CN110717683A - Method and system for generating monitoring information expert experience base - Google Patents

Method and system for generating monitoring information expert experience base Download PDF

Info

Publication number
CN110717683A
CN110717683A CN201910978973.5A CN201910978973A CN110717683A CN 110717683 A CN110717683 A CN 110717683A CN 201910978973 A CN201910978973 A CN 201910978973A CN 110717683 A CN110717683 A CN 110717683A
Authority
CN
China
Prior art keywords
monitoring information
expert experience
type
under
selection unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910978973.5A
Other languages
Chinese (zh)
Inventor
曹德发
李志华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Power Grid Co Ltd
Meizhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Original Assignee
Guangdong Power Grid Co Ltd
Meizhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Power Grid Co Ltd, Meizhou Power Supply Bureau of Guangdong Power Grid Co Ltd filed Critical Guangdong Power Grid Co Ltd
Priority to CN201910978973.5A priority Critical patent/CN110717683A/en
Publication of CN110717683A publication Critical patent/CN110717683A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/90Details of database functions independent of the retrieved data types
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Theoretical Computer Science (AREA)
  • Strategic Management (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Databases & Information Systems (AREA)
  • Development Economics (AREA)
  • Data Mining & Analysis (AREA)
  • Educational Administration (AREA)
  • General Engineering & Computer Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Game Theory and Decision Science (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Water Supply & Treatment (AREA)
  • Public Health (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a method and a system for generating a monitoring information expert experience base, wherein the method comprises the steps of selecting a station type, an equipment type under the station type and an interval model under the equipment type corresponding to monitoring information through a selection module; and inputting expert experience information corresponding to the monitoring information under the interval type through an expert experience generation module to generate a monitoring information expert experience library. According to the invention, through integrating the experience of monitoring information audit by experts and finally integrating the experience into an expert experience library which can be used for checking and accepting the monitoring information, a plurality of problems caused by traditional manual audit can be avoided, a power grid company can be assisted to realize intelligent check and acceptance, the workload of manual audit is greatly reduced, and the normalization and the accuracy of scheduling and monitoring information are guaranteed, so that the operation safety of equipment and a power grid is guaranteed, the working efficiency of regulation and control integration is improved, the method has positive significance for improving the regulation and control integration level, and huge economic benefits and social benefits are brought to the power grid company.

Description

Method and system for generating monitoring information expert experience base
Technical Field
The invention relates to the technical field of power system information, in particular to a method and a system for generating a monitoring information expert experience base.
Background
With the rapid development of regulation and control integration and the deepened application of unattended transformer substations, a power grid company puts higher requirements on the quality of monitoring information, the monitoring information and alarm setting of an access scheduling end are standardized, and new challenges are brought to the access of the monitoring information of the transformer substations.
At present, in the face of a large amount of monitoring information of a transformer substation, a manual auditing method is mainly adopted for centralized access work of the transformer substation, and the problems of complex basic data collection process, multiple information table versions, easy compilation error, no fixed auditing standard and the like exist, so that the universality and the wide applicability are not realized.
Therefore, a comprehensive and widely-applied monitoring information expert experience base is urgently needed to be established so as to accumulate and form expert auditing experience and assist a power grid company to realize better monitoring information auditing.
Disclosure of Invention
The invention provides a method and a system for generating a monitoring information expert experience base, which aim to overcome the defects of the prior art.
In order to achieve the above purpose, the present invention provides the following technical solutions:
in a first aspect, an embodiment of the present invention provides a method for generating a monitoring information expert experience library, where the method is implemented by a system for generating a monitoring information expert experience library, where the system for generating a monitoring information expert experience library includes a selection module and an expert experience generation module, and the method includes:
selecting a station type corresponding to monitoring information, a device type under the station type and an interval model under the device type through the selection module;
and inputting expert experience information corresponding to the monitoring information under the interval type through the expert experience generation module to generate a monitoring information expert experience library.
Further, in the method for generating the expert experience base of the monitoring information, the selection module comprises a station type selection unit, an equipment type selection unit and an interval model selection unit;
correspondingly, the step of selecting the station type corresponding to the monitoring information, the equipment type under the station type and the interval model under the equipment type through the selection module comprises the following steps:
selecting a station type corresponding to the monitoring information through the station type selection unit;
selecting the equipment type under the station type through the equipment type selection unit;
and selecting the interval model under the equipment type through the interval model selecting unit.
Further, in the method for generating the monitoring information expert experience base, the monitoring information expert experience base further comprises a modification module;
correspondingly, the method further comprises the following steps:
and newly adding, modifying or deleting the monitoring information expert experience base through the modification module.
In a second aspect, an embodiment of the present invention provides a system for generating a monitoring information expert experience library, where the system includes a selection module and an expert experience generation module;
the selection module is used for a worker to select a station type corresponding to the monitoring information, a device type under the station type and an interval model under the device type according to the monitoring information;
and the expert experience generating module is used for the staff to input corresponding expert experience information under the interval type so as to generate a monitoring information expert experience base.
Furthermore, in the generation system of the expert experience base of the monitoring information, the selection module comprises a station type selection unit, an equipment type selection unit and an interval model selection unit; wherein the content of the first and second substances,
the station type selection unit is used for a worker to select a station type corresponding to the monitoring information according to the monitoring information;
the equipment type selection unit is used for allowing a worker to select the equipment type under the station type;
the interval model selection unit is used for a worker to select the interval model under the equipment type.
Further, in the system for generating the monitoring information expert experience base, the monitoring information expert experience base further comprises a modification module;
and the modification module is used for a worker to newly add, modify or delete the monitoring information expert experience base.
According to the method and the system for generating the expert experience base of the monitoring information, provided by the embodiment of the invention, the experience of monitoring information is checked by the integrated experts and finally integrated into the expert experience base which can be used for checking and accepting the monitoring information, so that various problems caused by traditional manual checking can be avoided, a power grid company can be assisted to realize intelligent checking and accepting, the workload of manual checking is greatly reduced, the normalization and the accuracy of scheduling and monitoring information are ensured, the operation safety of equipment and a power grid is ensured, the working efficiency of regulation and control integration is improved, the method and the system have positive significance for improving the regulation and control integration level, and great economic benefits and social benefits are brought to the power grid company.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without inventive exercise.
Fig. 1 is a schematic flowchart of a method for generating a monitoring information expert experience base according to an embodiment of the present invention;
fig. 2 is a schematic structural diagram of a system for generating a monitoring information expert experience base according to a second embodiment of the present invention.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings and examples. It is to be understood that the specific embodiments described herein are merely illustrative of the invention and are not limiting of the invention. It should be further noted that, for the convenience of description, only some of the structures related to the present invention are shown in the drawings, not all of the structures.
Example one
Referring to fig. 1, a flow diagram of a method for generating a monitoring information expert experience base according to an embodiment of the present invention is shown, where the method is implemented by a system for generating a monitoring information expert experience base, and the system for generating a monitoring information expert experience base includes a selection module and an expert experience generation module. The method specifically comprises the following steps:
s101, selecting a station type corresponding to monitoring information, a device type under the station type and an interval model under the device type through the selection module;
preferably, the selection module comprises a station type selection unit, an equipment type selection unit and an interval model selection unit;
correspondingly, the step S102 further includes:
and (1) selecting the station type corresponding to the monitoring information through the station type selection unit.
It should be noted that the plant station types are divided into an intelligent station and a conventional station, and because the types are different, the requirements for monitoring information are different, and expert experience information is also different, the module is provided with two types for selection.
And (2) selecting the equipment type under the station type through the equipment type selection unit.
It should be noted that, after the plant type is selected in step (1), a device type needs to be set under each plant type to provide a selection. The device types are mainly divided according to voltage grades and device attributes, and are divided as follows: 220kV main transformer, 220kV bus, 220kV circuit, 110kV bus, 110kV circuit, 10kV equipment, public equipment.
And (3) selecting the interval model under the equipment type through the interval model selecting unit.
It should be noted that a specific interval model needs to be set below each device type, so as to facilitate selection of the specific interval model for inputting model information. The specific settings are as follows:
220kV bus: 220kV bus equipment, 220kV bus coupler and 220 kVPT;
220kV line: 220kV line interval and 220kV bypass interval;
110kV bus: 110kV bus equipment, 110kV bus coupler and 110 kVPT;
110kV line: 110kV line interval and 110kV bypass interval;
10kV equipment: the transformer comprises a 10kV line, a 10kV section, a 10kVPT, a 10kV capacitor, a 10kV reactor, a 10kV station transformer and a 10kV grounding transformer;
a common device: the system comprises a direct current system, an alternating current system, a spare power automatic switching system, a stability control system, an arc extinction system, a fire fighting system, a UPS system, a PT parallel device, a fault recorder and the like.
And S102, inputting expert experience information corresponding to the monitoring information under the interval type through the expert experience generation module to generate a monitoring information expert experience library.
It should be noted that the expert experience information may be standardized monitoring information in the "monitoring information and alarm setting specification of the power grid regulation and control integrated equipment", or may be experience information formed in the process of examining and controlling the point table by the expert. As shown in table 1, the following input interfaces are provided in the system, which mainly include: expert information specification naming, information classification and information uploading attribute:
table 1: expert experience information table
Figure BDA0002234569990000051
The expert information is named in a standard mode, and standard information is input and is used for comparing with monitoring information to be checked and checking;
the information classification, the information classification provides accident, abnormal, out-of-limit, inform, five kinds of switch information for selection, thus, when the expert inputs the standardized information, the information can be classified and set at the same time, such as '2220 kV x line switch control loop disconnection', which belongs to abnormal information;
the information uploading attribute mainly defines the mode of the monitoring information uploading scheduling monitoring terminal, and comprises the following steps: the system comprises a real-time information window, an accident information window, an abnormal information window, an informing information window, whether a photon plate is added or not, a voice alarm and whether the confirmation mode is automatic or not, wherein the eight attributes are selected in a mode of yes and no, the requirement of sending monitoring information to a dispatching monitoring end is defined, such as '220 kV x line switch control loop disconnection', the information real-time alarm window, the abnormal information window, whether the light plate is added or not and the voice alarm are set to be yes, the other setting is no, when the abnormal information occurs, the two monitoring windows of an implementation alarm window and the abnormal information window of the dispatching monitoring end need to be displayed, the light plate is set in an interval picture, the voice alarm needs to be started, and automatic confirmation cannot be carried out (the manual confirmation party can return).
Preferably, the monitoring information expert experience base further comprises a modification module;
correspondingly, the method further comprises the following steps:
and newly adding, modifying or deleting the monitoring information expert experience base through the modification module.
It should be noted that, after the expert experience base of the monitoring information is generated, the expert experience base is not invariable, when the information of the experience base changes or an error is found and needs to be added, modified or deleted, the information can be added according to the steps generated by the expert experience base information, or the information can be modified or deleted by entering the expert experience base of the monitoring information through a modification module or according to the same method.
According to the method for generating the expert experience base of the monitoring information, provided by the embodiment of the invention, the experience of monitoring information is integrated and the expert experience base of the monitoring information can be finally integrated into the expert experience base which can be used for checking and accepting the monitoring information, so that various problems caused by traditional manual checking can be avoided, a power grid company can be assisted to realize intelligent checking and accepting, the workload of manual checking and accepting is greatly reduced, the normalization and the accuracy of scheduling and monitoring information are ensured, the operation safety of equipment and a power grid is ensured, the working efficiency of regulation and control integration is improved, the method has positive significance for improving the regulation and control integration level, and great economic benefits and social benefits are brought to the power grid company.
Example two
Referring to fig. 2, an embodiment of the present invention provides a system for generating an expert experience database of monitoring information, where the system includes a selection module 10 and an expert experience generation module 20;
the selection module 10 is configured to enable a worker to select, according to monitoring information, a station type corresponding to the monitoring information, a device type in the station type, and an interval model in the device type;
the expert experience generating module 20 is used for the staff to input the corresponding expert experience information under the interval type to generate the monitoring information expert experience base.
Preferably, the selection module 10 includes a station type selection unit, an equipment type selection unit and an interval model selection unit; wherein the content of the first and second substances,
the station type selection unit is used for a worker to select a station type corresponding to the monitoring information according to the monitoring information;
the equipment type selection unit is used for allowing a worker to select the equipment type under the station type;
the interval model selection unit is used for a worker to select the interval model under the equipment type.
Preferably, the monitoring information expert experience base further comprises a modification module;
and the modification module is used for a worker to newly add, modify or delete the monitoring information expert experience base.
According to the system for generating the expert experience base of the monitoring information, which is provided by the embodiment of the invention, the experience of monitoring information is integrated and the experience base of the monitoring information is finally integrated into the expert experience base which can be used for checking and accepting the monitoring information, so that various problems caused by traditional manual checking can be avoided, a power grid company can be assisted to realize intelligent checking and accepting, the workload of manual checking and accepting is greatly reduced, the normalization and the accuracy of scheduling and monitoring information are ensured, the operation safety of equipment and a power grid is ensured, the working efficiency of regulation and control integration is improved, the system has positive significance for improving the regulation and control integration level, and great economic benefits and social benefits are brought to the power grid company.
The above embodiments are merely to illustrate the technical solutions of the present invention, and not to limit the same; although the present invention has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; and such modifications or substitutions do not depart from the spirit and scope of the corresponding technical solutions of the embodiments of the present invention.

Claims (6)

1. A generation method of a monitoring information expert experience base is characterized in that the method is realized by a generation system of the monitoring information expert experience base, the generation system of the monitoring information expert experience base comprises a selection module and an expert experience generation module, and the method comprises the following steps:
selecting a station type corresponding to monitoring information, a device type under the station type and an interval model under the device type through the selection module;
and inputting expert experience information corresponding to the monitoring information under the interval type through the expert experience generation module to generate a monitoring information expert experience library.
2. The method for generating the expert experience base for monitoring information according to claim 1, wherein the selection module comprises a station type selection unit, an equipment type selection unit and an interval model selection unit;
correspondingly, the step of selecting the station type corresponding to the monitoring information, the equipment type under the station type and the interval model under the equipment type through the selection module comprises the following steps:
selecting a station type corresponding to the monitoring information through the station type selection unit;
selecting the equipment type under the station type through the equipment type selection unit;
and selecting the interval model under the equipment type through the interval model selecting unit.
3. The method for generating a monitoring information expert experience base according to claim 1, wherein the monitoring information expert experience base further comprises a modification module;
correspondingly, the method further comprises the following steps:
and newly adding, modifying or deleting the monitoring information expert experience base through the modification module.
4. The system for generating the expert experience base of the monitoring information is characterized by comprising a selection module and an expert experience generation module;
the selection module is used for a worker to select a station type corresponding to the monitoring information, a device type under the station type and an interval model under the device type according to the monitoring information;
and the expert experience generating module is used for the staff to input corresponding expert experience information under the interval type so as to generate a monitoring information expert experience base.
5. The system for generating an expert experience base for monitoring information according to claim 4, wherein the selection module includes a station type selection unit, an equipment type selection unit and an interval model selection unit; wherein the content of the first and second substances,
the station type selection unit is used for a worker to select a station type corresponding to the monitoring information according to the monitoring information;
the equipment type selection unit is used for allowing a worker to select the equipment type under the station type;
the interval model selection unit is used for a worker to select the interval model under the equipment type.
6. The system for generating a monitoring information expert experience base according to claim 4, wherein the monitoring information expert experience base further includes a modification module;
and the modification module is used for a worker to newly add, modify or delete the monitoring information expert experience base.
CN201910978973.5A 2019-10-15 2019-10-15 Method and system for generating monitoring information expert experience base Pending CN110717683A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910978973.5A CN110717683A (en) 2019-10-15 2019-10-15 Method and system for generating monitoring information expert experience base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910978973.5A CN110717683A (en) 2019-10-15 2019-10-15 Method and system for generating monitoring information expert experience base

Publications (1)

Publication Number Publication Date
CN110717683A true CN110717683A (en) 2020-01-21

Family

ID=69212612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910978973.5A Pending CN110717683A (en) 2019-10-15 2019-10-15 Method and system for generating monitoring information expert experience base

Country Status (1)

Country Link
CN (1) CN110717683A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103868202A (en) * 2014-03-24 2014-06-18 南京信息职业技术学院 Remote variable strategy transformer substation temperature and humidity control system
CN104318397A (en) * 2014-10-29 2015-01-28 国家电网公司 Risk assessment and analysis method based on power grid short-time run-time behaviors
CN104808615A (en) * 2015-03-03 2015-07-29 国家电网公司 Method of automatically generating power device monitoring information table
CN105912567A (en) * 2016-03-25 2016-08-31 北京用尚科技股份有限公司 Power equipment monitoring information point table automatic generation method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103868202A (en) * 2014-03-24 2014-06-18 南京信息职业技术学院 Remote variable strategy transformer substation temperature and humidity control system
CN104318397A (en) * 2014-10-29 2015-01-28 国家电网公司 Risk assessment and analysis method based on power grid short-time run-time behaviors
CN104808615A (en) * 2015-03-03 2015-07-29 国家电网公司 Method of automatically generating power device monitoring information table
CN105912567A (en) * 2016-03-25 2016-08-31 北京用尚科技股份有限公司 Power equipment monitoring information point table automatic generation method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
高剑: "四川省调监控信息智能决策专家系统的设计与实现", 《中国优秀博硕士学位论文全文数据库》 *

Similar Documents

Publication Publication Date Title
CN109740837B (en) Power grid province and land network command and safety error prevention method based on regulation and control integration
CN110795921B (en) Automatic generation and verification method for monitoring information of intelligent substation equipment
CN111049266B (en) Intelligent second-level power restoration method and system for regulation and control service
CN111179112A (en) Transformer substation operation and maintenance assistance and risk management and control system and method
CN110705885A (en) Intelligent statistical analysis method for photovoltaic permeability of power grid equipment
CN113364131B (en) Equipped patrol system based on secondary equipment intelligent management and control platform
CN110705001A (en) Equipment-based monitoring information objectification modeling method for power system
CN110717683A (en) Method and system for generating monitoring information expert experience base
CN114841627B (en) Maintenance plan checking method, device, equipment and storage medium
CN111738461A (en) Fault emergency processing system based on ubiquitous power Internet of things
CN111476547A (en) Method for analyzing assets of distribution network line ring-out point arrangement in user
CN112446619B (en) Power distribution network rush-repair processing method and device
CN108303956B (en) Automatic on-duty centralized monitoring system for power grid dispatching
CN211207443U (en) Electric power monitoring intelligent voice reminding system
CN104966152B (en) Electric power safety production management system
CN110942161B (en) Method for improving power supply reliability based on business middle station
CN112670942A (en) Distribution network system relay protection setting calculation and data management system
CN110598805A (en) Method and system for identifying monitoring information of power system
CN107104508B (en) Power cut-off and power transmission time automatic calculation system integrating interactive communication function
CN105894187B (en) Automatic design system for transformer substation technical improvement project
CN111162607A (en) Remote real-time centralized monitoring system for clean energy
CN110852606A (en) Production early report data object analysis method based on regulation cloud
Xu et al. Research on Intelligent Operation and Maintenance Platform of User Distribution Equipment
CN113672647B (en) Planned power outage specification verification method and device
Tian et al. Research on Construction Scheme of New Generation Centralized Control Station Intelligent Monitoring System

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200121