Prior art keywords
pile foundation
fixed block
cushion cap
movable
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911138921.3A
Other languages
Chinese (zh)
Inventor
尹振礼
卢立海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenzhou Zhenan Geological Engineering Co Ltd
Original Assignee
Wenzhou Zhenan Geological Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenzhou Zhenan Geological Engineering Co Ltd filed Critical Wenzhou Zhenan Geological Engineering Co Ltd
Priority to CN201911138921.3A priority Critical patent/CN110847184A/en
Publication of CN110847184A publication Critical patent/CN110847184A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder

Abstract

The invention relates to a pile foundation settlement reinforcement jacking leveling structure which comprises a pile foundation bearing platform, a reinforcing layer, a fixing block, a movable groove, movable plates, a limiting rod and an accommodating groove, wherein one end of each movable plate, which is far away from the fixing block, is arranged to be sharp, a micro cylinder arranged above the movable groove is arranged inside the fixing block, the micro cylinder is connected with a triangular block, and one end, which faces each other, of each movable plate is provided with a triangular notch. The three hornblocks are driven by the micro cylinder to move towards the joint of the two movable plates, the gap is formed so that the three hornblocks can be clamped between the two movable plates conveniently, the two movable plates can be driven to move towards the direction away from each other, and the movable plates move outwards towards the fixed block along with the movement of the movable plates, so that the connection strength between the fixed block and the reinforcing layer is enhanced. The cooperation of gag lever post and holding tank lets the fly leaf have a part to be in the fixed block all the time, can't separate with the fixed block.

Description

Pile foundation subsides and consolidates jacking leveling structure
Technical Field
The invention relates to the technical field of building facilities, in particular to a pile foundation settlement reinforcement jacking leveling structure.
Background
Before building construction, a backfill soil layer or a soft foundation with a large depth is treated, most buildings need to be driven to form a foundation under the condition that a natural foundation is not available, and then an upper building structure is constructed. Because the foundation treatment is not compact, the foundation coating has higher compressibility and insufficient foundation bearing capacity; or the underground water erosion phenomenon is formed along with the change of the drainage condition of the underground water, so that the bearing capacity of the foundation is reduced; or a weak interlayer exists between the pile end and the bedrock; or the inclination of the rock surface is large, and the side slip is caused by insufficient rock-entering depth of the pile end; or uneven settlement of the pile foundation is caused by loose soil around the pile, low soft friction coefficient and the like. Therefore, the pile foundation bearing platform needs to be jacked and leveled and the pile end bearing force layer is pressed for reinforcing, the bearing force requirement of the foundation is met or the allowable settlement deviation range is designed, the height difference between the building pile foundations is reduced, and the structural safety of a factory building is ensured.
Disclosure of Invention
Aiming at the defects in the prior art, the invention aims to provide a pile foundation settlement reinforcement jacking leveling structure. The method has the advantages of jacking and leveling the bearing platform of the pile foundation and grouting and reinforcing the pile end bearing force, meeting the requirement of foundation bearing capacity or within the design allowable settlement deviation range, reducing the height difference between the pile foundations of the building and ensuring the structural safety of a factory building.
In order to achieve the purpose, the invention provides the following technical scheme: the utility model provides a pile foundation subsides and consolidates jacking leveling structure, includes pile foundation cushion cap and is in the back up coat of pile foundation cushion cap below, the bottom of pile foundation cushion cap is provided with distributes in pile foundation cushion cap fixed block all around, the fixed block is provided with the activity groove that runs through the fixed block, the fixed block is provided with two fly leafs that are in the activity inslot, the side fixedly connected with of fly leaf is in the gag lever post in the fixed block, the fixed block is provided with the holding tank that just is used for holding the gag lever post with activity groove intercommunication, the one end that the fixed block was kept away from to the fly leaf sets up to sharp-pointed form, the inside of fixed block is provided with the miniature cylinder that is in activity groove top, miniature cylinder is connected with three hornblocks.
Through adopting above-mentioned technical scheme, the three hornblocks of miniature cylinder drive move towards the junction of two fly leafs, and the setting up of breach makes things convenient for the three hornblocks card to go into between two fly leafs to can drive two fly leafs and remove towards the direction of keeping away from each other, thereby along with the removal of fly leaf outside the fixed block remove the joint strength between reinforcing layer and the fixed block of reinforcing. The cooperation of gag lever post and holding tank lets the fly leaf have a part to be in the fixed block all the time, can't separate with the fixed block. The movable plate can enhance the connection strength between the fixed block and the reinforcing layer, so that the descending range of the pile foundation bearing platform is reduced and eliminated.
The invention is further configured to: one side that pile foundation cushion cap was kept away from to the fixed block is provided with the recess, the first cylinder of tank bottom fixedly connected with of recess, first cylinder is connected with the mounting panel, the first motor of fixedly connected with on the mounting panel, first motor is connected with the extrusion dish.
Through adopting above-mentioned technical scheme, first cylinder can drive the mounting panel and reciprocate and then drive first motor and reciprocate, and first motor can drive the extrusion dish and reciprocate, and this in-process first motor can drive the extrusion dish and rotate round the axial lead of self, therefore the extrusion dish will reciprocate and rotate, and the reinforcement layer that the extrusion dish below will be extruded to the extrusion dish downstream, lifts pile foundation cushion cap under reaction force afterwards to reply the horizontally state.
The invention is further configured to: one side of the extrusion disc is integrally connected with a spiral plate.
Through adopting above-mentioned technical scheme, the setting up of spiral plate has strengthened the extrusion dish and has stirred the ability of back up coat.
The invention is further configured to: the extrusion disc is provided with a flow guide pipe attached to the extrusion disc in a penetrating mode, and the flow guide pipe penetrates through the fixed block and the pile foundation bearing platform.
Through adopting above-mentioned technical scheme, at extrusion disk and spiral plate pivoted in-process, if the rigidity of the back up coat that is in the extrusion disk below is not enough, can increase the displacement of extrusion disk, increases the risk, consequently in leading-in the back up coat of grout through the honeycomb duct, the rigidity of reinforcing layer is strengthened, not only can strengthen the rigidity of back up coat, can reduce the displacement of extrusion disk moreover, the extrusion disk lifting pile foundation cushion cap of being convenient for.
The invention is further configured to: pile foundation cushion cap is provided with the cross slot that runs through pile foundation cushion cap, pile foundation cushion cap is provided with the moving member that is in the cross slot opening part, the moving member is connected with the reinforced pipe, the lateral wall an organic whole of reinforced pipe is connected with a plurality of circular arc pieces, and is a plurality of the circular arc piece distributes along the length direction of reinforced pipe, the circular arc piece be provided with run through the circular arc piece and with the inside intercommunication groove that communicates of reinforced pipe, the inside an organic whole of fixed pipe is connected with the guide board that is in circular arc piece department.
Through adopting above-mentioned technical scheme, the moving member can remove along the length direction of horizontal groove repeatedly, and the removal of moving member can drive the reinforced pipe and remove, and along with the removal of reinforced pipe, the reinforced pipe can drive a plurality of circular arc pieces and remove and then drive the guide board and remove, to the intraductal grout of pouring into of reinforced pipe, and grout flows in the guide board gets into the circular arc piece and then from the intercommunication inslot, strengthens the intensity of back up coat, in addition through the removal of moving member, can pertinence and strengthen the intensity of a plurality of positions of back up coat comprehensively.
The invention is further configured to: the moving member includes the rack of fixed connection on pile foundation cushion cap, the rack toothing has the gear, the axial lead fixedly connected with connecting axle of gear, connecting axle fixedly connected with second motor, the second motor is towards one side fixedly connected with L shape pole of pile foundation cushion cap, the middle part of rack is provided with the shifting chute, the one end that the second motor was kept away from to L shape pole is in the shifting chute.
Through adopting above-mentioned technical scheme, the second motor drives the connecting axle and rotates and then drive gear revolve, rack fixed connection is on pile foundation cushion cap, therefore the gear revolve back, the gear will move and then drive the reinforcement pipe and remove along the length direction of rack, and this in-process, L shape pole is in the shifting chute all the time, and L shape pole and shifting chute cooperation let the second motor can only remove along the length direction of shifting chute.
In conclusion, the invention has the following beneficial effects:
the three hornblocks are driven by the micro cylinder to move towards the joint of the two movable plates, the gap is formed so that the three hornblocks can be clamped between the two movable plates conveniently, the two movable plates can be driven to move towards the direction away from each other, and the movable plates move outwards towards the fixed block along with the movement of the movable plates, so that the connection strength between the fixed block and the reinforcing layer is enhanced. The cooperation of gag lever post and holding tank lets the fly leaf have a part to be in the fixed block all the time, can't separate with the fixed block.
Drawings
FIG. 1 is a perspective view of an embodiment;
FIG. 2 is a top view of the embodiment;
fig. 3 is a schematic structural diagram of a connection relationship between the rack, the L-shaped rod and the second motor in the embodiment.
Reference numerals: 1. a pile foundation cap; 2. a fixed block; 3. a movable groove; 4. a movable plate; 5. a limiting rod; 6. accommodating grooves; 7. a micro cylinder; 8. a triangular block; 9. a groove; 10. a first cylinder; 11. mounting a plate; 12. a first motor; 13. an extrusion disc; 14. a spiral plate; 15. a flow guide pipe; 16. a transverse groove; 17. reinforcing the pipe; 18. an arc block; 19. a communicating groove; 20. a guide plate; 21. a rack; 22. a gear; 23. a connecting shaft; 24. a second motor; 25. an L-shaped rod; 26. a moving groove; 27. and a reinforcing layer.
Detailed Description
The invention is further described with reference to the accompanying drawings.
The utility model provides a pile foundation subsides and consolidates jacking leveling structure, as shown in figure 1-figure 3, includes pile foundation cushion cap 1 and be in the reinforced layer 27 of pile foundation cushion cap 1 below, the bottom of pile foundation cushion cap 1 is provided with the fixed block 2 of distributing around pile foundation cushion cap 1, fixed block 2 is provided with the activity groove 3 that runs through fixed block 2, and activity groove 3 transversely runs through fixed block 2, fixed block 2 is provided with two fly leaves 4 that are in activity groove 3, the side fixedly connected with of fly leaf 4 is in the gag lever post 5 of fixed block 2, fixed block 2 is provided with the holding tank 6 that communicates with activity groove 3 and is used for holding gag lever post 5, and gag lever post 5 can remove along the length direction of holding tank 6, the one end that fixed block 2 was kept away from to fly leaf 4 sets up to sharp-pointed shape, the inside of fixed block 2 is provided with the miniature cylinder 7 that, one end of the micro cylinder 7 facing the movable plate 4 is connected with a triangular block 8, the vertex of the triangular block 8 faces the movable plate 4, and one end of the two movable plates 4 facing each other is provided with a triangular notch. After the triangular block 8 moves into the gap, the triangular block 8 will press the two movable plates 4, so that the two movable plates 4 move away from each other.
One side that pile foundation cushion cap 1 was kept away from to fixed block 2 is provided with recess 9, and recess 9's opening orientation deviates from pile foundation cushion cap 1's direction, the first cylinder 10 of tank bottom fixedly connected with of recess 9, first cylinder 10 is connected with mounting panel 11, the first motor 12 of direction fixedly connected with of first cylinder 10 is kept away from to mounting panel 11, first motor 12 is connected with extrusion dish 13.
A spiral plate 14 is integrally connected to one side of the extrusion disk 13.
The extrusion disc 13 is provided with a guide pipe 15 attached to the extrusion disc 13 in a penetrating manner, and the guide pipe 15 penetrates through the fixed block 2 and the pile foundation bearing platform 1. During the downward rotation of the spiral plate 14, cement slurry can flow out of the draft tube 15, so that the part of the reinforcing layer 27 below the extrusion disc 13 is continuously reinforced in the process of stirring the reinforcing layer 27, and the cement slurry seeps downwards under the guidance of the spiral plate 14, so that the moving distance of the extrusion disc 13 is reduced, and the power consumption and the accident risk are reduced.
Pile foundation cushion cap 1 is provided with the cross slot 16 that runs through pile foundation cushion cap 1, pile foundation cushion cap 1 is provided with the moving member that is in the opening part of cross slot 16, the moving member is connected with reinforced pipe 17, reinforced pipe 17's lateral wall an organic whole is connected with a plurality of circular arc pieces 18, and is a plurality of circular arc piece 18 distributes along reinforced pipe 17's length direction, circular arc piece 18 is provided with run through circular arc piece 18 and with reinforced pipe 17 inside intercommunication groove 19, the inside an organic whole of fixed pipe is connected with the guide board 20 that is in circular arc piece 18 department.
The moving member includes rack 21 fixed connection on pile foundation cushion cap 1, rack 21 meshes there is gear 22, gear 22's axial lead fixedly connected with connecting axle 23, connecting axle 23 fixedly connected with second motor 24, second motor 24 is towards one side fixedly connected with L shape pole 25 of pile foundation cushion cap 1, the middle part of rack 21 is provided with shifting chute 26, the one end that second motor 24 was kept away from to L shape pole 25 is in shifting chute 26.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like made within the design concept of the present invention should be included in the scope of the present invention.

Claims (6)

1. The utility model provides a pile foundation subsides and consolidates jacking leveling structure, includes pile foundation cushion cap (1) and reinforced layer (27) that are in pile foundation cushion cap (1) below, its characterized in that: the bottom of the pile foundation bearing platform (1) is provided with fixed blocks (2) distributed around the pile foundation bearing platform (1), the fixed block (2) is provided with a movable groove (3) which penetrates through the fixed block (2), the fixed block (2) is provided with two movable plates (4) positioned in the movable groove (3), the side surface of the movable plate (4) is fixedly connected with a limiting rod (5) positioned in the fixed block (2), the fixed block (2) is provided with an accommodating groove (6) which is communicated with the movable groove (3) and is used for accommodating the limiting rod (5), one end of the movable plate (4) far away from the fixed block (2) is arranged to be sharp, a micro cylinder (7) positioned above the movable groove (3) is arranged in the fixed block (2), the micro cylinder (7) is connected with a triangular block (8), and one end, facing each other, of the movable plate (4) is provided with a triangular notch.
2. The pile foundation settlement reinforcement jacking leveling structure of claim 1, characterized in that: one side that pile foundation cushion cap (1) was kept away from in fixed block (2) is provided with recess (9), the first cylinder of tank bottom fixedly connected with (10) of recess (9), first cylinder (10) are connected with mounting panel (11), first motor of fixedly connected with (12) are gone up in mounting panel (11), first motor (12) are connected with extrusion dish (13).
3. The pile foundation settlement reinforcement jacking leveling structure of claim 2, characterized in that: one side of the extrusion disc (13) is integrally connected with a spiral plate (14).
4. The pile foundation settlement reinforcement jacking leveling structure of claim 3, characterized in that: extrusion dish (13) are worn to be equipped with honeycomb duct (15) of depending on extrusion dish (13), honeycomb duct (15) run through fixed block (2) and pile foundation cushion cap (1).
5. The pile foundation settlement reinforcement jacking leveling structure of claim 1, characterized in that: pile foundation cushion cap (1) is provided with transverse groove (16) that runs through pile foundation cushion cap (1), pile foundation cushion cap (1) is provided with the moving member that is in transverse groove (16) opening part, the moving member is connected with reinforced pipe (17), the lateral wall an organic whole of reinforced pipe (17) is connected with a plurality of arc pieces (18), and is a plurality of arc piece (18) distribute along the length direction of reinforced pipe (17), arc piece (18) are provided with run through arc piece (18) and with reinforced pipe (17) inside intercommunication groove (19), the inside an organic whole of fixed pipe is connected with guide board (20) that are in arc piece (18) department.
6. The pile foundation settlement reinforcement jacking leveling structure of claim 5, characterized in that: the moving member includes rack (21) fixed connection on pile foundation cushion cap (1), rack (21) meshing has gear (22), the axial lead fixedly connected with connecting axle (23) of gear (22), connecting axle (23) fixedly connected with second motor (24), second motor (24) are towards one side fixedly connected with L shape pole (25) of pile foundation cushion cap (1), the middle part of rack (21) is provided with shifting chute (26), the one end that second motor (24) were kept away from in L shape pole (25) is in shifting chute (26).
CN201911138921.3A 2019-11-20 2019-11-20 Pile foundation subsides and consolidates jacking leveling structure Pending CN110847184A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911138921.3A CN110847184A (en) 2019-11-20 2019-11-20 Pile foundation subsides and consolidates jacking leveling structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911138921.3A CN110847184A (en) 2019-11-20 2019-11-20 Pile foundation subsides and consolidates jacking leveling structure

Publications (1)

Publication Number Publication Date
CN110847184A true CN110847184A (en) 2020-02-28

Family

ID=69602772

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911138921.3A Pending CN110847184A (en) 2019-11-20 2019-11-20 Pile foundation subsides and consolidates jacking leveling structure

Country Status (1)

Country Link
CN (1) CN110847184A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2669963A1 (en) * 2009-06-30 2010-12-30 Casey Moroschan Methods of lifting settled foundations
CN207582482U (en) * 2017-11-27 2018-07-06 王永康 Civil engineering built pile
CN108343102A (en) * 2018-04-26 2018-07-31 北京恒祥宏业基础加固技术有限公司 Jacking leveling structure and its construction method are reinforced in a kind of sedimentation of pile foundation
CN208219644U (en) * 2018-03-11 2018-12-11 肖礼全 A kind of oil exploitation is with beating ground pile
CN110080318A (en) * 2019-04-29 2019-08-02 兰州理工大学 A kind of method for correcting error that pile foundation building locally settles

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2669963A1 (en) * 2009-06-30 2010-12-30 Casey Moroschan Methods of lifting settled foundations
CN207582482U (en) * 2017-11-27 2018-07-06 王永康 Civil engineering built pile
CN208219644U (en) * 2018-03-11 2018-12-11 肖礼全 A kind of oil exploitation is with beating ground pile
CN108343102A (en) * 2018-04-26 2018-07-31 北京恒祥宏业基础加固技术有限公司 Jacking leveling structure and its construction method are reinforced in a kind of sedimentation of pile foundation
CN110080318A (en) * 2019-04-29 2019-08-02 兰州理工大学 A kind of method for correcting error that pile foundation building locally settles

Similar Documents

Publication Publication Date Title
CN204662425U (en) Polygonal cement mixing method
CN204662499U (en) Concrete of basement exterior wall, waterproof, fertile groove integrated construction structure
CN204370431U (en) A kind of occlusion long-short pile space enclosing structure
CN204662426U (en) Cement mixing method
CN108914961B (en) Communication iron tower foundation adopting spiral anchors and construction method
CN104314042B (en) Adopt the levee construction method of pile formula case barrel structure
CN102080382A (en) Building foundation adaptable to goaf foundation deformation
CN114319472A (en) Construction method for settlement, reinforcement and lifting of residential building foundation
CN205259210U (en) Modular retaining wall
CN110847184A (en) Pile foundation subsides and consolidates jacking leveling structure
CN102277876B (en) Multifunctional pile-raft foundation and construction process thereof
CN204780991U (en) Floor formula retaining wall
CN206928294U (en) A kind of counter-force seals stake loading system
CN106245673A (en) A kind of rib stake formula peg board retaining wall and construction method thereof
CN206220121U (en) Assembled point anchor barricade
CN202430724U (en) Cemented soil gravity type enclosure wall applied with pre-stress
CN202430682U (en) Permeable jetty
CN212772510U (en) Steel-pipe pile foundation reinforced structure
CN203960824U (en) Side slope wasteway structure
CN203668926U (en) Foundation for tapered concrete piles
CN103215965A (en) Laminate type high-rise platform pile tower crane foundation and construction method
CN209703541U (en) The tamper dentiform pile of superior performance
CN204662424U (en) Soil-cement bearing peg
CN206986879U (en) A kind of compression-resistant type embedded rock pile
CN201232188Y (en) Buttress type soil nail wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200228

RJ01 Rejection of invention patent application after publication