CN110797796A - 一种绝缘短杆断或接断路器流线作业方法 - Google Patents
一种绝缘短杆断或接断路器流线作业方法 Download PDFInfo
- Publication number
- CN110797796A CN110797796A CN201911231821.5A CN201911231821A CN110797796A CN 110797796 A CN110797796 A CN 110797796A CN 201911231821 A CN201911231821 A CN 201911231821A CN 110797796 A CN110797796 A CN 110797796A
- Authority
- CN
- China
- Prior art keywords
- insulating
- short
- rod
- insulation
- operator
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/02—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
Landscapes
- Electric Cable Installation (AREA)
- Train Traffic Observation, Control, And Security (AREA)
Abstract
本发明涉及电气维修工具领域技术领域,具体地说,涉及一种绝缘短杆断或接断路器流线作业方法,包括以下步骤:步骤S1、现场作业准备,其具体步骤如下:步骤S2、进入带电作业工位,步骤S3、作业人员在绝缘承载工具内检查作业范围内的设备及线路完好;步骤S4、作业人员在绝缘承载工具上手持短绝缘杆安装绝缘遮蔽;步骤S5、作业人员在绝缘承载工具上手持短绝缘杆逐相断或接隔离开关引流线;步骤S6、作业人员在绝缘承载工具上手持短绝缘杆拆除绝缘遮蔽;步骤S7、作业人员从绝缘承载工具上退出带电作业工位。本发明既解决短绝缘杆进行断或接引流线作业对作业人员技能要求较高,又能解决绝缘手套作业法直接接触带电体带来的安全隐患。
Description
技术领域
本发明涉及电气维修工具领域技术领域,具体地说,涉及一种绝缘短杆断或接断路器流线作业方法。
背景技术
在10kV配电网网架结构、配网自动化技术不完善的条件下,随着社会对供电可靠性要求的逐步提高,采用带电作业逐步成为一种趋势。目前国内10kV配网带电作业已得到大力发展,技术日趋成熟。当前10kV配网带电断(接)10kV隔离开关引流线作业方法主要有短绝缘杆作业法和绝缘手套作业法两种。短绝缘杆作业法是作业人员站在电杆上,采用短绝缘杆进行断(接)引流线作业,由于杆上作业人员站在电杆上,作业位置调整空间有限,因此对作业人员技能要求较高。绝缘手套作业法是作业人员穿戴全套绝缘防护,在绝缘斗臂车(平台)上直接与带电体接触进行作业,由于人员直接与带电体接触,安全风险相对较大。
发明内容
本发明的目的在于提供绝缘短杆断或接断路器流线作业方法,以解决上述背景技术中提出的问题。
为实现上述目的,本发明提供一种绝缘短杆断或接断路器流线作业方法,包括以下步骤:
步骤S1、现场作业准备,其具体步骤如下:
S11.装设现场安全设施,
S12.绝缘斗臂车停放、绝缘脚手架组装、检查,
S13.检查、检测工器具及材料,
S14.运行人员操作拉开隔离开关,使其不带负荷;
步骤S2、进入带电作业工位,其具体步骤如下:
S21.带电作业人员穿戴绝缘防护用具通过绝缘承载工具进入作业工位,
S22.对线路验电;
步骤S3、作业人员在绝缘承载工具内检查作业范围内的设备及线路完好;
步骤S4、作业人员在绝缘承载工具上手持短绝缘杆安装绝缘遮蔽;
步骤S5、作业人员在绝缘承载工具上手持短绝缘杆逐相断或接隔离开关引流线;
步骤S6、作业人员在绝缘承载工具上手持短绝缘杆拆除绝缘遮蔽;
步骤S7、作业人员从绝缘承载工具上退出带电作业工位。
作为优选,所述绝缘承载工具采用斗臂车或绝缘平台。
作为优选,所述绝缘防护用具为绝缘安全帽、绝缘手套、短绝缘杆、护目镜和安全带。
作为优选,所述绝缘遮蔽的安装按照由上至下、由近至远进行。
作为优选,所述短绝缘杆的有效长度不小于70cm,操作时作业人员的身体与带电体保持40cm以上安全距离。
作为优选,所述绝缘遮蔽的拆除按照由上至下、由远至近进行。
与现有技术相比,本发明的有益效果:本发明既解决短绝缘杆进行断或接引流线作业对作业人员技能要求较高,又能解决绝缘手套作业法直接接触带电体带来的安全隐患。
具体实施方式
下面将结合本发明实施例,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
本发明提供一种技术方案:一种绝缘短杆断或接断路器流线作业方法,包括以下步骤:
步骤S1、现场作业准备,其具体步骤如下:
S11.装设现场安全设施,
S12.绝缘斗臂车停放、绝缘脚手架组装、检查,
S13.检查、检测工器具及材料,
S14.运行人员操作拉开隔离开关,使其不带负荷;
步骤S2、进入带电作业工位,其具体步骤如下:
S21.带电作业人员穿戴绝缘防护用具通过绝缘承载工具进入作业工位,
S22.对线路验电;
步骤S3、作业人员在绝缘承载工具内检查作业范围内的设备及线路完好;
步骤S4、作业人员在绝缘承载工具上手持短绝缘杆安装绝缘遮蔽;
步骤S5、作业人员在绝缘承载工具上手持短绝缘杆逐相断或接隔离开关引流线;
步骤S6、作业人员在绝缘承载工具上手持短绝缘杆拆除绝缘遮蔽;
步骤S7、作业人员从绝缘承载工具上退出带电作业工位。
作为本发明的一种优选技术方案,绝缘承载工具采用斗臂车或绝缘平台。
作为本发明的一种优选技术方案,绝缘防护用具为绝缘安全帽、绝缘手套、短绝缘杆、护目镜和安全带。
作为本发明的一种优选技术方案,绝缘遮蔽的安装按照由上至下、由近至远进行。
作为本发明的一种优选技术方案,短绝缘杆的有效长度不小于70cm,操作时作业人员的身体与带电体保持40cm以上安全距离。
作为本发明的一种优选技术方案,绝缘遮蔽的拆除按照由上至下、由远至近进行。
本发明既解决短绝缘杆进行断或接引流线作业对作业人员技能要求较高,又能解决绝缘手套作业法直接接触带电体带来的安全隐患。
以上显示和描述了本发明的基本原理、主要特征和本发明的优点。本行业的技术人员应该了解,本发明不受上述实施例的限制,上述实施例和说明书中描述的仅为本发明的优选例,并不用来限制本发明,在不脱离本发明精神和范围的前提下,本发明还会有各种变化和改进,这些变化和改进都落入要求保护的本发明范围内。本发明要求保护范围由所附的权利要求书及其等效物界定。
Claims (6)
1.一种绝缘短杆断或接断路器流线作业方法,其特征在于:包括以下步骤:
步骤S1、现场作业准备,其具体步骤如下:
S11.装设现场安全设施,
S12.绝缘斗臂车停放、绝缘脚手架组装、检查,
S13.检查、检测工器具及材料,
S14.运行人员操作拉开隔离开关,使其不带负荷;
步骤S2、进入带电作业工位,其具体步骤如下:
S21.带电作业人员穿戴绝缘防护用具通过绝缘承载工具进入作业工位,
S22.对线路验电;
步骤S3、作业人员在绝缘承载工具内检查作业范围内的设备及线路完好;
步骤S4、作业人员在绝缘承载工具上手持短绝缘杆安装绝缘遮蔽;
步骤S5、作业人员在绝缘承载工具上手持短绝缘杆逐相断或接隔离开关引流线;
步骤S6、作业人员在绝缘承载工具上手持短绝缘杆拆除绝缘遮蔽;
步骤S7、作业人员从绝缘承载工具上退出带电作业工位。
2.根据权利要求1所述的绝缘短杆断或接断路器流线作业方法,其特征在于:所述绝缘承载工具采用斗臂车或绝缘平台。
3.根据权利要求1所述的绝缘短杆断或接断路器流线作业方法,其特征在于:所述绝缘防护用具为绝缘安全帽、绝缘手套、短绝缘杆、护目镜和安全带。
4.根据权利要求1所述的绝缘短杆断或接断路器流线作业方法,其特征在于:所述绝缘遮蔽的安装按照由上至下、由近至远进行。
5.根据权利要3所述的绝缘短杆断或接断路器流线作业方法,其特征在于:所述短绝缘杆的有效长度不小于70cm,操作时作业人员的身体与带电体保持40cm以上安全距离。
6.根据权利要求1所述的绝缘短杆断或接断路器流线作业方法,其特征在于:所述绝缘遮蔽的拆除按照由上至下、由远至近进行。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911231821.5A CN110797796A (zh) | 2019-12-05 | 2019-12-05 | 一种绝缘短杆断或接断路器流线作业方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911231821.5A CN110797796A (zh) | 2019-12-05 | 2019-12-05 | 一种绝缘短杆断或接断路器流线作业方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110797796A true CN110797796A (zh) | 2020-02-14 |
Family
ID=69447557
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911231821.5A Pending CN110797796A (zh) | 2019-12-05 | 2019-12-05 | 一种绝缘短杆断或接断路器流线作业方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110797796A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112531564A (zh) * | 2020-12-07 | 2021-03-19 | 国网上海市电力公司 | 一种旁路作业结合绝缘短杆桥接法检修方法 |
CN112909822A (zh) * | 2021-03-10 | 2021-06-04 | 国网河南省电力公司社旗县供电公司 | 一种基于无人机辅助的配电网不停电作业系统及方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0045001A1 (de) * | 1980-07-25 | 1982-02-03 | Siemens Aktiengesellschaft | Steckdosenanordnung mit Fehlerstromschutzschalter |
CN101719640A (zh) * | 2009-11-05 | 2010-06-02 | 齐齐哈尔电业局 | 10kV线路同杆架设多回路导线带电接引流线操作方法 |
CN103746315A (zh) * | 2013-12-30 | 2014-04-23 | 江苏省电力公司常州供电公司 | 10kV配电绝缘线路快速带电搭接引流线作业方法 |
CN104037648A (zh) * | 2014-05-14 | 2014-09-10 | 国家电网公司 | 35kV架空线路绝缘手套法带电断、接空载线路引线的作业方法 |
CN105449392A (zh) * | 2015-10-23 | 2016-03-30 | 云南电网有限责任公司临沧供电局 | 一种10kV线路带电搭接及拆除引流线作业装置及方法 |
-
2019
- 2019-12-05 CN CN201911231821.5A patent/CN110797796A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0045001A1 (de) * | 1980-07-25 | 1982-02-03 | Siemens Aktiengesellschaft | Steckdosenanordnung mit Fehlerstromschutzschalter |
CN101719640A (zh) * | 2009-11-05 | 2010-06-02 | 齐齐哈尔电业局 | 10kV线路同杆架设多回路导线带电接引流线操作方法 |
CN103746315A (zh) * | 2013-12-30 | 2014-04-23 | 江苏省电力公司常州供电公司 | 10kV配电绝缘线路快速带电搭接引流线作业方法 |
CN104037648A (zh) * | 2014-05-14 | 2014-09-10 | 国家电网公司 | 35kV架空线路绝缘手套法带电断、接空载线路引线的作业方法 |
CN105449392A (zh) * | 2015-10-23 | 2016-03-30 | 云南电网有限责任公司临沧供电局 | 一种10kV线路带电搭接及拆除引流线作业装置及方法 |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112531564A (zh) * | 2020-12-07 | 2021-03-19 | 国网上海市电力公司 | 一种旁路作业结合绝缘短杆桥接法检修方法 |
CN112909822A (zh) * | 2021-03-10 | 2021-06-04 | 国网河南省电力公司社旗县供电公司 | 一种基于无人机辅助的配电网不停电作业系统及方法 |
CN112909822B (zh) * | 2021-03-10 | 2022-08-30 | 国网河南省电力公司社旗县供电公司 | 一种基于无人机辅助的配电网不停电作业系统及方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110797796A (zh) | 一种绝缘短杆断或接断路器流线作业方法 | |
CN103001142A (zh) | 带负荷更换10kV柱上隔离开关的作业方法 | |
CN102931609A (zh) | 带负荷更换10kV跌落式熔断器的作业方法 | |
CN104779604A (zh) | 一种中性点接地电阻柜 | |
CN204614744U (zh) | 一种户外智能分界断路器总成 | |
CN210693223U (zh) | 一种应用于不停电作业的电压互感器隔离组合装置 | |
CN110797795A (zh) | 一种绝缘短杆断或接10kV绝缘导线线路分支线引流线作业方法 | |
CN116453781A (zh) | 一种带电作业开关绝缘护套 | |
CN201398034Y (zh) | 一种验电接地装置 | |
CN104426088A (zh) | 电压互感器手车 | |
CN110752549A (zh) | 一种绝缘短杆断或接10kV耐张杆引流线作业方法 | |
CN203387140U (zh) | 等电位载直流带电融冰装置 | |
CN110912023A (zh) | 一种绝缘短杆断或接10kV跌落熔断器引流线作业方法 | |
CN110120318B (zh) | 户外高压隔离开关主连杆脱扣装置及不停电检修操作方法 | |
CN102868230A (zh) | 10~20kV变压器台区设备状态检修智能管理装置 | |
CN208508525U (zh) | 一种新能源发电系统弧光保护装置 | |
CN102638107B (zh) | 变电站接地线状态信号采集装置 | |
CN202502939U (zh) | 远程控制智能化的高压真空断路器 | |
CN207559280U (zh) | 电气柜接地闭锁装置 | |
CN112186633A (zh) | 一种带电更换柱上电压互感器隔离装置的作业方法 | |
CN110676738B (zh) | 一种应用于不停电作业的电压互感器隔离组合装置 | |
CN214755169U (zh) | 绝缘挡板 | |
CN205565709U (zh) | 智能远程控制防架空绝缘保护装置 | |
CN103647242A (zh) | 一种共箱封闭母线联通结构 | |
CN208702246U (zh) | 新型集电线路杆塔 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200214 |
|
RJ01 | Rejection of invention patent application after publication |