CN110747706A - Construction method for replacing weak soil of foundation bearing layer - Google Patents

Construction method for replacing weak soil of foundation bearing layer Download PDF

Info

Publication number
CN110747706A
CN110747706A CN201910947268.9A CN201910947268A CN110747706A CN 110747706 A CN110747706 A CN 110747706A CN 201910947268 A CN201910947268 A CN 201910947268A CN 110747706 A CN110747706 A CN 110747706A
Authority
CN
China
Prior art keywords
concrete
layer
foundation
foundation pit
tamping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910947268.9A
Other languages
Chinese (zh)
Inventor
范伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Second Metallurgy Group Co Ltd
Original Assignee
China Second Metallurgy Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Second Metallurgy Group Co Ltd filed Critical China Second Metallurgy Group Co Ltd
Priority to CN201910947268.9A priority Critical patent/CN110747706A/en
Publication of CN110747706A publication Critical patent/CN110747706A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/22Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
    • E01C11/224Surface drainage of streets
    • E01C11/225Paving specially adapted for through-the-surfacing drainage, e.g. perforated, porous; Preformed paving elements comprising, or adapted to form, passageways for carrying off drainage
    • E01C11/226Coherent pavings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C21/00Apparatus or processes for surface soil stabilisation for road building or like purposes, e.g. mixing local aggregate with binder
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/10Coherent pavings made in situ made of road-metal and binders of road-metal and cement or like binders
    • E01C7/14Concrete paving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Repair (AREA)

Abstract

The application provides a construction method for replacing weak soil of a foundation bearing layer, and belongs to the technical field of road engineering construction. The construction method comprises the following steps: step one, base layer treatment, namely excavating a foundation pit on a road surface and tamping the excavated foundation pit; paving broken stones on the tamped foundation pit surface, and tamping the broken stone cushion layer; and step three, pouring concrete, namely pouring the concrete on the tamped broken stone cushion layer to form a concrete pavement and maintaining the pavement. The application provides a construction method of replacement ground holding layer weak soil, through the concrete that permeates water not only avoided the inconvenience that ponding brought, has good effect to washing hand ground noise and regulation space temperature and humidity moreover. The water permeability of the foundation is guaranteed through the broken stone cushion layer which is always laid in the foundation pit, the frost heaving resistance of the pavement structure can be improved, the load can be diffused, and the deformation of the foundation is reduced.

Description

Construction method for replacing weak soil of foundation bearing layer
Technical Field
The invention belongs to the technical field of road engineering construction, and particularly relates to a construction method for replacing weak soil of a foundation bearing layer, which is used for improving the condition of a soil foundation, improving the frost heaving resistance of a pavement structure and reducing the deformation of the soil foundation.
Background
In the prior art, when the pavement road construction is carried out, the soil foundation is diversified, and when the soil foundation is poor in condition, the problems of frozen soil, low frost heaving resistance, even pavement sinking and the like can be caused, so that the pavement concrete is seriously damaged, and the trip safety of people is influenced.
Disclosure of Invention
In view of the above, the present invention provides a construction method for replacing weak soil of a foundation bearing layer, so as to solve or overcome at least one technical problem in the prior art.
The application provides a construction method for replacing weak soil of a foundation bearing layer, which comprises the following steps:
step one, base layer treatment, namely excavating a foundation pit on a road surface and tamping the excavated foundation pit;
paving broken stones on the tamped foundation pit surface, and tamping the broken stone cushion layer;
and step three, pouring concrete, namely pouring the concrete on the tamped broken stone cushion layer to form a concrete pavement and maintaining the pavement.
Preferably, the step one includes:
and (4) erecting the mold in a working area, and controlling the height, the verticality and the water return gradient of the template.
Preferably, in the step one,
firstly, removing sundries such as humus soil;
adopting machinery to excavate a foundation pit, reserving a soil layer with the thickness of 10-20 cm on the surface of the foundation pit for manual cleaning, and preventing the foundation pit from being excavated too deep;
and tamping the foundation pit surface by using a tamping machine, and enabling the soil layer density of the foundation pit surface to reach a preset numerical value.
Preferably, the first step further comprises:
and detecting the density of the soil layer on the foundation pit surface after tamping by adopting a cutting ring method.
Preferably, in the second step, the quality of the crushed stone is controlled, impurities are removed, and the size range of the crushed stone particles is controlled.
Preferably, in the second step, the thickness of the laid gravel is more than or equal to 5cm, and finally, a tamping machine is adopted to tamp the gravel cushion layer.
Preferably, in the third step, the step (c),
paying off the gravel cushion layer at fixed points, wherein a preset distance is formed between every two points;
arranging a baffle plate at the edge of the gravel cushion layer;
and finally, pouring concrete to a preset elevation.
Preferably, before the concrete is poured, water is sprinkled on the gravel cushion layer, or a layer of mortar is laid.
Preferably, the concrete is pervious concrete.
Preferably, the time for transporting and paving the pervious concrete is less than or equal to 15 minutes, and the pervious concrete is paved in a blocking and cabin-separating mode;
tamping the pervious concrete by adopting a flat vibrator;
and coating the transparent sealing agent on the pervious concrete after the pervious concrete is formed and dried.
The application has the following beneficial effects:
the application provides a construction method of replacement ground holding layer weak soil, through the concrete that permeates water not only avoided the inconvenience that ponding brought, has good effect to washing hand ground noise and regulation space temperature and humidity moreover. The water permeability of the foundation is guaranteed through the broken stone cushion layer which is always laid in the foundation pit, the frost heaving resistance of the pavement structure can be improved, the load can be diffused, and the deformation of the foundation is reduced.
Drawings
The above and other objects, features and advantages of the present invention will become more apparent from the following description of the embodiments of the present invention with reference to the accompanying drawings.
Fig. 1 is a construction flow chart of a replacement foundation bearing layer weak soil provided according to an embodiment of the invention.
Detailed Description
Various embodiments of the present invention will be described in more detail below with reference to the accompanying drawings. Like elements in the various figures are denoted by the same or similar reference numerals. For purposes of clarity, the various features in the drawings are not necessarily drawn to scale.
As shown in fig. 1, the present invention provides a construction method for replacing weak soil of a foundation bearing layer, comprising:
and (5) erecting the mold, wherein the mold is erected in a required working area. Constructors firstly separate the vertical formwork and the regional vertical formwork according to design requirements, and control the height, the perpendicularity and the water-reflecting gradient of the formwork in the process of vertical formwork. The region that makes the needs excavation through founding the mould is more regular, also plays the guard action, struts the region that will excavate through the template.
Step one, base layer treatment, namely excavating foundation pits on a road surface, and tamping the excavated foundation pits to preset requirements; firstly, the humus is removed, and the hidden trouble of ground subsidence in the future is avoided. When mechanical excavation is adopted, reserving a soil layer with the thickness of 10 cm-20 cm on the surface of the foundation pit for manual cleaning, and preventing the excavation from being too deep; when the excavation is too deep, backfilling with soil or fine stones or the like cannot be performed. And (4) tamping the plain soil by using a tamping machine to achieve the compactness of ramming the plain soil according to the design requirement. And (5) testing the density of the soil layer on the surface of the foundation pit by adopting a cutting ring method. If the soil layer density of the foundation pit surface does not meet the design requirement, tamping should be carried out again until the design requirement is met.
The cutting ring method is to cut a soil sample by a cutting ring with known mass and volume, the mass of the cutting ring is subtracted after weighing to obtain the mass of the soil, and the volume of the cutting ring is the volume of the soil, so that the density of the soil can be obtained.
Paving broken stones on the tamped foundation pit surface, and tamping the broken stone cushion layer;
firstly, the quality of the crushed stone is controlled, impurities are removed, and the size range of the crushed stone particles is controlled. Organic matters such as weathered macadam or branches are prevented from being mixed in the water, and the quality of macadam particles is guaranteed. When backfilling is carried out, elevation control points are arranged in the site, and the control points are protected. The thickness of the virtual pavements is used at the beginning so as to achieve the thickness of the gravel cushion layer after the gravel is tamped.
And (3) the thickness of the broken stones which are virtually paved (before the broken stones are tamped by a tamping machine) is more than or equal to 5cm, and finally, the tamping machine is adopted to tamp the broken stone cushion layer. In actual working conditions, specific analysis is carried out according to differences of the width, the load and the application of the pavement, and the size and the paving thickness of the applied broken stones are finally determined.
And step three, pouring concrete, namely pouring the concrete on the tamped broken stone cushion layer to form a concrete pavement and maintaining the pavement.
Paying off the gravel cushion layer at fixed points, wherein the interval between every two points is 10 meters; arranging a baffle plate at the edge of the gravel cushion layer; and finally, pouring concrete to a preset elevation.
In this embodiment, before the concrete is poured, water is sprinkled on the gravel cushion layer, or a layer of mortar is laid. The gravel cushion layer is sprayed with water or paved with mortar, so that the gravel cushion layer and the concrete are better condensed together, and the condensing effect is better.
In this embodiment, the concrete used in the above description is pervious concrete. The pervious concrete has good water permeability, and plays a good role in the permeability of water on the ground and the ecological environment.
In this embodiment, the pervious concrete is a dry concrete material, which has a fast initial setting, so the transport time is generally controlled according to the climatic conditions. The time for transporting and paving the pervious concrete is less than or equal to 15 minutes, paving is carried out in a blocking and separating mode, and the loose paving coefficient is 1.1. The concrete is evenly spread on the gravel cushion layer, the flatness is found by a drawing ruler, and a certain flooding degree is controlled.
When concrete is poured, the thickness and the strength must be controlled, and the strength stone detection work of the concrete is performed according to the construction drawing, so that the design standard can be met.
Tamping the pervious concrete by adopting a flat vibrator; after the paving is finished, the elevation and the flatness are inspected to meet the requirements. When the temperature is high, the concrete pavement is required to be immediately covered with a plastic film to keep the moisture in order to reduce the evaporation of the moisture. The water spraying can also be adopted for curing, and all the curing periods are not less than 7 days, so that the strength of the product is gradually improved in the curing period. The curing time is determined according to the construction temperature, the curing period is generally 14-21 days, the curing period is not less than 14 days at high temperature, the curing period is not less than 21 days at low temperature, the construction is carried out at the temperature of below 5 ℃, and the curing period is not less than 28 days.
And coating the transparent sealing agent on the pervious concrete after the pervious concrete is formed and dried. The transparent sealing agent can enhance durability and aesthetic property, and prevent the holes of the pervious concrete from being polluted and blocked due to overlong time.
The application provides a construction method of replacement foundation bearing stratum weak soil, through the concrete that permeates water not only avoided the inconvenience that ponding brought, has good effect to washing hand ground noise and regulation space temperature and humidity moreover. The water permeability of the foundation is guaranteed through the broken stone cushion layer which is always laid in the foundation pit, the frost heaving resistance of the pavement structure can be improved, the load can be diffused, and the deformation of the foundation is reduced. It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising an … …" does not exclude the presence of other identical elements in a process, method, article, or apparatus that comprises the element.
Finally, it should be noted that: it should be understood that the above examples are only for clearly illustrating the present invention and are not intended to limit the embodiments. Other variations and modifications will be apparent to persons skilled in the art in light of the above description. And are neither required nor exhaustive of all embodiments. And obvious variations or modifications of the invention may be made without departing from the scope of the invention.

Claims (10)

1. A construction method for replacing weak soil of a foundation bearing layer is characterized by comprising the following steps:
step one, base layer treatment, namely excavating a foundation pit on a road surface and tamping the excavated foundation pit;
paving broken stones on the tamped foundation pit surface, and tamping the broken stone cushion layer;
and step three, pouring concrete, namely pouring the concrete on the tamped broken stone cushion layer to form a concrete pavement and maintaining the pavement.
2. The method for constructing a replacement foundation support layer weak soil according to claim 1, wherein the step one step further comprises:
and (4) erecting the mold in a working area, and controlling the height, the verticality and the water return gradient of the template.
3. The method for constructing a replacement foundation support layer weak soil according to claim 1, wherein in the first step,
firstly, removing sundries such as humus soil;
adopting machinery to excavate a foundation pit, reserving a soil layer with the thickness of 10-20 cm on the surface of the foundation pit for manual cleaning, and preventing the foundation pit from being excavated too deep;
and tamping the foundation pit surface by using a tamping machine, and enabling the soil layer density of the foundation pit surface to reach a preset numerical value.
4. The method for constructing a replacement foundation support layer weak soil according to claim 3, wherein the first step further comprises:
and detecting the density of the soil layer on the foundation pit surface after tamping by adopting a cutting ring method.
5. The method as claimed in claim 1, wherein in the second step, the quality of the crushed stone is controlled, impurities are removed, and the size range of the crushed stone particles is controlled.
6. The construction method for replacing the weak soil of the foundation bearing stratum according to claim 1, wherein in the second step, the thickness of the laid broken stones is greater than or equal to 5cm, and finally, a tamping machine is adopted to tamp the broken stone cushion layer.
7. The method for constructing a replacement foundation support layer weak soil according to claim 1, wherein in the third step,
paying off the gravel cushion layer at fixed points, wherein a preset distance is formed between every two points;
arranging a baffle plate at the edge of the gravel cushion layer;
and finally, pouring concrete to a preset elevation.
8. The method of claim 7, wherein water is sprayed on the gravel cushion layer or a mortar layer is laid before the concrete is poured.
9. The method for constructing a weak soil of replacement foundation support layer according to any one of claims 1 to 8, wherein the concrete is pervious concrete.
10. The method of constructing a replacement foundation support layer weak soil according to claim 9,
the time for transporting and paving the pervious concrete is less than or equal to 15 minutes, and the pervious concrete is paved in a blocking and compartment separation mode;
tamping the pervious concrete by adopting a flat vibrator;
and coating the transparent sealing agent on the pervious concrete after the pervious concrete is formed and dried.
CN201910947268.9A 2019-09-30 2019-09-30 Construction method for replacing weak soil of foundation bearing layer Pending CN110747706A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910947268.9A CN110747706A (en) 2019-09-30 2019-09-30 Construction method for replacing weak soil of foundation bearing layer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910947268.9A CN110747706A (en) 2019-09-30 2019-09-30 Construction method for replacing weak soil of foundation bearing layer

Publications (1)

Publication Number Publication Date
CN110747706A true CN110747706A (en) 2020-02-04

Family

ID=69277682

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910947268.9A Pending CN110747706A (en) 2019-09-30 2019-09-30 Construction method for replacing weak soil of foundation bearing layer

Country Status (1)

Country Link
CN (1) CN110747706A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115323854A (en) * 2022-10-12 2022-11-11 中交投资南京有限公司 Construction method of highway subgrade

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103195051A (en) * 2013-03-27 2013-07-10 山东大学 Limestone soil and pervious concrete pile composite foundation and treatment method thereof
CN104153383A (en) * 2014-08-08 2014-11-19 中建五局土木工程有限公司 Marine facies soft soil foundation structure and processing method thereof
CN108252181A (en) * 2018-01-02 2018-07-06 广东美景园林建设有限公司 A kind of pervious concrete pavement structure and construction method
CN109868700A (en) * 2019-01-23 2019-06-11 杜毅 A kind of highway engineering construction soft groundsill reinforcing equipment and reinforcement means
EP2478059B1 (en) * 2009-09-17 2020-10-14 Latexfalt B.V. Storage stable emulsions from low penetration grade bituminous binders

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2478059B1 (en) * 2009-09-17 2020-10-14 Latexfalt B.V. Storage stable emulsions from low penetration grade bituminous binders
CN103195051A (en) * 2013-03-27 2013-07-10 山东大学 Limestone soil and pervious concrete pile composite foundation and treatment method thereof
CN104153383A (en) * 2014-08-08 2014-11-19 中建五局土木工程有限公司 Marine facies soft soil foundation structure and processing method thereof
CN108252181A (en) * 2018-01-02 2018-07-06 广东美景园林建设有限公司 A kind of pervious concrete pavement structure and construction method
CN109868700A (en) * 2019-01-23 2019-06-11 杜毅 A kind of highway engineering construction soft groundsill reinforcing equipment and reinforcement means

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115323854A (en) * 2022-10-12 2022-11-11 中交投资南京有限公司 Construction method of highway subgrade

Similar Documents

Publication Publication Date Title
CN103774616B (en) From the Ecological Retaining Wall construction method that embedded block is built by laying bricks or stones
CN203295913U (en) Novel ecological permeable road structure
CN109958018A (en) A kind of heavy rainfall urban road water-permeable pavement structure and its construction method
CN107989153A (en) A kind of novel construction method for building sponge city
CN111778806A (en) Paving process for sidewalk floor tiles and floor tile structure thereof
Sattikhodjaevich DEVELOPMENT OF MEASURES TO ENSURE CLIMATIC STABILITY OF HIGHWAYS BUILT ON EMPTY SOIL
CN110747706A (en) Construction method for replacing weak soil of foundation bearing layer
CN110042723A (en) The construction method of the permeable road of full precast splice type
CN106592565A (en) Dam fixing and protecting construction method using soil stabilizer in land reclamation project
CN111549603A (en) Pavement considering water load coupling and construction method thereof
Mata Sedimentation of pervious concrete pavement systems
KR20110100805A (en) Pavement road including a plurality of water-permeable layers and water-bearing layers and pavement method of the road
CN113186951B (en) Ecological reinforcing method for loose coarse-grained mixed soil slope
CN204982588U (en) Basic unit on square, parking area and garden way structure of mating formation
CN114837038A (en) Construction method of barrier pedestrian path permeable base layer by adopting paver
JP6173370B2 (en) Distributed water storage method
CN113279297A (en) Construction method for improving roadbed seismic resistance
CN208486146U (en) A kind of novel filter infiltration garden road step and sunk type square laying structure
Zhu et al. Treatment of collapsible loess foundation
CN110820458A (en) Sidewalk and floor tile combined structure and paving construction method thereof
CN109629364A (en) A kind of anti-accumulation of salt in the surface soil method in garden paving road surface
CN104195918A (en) Method for paving face bricks on pavement of pedestrian walkway
CN109183551A (en) A kind of porous colour gap bituminous pavement and its construction method
Ulfiana et al. Minimize surface runoff from parking lots with permeable pavement systems
CN213681563U (en) Sidewalk rainwater drainage and reuse structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200204

RJ01 Rejection of invention patent application after publication