring holes, and preset pre-embedded steel plates on the inner side;

步骤二:在主梁翼缘板端部分别预设主梁翼缘板内侧预留短钢筋和主梁翼缘板外侧预留长钢筋,竖向伸出主梁翼缘板表面;Step 2: Preset the short steel bars on the inner side of the main girder flange plate and the long steel bars on the outside of the main girder flange plate at the end of the main girder flange plate respectively, and extend vertically from the surface of the main girder flange plate;

步骤三:将预制混凝土护栏吊装至主梁翼缘板端部,主梁翼缘板内侧预留短钢筋与预埋钢板双面焊接,主梁翼缘板外侧预留长钢筋插入护栏预留锚固孔道并灌注浆料锚固于护栏内;Step 3: Hoist the prefabricated concrete guardrail to the end of the main girder flange plate. The short steel bars reserved on the inner side of the main girder flange plate and the embedded steel plate are welded on both sides, and the long steel bars reserved on the outside of the main girder flange plate are inserted into the reserved anchoring holes of the guardrail and poured into the slurry for anchoring. in the guardrail;

步骤四:施工下一节段预制混凝土护栏,节段间采用传力杆连接;Step 4: construct the next segment of precast concrete guardrail, and use dowel rods to connect the segments;

步骤五:主梁翼缘板上方的桥面板外端与预制混凝土护栏的内侧面之间留有纵向的间隙,浇筑混凝土形成后浇带。Step 5: There is a longitudinal gap between the outer end of the bridge deck above the main girder flange plate and the inner side of the precast concrete guardrail, and the concrete is poured to form a post-pouring belt.

本发明具有以下优点:The present invention has the following advantages:

本发明中,采用焊接基础钢筋+锚栓连接,操作简单,连接方便快捷,连接容差大。且其受力性能较好,吊装、运输方便,耐久性好,施工风险小,适用性强。由于预制节段两端设有加劲段,可直接用传力杆连接,且操作简单,易于实现。In the present invention, the welded basic steel bar and the anchor bolt are used for connection, the operation is simple, the connection is convenient and fast, and the connection tolerance is large. And its mechanical performance is good, hoisting, transportation is convenient, durability is good, construction risk is small, and applicability is strong. Since the two ends of the prefabricated segment are provided with stiffening segments, they can be directly connected with dowel rods, and the operation is simple and easy to implement.

附图说明Description of drawings

图1为标准部连接构造结构图。FIG. 1 is a structural diagram of the connection structure of the standard part.

图2为加劲部连接构造结构图。FIG. 2 is a structural diagram of the connection structure of the stiffener.

图3为A-A局部大样示意图。Figure 3 is a schematic diagram of a partial large sample of A-A.

图4为连接构造立面图。Figure 4 is an elevation view of the connection structure.

图中:1—主梁翼缘板;2—预制混凝土护栏;3—后浇带;4—主梁翼缘板内侧预留短钢筋;5—主梁翼缘板外侧预留长钢筋;6—预埋钢板;7—钢板锚固钢筋;8—护栏预留锚固孔道;9—桥面板;10—传力杆。In the figure: 1—main girder flange plate; 2—precast concrete guardrail; 3—post-casting belt; 4—reserved short steel bars on the inner side of the main beam flange plate; 5—reserved long steel bars on the outside of the main beam flange plate; 6—pre-embedded steel plate; 7 - Steel plate anchoring steel bar; 8 - reserved anchoring channel for guardrail; 9 - bridge deck; 10 - dowel rod.

具体实施方式Detailed ways

下面结合具体实施方式对本发明进行详细的说明。The present invention will be described in detail below with reference to specific embodiments.

本发明涉及一种预制混凝土护栏连接构造,所述连接构造包括主梁翼缘板1及其横向外侧竖直的预制混凝土护栏2;主梁翼缘板1端部分别设置有主梁翼缘板内侧预留短钢筋4和主梁翼缘板外侧预留长钢筋3,竖向伸出主梁翼缘板1表面;预制混凝土护栏2的内侧面设置有预埋钢板6,与主梁翼缘板内侧预留短钢筋4焊接固定;预制混凝土护栏2外侧设置有竖向的护栏预留锚固孔道8,主梁翼缘板外侧预留长钢筋3插入护栏预留锚固孔道8并通过灌浆实现固定,护栏预留锚固孔道8内壁设置有波纹管。The invention relates to a prefabricated concrete guardrail connection structure. The connection structure includes a main girder flange plate 1 and a vertical prefabricated concrete fence 2 on the lateral outer side thereof; the ends of the main girder flange plate 1 are respectively provided with short steel bars 4 reserved on the inner side of the main girder flange plate. Long steel bars 3 are reserved on the outside of the girder flange plate and the main girder flange plate, which extends vertically from the surface of the main girder flange plate 1; the inner side of the precast concrete guardrail 2 is provided with a pre-embedded steel plate 6, which is welded and fixed with the short steel bars 4 reserved on the inside of the main girder flange plate; precast concrete The outer side of the guardrail 2 is provided with a vertical guardrail reserved anchoring hole 8, the long steel bar 3 reserved on the outer side of the main girder flange plate is inserted into the guardrail reserved anchoring hole 8 and fixed by grouting, and the inner wall of the guardrail reserved anchoring hole 8 is provided with a corrugated pipe.

预制混凝土护栏2内设置有钢板锚固钢筋7,预埋钢板6焊接于钢板锚固钢筋7并被锚于预制混凝土护栏2内部。A steel plate anchoring steel bar 7 is arranged in the precast concrete guardrail 2 , and the embedded steel plate 6 is welded to the steel plate anchoring steel bar 7 and is anchored inside the precast concrete guardrail 2 .

主梁翼缘板1上方设置桥面板9,桥面板9外端与预制混凝土护栏2的内侧面之间留有纵向的间隙,浇筑混凝土形成后浇带3。A bridge deck 9 is arranged above the main girder flange plate 1 , and a longitudinal gap is left between the outer end of the bridge deck 9 and the inner side of the precast concrete guardrail 2 , and the post-casting belt 3 is formed by pouring concrete.

预制混凝土护栏2纵向分节段预制,每一节段包括纵向两端的加劲部和中间的标准部;标准部设置有纵向的花槽;加劲部开设有减重孔。预制混凝土护栏2每一节段的加劲部均设置有纵向开孔,相邻节段之间通过开孔位置设置的传力杆10实现纵向连接;传力杆10为不锈钢螺杆,端部通过螺母固定。The prefabricated concrete guardrail 2 is prefabricated in longitudinal sections, and each section includes stiffening parts at both ends of the longitudinal direction and a standard part in the middle; the standard part is provided with a longitudinal flower groove; the stiffening part is provided with a weight reduction hole. The stiffening part of each segment of the prefabricated concrete guardrail 2 is provided with longitudinal openings, and the longitudinal connection between adjacent segments is realized by dowel bars 10 arranged at the opening positions; the dowel bars 10 are stainless steel screws, and the ends are connected by nuts fixed.

预制混凝土护栏2底面外侧设置有向下延伸的限位部,限位部内侧面紧靠主梁翼缘板1的外端面。The outer side of the bottom surface of the precast concrete guardrail 2 is provided with a limiting portion extending downward, and the inner side surface of the limiting portion is close to the outer end surface of the main beam flange plate 1 .

预制混凝土护栏2底面与主梁翼缘板1表面之间设置有砂浆垫层。A mortar cushion is arranged between the bottom surface of the precast concrete guardrail 2 and the surface of the main beam flange plate 1 .

上述预制混凝土护栏连接构造的拼装方法,包括以下步骤:The assembling method of the above-mentioned precast concrete guardrail connection structure includes the following steps:

步骤一:分节段预制混凝土护栏2,在预制混凝土护栏2外侧预设竖向的护栏预留锚固孔道8,内侧面预设预埋钢板6;Step 1: prefabricating the concrete guardrail 2 in sections, prefabricating a vertical guardrail on the outer side of the prefabricated concrete guardrail 2 to reserve anchoring holes 8, and prefabricating a pre-embedded steel plate 6 on the inner side;

步骤二:在主梁翼缘板1端部分别预设主梁翼缘板内侧预留短钢筋4和主梁翼缘板外侧预留长钢筋3,竖向伸出主梁翼缘板1表面;Step 2: Presetting the short steel bars 4 on the inner side of the main beam flange plate 1 and the long steel bars 3 on the outside of the main beam flange plate, respectively, at the end of the main beam flange plate 1, and extending vertically from the surface of the main beam flange plate 1;

步骤三:将预制混凝土护栏2吊装至主梁翼缘板1端部,主梁翼缘板内侧预留短钢筋4与预埋钢板6双面焊接,主梁翼缘板外侧预留长钢筋3插入护栏预留锚固孔道8并灌注浆料锚固于护栏内;Step 3: Hoist the precast concrete guardrail 2 to the end of the main girder flange plate 1, the short steel bars 4 reserved on the inner side of the main girder flange plate and the embedded steel plates 6 are welded on both sides, and the long steel bars 3 reserved on the outside of the main girder flange plate are inserted into the guardrail to reserve anchoring holes 8 and pour slurry to anchor in the guardrail;

步骤四:施工下一节段预制混凝土护栏2,节段间采用传力杆10连接;Step 4: construct the next segment of precast concrete guardrail 2, and use dowel rods 10 to connect the segments;

步骤五:主梁翼缘板1上方的桥面板9外端与预制混凝土护栏2的内侧面之间留有纵向的间隙,浇筑混凝土形成后浇带3。Step 5: There is a longitudinal gap between the outer end of the bridge deck 9 above the main girder flange plate 1 and the inner side of the precast concrete guardrail 2, and the post-casting belt 3 is formed by pouring concrete.

如图所示,本发明的结构包括至少一节段预制混凝土护栏、主梁翼缘板。该预制护栏通过桥面板预留的竖向主筋与护栏内侧底部的预埋钢板间焊接;以及采用灌浆的方法,使得主梁翼缘板预留钢筋锚固于护栏预留孔道内,实现预制护栏与桥面板间的连接;预制节段两端设有加劲段。As shown, the structure of the present invention includes at least one segment of a precast concrete guardrail and a main beam flange plate. The prefabricated guardrail is welded between the vertical main bars reserved for the bridge deck and the embedded steel plates at the inner bottom of the guardrail; and the method of grouting is used to make the steel bars reserved for the main girder flange plate anchored in the reserved holes of the guardrail to realize the prefabricated guardrail and the bridge deck. The connection between the prefabricated segments is provided with stiffening segments at both ends.

护栏预制施工时,在护栏预制块底部预埋钢板及锚固孔道;主梁预制施工时,在主梁翼缘板对应位置预埋钢筋;桥面板施工时,在靠护栏处预留20~25cm的预留后浇带;预制节段间采用传力杆连接。During the prefabrication of the guardrail, the steel plate and the anchoring tunnel shall be pre-buried at the bottom of the guardrail prefabricated block; during the prefabrication of the main girder, the steel bars shall be pre-embedded at the corresponding position of the flange plate of the main girder; during the construction of the bridge deck, a reserve of 20-25 cm shall be reserved near the guardrail. Post-casting belt; Dowel rods are used to connect the prefabricated segments.

本发明的施工流程为:The construction process of the present invention is:

1)护栏工厂预制1) Guardrail factory prefabricated

护栏预制时,预留主梁锚固钢筋穿过的孔道和约主梁锚固钢筋焊接的锚固钢板;When the guardrail is prefabricated, reserve the channel through which the main beam anchoring steel bar passes and the anchoring steel plate welded with the main beam anchoring steel bar;

2)预制护栏构件堆放、吊装与运输2) Stacking, hoisting and transportation of prefabricated guardrail components

预制护栏构件应按照其刚度及受力情况制定对应的堆放方案,竖放时应考虑必要的支护措施。The prefabricated guardrail members should formulate a corresponding stacking plan according to their rigidity and stress conditions, and the necessary support measures should be considered when they are erected.

3)预制护栏的吊装定位3) Hoisting and positioning of prefabricated guardrails

预制护栏的吊装采用可根据起吊护栏重量选用汽车吊或架桥机机等起吊工具;护栏起吊时应平稳缓慢,严禁磕碰等发生;在护栏节段吊装就位后,应通过临时稳固措施及节段间的连接措施对护栏进行定位固定,以保证护栏的稳定性。The lifting tools of the prefabricated guardrail can be selected according to the weight of the lifting guardrail, such as a truck crane or a bridge erecting machine; the guardrail should be hoisted steadily and slowly, and bumping is strictly prohibited; The connection measures between the sections are used to position and fix the guardrail to ensure the stability of the guardrail.

4)预制护栏与主梁的现场拼装4) Field assembly of prefabricated guardrail and main beam

对预制护栏底部和主梁翼缘板处的拼接面进行粗糙处理,并用洁净水浸润后,铺设20mm厚的TGM60砂浆垫层;对护栏预埋钢板和主梁翼缘板预留钢筋进行除锈处理;将预制护栏吊装就位,将主梁内侧预留钢筋与护栏预埋钢板进行双面焊接,主梁外侧预留钢筋穿过预留金属波纹管孔道,并灌注高强无收缩水泥灌浆料锚固于护栏内;焊接桥面钢筋网与护栏预埋钢板外侧面,随后浇筑自密实微膨胀混凝土,完成预制护栏与主梁的拼接施工;按上述流程依次施工下一节段预制护栏,护栏节段间采用M27不锈钢螺杆连接。Roughly treat the splicing surface at the bottom of the prefabricated guardrail and the flange plate of the main girder, and after soaking with clean water, lay a 20mm thick TGM60 mortar cushion; perform rust removal treatment on the embedded steel plate of the guardrail and the steel bars reserved for the flange plate of the main girder; The guardrail is hoisted into place, the steel bars reserved on the inner side of the main girder and the steel plates embedded in the guardrail are welded on both sides, the steel bars reserved on the outside of the main girder pass through the reserved metal bellows channel, and high-strength non-shrinkage cement grouting material is poured to anchor in the guardrail; Weld the steel mesh of the bridge deck and the outer side of the embedded steel plate of the guardrail, and then pour the self-compacting micro-expanded concrete to complete the splicing construction of the prefabricated guardrail and the main beam; construct the next section of the prefabricated guardrail in sequence according to the above process, and use M27 stainless steel between the guardrail sections. Screw connection.

本发明的内容不限于实施例所列举,本领域普通技术人员通过阅读本发明说明书而对本发明技术方案采取的任何等效的变换,均为本发明的权利要求所涵盖。The content of the present invention is not limited to those listed in the embodiments, and any equivalent transformations taken by those of ordinary skill in the art to the technical solutions of the present invention by reading the description of the present invention are covered by the claims of the present invention.

Claims (9)

1.预制混凝土护栏连接构造,其特征在于:1. The connection structure of the precast concrete guardrail is characterized in that: 所述连接构造包括主梁翼缘板(1)及其横向外侧竖直的预制混凝土护栏(2);The connection structure comprises a main girder flange plate (1) and its laterally outer vertical precast concrete guardrail (2); 主梁翼缘板(1)端部分别设置有主梁翼缘板内侧预留短钢筋(4)和主梁翼缘板外侧预留长钢筋(3),竖向伸出主梁翼缘板(1)表面;The ends of the main beam flange plate (1) are respectively provided with short steel bars (4) reserved on the inner side of the main beam flange plate and long steel bars (3) reserved on the outside of the main beam flange plate, extending vertically from the surface of the main beam flange plate (1); 预制混凝土护栏(2)的内侧面设置有预埋钢板(6),与主梁翼缘板内侧预留短钢筋(4)焊接固定;预制混凝土护栏(2)外侧设置有竖向的护栏预留锚固孔道(8),主梁翼缘板外侧预留长钢筋(3)插入护栏预留锚固孔道(8)并通过灌浆实现固定。The inner side of the precast concrete guardrail (2) is provided with a pre-embedded steel plate (6), which is welded and fixed with the reserved short steel bars (4) on the inner side of the main girder flange plate; the outer side of the precast concrete guardrail (2) is provided with a vertical guardrail reserved for anchoring holes (8), long steel bars (3) are reserved on the outside of the flange plate of the main girder and are inserted into the reserved anchoring holes (8) of the guardrail and fixed by grouting. 2.根据权利要求1所述的预制混凝土护栏连接构造,其特征在于:2. The precast concrete guardrail connection structure according to claim 1, wherein: 预制混凝土护栏(2)内设置有钢板锚固钢筋(7),预埋钢板(6)焊接于钢板锚固钢筋(7)并被锚于预制混凝土护栏(2)内部。A steel plate anchoring steel bar (7) is arranged in the precast concrete guardrail (2), and the embedded steel plate (6) is welded to the steel plate anchoring steel bar (7) and is anchored inside the precast concrete guardrail (2). 3.根据权利要求2所述的预制混凝土护栏连接构造,其特征在于:3. The precast concrete guardrail connection structure according to claim 2, wherein: 主梁翼缘板(1)上方设置桥面板(9),桥面板(9)外端与预制混凝土护栏(2)的内侧面之间留有纵向的间隙,浇筑混凝土形成后浇带(3)。A bridge deck (9) is arranged above the main girder flange plate (1), a longitudinal gap is left between the outer end of the bridge deck (9) and the inner side of the precast concrete guardrail (2), and the concrete is poured to form a post-pouring belt (3). 4.根据权利要求3所述的预制混凝土护栏连接构造,其特征在于:4. The precast concrete guardrail connection structure according to claim 3, wherein: 预制混凝土护栏(2)纵向分节段预制,每一节段包括纵向两端的加劲部和中间的标准部;标准部设置有纵向的花槽;加劲部开设有减重孔。The prefabricated concrete guardrail (2) is prefabricated longitudinally in segments, each segment includes stiffening parts at both ends of the longitudinal direction and a standard part in the middle; the standard part is provided with a longitudinal flower groove; the stiffening part is provided with a weight reduction hole. 5.根据权利要求4所述的预制混凝土护栏连接构造,其特征在于:5. The precast concrete guardrail connection structure according to claim 4, wherein: 预制混凝土护栏(2)每一节段的加劲部均设置有纵向开孔,相邻节段之间通过开孔位置设置的传力杆(10)实现纵向连接;The stiffening part of each segment of the precast concrete guardrail (2) is provided with longitudinal openings, and the longitudinal connection between adjacent segments is realized by dowel rods (10) arranged at the opening positions; 传力杆(10)为不锈钢螺杆,端部通过螺母固定。The dowel rod (10) is a stainless steel screw, and the end is fixed by a nut. 6.根据权利要求5所述的预制混凝土护栏连接构造,其特征在于:6. The precast concrete guardrail connection structure according to claim 5, wherein: 预制混凝土护栏(2)底面外侧设置有向下延伸的限位部,限位部内侧面紧靠主梁翼缘板(1)的外端面。A limit portion extending downward is provided on the outer side of the bottom surface of the precast concrete guardrail (2), and the inner side surface of the limit portion abuts against the outer end face of the main beam flange plate (1). 7.根据权利要求6所述的预制混凝土护栏连接构造,其特征在于:7. The precast concrete guardrail connection structure according to claim 6, wherein: 预制混凝土护栏(2)底面与主梁翼缘板(1)表面之间设置有砂浆垫层。A mortar cushion is arranged between the bottom surface of the precast concrete guardrail (2) and the surface of the main beam flange plate (1). 8.根据权利要求7所述的预制混凝土护栏连接构造,其特征在于:8. The precast concrete guardrail connection structure according to claim 7, wherein: 护栏预留锚固孔道(8)内壁设置有波纹管。A corrugated pipe is arranged on the inner wall of the anchoring hole (8) reserved for the guardrail. 9.预制混凝土护栏连接构造的拼装方法,其特征在于:9. The assembling method of the connection structure of the precast concrete guardrail is characterized in that: 所述方法包括以下步骤:The method includes the following steps: 步骤一:分节段预制混凝土护栏(2),在预制混凝土护栏(2)外侧预设竖向的护栏预留锚固孔道(8),内侧面预设预埋钢板(6);Step 1: prefabricating the concrete guardrail (2) in sections, prefabricating a vertical guardrail on the outer side of the prefabricated concrete guardrail (2) to reserve anchoring holes (8), and prefabricating a pre-embedded steel plate (6) on the inner side; 步骤二:在主梁翼缘板(1)端部分别预设主梁翼缘板内侧预留短钢筋(4)和主梁翼缘板外侧预留长钢筋(3),竖向伸出主梁翼缘板(1)表面;Step 2: Preset the short steel bars (4) on the inner side of the main beam flange plate (4) and the long steel bars (3) on the outside of the main beam flange plate at the end of the main beam flange plate (1) respectively, and extend vertically from the surface of the main beam flange plate (1). ; 步骤三:将预制混凝土护栏(2)吊装至主梁翼缘板(1)端部,主梁翼缘板内侧预留短钢筋(4)与预埋钢板(6)双面焊接,主梁翼缘板外侧预留长钢筋(3)插入护栏预留锚固孔道(8)并灌注浆料锚固于护栏内;Step 3: Hoist the precast concrete guardrail (2) to the end of the main girder flange plate (1), reserve short steel bars (4) on the inner side of the main girder flange plate and weld the embedded steel plate (6) on both sides, and reserve a long length on the outside of the main girder flange plate. Reinforcing bars (3) are inserted into the guardrail to reserve anchoring holes (8), and the grout is poured into the guardrail for anchoring; 步骤四:施工下一节段预制混凝土护栏(2),节段间采用传力杆(10)连接;Step 4: construct the next segment of the precast concrete guardrail (2), and connect the segments with dowel rods (10); 步骤五:主梁翼缘板(1)上方的桥面板(9)外端与预制混凝土护栏(2)的内侧面之间留有纵向的间隙,浇筑混凝土形成后浇带(3)。Step 5: A longitudinal gap is left between the outer end of the bridge deck (9) above the main girder flange plate (1) and the inner side of the precast concrete guardrail (2), and concrete is poured to form a post-pouring belt (3).
CN201911321889.2A 2019-12-20 2019-12-20 Precast concrete guardrail connecting structure and assembling method Pending CN110872813A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911321889.2A CN110872813A (en) 2019-12-20 2019-12-20 Precast concrete guardrail connecting structure and assembling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911321889.2A CN110872813A (en) 2019-12-20 2019-12-20 Precast concrete guardrail connecting structure and assembling method

Publications (1)

Publication Number Publication Date
CN110872813A true CN110872813A (en) 2020-03-10

Family

ID=69717578

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911321889.2A Pending CN110872813A (en) 2019-12-20 2019-12-20 Precast concrete guardrail connecting structure and assembling method

Country Status (1)

Country Link
CN (1) CN110872813A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111395160A (en) * 2020-03-12 2020-07-10 广东省交通规划设计研究院股份有限公司 Rapid construction method for bridge guardrail with flower bed and prefabricated external flower bed
CN113737651A (en) * 2021-07-30 2021-12-03 中铁十九局集团第五工程有限公司 Assembled anti-collision guardrail and mounting method thereof
CN114427193A (en) * 2022-03-11 2022-05-03 湖南大学 Anchored UHPC curved anti-collision guardrail for bridge in splash zone and construction method thereof
CN116356683A (en) * 2023-04-10 2023-06-30 山东高速股份有限公司 Guardrail construction method and modularized UHPC bridge guardrail

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013036206A (en) * 2011-08-05 2013-02-21 Dc Co Ltd Structure for joining precast barrier curbs to each other
CN107489098A (en) * 2017-07-06 2017-12-19 浙江交工宏途交通建设有限公司 Concrete prefabricated solder type guardrail and construction method of installation
CN107587422A (en) * 2016-07-07 2018-01-16 上海公路桥梁(集团)有限公司 Precast splice type anti-collision wall and its manufacture method
CN207944338U (en) * 2018-02-08 2018-10-09 贵州省绿筑科建住宅产业化发展有限公司 A kind of assembly concrete anticollision barrier and its connection structure
CN110205931A (en) * 2019-07-03 2019-09-06 广州市市政工程机械施工有限公司 A kind of prefabricated assembled Collison fence for bridge
CN211596396U (en) * 2019-12-20 2020-09-29 中交第一公路勘察设计研究院有限公司 Precast concrete guardrail connection structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013036206A (en) * 2011-08-05 2013-02-21 Dc Co Ltd Structure for joining precast barrier curbs to each other
CN107587422A (en) * 2016-07-07 2018-01-16 上海公路桥梁(集团)有限公司 Precast splice type anti-collision wall and its manufacture method
CN107489098A (en) * 2017-07-06 2017-12-19 浙江交工宏途交通建设有限公司 Concrete prefabricated solder type guardrail and construction method of installation
CN207944338U (en) * 2018-02-08 2018-10-09 贵州省绿筑科建住宅产业化发展有限公司 A kind of assembly concrete anticollision barrier and its connection structure
CN110205931A (en) * 2019-07-03 2019-09-06 广州市市政工程机械施工有限公司 A kind of prefabricated assembled Collison fence for bridge
CN211596396U (en) * 2019-12-20 2020-09-29 中交第一公路勘察设计研究院有限公司 Precast concrete guardrail connection structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111395160A (en) * 2020-03-12 2020-07-10 广东省交通规划设计研究院股份有限公司 Rapid construction method for bridge guardrail with flower bed and prefabricated external flower bed
CN113737651A (en) * 2021-07-30 2021-12-03 中铁十九局集团第五工程有限公司 Assembled anti-collision guardrail and mounting method thereof
CN114427193A (en) * 2022-03-11 2022-05-03 湖南大学 Anchored UHPC curved anti-collision guardrail for bridge in splash zone and construction method thereof
CN116356683A (en) * 2023-04-10 2023-06-30 山东高速股份有限公司 Guardrail construction method and modularized UHPC bridge guardrail

Similar Documents

Publication Publication Date Title
CN110872813A (en) Precast concrete guardrail connecting structure and assembling method
CN109183607B (en) Prefabricated spliced UHPC pipe-concrete ultra-high bridge pier and construction method
CN105484142B (en) A kind of pin-connected panel precast segment concrete hollow slab beam structure and preparation method thereof
CN108867310A (en) The short rib T beam bridge of pretensioning prestressed concrete and its construction method
CN109667376B (en) Novel superposed floor system suitable for H-shaped steel beam of steel structure and construction method thereof
CN102839601A (en) Consolidated structure of steel piers and caps of portal-type rigid frame overpass and its construction method
CN114892552A (en) Box girder type bridge reconstruction construction method
CN110792164B (en) A kind of horizontal assembly device and assembly method of prefabricated shear wall
CN109025064A (en) Method for manufacturing and installing prefabricated concrete column and column assembly type connecting node
CN108104284B (en) Wall panel connection structure and assembly method with steel arm of shear wall embedded in floor slab
CN208685438U (en) A block type bridge deck wet seam connection form
CN202787055U (en) Pier fixed connection structure of steel structure overhead bridge
CN113719029A (en) Assembly type beam-column connecting joint based on hidden corbels and construction method thereof
CN110552706A (en) Permanent-temporary combined shield hoisting hole sealing structure and method
CN110106772A (en) A kind of highway clod wash U-shaped composite beam bridge and its construction method
CN104294920A (en) Joint assembly of U-shaped steel reinforced concrete combined beam and special-shaped concrete-filled steel tube column and manufacturing method of joint assembly
CN112681822A (en) Double-column-support four-column assembled elevated station
CN109763428B (en) Box girder formwork
CN104074131B (en) A kind of assembled inverted T-shaped slab bridge structure and construction method thereof
CN112095780A (en) An upper cover structure system applied to a track operation line and its implementation method
CN114561873A (en) Bridge high pier construction method
CN210658013U (en) Hanging basket structure for construction of wet joints of prefabricated erected small box girder cross-line bridge
EP4350074A1 (en) Prefabricated track structure for built-in pump house section in rail transportation and construction method
CN209779683U (en) Jigsaw assembled comprehensive pipe gallery
CN209114299U (en) A single box multi-chamber box girder bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination