CN110644696A - Soft soil foundation outdoor step structure and construction method thereof - Google Patents

Soft soil foundation outdoor step structure and construction method thereof Download PDF

Info

Publication number
CN110644696A
CN110644696A CN201910780224.1A CN201910780224A CN110644696A CN 110644696 A CN110644696 A CN 110644696A CN 201910780224 A CN201910780224 A CN 201910780224A CN 110644696 A CN110644696 A CN 110644696A
Authority
CN
China
Prior art keywords
foundation
reinforcement cage
column
soil
outdoor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910780224.1A
Other languages
Chinese (zh)
Other versions
CN110644696B (en
Inventor
虞靖彬
张恒
胡文兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUAHENG CONSTRUCTION GROUP CO Ltd
Original Assignee
HUAHENG CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUAHENG CONSTRUCTION GROUP CO Ltd filed Critical HUAHENG CONSTRUCTION GROUP CO Ltd
Priority to CN201910780224.1A priority Critical patent/CN110644696B/en
Publication of CN110644696A publication Critical patent/CN110644696A/en
Application granted granted Critical
Publication of CN110644696B publication Critical patent/CN110644696B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations

Abstract

The invention discloses a soft soil foundation outdoor step structure and a construction method thereof, belongs to the field of buildings, and has the advantage of reducing cracking of soft soil foundation outdoor steps.

Description

Soft soil foundation outdoor step structure and construction method thereof
Technical Field
The invention relates to the field of buildings, in particular to a soft soil foundation outdoor step structure and a construction method thereof.
Background
At present, in the construction process of buildings, outdoor steps need to be designed and constructed at a service entrance, the construction of the outdoor steps is basically that after the construction of a main building is finished, the outdoor steps are poured, and at present, particularly after the construction is carried out on a soft soil foundation, the outdoor steps are greatly settled by a swimming suit, so that the outdoor steps and the main building are greatly cracked and staggered, and the outdoor steps are easy to crack.
Chinese patent publication No. CN105155789A discloses a method for cast-in-situ outdoor steps and reducing differential settlement between outdoor steps and main building, which is supported by connecting members connected with the main building body and pipe piles extending into soil. Although the connection between the outdoor step and the main building can be improved by the aid of the structure, the contact surface between the outdoor step and soil can be improved, the supporting effect can be improved, the connection between the outdoor step and the main building can be strengthened, the overall settlement under a soft soil foundation cannot be avoided, and the time for fracture after settlement can be delayed slightly, so that the outdoor step is cracked.
Disclosure of Invention
The invention aims to provide a soft soil foundation outdoor step structure and a construction method thereof, which have the advantage of reducing cracking of the soft soil foundation outdoor step.
The technical purpose of the invention is realized by the following technical scheme: the utility model provides an outdoor stair structure of soft soil foundation, includes ground foundation pile, building base member, the step body, and in a plurality of foundation piles inserted earth, the building base member sets up on ground foundation pile, the step body sets up in building base side, and the step body below is equipped with foundation column, support column, the foundation column slope sets up, two foundation column one end is contradicted respectively in two ground foundation pile sides that are close to the step body, two the foundation column other end is contradicted each other, a plurality of the support column one end is contradicted on the side that the foundation column is close to the building base member, the support column other end sets up on the building base member, be equipped with the steel reinforcement cage that the case step body extends on the support column, the pouring has concrete layer in the steel reinforcement cage.
Through adopting above-mentioned technical scheme, support on foundation pile through setting up the foundation column, and compile the steel reinforcement cage and be used for pouring concrete layer, the support column is being connected to the steel reinforcement cage, consequently makes the concrete layer after the pouring actually support on foundation pile, and the concrete layer that consequently forms can form integratively with the building base member, promotes the supporting role to the step body to the effectual fracture phenomenon that has reduced outdoor step on the soft soil foundation.
Furthermore, the side surface of the foundation pile is provided with a limiting hole, and the foundation column is supported in the limiting hole.
Through adopting above-mentioned technical scheme, spacing hole supplies the foundation column to support, promotes the limiting displacement to the foundation column, avoids producing after the foundation column is fixed and slides downwards.
Further, concrete layer pouring is steel reinforcement cage upper portion, steel reinforcement cage lower part is filled earth.
Through adopting above-mentioned technical scheme, fill earth and be used for melting into outside other earth, make steel reinforcement cage upper portion have better design effect before the pouring, promote the stability to concrete layer pouring process and after the pouring, promote the pouring effect.
Furthermore, the reinforcement cage extends into the step body and the building base body.
Through adopting above-mentioned technical scheme, it is that the step body forms an organic whole with the building base member through the setting of steel reinforcement cage, promotes holistic joint strength, the effectual fracture phenomenon that has reduced.
A construction method of soft soil foundation outdoor steps is characterized in that: the method comprises the following steps:
the method comprises the following steps: excavating earth;
step two: processing earthwork;
step three: setting foundation piles;
step four: backfilling earthwork: backfilling soil in the earthwork to be smooth;
step four, step one: filling soil to the height of the limiting hole, abutting one end of each foundation column against the position of the limiting hole, and abutting the other ends of the two foundation columns against each other;
step four, step two: continuously backfilling the soil until the soil buries at least half of the foundation pillar, and ensuring the stability of the foundation pillar;
step four, step three: vertically inserting the support column into soil to be abutted against the foundation column, and continuously backfilling the soil;
step four, step four: backfilling soil to ensure the stability of the support column, putting the support column into a reinforcement cage, penetrating the support column through the reinforcement cage, and continuously backfilling soil to submerge part of the reinforcement cage;
step four, step five: then pouring concrete at the position of the reinforcement cage until the position of the reinforcement cage is level to the construction surface to form a concrete layer;
step five: pouring a building matrix at the position after backfilling;
step six: and pouring the step body on the concrete layer.
Through adopting above-mentioned technical scheme, at the in-process that the earthwork was backfilled, set up the position to foundation column, support column and steel reinforcement cage and carry out the segmentation and backfill, the effectual setting effect of strengthening the structure of step body bottom of strengthening, the overall structure's of being convenient for setting up to and the support effect to the step body in promotion later stage.
Step four, step one: the two foundation columns are preliminarily fixed through a wood frame;
step four, step three: the support column is preliminarily fixed through a wooden frame.
Through adopting above-mentioned technical scheme, carry out basic fixed through the wooden frame, carry out the earthwork again and backfill, avoid producing the position and influence the support effect to the step body at the in-process foundation post and the support column that the earthwork was backfilled.
Step four, step four: the reinforcement cage is bound on the support column through an iron wire.
Through adopting above-mentioned technical scheme, through the binding of iron wire, promote the fixed effect of steel reinforcement cage before concrete placement.
Step five: the steel reinforcement cage is higher than the construction surface, and the building base body and the step body are both cast and molded on the steel reinforcement cage higher than the construction surface.
Through adopting above-mentioned technical scheme, through the mode that same steel reinforcement cage was pour, be connected integratively with concrete layer, promote the wholeness after the pouring, promote fixed effect.
In conclusion, the invention has the following beneficial effects:
1. by arranging the effective supporting structure, the supporting effect on the outdoor step is improved, and the cracking phenomenon is reduced;
2. the reinforcing cage is arranged, so that the connection strength between the outdoor step and the building base body is greatly improved, and the cracking phenomenon is reduced.
Drawings
FIG. 1 is a view showing an installation state of a base column and a support column;
FIG. 2 is a view showing the installation state of the reinforcement cage;
FIG. 3 is a view showing a state of casting of a concrete layer;
FIG. 4 is a diagram of a poured state of a building matrix;
FIG. 5 is a pouring state diagram of the step body;
fig. 6 is a schematic view of the arrangement of the building base and the step body on the ground.
In the figure, 1, a foundation pile; 2. a building matrix; 3. a step body; 4. a base pillar; 41. a limiting hole; 5. a support pillar; 6. a reinforcement cage; 7. and a concrete layer.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
The utility model provides an outdoor stair structure of soft soil foundation, as shown in fig. 5, includes foundation pile 1, building base member 2, the step body 3, in a plurality of foundation piles 1 inserted earth, building base member 2 set up on foundation pile 1, step body 3 sets up in building base member 2 sides, and foundation pile 1 is effectual supports building base member 2, guarantees building base member 2's stability, promotes the whole supporting effect of later stage building.
As shown in fig. 1, 5, be equipped with foundation column 4 below the step body 3, support column 5 is used for carrying out effectual support to the step body 3, wherein set up two 4 slopes of foundation column and set up, and two 4 one ends of foundation column are contradicted respectively and are being close to two foundation pile 1 sides of the step body 3, two 4 other ends of foundation column are contradicted each other, and foundation pile 1 side receives the position of two 4 conflicts of foundation column and has set up spacing hole 41, thereby foundation column 4 can support in spacing hole 41, spacing hole 41 supplies foundation column 4 to support, promote the limiting displacement to foundation column 4, avoid foundation column 4 to produce after fixed and slide downwards, and foundation column 4 after the installation can be in earth, thereby the effectual connection effect who guarantees foundation column 4.
As shown in fig. 1, 4, 5 one end of a plurality of support column is contradicted on the side that foundation column 4 is close to building base body 2, the support column 5 other end forms fixed knot in building base body 2 pouring's in-process direct pouring to building base body 2, thereby support column 5 both ends homoenergetic receives effectual fixed, because foundation column 4's one end supports in spacing hole 41, realized fixedly, and the other end is contradicted each other again, after receiving the effect that support column 5 pushed down, still can keep good supporting effect, and support column 5 also buries underground in earth, thereby also avoided support column 5 to produce great displacement, whole stability has been improved.
As shown in fig. 2, 3 and 5, the reinforcement cage 6 is fixed by iron wires to form the reinforcement cage 6 with a rectangular parallelepiped structure, the supporting column 5 penetrates into the reinforcement cage 6, the supporting column 5 and the reinforcement cage 6 are fixed through iron wires, thereby improving the stability of the steel reinforcement cage 6 after being arranged, backfilling soil on the lower part of the steel reinforcement cage 6 and compacting, pouring concrete on the upper part of the steel reinforcement cage 6 until the elevation height of the ground is the same, improving the connection effect between the steel reinforcement cage 6 and the original soil through the arrangement of soil backfilling, the mutual relation between the later stage and the surrounding environment is promoted, the function of independent sedimentation is reduced, the formed concrete is poured to form a good connecting platform for the step body 3, the influence of the land on the pouring is reduced, and the subsequent retreatment to the pouring soft soil ground is avoided, and the pouring effect of the subsequent step body 3 is improved, so that the cracking phenomenon of the outdoor step on the soft soil foundation is effectively reduced.
As shown in fig. 3, 4 and 5, and steel reinforcement cage 6 sets up the height and exceeds the ground elevation, and the follow-up direct pouring of 6 positions of steel reinforcement cage that extend out is to step body 3 and building base member 2 in to make steel reinforcement cage 6 can effectual connection step body 3, building base member 2 and concrete layer 7, promote holistic joint strength, the effectual fracture phenomenon that has reduced.
A construction method of outdoor steps of a soft soil foundation is combined with the attached drawings, and comprises the following steps:
the method comprises the following steps: excavating earth;
step two: processing earthwork;
step three: arranging foundation piles 1;
step four: backfilling earthwork: backfilling soil in the earthwork to be smooth;
step four, step one: the soil is firstly filled to the height of the limiting hole 41, one end of each foundation column 4 is abutted against the position of the limiting hole 41, the other ends of the two foundation columns 4 are abutted against each other, and the two foundation columns 4 are preliminarily fixed through a wood frame;
step four, step two: continuously backfilling the soil until the soil buries at least half of the foundation pillar 4, and ensuring the stability of the foundation pillar 4;
step four, step three: vertically inserting the support column 5 into the soil to be abutted against the foundation column 4, primarily fixing the support column 5 through a wood frame, and continuously backfilling the soil;
step four, step four: soil is backfilled to ensure that the support column 5 is stable, then the reinforcement cage 6 is placed, the support column 5 penetrates through the reinforcement cage 6, the reinforcement cage 6 is bound on the support column 5 through an iron wire, and then soil is backfilled continuously to submerge a part of the reinforcement cage 6;
step four, step five: then pouring concrete at the position of the reinforcement cage 6 until the position is level with the construction surface to form a concrete layer 7;
step five: the steel reinforcement cage 6 is higher than the construction surface, the building matrix 2 and the step body 3 are both cast and molded on the steel reinforcement cage 6 higher than the construction surface, and the building matrix 2 is cast at the position after backfilling;
step six: and pouring the step body 3 on the concrete layer.
At the in-process that the earthwork was backfilled, set up the position to foundation column 4, support column 5 and steel reinforcement cage 6 and carry out the segmentation and backfill, the effectual 3 bottom strengthening structures's of the step body of strengthening setting up the effect, the overall structure's of being convenient for setting up to and the support effect to the step body 3 that promotes the later stage.
The present embodiment is only for explaining the present invention, and it is not limited to the present invention, and those skilled in the art can make modifications of the present embodiment without inventive contribution as needed after reading the present specification, but all of them are protected by patent law within the scope of the claims of the present invention.

Claims (8)

1. The utility model provides an outdoor stair structure of soft soil foundation, includes foundation pile (1), building base member (2), the step body (3), in a plurality of foundation piles (1) inserted earth, building base member (2) set up on foundation pile (1), the step body (3) set up in building base member (2) side, characterized by: step body (3) below is equipped with foundation column (4), support column (5), foundation column (4) slope sets up, two foundation column (4) one end is contradicted respectively and is being close to two foundation column (4) sides of step body (3), two foundation column (4) other end is contradicted each other, a plurality of support column (5) one end is contradicted on foundation column (4) is close to the side of building base member (2), support column (5) other end sets up on building base member (2), be equipped with steel reinforcement cage (6) that case step body (3) extended on support column (5), the pouring has concrete layer (7) in steel reinforcement cage (6).
2. The outdoor stair structure of soft soil foundation of claim 1, wherein: the side surface of the foundation pile (1) is provided with a limiting hole (41), and the foundation column (4) is supported in the limiting hole (41).
3. The outdoor stair structure of soft soil foundation of claim 1, wherein: concrete layer (7) pouring is steel reinforcement cage (6) upper portion, steel reinforcement cage (6) lower part is filled earth.
4. The outdoor stair structure of soft soil foundation of claim 1, wherein: the reinforcement cage (6) extends into the step body (3) and the building base body (2).
5. A construction method of soft soil foundation outdoor steps is characterized in that: the method comprises the following steps:
the method comprises the following steps: excavating earth;
step two: processing earthwork;
step three: arranging foundation piles (1);
step four: backfilling earthwork: backfilling soil in the earthwork to be smooth;
step four, step one: filling soil to the height of the limiting hole (41), abutting one end of each foundation column (4) against the position of the limiting hole (41), and abutting the other ends of the two foundation columns (4) against each other;
step four, step two: continuously backfilling the soil until the soil buries at least half of the foundation pillar (4), so as to ensure the stability of the foundation pillar (4);
step four, step three: then vertically inserting the support column (5) into soil to be abutted against the foundation column (4), and then continuously backfilling the soil;
step four, step four: soil is backfilled to ensure that the support column (5) is stable, then the reinforcement cage (6) is placed, the support column (5) penetrates through the reinforcement cage (6), and then soil is backfilled continuously to submerge a part of the reinforcement cage (6);
step four, step five: then concrete is poured to the position of the reinforcement cage (6) until the position of the reinforcement cage is level to the construction surface, so that a concrete layer (7) is formed;
step five: pouring the building matrix (2) at the position after backfilling;
step six: and pouring the step body (3) on the concrete layer.
6. The construction method of the outdoor step of the soft soil foundation according to claim 5, characterized in that:
step four, step one: the two foundation columns (4) are preliminarily fixed through a wooden frame;
step four, step three: the support columns (5) are preliminarily fixed through a wood frame.
7. The construction method of the outdoor step of the soft soil foundation according to claim 5, characterized in that:
step four, step four: the reinforcement cage (6) is bound on the support column (5) through iron wires.
8. The construction method of the outdoor step of the soft soil foundation according to claim 5, characterized in that:
step five: the steel reinforcement cage (6) is higher than a construction surface, and the building base body (2) and the step body (3) are both cast and molded on the steel reinforcement cage (6) higher than the construction surface.
CN201910780224.1A 2019-08-22 2019-08-22 Soft soil foundation outdoor step structure and construction method thereof Active CN110644696B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910780224.1A CN110644696B (en) 2019-08-22 2019-08-22 Soft soil foundation outdoor step structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910780224.1A CN110644696B (en) 2019-08-22 2019-08-22 Soft soil foundation outdoor step structure and construction method thereof

Publications (2)

Publication Number Publication Date
CN110644696A true CN110644696A (en) 2020-01-03
CN110644696B CN110644696B (en) 2020-12-11

Family

ID=68990312

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910780224.1A Active CN110644696B (en) 2019-08-22 2019-08-22 Soft soil foundation outdoor step structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN110644696B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3032868A1 (en) * 1980-09-01 1982-04-15 Georg 3588 Homberg Ritter Prefab. concrete component assembled outdoor staircase - has step brackets joined to cut=outs in cross beams on support piles
CN101476325A (en) * 2008-11-28 2009-07-08 华南理工大学 Rigid gridding and pile combined foundation and its use in soft soil foundation reinforcement
CN101509261B (en) * 2009-01-20 2010-12-08 中国科学院武汉岩土力学研究所 Method for pile plate base for ultra-high voltage electric power line steel tower on soft foundation
CN105155789A (en) * 2015-06-18 2015-12-16 山河建设集团有限公司 Cast-in-place outdoor step member and method of decreasing differential settlement between outdoor step member and main building
CN106337537A (en) * 2016-08-31 2017-01-18 中国建筑第八工程局有限公司 Crack-resistant structure applied to outdoor step and main body engineering and construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3032868A1 (en) * 1980-09-01 1982-04-15 Georg 3588 Homberg Ritter Prefab. concrete component assembled outdoor staircase - has step brackets joined to cut=outs in cross beams on support piles
CN101476325A (en) * 2008-11-28 2009-07-08 华南理工大学 Rigid gridding and pile combined foundation and its use in soft soil foundation reinforcement
CN101509261B (en) * 2009-01-20 2010-12-08 中国科学院武汉岩土力学研究所 Method for pile plate base for ultra-high voltage electric power line steel tower on soft foundation
CN105155789A (en) * 2015-06-18 2015-12-16 山河建设集团有限公司 Cast-in-place outdoor step member and method of decreasing differential settlement between outdoor step member and main building
CN106337537A (en) * 2016-08-31 2017-01-18 中国建筑第八工程局有限公司 Crack-resistant structure applied to outdoor step and main body engineering and construction method thereof

Also Published As

Publication number Publication date
CN110644696B (en) 2020-12-11

Similar Documents

Publication Publication Date Title
CN106522242A (en) Foundation pit supporting system for subsurface structure close to soft ground stratum and construction method of foundation pit supporting system
CN106988303B (en) A kind of pile foundation and its construction method
CN102864796B (en) Construction spreading foundation adaptive to filled ground settlement and construction method
CN110820793A (en) Composite foundation for collapsible loess area and construction method
CN207959264U (en) Soft clay foundation adjoins High-filled emkankment pipe gallery
CN108331015A (en) Soft clay foundation adjoins High-filled emkankment pipe gallery and its construction technology
CN209855277U (en) Conversion layer structure for underground added layer of existing building
CN113417300A (en) Slope support system and construction method thereof
CN110644696B (en) Soft soil foundation outdoor step structure and construction method thereof
CN206337566U (en) Foundation ditch vertical prestressing anchor pole supporting construction
US4232491A (en) Swimming pool deck
CN110093929A (en) A kind of underground engineering is along practice construction method and structure
CN106120853B (en) A kind of inverted construction method of frame bridge
CN212375896U (en) Line tower type-returning pile-anchor composite foundation suitable for karst region
CN211447000U (en) Foundation pit backfill area construction elevator foundation
AU2020100004A4 (en) A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method
CN209907410U (en) Slope reinforcement supporting structure and pile plate retaining wall
CN109680978B (en) Basement storey-adding underpinning construction method
CN210507517U (en) Combined member suitable for retaining wall heightening
CN103981859B (en) Construction method of node structure of guide walls of underground diaphragm wall and ground under heavy load
CN106120690A (en) A kind of inverter box flattens platform and preparation method thereof
CN209260748U (en) A kind of stepped tower crane
CN106592568A (en) Ground uniform settlement structure and construction method
CN205444180U (en) Pilework suitable for areas formerly flooded by huanghe river
JP4749858B2 (en) Method for enhancing bearing capacity in extension or reconstruction of superstructures of existing buildings

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant