CN110748017A - 一种高注合金蜂巢芯二次开孔密封防水方法 - Google Patents
一种高注合金蜂巢芯二次开孔密封防水方法 Download PDFInfo
- Publication number
- CN110748017A CN110748017A CN201911049437.3A CN201911049437A CN110748017A CN 110748017 A CN110748017 A CN 110748017A CN 201911049437 A CN201911049437 A CN 201911049437A CN 110748017 A CN110748017 A CN 110748017A
- Authority
- CN
- China
- Prior art keywords
- reserved
- hole
- diameter
- honeycomb core
- bottom plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/43—Floor structures of extraordinary design; Features relating to the elastic stability; Floor structures specially designed for resting on columns only, e.g. mushroom floors
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Gasket Seals (AREA)
Abstract
本发明涉及一种高注合金蜂巢芯二次开孔密封防水方法,包括如下步骤:S01、在模盒及底板上分别开孔a和孔b,底板上所开孔b的内径为设计所需的预留外管的外径,模盒上部所开孔a的直径比预留外管的外径大,然后将预留外管安装在底板上;S02、在预留外管内部承插预留内管,并于预留内管与预留外管之间的间隙内填充防水材料;S03、将预留外管周围的保护层板浇筑密实。本发明的有益效果是:本方法可以根据施工现场临时增设管路及设计变更的要求,及时做出同步预留,确保蜂巢芯无梁楼盖结构的安全性;本方法适用于高注合金蜂巢芯二次开孔要求,避免因二次开孔施工不当,造成密封防水性能降低。
Description
技术领域
本发明涉及建筑施工领域,尤其涉及一种高注合金蜂巢芯二次开孔密封防水方法。
背景技术
根据高注合金蜂巢芯的节点细化措施要求,在空心楼板施工过程中,存在穿过楼板的立管及阳台板地漏安装等预留孔洞,需要用到非常规规格的高注合金蜂巢芯材料进行预留施工。但是,由于加工基地内部生产工艺及二次装修方案暂未确定,难免存在少量的建筑设计缺陷。因此,施工过程中存在二次开孔的地方,尤其是在外部阳台板开孔时,模盒同底板一起直接开孔,必须考虑防水效果,而目前并没有很好的方法去解决防漏水问题。
发明内容
本发明所要解决的技术问题是提供一种高注合金蜂巢芯二次开孔密封防水方法,以克服上述现有技术中的不足。
本发明解决上述技术问题的技术方案如下:一种高注合金蜂巢芯二次开孔密封防水方法,包括如下步骤:
S01、在模盒及底板上分别开孔a和孔b,底板上所开孔b的内径为设计所需的预留外管的外径,模盒上部所开孔a的直径比预留外管的外径大,然后将预留外管安装在底板上;
S02、在预留外管内部承插预留内管,并于预留内管与预留外管之间的间隙内填充防水材料;
S03、将预留外管周围的保护层板浇筑密实。
在上述技术方案的基础上,本发明还可以做如下改进。
在上述方案中,预留外管采用钢制镀锌管材。
在上述方案中,防水材料为发泡密实防水材料。
在上述方案中,开孔a的直径比预留外管的外径大50mm~100mm。
本发明的有益效果是:
1、本方法可以根据施工现场临时增设管路及设计变更的要求,及时做出同步预留,确保蜂巢芯无梁楼盖结构的安全性;
2、本方法不用破坏蜂巢芯密肋梁中的内部结构,不在蜂巢芯密肋梁中开孔,也避免了蜂巢芯安装人员对密肋梁钢筋的破坏的影响,有效保证了蜂巢芯的防水效果;
3、开孔预留法高效、省时,有效避免重复返工,节省劳动力,确保了施工进度;
4、采取在模盒及底板上分别开孔的方法,有效保证了蜂巢芯的防水密封性;
5、模盒上部所开孔洞直径D大小比预留管直径稍大并将套管安装在底板上,使得内外管之间存在一定间隙,用于防水材料填充,确保防水密封效果;
6、本方法适用于高注合金蜂巢芯二次开孔要求,避免因二次开孔施工不当,造成密封防水性能降低。
附图说明
图1为本发明所述高注合金蜂巢芯二次开孔密封防水结构的结构示意图;
图2为本发明所述高注合金蜂巢芯二次开孔密封防水结构的俯视图;
图3为本发明所述高注合金蜂巢芯二次开孔密封防水结构的剖视图。
具体实施方式
以下结合附图对本发明的原理和特征进行描述,所举实例只用于解释本发明,并非用于限定本发明的范围。
实施例1,如图1、图2、图3所示,一种高注合金蜂巢芯二次开孔密封防水方法,包括如下步骤:
S01、在模盒1及底板2上分别开孔a110和孔b210,底板2上所开孔b210的内径为设计所需的预留外管3的外径,模盒1上部所开孔a110的直径比预留外管3的外径大,然后将预留外管3安装在底板2上;
S02、在预留外管3内部承插预留内管4,并于预留内管4与预留外管3之间的间隙内填充防水材料;
S03、将预留外管3周围的保护层板浇筑密实。
S03中,在浇筑时,通常将预留外管3周围的60mm厚保护层板浇筑密实。
实施例2,如图1、图2、图3所示,本实施例为在实施例1的基础上所进行的进一步改进,具体如下:
预留外管3优选采用钢制镀锌管材。
实施例3,如图1、图2、图3所示,本实施例为在实施例1或2的基础上所进行的进一步改进,具体如下:
防水材料优选为发泡密实防水材料。
实施例4,如图1、图2、图3所示,本实施例为在实施例1或2或3的基础上所进行的进一步改进,具体如下:
开孔a的直径比预留外管的外径大50mm~100mm,具体可为50mm、75mm、80mm或100mm,该范围可以确保防水密封效果。
尽管上面已经示出和描述了本发明的实施例,可以理解的是,上述实施例是示例性的,不能理解为对本发明的限制,本领域的普通技术人员在本发明的范围内可以对上述实施例进行变化、修改、替换和变型。
Claims (4)
1.一种高注合金蜂巢芯二次开孔密封防水方法,其特征在于,包括如下步骤:
S01、在模盒及底板上分别开孔a和孔b,底板上所开孔b的内径为设计所需的预留外管的外径,模盒上部所开孔a的直径比预留外管的外径大,然后将预留外管安装在底板上;
S02、在预留外管内部承插预留内管,并于预留内管与预留外管之间的间隙内填充防水材料;
S03、将预留外管周围的保护层板浇筑密实。
2.根据权利要求1所述的一种高注合金蜂巢芯二次开孔密封防水方法,其特征在于,所述预留外管采用钢制镀锌管材。
3.根据权利要求1所述的一种高注合金蜂巢芯二次开孔密封防水方法,其特征在于,所述防水材料为发泡密实防水材料。
4.根据权利要求1所述的一种高注合金蜂巢芯二次开孔密封防水方法,其特征在于,所述开孔a的直径比预留外管的外径大50mm~100mm。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911049437.3A CN110748017A (zh) | 2019-10-31 | 2019-10-31 | 一种高注合金蜂巢芯二次开孔密封防水方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911049437.3A CN110748017A (zh) | 2019-10-31 | 2019-10-31 | 一种高注合金蜂巢芯二次开孔密封防水方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110748017A true CN110748017A (zh) | 2020-02-04 |
Family
ID=69281377
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911049437.3A Pending CN110748017A (zh) | 2019-10-31 | 2019-10-31 | 一种高注合金蜂巢芯二次开孔密封防水方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110748017A (zh) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101063325A (zh) * | 2006-04-27 | 2007-10-31 | 邱则有 | 一种钢筋砼预制板 |
EP2213808A1 (de) * | 2009-01-29 | 2010-08-04 | Ziegelwerk Otto Staudacher GmbH & Co. KG | Decken- oder Wandbauteil, Halbfertigteil und Verfahren zu dessen Herstellung |
CN203258206U (zh) * | 2013-05-14 | 2013-10-30 | 中国建筑第八工程局有限公司 | 有套管穿楼板管道防渗漏结构 |
CN108661223A (zh) * | 2018-05-07 | 2018-10-16 | 浙江省建工集团有限责任公司 | 一种装配式建筑预制叠合板预留线槽的施工工艺 |
-
2019
- 2019-10-31 CN CN201911049437.3A patent/CN110748017A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101063325A (zh) * | 2006-04-27 | 2007-10-31 | 邱则有 | 一种钢筋砼预制板 |
EP2213808A1 (de) * | 2009-01-29 | 2010-08-04 | Ziegelwerk Otto Staudacher GmbH & Co. KG | Decken- oder Wandbauteil, Halbfertigteil und Verfahren zu dessen Herstellung |
CN203258206U (zh) * | 2013-05-14 | 2013-10-30 | 中国建筑第八工程局有限公司 | 有套管穿楼板管道防渗漏结构 |
CN108661223A (zh) * | 2018-05-07 | 2018-10-16 | 浙江省建工集团有限责任公司 | 一种装配式建筑预制叠合板预留线槽的施工工艺 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101575913A (zh) | 防止管道预留洞渗漏水的施工方法 | |
CN207469307U (zh) | 一种市政道路管线的检查井现浇施工的组合模板结构 | |
CN107366385A (zh) | 一种保温构造柱及其施工方法 | |
CN103741944B (zh) | 固定组件、含该固定组件的模板系统及墙体浇筑方法 | |
CN220318582U (zh) | 一种市政管井的井壁施工模板 | |
CN110748017A (zh) | 一种高注合金蜂巢芯二次开孔密封防水方法 | |
CN202164698U (zh) | 污水检查井钢模 | |
CN107762053A (zh) | 预制地下室管道模块及其制作方法 | |
CN208966025U (zh) | 一种楼面垂直无管道预留洞口预埋装置 | |
KR100805622B1 (ko) | 조립식 맨홀의 세그먼트 제작을 위한 거푸집 장치 | |
CN107419780B (zh) | 模块上下楼层无压力管之间的连接结构及方法 | |
CN113373985B (zh) | 地下室防水施工方法 | |
CN109518769A (zh) | 一种利用pvc止水节安装下水管道的方法及结构 | |
KR20170000255A (ko) | 복합공법을 이용한 욕실의 시공방법 및 이를 이용하여 형성된 욕실 | |
CN108086678A (zh) | 对拉螺栓端部处理方法 | |
CN104908150B (zh) | 一种管道井制作模板及基于工厂化生产管道井的方法 | |
CN211923600U (zh) | 高层住宅外墙穿插施工截水系统 | |
CN211499772U (zh) | 用于屋面女儿墙的模板结构 | |
CN107059944A (zh) | 地下室渗水点渐堵漏结构及施工方法 | |
CN112628477A (zh) | 一种带伸缩及防排水功能的排水管预埋装置及安装方法 | |
CN215368736U (zh) | 一种结构板预留水平洞口模具 | |
CN110565953A (zh) | 一种预留管道洞口的施工方法 | |
CN101761253A (zh) | 带内衬耐磨钢板落煤筒的施工方法 | |
CN105113783B (zh) | 一种石膏现浇墙体的施工模板及其施工方法 | |
CN114809071B (zh) | 以格构柱施工地下结构板的节点及割除格构柱的防水方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200204 |
|
RJ01 | Rejection of invention patent application after publication |