CN110654977A - Flexible-straight converter valve submodule replacing tool and method - Google Patents
Flexible-straight converter valve submodule replacing tool and method Download PDFInfo
- Publication number
- CN110654977A CN110654977A CN201910903352.0A CN201910903352A CN110654977A CN 110654977 A CN110654977 A CN 110654977A CN 201910903352 A CN201910903352 A CN 201910903352A CN 110654977 A CN110654977 A CN 110654977A
- Authority
- CN
- China
- Prior art keywords
- module
- converter valve
- sub
- valve sub
- tower
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C11/00—Trolleys or crabs, e.g. operating above runways
- B66C11/02—Trolleys or crabs, e.g. operating above runways with operating gear or operator's cabin suspended, or laterally offset, from runway or track
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/08—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Gas-Insulated Switchgears (AREA)
Abstract
本发明提出一种柔直换流阀子模块更换工装及方法,用于更换柔性直流输电换流站的阀塔处的换流阀子模块,所述更换工装包括轨道梁和用于支撑轨道梁的梁架;所述轨道梁位于阀塔的塔层处,轨道梁端部从阀塔侧面处探出,轨道梁处设有可供行走小车移动的轨道;当更换塔层处的换流阀子模块时,所述换流阀子模块由行走小车以吊装组件吊装,并以行走小车经轨道梁把换流阀子模块运至预设位处;本发明针对阀塔结构,可达到节省子模块更换人力及时间,保障工作安全性的目的。
The present invention provides a flexible DC converter valve sub-module replacement tool and method for replacing the converter valve sub-module at the valve tower of a flexible DC power transmission converter station. The replacement tool includes a rail beam and a rail beam for supporting the rail beam. The rail beam is located at the tower layer of the valve tower, the end of the rail beam protrudes from the side of the valve tower, and the rail beam is provided with a track that can be moved by the walking trolley; when replacing the converter valve at the tower layer When the sub-module is used, the converter valve sub-module is hoisted by the traveling trolley with the hoisting component, and the traveling trolley transports the converter valve sub-module to the preset position through the rail beam; the present invention is aimed at the valve tower structure, and can save the cost of the sub-module. Module replacement manpower and time, the purpose of ensuring work safety.
Description
技术领域technical field
本发明涉及电力设施领域,尤其是一种柔直换流阀子模块更换工装及方法。The invention relates to the field of electric power facilities, in particular to a flexible DC converter valve sub-module replacement tool and method.
背景技术Background technique
柔性直流输电技术是目前较新型的输电技术,截至2019年8月,全国在运柔性直流输电工程仅有5个。换流阀是柔直直流输电换流站的核心设备,采用MMC技术及全控型IGBT器件实现柔性换流功能。柔性直流输电换流阀是由很多子模块组合而成,以厦门柔直工程为例,一组换流阀由1296个子模块组成,分为18个阀塔,每个阀塔72个子模块分三层四面布置,阀塔落地布置,最高层离地约7米。当某个或某些子模块故障时,需要更换子模块,由于子模块位于阀塔上,每个子模块重量达250kG。Flexible DC transmission technology is a relatively new type of transmission technology. As of August 2019, there are only 5 flexible DC transmission projects in operation nationwide. The converter valve is the core equipment of the flexible DC transmission converter station. It adopts MMC technology and fully controlled IGBT devices to realize the flexible converter function. The flexible HVDC converter valve is composed of many sub-modules. Taking the Xiamen flexible straight project as an example, a set of converter valves is composed of 1296 sub-modules, which are divided into 18 valve towers, and each valve tower has 72 sub-modules divided into three The floor is arranged on all sides, the valve tower is arranged on the ground, and the highest floor is about 7 meters above the ground. When one or some sub-modules fail, the sub-modules need to be replaced. Since the sub-modules are located on the valve tower, each sub-module weighs 250kG.
目前市场上没有可以直接应用于此类阀塔检修的工装。拆装需要耗费大量的人力及时间。There is currently no tooling on the market that can be directly applied to this type of valve tower overhaul. Disassembly requires a lot of manpower and time.
发明内容SUMMARY OF THE INVENTION
本发明提出一种柔直换流阀子模块更换工装及方法,针对阀塔结构,可达到节省子模块更换人力及时间,保障工作安全性的目的。The invention proposes a sub-module replacement tool and method for a flexible-DC converter valve, aiming at the valve tower structure, which can achieve the purpose of saving manpower and time for sub-module replacement and ensuring work safety.
本发明采用以下方案。The present invention adopts the following scheme.
一种柔直换流阀子模块更换工装,用于更换柔性直流输电换流站的阀塔处的换流阀子模块,所述更换工装包括轨道梁和用于支撑轨道梁的梁架;所述轨道梁位于阀塔的塔层处,轨道梁端部从阀塔侧面处探出,轨道梁处设有可供行走小车移动的轨道;当更换塔层处的换流阀子模块时,所述换流阀子模块由行走小车以吊装组件吊装,并以行走小车经轨道梁把换流阀子模块运至预设位处。A flexible DC converter valve sub-module replacement tool is used for replacing a converter valve sub-module at a valve tower of a flexible DC power transmission converter station, the replacement tool includes a rail beam and a beam frame for supporting the rail beam; The track beam is located at the tower layer of the valve tower, the end of the track beam protrudes from the side of the valve tower, and the track beam is provided with a track that can be moved by the walking trolley; when replacing the converter valve sub-module at the tower layer, the The converter valve sub-module is hoisted by a traveling trolley with a hoisting component, and the converter valve sub-module is transported to a preset position by the traveling trolley through the track beam.
当更换塔层处的换流阀子模块时,所述换流阀子模块被带电动葫芦的可移动龙门吊提起或降下。When replacing the converter valve sub-module at the tower layer, the converter valve sub-module is lifted or lowered by a movable gantry crane with an electric hoist.
当更换换流阀子模块时,新的换流阀子模块先由龙门吊起吊至换流站的升高车处,再以升高车把换流阀子模块转运至轨道梁处,然后以行走小车把换流阀子模块送至阀塔处的指定安装位置。When replacing the converter valve sub-module, the new converter valve sub-module is first hoisted by the gantry to the lifting car of the converter station, and then transported to the track beam by the lifting handlebar, and then the walking The trolley sends the converter valve sub-module to the designated installation position at the valve tower.
所述升高车处设有子模块支架用于支撑换流阀子模块;当换下的换流阀子模块从阀塔推出时,可暂置于子模块支架处。A sub-module bracket is provided at the lift car for supporting the converter valve sub-module; when the replaced converter valve sub-module is pushed out from the valve tower, it can be temporarily placed at the sub-module bracket.
当更换阀塔顶部的换流阀子模块时,所述梁架使用钢梁,所述钢梁以阀塔顶部的绝缘子垫片安装于阀塔顶层的支柱绝缘子上,所述钢梁和绝缘子垫片可在换流阀子模块更换作业结束后拆除。When replacing the converter valve sub-module on the top of the valve tower, the beam frame uses a steel beam, and the steel beam is installed on the pillar insulator on the top of the valve tower with the insulator gasket on the top of the valve tower. The steel beam and the insulator gasket The sheet can be removed after the replacement of the converter valve sub-module is completed.
当更换阀塔中间塔层或底层的换流阀子模块时,所述梁架为该塔层的换流阀子模块上方的绝缘槽梁。When replacing the converter valve sub-module on the middle tower layer or the bottom layer of the valve tower, the beam frame is an insulating groove beam above the converter valve sub-module on the tower layer.
所述吊装组件包括以花篮螺栓与行走小车相连的吊具,所述吊具设有两个或两个以上可插入换流阀子模块吊装孔的吊臂;所述吊具可用于换流阀子模块起吊。The hoisting assembly includes a sling connected to the traveling trolley with a turnbuckle bolt, the sling is provided with two or more hoisting arms that can be inserted into the hoisting holes of the converter valve sub-module; the sling can be used for the converter valve The submodule is lifted.
所述吊装组件还包括吊带,当更换阀塔顶部的换流阀子模块时采用4m吊带,当更换阀塔中间层的换流阀子模块时采用3m吊带。The hoisting assembly also includes a sling, a 4m sling is used when replacing the converter valve sub-module on the top of the valve tower, and a 3m sling is used when the converter valve sub-module in the middle layer of the valve tower is replaced.
一种柔直换流阀子模块更换方法,所述更换方法采用以上所述的一种柔直换流阀子模块更换工装,其方法包括安装阀塔各层换流阀子模块的方法、拆除换流阀子模块的方法;A flexible-to-DC converter valve sub-module replacement method, the replacement method adopts the above-mentioned flexible-to-DC converter valve sub-module replacement tool, the method includes a method for installing the converter valve sub-modules of each layer of a valve tower, removing The method of the converter valve sub-module;
所述安装阀塔各层换流阀子模块的方法包括以下步骤:The method for installing the converter valve sub-modules of each layer of the valve tower includes the following steps:
A1、把子模块支架置于换流站的升高车上;以电动葫芦把换流阀子模块吊至子模块支架上;A1. Place the sub-module bracket on the lifting car of the converter station; hoist the converter valve sub-module to the sub-module bracket with an electric hoist;
A2、移动升高车,把换流阀子模块运至轨道梁下方;提升升高车高度直至换流阀子模块到达行走小车的吊装位处;然后在换流阀子模块上安装吊具;再以吊具的花篮螺栓与行走小车相连;A2. Move the lift car and transport the converter valve sub-module to the bottom of the track beam; raise the height of the lift car until the converter valve sub-module reaches the hoisting position of the traveling trolley; then install a spreader on the converter valve sub-module; Then connect it with the walking trolley by the flower basket bolts of the spreader;
A3、手动牵引行走小车,把换流阀子模块移动至阀塔内的安装位置后,释放换流阀子模块使之落稳在绝缘槽梁处,再以紧固件固定,最后摘掉吊具并把行走小车移至阀塔外部。A3. Manually pull the walking trolley, move the converter valve sub-module to the installation position in the valve tower, release the converter valve sub-module to make it fall firmly on the insulating groove beam, fix it with fasteners, and finally remove the hanging equipment and move the walking trolley to the outside of the valve tower.
所述拆除换流阀子模块的方法包括以下步骤;The method for removing the converter valve sub-module includes the following steps;
B1、组装轨道梁;再把装有吊具的行走小车安装于轨道梁处;B1. Assemble the track beam; then install the traveling trolley equipped with the spreader on the track beam;
B2、把行走小车移至需要更换的换流阀子模块正上方,把吊具底部的偏心销插入换流阀子模块的下部两侧的吊装孔后,拆去换流阀子模块底部的固定螺栓;B2. Move the walking trolley to the top of the converter valve sub-module to be replaced, insert the eccentric pins at the bottom of the spreader into the hoisting holes on both sides of the lower part of the converter valve sub-module, and remove the bottom of the converter valve sub-module. bolt;
B3、锁定行走小车位置后,旋转吊具的花篮螺栓,使吊具把换流阀子模块提升至离开绝缘横梁1~2cm;B3. After locking the position of the walking trolley, rotate the turnbuckle of the spreader, so that the spreader lifts the converter valve sub-module to 1~2cm away from the insulating beam;
B4、把升高车移至轨道梁端部下方,手动牵引行走小车,使换流阀子模块移至轨道梁的端部处,调整换流阀子模块姿态使其长边方向与升高车长边方向平行;B4. Move the lift car to the bottom of the rail beam, manually pull the traveling trolley, move the converter valve sub-module to the end of the rail beam, and adjust the posture of the converter valve sub-module so that its long side direction is the same as that of the lift car. The long sides are parallel;
B5、降低升高车的平台高度,把换流阀子模块移至升高车正上方,然后提升升高车高度,使换流阀子模块可放置于升高车的子模块支架上,然后把换流阀子模块固定于子模块支架上,再把吊具从换流阀子模块处拆除。B5. Lower the platform height of the lift car, move the converter valve sub-module directly above the lift car, and then raise the height of the lift car so that the converter valve sub-module can be placed on the sub-module bracket of the lift car, and then Fix the converter valve sub-module on the sub-module bracket, and then remove the spreader from the converter valve sub-module.
本发明为柔性直流输电换流阀子模块更换提供了更换工装方案,该方案针对阀塔结构,可达到节省子模块更换人力及时间,保障工作安全性的目的。The invention provides a replacement tooling solution for the replacement of the flexible direct current transmission converter valve sub-module. The solution is aimed at the valve tower structure, and can achieve the purpose of saving manpower and time for sub-module replacement and ensuring work safety.
附图说明Description of drawings
下面结合附图和具体实施方式对本发明进一步详细的说明:The present invention will be described in further detail below in conjunction with the accompanying drawings and specific embodiments:
附图1是本发明所述阀塔、轨道梁的示意图;
附图2是轨道梁、梁架和吊具的示意图;Accompanying
附图3是行走小车和吊具的示意图;Accompanying
附图4是以升高车配合进行更换换流阀子模块的示意图;4 is a schematic diagram of replacing the converter valve sub-module with the cooperation of the lift truck;
图中:1-阀塔;2-轨道梁;3-换流阀子模块;4-吊具;5-梁架;6-行走小车;7-花篮螺栓。In the picture: 1- valve tower; 2- track beam; 3- converter valve sub-module; 4- spreader; 5- beam frame; 6- walking trolley; 7- turnbuckle bolt.
具体实施方式Detailed ways
如图1-4所示,一种柔直换流阀子模块更换工装,用于更换柔性直流输电换流站的阀塔处的换流阀子模块3,所述更换工装包括轨道梁和用于支撑轨道梁2的梁架5;所述轨道梁位于阀塔1的塔层处,轨道梁端部从阀塔侧面处探出,轨道梁处设有可供行走小车移动的轨道;当更换塔层处的换流阀子模块时,所述换流阀子模块由行走小车6以吊装组件吊装,并以行走小车经轨道梁把换流阀子模块运至预设位处。As shown in Figures 1-4, a flexible DC converter valve sub-module replacement tool is used to replace the
当更换塔层处的换流阀子模块时,所述换流阀子模块被带电动葫芦的可移动龙门吊提起或降下。When replacing the converter valve sub-module at the tower layer, the converter valve sub-module is lifted or lowered by a movable gantry crane with an electric hoist.
当更换换流阀子模块时,新的换流阀子模块先由龙门吊起吊至换流站的升高车处,再以升高车把换流阀子模块转运至轨道梁处,然后以行走小车把换流阀子模块送至阀塔处的指定安装位置。When replacing the converter valve sub-module, the new converter valve sub-module is first hoisted by the gantry to the lifting car of the converter station, and then transported to the track beam by the lifting handlebar, and then the walking The trolley sends the converter valve sub-module to the designated installation position at the valve tower.
所述升高车处设有子模块支架用于支撑换流阀子模块;当换下的换流阀子模块从阀塔推出时,可暂置于子模块支架处。A sub-module bracket is provided at the lift car for supporting the converter valve sub-module; when the replaced converter valve sub-module is pushed out from the valve tower, it can be temporarily placed at the sub-module bracket.
当更换阀塔顶部的换流阀子模块时,所述梁架使用钢梁,所述钢梁以阀塔顶部的绝缘子垫片安装于阀塔顶层的支柱绝缘子上,所述钢梁和绝缘子垫片可在换流阀子模块更换作业结束后拆除。When replacing the converter valve sub-module on the top of the valve tower, the beam frame uses a steel beam, and the steel beam is installed on the pillar insulator on the top of the valve tower with the insulator gasket on the top of the valve tower. The steel beam and the insulator gasket The sheet can be removed after the replacement of the converter valve sub-module is completed.
当更换阀塔中间塔层或底层的换流阀子模块时,所述梁架为该塔层的换流阀子模块上方的绝缘槽梁。When replacing the converter valve sub-module on the middle tower layer or the bottom layer of the valve tower, the beam frame is an insulating groove beam above the converter valve sub-module on the tower layer.
所述吊装组件包括以花篮螺栓7与行走小车相连的吊具4,所述吊具设有两个或两个以上可插入换流阀子模块吊装孔的吊臂;所述吊具可用于换流阀子模块起吊。The hoisting assembly includes a
所述吊装组件还包括吊带,当更换阀塔顶部的换流阀子模块时采用4m吊带,当更换阀塔中间层的换流阀子模块时采用3m吊带。The hoisting assembly also includes a sling, a 4m sling is used when replacing the converter valve sub-module on the top of the valve tower, and a 3m sling is used when the converter valve sub-module in the middle layer of the valve tower is replaced.
一种柔直换流阀子模块更换方法,所述更换方法采用以上所述的一种柔直换流阀子模块更换工装,其方法包括安装阀塔各层换流阀子模块的方法、拆除换流阀子模块的方法;A flexible-to-DC converter valve sub-module replacement method, the replacement method adopts the above-mentioned flexible-to-DC converter valve sub-module replacement tool, the method includes a method for installing the converter valve sub-modules of each layer of a valve tower, removing The method of the converter valve sub-module;
所述安装阀塔各层换流阀子模块的方法包括以下步骤:The method for installing the converter valve sub-modules of each layer of the valve tower includes the following steps:
A1、把子模块支架置于换流站的升高车上;以电动葫芦把换流阀子模块吊至子模块支架上;A1. Place the sub-module bracket on the lifting car of the converter station; hoist the converter valve sub-module to the sub-module bracket with an electric hoist;
A2、移动升高车,把换流阀子模块运至轨道梁下方;提升升高车高度直至换流阀子模块到达行走小车的吊装位处;然后在换流阀子模块上安装吊具;再以吊具的花篮螺栓与行走小车相连;A2. Move the lift car and transport the converter valve sub-module to the bottom of the track beam; raise the height of the lift car until the converter valve sub-module reaches the hoisting position of the traveling trolley; then install a spreader on the converter valve sub-module; Then connect it with the walking trolley by the flower basket bolts of the spreader;
A3、手动牵引行走小车,把换流阀子模块移动至阀塔内的安装位置后,释放换流阀子模块使之落稳在绝缘槽梁处,再以紧固件固定,最后摘掉吊具并把行走小车移至阀塔外部。A3. Manually pull the walking trolley, move the converter valve sub-module to the installation position in the valve tower, release the converter valve sub-module to make it fall firmly on the insulating groove beam, fix it with fasteners, and finally remove the hanging equipment and move the walking trolley to the outside of the valve tower.
所述拆除换流阀子模块的方法包括以下步骤;The method for removing the converter valve sub-module includes the following steps;
B1、组装轨道梁;再把装有吊具的行走小车安装于轨道梁处;B1. Assemble the track beam; then install the traveling trolley equipped with the spreader on the track beam;
B2、把行走小车移至需要更换的换流阀子模块正上方,把吊具底部的偏心销插入换流阀子模块的下部两侧的吊装孔后,拆去换流阀子模块底部的固定螺栓;B2. Move the walking trolley to the top of the converter valve sub-module to be replaced, insert the eccentric pins at the bottom of the spreader into the hoisting holes on both sides of the lower part of the converter valve sub-module, and remove the bottom of the converter valve sub-module. bolt;
B3、锁定行走小车位置后,旋转吊具的花篮螺栓,使吊具把换流阀子模块提升至离开绝缘横梁1~2cm;B3. After locking the position of the walking trolley, rotate the turnbuckle of the spreader, so that the spreader lifts the converter valve sub-module to 1~2cm away from the insulating beam;
B4、把升高车移至轨道梁端部下方,手动牵引行走小车,使换流阀子模块移至轨道梁的端部处,调整换流阀子模块姿态使其长边方向与升高车长边方向平行;B4. Move the lift car to the bottom of the rail beam, manually pull the traveling trolley, move the converter valve sub-module to the end of the rail beam, and adjust the posture of the converter valve sub-module so that its long side direction is the same as that of the lift car. The long sides are parallel;
B5、降低升高车的平台高度,把换流阀子模块移至升高车正上方,然后提升升高车高度,使换流阀子模块可放置于升高车的子模块支架上,然后把换流阀子模块固定于子模块支架上,再把吊具从换流阀子模块处拆除。B5. Lower the platform height of the lift car, move the converter valve sub-module directly above the lift car, and then raise the height of the lift car so that the converter valve sub-module can be placed on the sub-module bracket of the lift car, and then Fix the converter valve sub-module on the sub-module bracket, and then remove the spreader from the converter valve sub-module.
本例中,当更换阀塔顶部的换流阀子模块时,所述梁架使用C50型号的钢梁。In this example, when replacing the converter valve sub-module at the top of the valve tower, the beam frame uses a C50 model steel beam.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910903352.0A CN110654977A (en) | 2019-09-24 | 2019-09-24 | Flexible-straight converter valve submodule replacing tool and method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910903352.0A CN110654977A (en) | 2019-09-24 | 2019-09-24 | Flexible-straight converter valve submodule replacing tool and method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN110654977A true CN110654977A (en) | 2020-01-07 |
Family
ID=69038826
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201910903352.0A Pending CN110654977A (en) | 2019-09-24 | 2019-09-24 | Flexible-straight converter valve submodule replacing tool and method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN110654977A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111704064A (en) * | 2020-06-18 | 2020-09-25 | 五冶集团上海有限公司 | A kind of method and trolley for replacing electrolyzer |
| CN111807237A (en) * | 2020-06-29 | 2020-10-23 | 国网福建省电力有限公司检修分公司 | Maintenance device suitable for replacing sub-module of M2000 type high-pressure flexible DC converter valve and its working method |
| CN111994802A (en) * | 2020-08-14 | 2020-11-27 | 中国南方电网有限责任公司超高压输电公司 | Device is changed to gentle straight converter valve power module |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE102005038820A1 (en) * | 2005-08-17 | 2007-02-22 | EISENMANN Fördertechnik GmbH & Co. KG | Movable lifting device for e.g. paint finishing system, has balancing device positively controlled in such manner that it avoids lateral misalignment of lifting frame opposite to carriage during lifting or lowering |
| CN108163710A (en) * | 2016-12-07 | 2018-06-15 | 中电普瑞电力工程有限公司 | A kind of replacement fitting device of converter valve cassette tube assembly |
| CN209081259U (en) * | 2018-11-06 | 2019-07-09 | 杭州三阳建设工程有限公司 | A kind of suspender for the lifting of rectangle piping lane tube coupling level |
-
2019
- 2019-09-24 CN CN201910903352.0A patent/CN110654977A/en active Pending
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE102005038820A1 (en) * | 2005-08-17 | 2007-02-22 | EISENMANN Fördertechnik GmbH & Co. KG | Movable lifting device for e.g. paint finishing system, has balancing device positively controlled in such manner that it avoids lateral misalignment of lifting frame opposite to carriage during lifting or lowering |
| CN108163710A (en) * | 2016-12-07 | 2018-06-15 | 中电普瑞电力工程有限公司 | A kind of replacement fitting device of converter valve cassette tube assembly |
| CN209081259U (en) * | 2018-11-06 | 2019-07-09 | 杭州三阳建设工程有限公司 | A kind of suspender for the lifting of rectangle piping lane tube coupling level |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111704064A (en) * | 2020-06-18 | 2020-09-25 | 五冶集团上海有限公司 | A kind of method and trolley for replacing electrolyzer |
| CN111807237A (en) * | 2020-06-29 | 2020-10-23 | 国网福建省电力有限公司检修分公司 | Maintenance device suitable for replacing sub-module of M2000 type high-pressure flexible DC converter valve and its working method |
| CN111994802A (en) * | 2020-08-14 | 2020-11-27 | 中国南方电网有限责任公司超高压输电公司 | Device is changed to gentle straight converter valve power module |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110654977A (en) | Flexible-straight converter valve submodule replacing tool and method | |
| CN104400750B (en) | Pipeline valve dismounting assistive tool and pipeline valve dismounting method | |
| CN207827760U (en) | Tooling rotating lifting trolley | |
| CN207845059U (en) | A kind of tooling for replacing flexible direct current transmission converter valve power module | |
| CN207932974U (en) | Vehicle bridge installation carriage | |
| WO2017008717A1 (en) | Bridge crane suspension device and method for valve tower | |
| CN103981811A (en) | Cross over type multifunctional cantilever external anti-collision wall installing and moving device and construction method thereof | |
| CN204322004U (en) | A kind of pipe valve dismounting accessory | |
| CN203998580U (en) | Indoor GIS equipment transport carriage | |
| CN111392596B (en) | GIS current transformer integral dismounting device and dismounting method | |
| CN212050215U (en) | Integral disassembly and assembly device of GIS current transformer | |
| CN114291120A (en) | Power equipment conveyer | |
| CN205141485U (en) | Gentle straight module dismounting device | |
| CN209922790U (en) | A secondary lifting mechanism for an assembly trolley | |
| CN202729645U (en) | Tower crane with elevator | |
| CN218370089U (en) | Self-lifting cableway trolley transportation system | |
| CN113948993B (en) | Device for overhauling and maintaining power module of support type converter valve | |
| CN216549203U (en) | A wind turbine and its radiator replacement device | |
| CN110803663A (en) | Hoisting equipment for maintenance of power equipment | |
| CN216190533U (en) | Lifting appliance device for overhauling converter station | |
| CN213243371U (en) | Power transmission converter valve submodule replacing device | |
| CN210557188U (en) | Walking wheel structure for equipment transportation and installation | |
| CN207016387U (en) | A kind of photovoltaic module lifting device | |
| CN219365445U (en) | Auxiliary handling and installation equipment for construction formwork | |
| CN211496785U (en) | Tool dolly jacking device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200107 |
