CN110777650A - Embedded assembly type expansion joint overlength installation suspension leveling positioning system and construction method - Google Patents

Embedded assembly type expansion joint overlength installation suspension leveling positioning system and construction method Download PDF

Info

Publication number
CN110777650A
CN110777650A CN201911206426.1A CN201911206426A CN110777650A CN 110777650 A CN110777650 A CN 110777650A CN 201911206426 A CN201911206426 A CN 201911206426A CN 110777650 A CN110777650 A CN 110777650A
Authority
CN
China
Prior art keywords
expansion joint
suspension
positioning system
installation
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911206426.1A
Other languages
Chinese (zh)
Inventor
欧永迁
高晨
周伯华
王舒哲
王�锋
肖礼鹏
彭建锋
黎平
张曼
高悦
陈鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Original Assignee
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Engineering Co Ltd of China Construction Third Engineering Division filed Critical Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority to CN201911206426.1A priority Critical patent/CN110777650A/en
Publication of CN110777650A publication Critical patent/CN110777650A/en
Priority to PCT/CN2020/123928 priority patent/WO2021103895A1/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/06Arrangement, construction or bridging of expansion joints
    • E01D19/062Joints having intermediate beams
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

The invention relates to a pre-embedded assembled expansion joint overlength installation suspension leveling positioning system and a construction method, wherein the suspension leveling positioning system is structurally characterized in that two ends of a section steel main beam are respectively fixed on two bases; three horizontal casters are arranged on each base; the middle part of the section steel main beam is provided with two hollow chutes which are not communicated, two handle suspension rods are arranged in each chute, the lower end of each handle suspension rod is provided with a suspension nut, and the suspension nuts are connected with the expansion joint embedded assembly; the horizontal caster takes the concrete beam as a pivot. The suspension leveling positioning system is arranged above the expansion joint embedded component along the transverse bridge span joint at intervals, is connected with a suspension rod nut fixed on the inner side of the expansion joint embedded component through a handle suspension rod, and accurately adjusts the elevation, the smoothness and the cross slope of the expansion joint embedded component through the handle suspension rod and a horizontal caster; and (5) after the concrete is poured and the initial setting of the concrete is completed, removing the concrete, and completing the high-precision installation of the embedded assembly. The condition is created for the whole accurate installation of overlength embedded component, ensures expansion joint installation quality.

Description

Embedded assembly type expansion joint overlength installation suspension leveling positioning system and construction method
The technical field is as follows:
the invention relates to the field of bridge engineering, in particular to an overlength installation, suspension, leveling and positioning system for a pre-embedded assembly type expansion joint and a construction method.
Background art:
at present, the prestressed cast-in-place box girder expansion joint is constructed by adopting a 'rear embedding method', namely, when a concrete box girder main body structure is constructed, an expansion joint notch is reserved at the end of each box girder, secondary reverse cutting is carried out after asphalt paving of a bridge deck is finished, and the installation height and the smoothness of the expansion joint can be adjusted according to the asphalt finishing surface when the expansion joint is installed. The installation process can overcome the defects of long construction period, multiple temporary measures, resource waste and the like of the traditional 'rear embedding method', but the preposition of the embedded assembly has high requirement on the installation precision and great overlength installation and leveling difficulty.
Disclosure of Invention
The invention aims to solve the problems of high precision requirement and high positioning and adjusting difficulty of ultra-long installation of an embedded assembly type expansion joint, meet the high quality requirement of expansion joint installation, and provide a suspension leveling and positioning system and a construction method for high precision leveling and fixing of the embedded assembly of the ultra-long assembly type expansion joint. The embedded component of expansion joint is fixed in the girder below through the handle polished rod, and the embedded component elevation of its handle polished rod accessible rotation adjustment and position, the whole accurate location of the embedded component of overlength of being convenient for, the installation is firm, non-deformable, satisfies embedded component installation high accuracy requirement, improves smooth-going degree and the durability of expansion joint installation.
The technical scheme adopted by the invention for solving the technical problem is as follows:
leveling positioning system is suspended in midair in overlength installation of pre-buried assembled expansion joint, including shaped steel girder, four handle suspension rods, six horizontal truckles, two bases, suspension rod nut, its characterized in that: two ends of the section steel main beam are respectively fixed on the two bases; three horizontal casters are arranged on each base; the middle part of the section steel main beam is provided with two hollow chutes which are not communicated, two handle suspension rods are arranged in each chute, the lower end of each handle suspension rod is provided with a suspension nut, and the suspension nuts are connected with the expansion joint embedded assembly; each horizontal caster takes the concrete beam as a pivot.
The distance between the two hollow chutes is 10 cm.
The section steel main beam is made of channel steel and is 1.5m in length.
The handle suspension rod is a handle bolt.
The base is made of a steel plate.
When the expansion joint pre-embedded component is used, a plurality of suspension leveling positioning systems can be adopted at the same time, each suspension leveling positioning system is arranged above the expansion joint pre-embedded component along the transverse span of the bridge at a certain interval, the suspension leveling positioning systems are connected with suspension rod nuts fixed on the inner side of the expansion joint pre-embedded component through handle suspension rods, the elevation of the expansion joint pre-embedded component is adjusted through rotation of the handle suspension rods, and the smoothness and the transverse slope of the expansion joint pre-embedded component are adjusted through horizontal trundles fixed at two ends of a section steel main beam.
The construction method for installing, suspending, leveling and positioning system by using the ultra-long embedded assembly type expansion joint of claim 1 is characterized by comprising the following steps:
firstly, installation of an expansion joint embedded assembly: integrally hoisting the expansion joint embedded component to an expansion joint installation notch, checking the plane position of the expansion joint embedded component, and symmetrically fixing two suspension rod nuts every 2m along the inner side of the expansion joint embedded component;
secondly, installing a suspension leveling positioning system: arranging the suspension leveling and positioning system above the expansion joint embedded assembly along the transverse bridge span joint at intervals of 2m, aligning the suspension leveling and positioning system with a suspension rod nut fixed on the expansion joint embedded assembly, and connecting a handle suspension rod with the suspension rod nut fixed on the inner side of the expansion joint embedded assembly to enable the suspension leveling and positioning system and the expansion joint embedded assembly to form a whole; adjusting the elevation of the expansion joint embedded assembly through rotation of the handle suspension rod, adjusting the smoothness and the cross slope of the expansion joint embedded assembly through movement of the horizontal caster wheel on the concrete beam, and rechecking the elevation and the smoothness of the expansion joint embedded assembly for the second time to ensure that the installation error of the expansion joint embedded assembly is less than or equal to 2 mm;
thirdly, pouring concrete: c50 steel fiber concrete is poured into the box girder to reserve the slot opening of the expansion joint, the concrete is poured, and a 30-type vibrating rod is used for vibrating and compacting the concrete; after concrete pouring is finished, finishing surface light collection, covering with a plastic film, and arranging warning signs around a manhole to avoid trampling by personnel;
and fourthly, releasing the suspension leveling positioning system: and after the concrete is initially set, rotating the handle suspension rod, and removing the connection between the suspension leveling positioning system and the expansion joint embedded assembly to complete the positioning and installation of the expansion joint embedded assembly.
The invention carries out positioning and leveling installation through the suspension embedded assembly, creates conditions for the overall accurate installation of the overlength embedded assembly, realizes that the embedded assembly is convenient to position, firm to install and not easy to deform, meets the requirement of high installation accuracy of the overlength embedded assembly, improves the smoothness and durability of installation of the expansion joint, and ensures the installation quality of the expansion joint.
Description of the drawings:
fig. 1 is a schematic cross-sectional view of the present invention.
Fig. 2 is a schematic plan view of the present invention.
Reference numerals: the method comprises the following steps of 1-section steel main beam, 2-handle suspension rod, 3-handle bolt, 4-horizontal caster, 5-base, 6-suspension rod nut, 8-expansion joint pre-embedded assembly, 9-pre-embedded U-shaped steel bar and 10-expansion joint positioning bar.
The specific implementation mode is as follows:
the invention is further described with reference to the following figures and specific embodiments.
As shown in fig. 1 and 2, the invention comprises a section steel main beam 1, four handle suspension rods 2, handle bolts 3, six horizontal casters 4, two bases 5 and suspension rod nuts 6, and is characterized in that: two ends of the section steel main beam 1 are respectively fixed on two bases 5 through handle bolts 3; three horizontal casters 4 are arranged on each base 5; two non-communicated hollow chutes are arranged in the middle of the section steel main beam 1, a partition of 10cm is reserved between the two hollow chutes, two handle suspension rods 2 are installed in each chute, a suspension nut 6 is arranged at the lower end of each handle suspension rod 2, and the suspension nut 6 is connected with an expansion joint embedded assembly 8; each horizontal caster 4 is pivoted on a concrete beam 7. The section steel main beam adopts 10# channel steel of Q235A, the length is 1.5M, the handle suspension rod is an M12X 100 handle bolt, the handle bolt is an M12X 60 bolt, and the horizontal caster wheel is a 10# horizontal adjusting wheel; the suspension rod nut is an M12 long hole nut, and the base is made of a Q235 steel plate with the thickness of 2 mm.
The construction method for installing the suspension leveling positioning system by utilizing the super-long embedded assembly type expansion joint is characterized by comprising the following steps of:
1. manufacturing of suspension leveling and positioning system
The section steel girder 1 adopts Q235A's 10# channel-section steel, and length is 1.5M, respectively sets up a screw of M12 at 15cm department apart from 1 both ends edge of section steel girder, sets up 2 fretwork spouts that do not communicate in section steel girder 1 middle part, reserves 10 cm's wall between two fretwork spouts. The base 5 is made into an equilateral triangle with the side length of 15cm by adopting a Q235 steel plate with the thickness of 2mm, the center of the triangle is provided with an M12 screw hole, and three corners of the base 5 are respectively provided with a horizontal caster 4. The steel girder 1 is connected with the base 5 by using M12 handle bolts 3. The handle suspension rod 2 adopts a 10cm long M12 handle screw, and the suspension rod nut 6 adopts a 10cm long M12 nut; the handle suspension rods 2 are arranged in hollow chutes of the section steel main beam 1, and two chutes are arranged on each chute.
2. Installation of expansion joint embedded component
The embedded assembly 8 of pre-buried assembled expansion joint of 9 and expansion joint location muscle 10 processing preparation of pre-buried U shaped steel muscle, expansion joint pre-buried assembly 8 integral hoisting to expansion joint installation notch, check the 8 planar position of expansion joint pre-buried assembly, guarantee that its error is less than or equal to 2 mm. And two suspension rod nuts 6 are symmetrically fixed every 2m along the inner side of the expansion joint embedded component 8.
3. Suspension leveling positioning system installation
Arranging each suspension leveling positioning system above the expansion joint embedded component 8 along the transverse bridge span joint at intervals of 2m, aligning the suspension leveling positioning systems with a suspension rod nut 6 fixed on the expansion joint embedded component, connecting a handle suspension rod 2 with the suspension rod nut 6 fixed on the inner side of the expansion joint embedded component 8, and integrating the suspension leveling positioning systems with the expansion joint embedded component 8; the elevation of the expansion joint embedded assembly 8 is adjusted through rotation of the handle suspension rod 2, the smoothness and the cross slope of the expansion joint embedded assembly 8 are adjusted through movement of the horizontal caster 4 on the concrete beam 7, the elevation and the smoothness of the expansion joint embedded assembly are rechecked for the second time, and the installation error of the expansion joint embedded assembly is ensured to be less than or equal to 2 mm.
4. Pouring of concrete
C50 steel fiber concrete pouring box girder is adopted to reserve an expansion joint notch, concrete is poured in a manual low altitude mode, a 30-type vibrating rod is used for vibrating and compacting the concrete, and the vibrating rod is prevented from touching a suspension leveling positioning system as much as possible in the vibrating process; and after concrete pouring is finished, finishing surface light collection, covering by using a plastic film, and arranging warning signs around the manhole to avoid trampling by personnel.
5. Suspension leveling positioning system release
And after the concrete is initially set, rotating the handle suspension rod 2, and removing the connection between the suspension leveling positioning system and the expansion joint embedded component 8 to complete the positioning and installation of the expansion joint embedded component.

Claims (6)

1. Leveling positioning system is suspended in midair in overlength installation of pre-buried assembled expansion joint, including shaped steel girder, four handle suspension rods, six horizontal truckles, two bases, suspension rod nut, its characterized in that: two ends of the section steel main beam are respectively fixed on the two bases; three horizontal casters are arranged on each base; the middle part of the section steel main beam is provided with two hollow chutes which are not communicated, two handle suspension rods are arranged in each chute, the lower end of each handle suspension rod is provided with a suspension nut, and the suspension nuts are connected with the expansion joint embedded assembly; each horizontal caster takes the concrete beam as a pivot.
2. The system of claim 1, wherein the system comprises: the distance between the two hollow chutes is 10 cm.
3. The overlength installation of pre-buried assembled expansion joint suspends leveling positioning system in midair of claim 1 or 2 characterized in that: the section steel main beam is made of channel steel and is 1.5m in length.
4. The overlength installation of pre-buried assembled expansion joint suspends leveling positioning system in midair of claim 1 or 2 characterized in that: the handle suspension rod is a handle bolt.
5. The overlength installation of pre-buried assembled expansion joint suspends leveling positioning system in midair of claim 1 or 2 characterized in that: the base is made of a steel plate.
6. The construction method for installing, suspending, leveling and positioning system by using the ultra-long embedded assembly type expansion joint of claim 1 is characterized by comprising the following steps:
firstly, installation of an expansion joint embedded assembly: integrally hoisting the expansion joint embedded component to an expansion joint installation notch, checking the plane position of the expansion joint embedded component, and symmetrically fixing two suspension rod nuts every 2m along the inner side of the expansion joint embedded component;
secondly, installing a suspension leveling positioning system: arranging the suspension leveling and positioning system above the expansion joint embedded assembly along the transverse bridge span joint at intervals of 2m, aligning the suspension leveling and positioning system with a suspension rod nut fixed on the expansion joint embedded assembly, and connecting a handle suspension rod with the suspension rod nut fixed on the inner side of the expansion joint embedded assembly to enable the suspension leveling and positioning system and the expansion joint embedded assembly to form a whole; adjusting the elevation of the expansion joint embedded assembly through rotation of the handle suspension rod, adjusting the smoothness and the cross slope of the expansion joint embedded assembly through movement of the horizontal caster wheel on the concrete beam, and rechecking the elevation and the smoothness of the expansion joint embedded assembly for the second time to ensure that the installation error of the expansion joint embedded assembly is less than or equal to 2 mm;
thirdly, pouring concrete: c50 steel fiber concrete is poured into the box girder to reserve the slot opening of the expansion joint, the concrete is poured, and a 30-type vibrating rod is used for vibrating and compacting the concrete; after concrete pouring is finished, finishing surface light collection, covering with a plastic film, and arranging warning signs around a manhole to avoid trampling by personnel;
and fourthly, releasing the suspension leveling positioning system: and after the concrete is initially set, rotating the handle suspension rod, and removing the connection between the suspension leveling positioning system and the expansion joint embedded assembly to complete the positioning and installation of the expansion joint embedded assembly.
CN201911206426.1A 2019-11-29 2019-11-29 Embedded assembly type expansion joint overlength installation suspension leveling positioning system and construction method Pending CN110777650A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201911206426.1A CN110777650A (en) 2019-11-29 2019-11-29 Embedded assembly type expansion joint overlength installation suspension leveling positioning system and construction method
PCT/CN2020/123928 WO2021103895A1 (en) 2019-11-29 2020-10-27 Pre-embedded assembly type expansion joint ultra-long installation suspension leveling positioning system and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911206426.1A CN110777650A (en) 2019-11-29 2019-11-29 Embedded assembly type expansion joint overlength installation suspension leveling positioning system and construction method

Publications (1)

Publication Number Publication Date
CN110777650A true CN110777650A (en) 2020-02-11

Family

ID=69393415

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911206426.1A Pending CN110777650A (en) 2019-11-29 2019-11-29 Embedded assembly type expansion joint overlength installation suspension leveling positioning system and construction method

Country Status (1)

Country Link
CN (1) CN110777650A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111794107A (en) * 2020-07-14 2020-10-20 河北耀腾路桥工程有限公司 Adjusting device for bridge expansion joint
WO2021103895A1 (en) * 2019-11-29 2021-06-03 中建三局第二建设工程有限责任公司 Pre-embedded assembly type expansion joint ultra-long installation suspension leveling positioning system and construction method
CN114016434A (en) * 2021-12-29 2022-02-08 山东天齐置业集团股份有限公司 Construction method of large-span space torsional cross-section double-arch bridge

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021103895A1 (en) * 2019-11-29 2021-06-03 中建三局第二建设工程有限责任公司 Pre-embedded assembly type expansion joint ultra-long installation suspension leveling positioning system and construction method
CN111794107A (en) * 2020-07-14 2020-10-20 河北耀腾路桥工程有限公司 Adjusting device for bridge expansion joint
CN114016434A (en) * 2021-12-29 2022-02-08 山东天齐置业集团股份有限公司 Construction method of large-span space torsional cross-section double-arch bridge

Similar Documents

Publication Publication Date Title
CN110777650A (en) Embedded assembly type expansion joint overlength installation suspension leveling positioning system and construction method
WO2012173297A1 (en) Method for manufacturing solid three-dimensional concrete block and method for laying concrete tracks using concrete block manufactured using the method
US10006173B2 (en) Apparatus and method for servicing pavement
CN103255717A (en) Method for constructing hit-preventing wall
CN214992797U (en) Assembled road plate
CN113584956A (en) Built-in spacing module pin-connected panel track structure
CN211522857U (en) Embedded assembled expansion joint overlength installation suspension leveling positioning system
CN112411308A (en) Sleeve telescopic force transmission device for assembled pavement structure and construction method
CN103470003B (en) A kind of intelligent super-large spliced plateform system
CN113373817A (en) Precise adjusting construction method and device for wedge-shaped blocks of longitudinal and transverse slopes of precast beam
WO2021103895A1 (en) Pre-embedded assembly type expansion joint ultra-long installation suspension leveling positioning system and construction method
CN211922298U (en) Recyclable tunnel anchor cable strand embedded pipe fine adjustment device
CN110863652A (en) Precise positioning and mounting method for prefabricated and assembled double-section stand column
WO2012128411A1 (en) Manufacturing method for prefabricated solid-bed track having solid three-dimensional shape, and construction method for concrete solid-bed track using prefabricated solid-bed track manufactured by the method
CN113550176B (en) External spacing module pin-connected panel track structure
CN113295249B (en) Spliced flat-plate composite dynamic truck scale and mounting method thereof
CN213538591U (en) Concrete false joint dowel bar bracket
CN110872807A (en) Construction method of steel temporary bridge and steel temporary bridge
CN203583835U (en) Intelligent ultra-large spliced platform system
CN210482011U (en) Pre-buried positioner of cable-stay bridge cable steel pipe
JP2019078065A (en) Laying method of cantilever-type retaining wall
CN108625262B (en) Stud and construction method for fine adjustment of lifting height of pavement formwork of stud
CN113047111B (en) Airfield runway angle steel assembly type pavement slab structure
CN211815411U (en) Road edge brick laying tool
CN215164272U (en) Assembled precast concrete pavement slab assembly and pavement structure

Legal Events