CN110632410A - An intelligent debugging system for intelligent substation automation equipment and its application method - Google Patents
An intelligent debugging system for intelligent substation automation equipment and its application method Download PDFInfo
- Publication number
- CN110632410A CN110632410A CN201910764363.5A CN201910764363A CN110632410A CN 110632410 A CN110632410 A CN 110632410A CN 201910764363 A CN201910764363 A CN 201910764363A CN 110632410 A CN110632410 A CN 110632410A
- Authority
- CN
- China
- Prior art keywords
- test
- intelligent
- data
- telecontrol
- station
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R31/00—Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Maintenance And Management Of Digital Transmission (AREA)
Abstract
本发明公开了一种智能变电站自动化设备智能调试系统及其应用方法,智能变电站自动化设备智能调试系统包括智能调试设备和智能验收信号仿真装置,智能调试设备分别与智能验收信号仿真装置、智能变电站的站控层网络、智能变电站站控层的远动机连接,智能验收信号仿真装置分别与智能变电站的间隔层网络、过程层网络连接;应用方法包括用于智能变电站遥测、遥信、遥控等试验的自动闭环测试。本发明能够利用纵向跨层网络数据分析,实现全站遥信、遥测、遥控预置试验的自动闭环测试,可用于实现对间隔层设备、站控层设备的各个功能指标和性能指标的综合自动测试,以便直观、准确的定位出故障原因和故障位置、提高智能站验收质量和效率,保证智能站的可靠运行。
The invention discloses an intelligent debugging system for automation equipment of an intelligent substation and an application method thereof. The intelligent debugging system for an automation equipment of an intelligent substation includes intelligent debugging equipment and an intelligent acceptance signal simulation device. The station control layer network, the remote machine connection of the station control layer of the smart substation, and the intelligent acceptance signal simulation device are respectively connected with the bay layer network and the process layer network of the smart substation; Automatic closed loop test. The present invention can utilize vertical cross-layer network data analysis to realize the automatic closed-loop test of the whole station remote signaling, telemetry and remote control preset test, and can be used to realize the comprehensive and automatic comprehensive automatic test of each functional index and performance index of the interval layer equipment and station control layer equipment. Test in order to intuitively and accurately locate the cause and location of the fault, improve the acceptance quality and efficiency of the intelligent station, and ensure the reliable operation of the intelligent station.
Description
技术领域technical field
本发明属于变电站自动化设备智能调试技术领域,具体涉及一种智能变电站自动化设备智能调试系统及其应用方法,可用于智能变电站遥测、遥信、遥控等试验的自动闭环测试。The invention belongs to the technical field of intelligent debugging of substation automation equipment, and specifically relates to an intelligent debugging system of intelligent substation automation equipment and an application method thereof, which can be used for automatic closed-loop testing of intelligent substation telemetry, remote signaling, remote control and other tests.
背景技术Background technique
智能变电站自动化系统的验收测试缺乏专业的设备和手段,验收过程中需要涉及过程层设备、间隔层设备、站控层设备以及远动主站,同时会涉及过程层通讯、站控层通讯以及远动通讯等诸多环节,由此,在智能变电站自动化系统的验收测试中,对验收人员的专业技能要求非常高且涉及面非常广,比如在遥测、遥信的传动试验过程中,需要在过程层模拟遥测和遥信的源输出,同时需要检测间隔层的保护、测控等设备是否正确接收并处理过程层设备输出的SV和GOOSE信号,并转换为对应的DL/T860.8协议数据与站控层设备和/或远动设备进行数据交互,同时还需检查远动设备是否正确将DL/T860.8协议数据转换为对应的101或者104协议与远动主站进行交互,在这一系列过程中,没有专业的测试设备,测试人员只能通过传统的标准源设备或保护测试设备进行输出,然后再发现异常的时候,通过WireShark等通用的软件进行人工报文分析和诊断,这需要测试人员对各种报文的结构、组成和机制、过程等十分清晰,了如指掌,测试分析才能得以进行,然而一般的测试人员很难做到对所有的协议和报文都完全了解,所以,在目前缺乏专业测试工具的情况下,现场验收对测试人员在自动化通讯协议等方面的要求极高,同时,即使专业的测试人员,在人工分析过程中,效率也非常低,也往往由此使得智能变电站自动化系统的验收测试工期一拖再拖,难以如期保质保量的完成。The acceptance test of the intelligent substation automation system lacks professional equipment and means. The acceptance process needs to involve process level equipment, bay level equipment, station control level equipment and telecontrol master station, as well as process level communication, station control level Therefore, in the acceptance test of the intelligent substation automation system, the requirements for the professional skills of the acceptance personnel are very high and the scope is very wide. Simulate the source output of telemetry and remote signaling. At the same time, it is necessary to check whether the protection, measurement and control equipment at the bay layer correctly receive and process the SV and GOOSE signals output by the equipment at the process layer, and convert them into corresponding DL/T860.8 protocol data and station control. layer device and/or telecontrol device for data interaction, and also check whether the telecontrol device correctly converts the DL/T860.8 protocol data into the corresponding 101 or 104 protocol to interact with the telecontrol master station, in this series of processes In the absence of professional test equipment, testers can only output through traditional standard source equipment or protection test equipment, and then when abnormalities are found, manual packet analysis and diagnosis are performed through general-purpose software such as WireShark, which requires testers The structure, composition, mechanism, and process of various messages are very clear and well understood, and test analysis can be carried out. However, it is difficult for ordinary testers to fully understand all protocols and messages. Therefore, there is currently a lack of In the case of professional testing tools, on-site acceptance has extremely high requirements for testers in terms of automation communication protocols. At the same time, even professional testers have very low efficiency in the manual analysis process, which often leads to smart substation automation. The acceptance test period of the system has been delayed again and again, and it is difficult to complete the quality and quantity as scheduled.
发明内容Contents of the invention
本发明要解决的技术问题:针对现有技术的上述问题,提供一种智能变电站自动化设备智能调试系统及其应用方法,本发明能够利用纵向跨层网络数据分析,实现全站遥信、遥测、遥控预置试验的自动闭环测试,可用于实现对间隔层设备、站控层设备的各个功能指标和性能指标的综合自动测试,以便直观、准确的定位出故障原因和故障位置、提高智能站验收质量和效率,保证智能站的可靠运行。The technical problem to be solved by the present invention: Aiming at the above-mentioned problems of the prior art, an intelligent debugging system and its application method for the automation equipment of the intelligent substation are provided. The present invention can realize the whole station remote signaling, telemetry, The automatic closed-loop test of the remote control preset test can be used to realize the comprehensive automatic test of each functional index and performance index of the bay layer equipment and station control layer equipment, so as to intuitively and accurately locate the cause and location of the fault, and improve the acceptance of the intelligent station Quality and efficiency ensure the reliable operation of intelligent stations.
为了解决上述技术问题,本发明采用的技术方案为:In order to solve the problems of the technologies described above, the technical solution adopted in the present invention is:
一种智能变电站自动化设备智能调试系统,包括智能调试设备和智能验收信号仿真装置,所述智能调试设备分别与智能验收信号仿真装置、智能变电站的站控层网络、智能变电站站控层的远动机双向数据连接,所述智能验收信号仿真装置分别与智能变电站的间隔层网络、过程层网络双向数据连接。An intelligent debugging system for intelligent substation automation equipment, including intelligent debugging equipment and an intelligent acceptance signal simulation device. Two-way data connection, the intelligent acceptance signal simulation device is respectively connected to the bay layer network and the process layer network of the intelligent substation for two-way data connection.
此外,本发明还提供一种前述智能变电站自动化设备智能调试系统的应用方法,包括应用于遥测试验的自动闭环测试的步骤,详细步骤包括:In addition, the present invention also provides an application method of the intelligent debugging system of the aforementioned intelligent substation automation equipment, including the steps of automatic closed-loop testing applied to the telemetry test, and the detailed steps include:
A1)拟定遥测测试方案,初始化设定智能验收信号仿真装置持续输出无效信号时间T0、有效信号时间T1;从遥测测试方案中选择一个测试点作为当前的测试点;A1) Draw up a telemetry test plan, initialize and set the intelligent acceptance signal simulation device to continuously output invalid signal time T0 and valid signal time T1; select a test point from the telemetry test plan as the current test point;
A2)针对当前的测试点,智能验收信号仿真装置默认输出无效信号,在延迟无效信号时间T0后控制控制智能验收信号仿真装置向智能变电站的过程层网络发送SV报文作为测试报文且持续输出有效信号时间T1;A2) For the current test point, the intelligent acceptance signal simulation device outputs an invalid signal by default. After delaying the invalid signal time T0, the intelligent acceptance signal simulation device is controlled to send SV messages to the process layer network of the smart substation as test messages and continue to output Valid signal time T1;
A3)位于智能变电站间隔层的智能测控装置采集SV报文并进行计算处理,将数据转换成61850-8协议的MMS制造报文传给站控层网络;A3) The intelligent measurement and control device located at the bay layer of the smart substation collects SV messages and performs calculation and processing, and converts the data into MMS manufacturing messages of the 61850-8 protocol and transmits them to the station control layer network;
A4)智能调试设备在站控层网络监听的61850-8协议的MMS制造报文进行解析,获取相应MMXU节点中的数据,并将MMXU节点中的数据与SV报文中的遥测数据进行比对分析,如果两者匹配则判定测试合格,跳转执行步骤A5);如果两者不匹配,则判定测试不合格,若重复测试次数小于最大重复测试次数T则跳转执行步骤A2),否则跳转执行步骤A8);A4) The intelligent debugging device analyzes the MMS manufacturing message of the 61850-8 protocol monitored by the station control layer network, obtains the data in the corresponding MMXU node, and compares the data in the MMXU node with the telemetry data in the SV message Analysis, if the two match, it is determined that the test is qualified, and jump to step A5); if the two do not match, it is determined that the test is unqualified, if the number of repeated tests is less than the maximum number of repeated tests T, then jump to step A2), otherwise skip Go to step A8);
A5)站控层网络继续将61850-8协议的MMS制造报文传给站控层的远动机,远动机将61850-8协议的MMS制造报文转换为远动协议数据;A5) The station control layer network continues to transmit the MMS manufacturing message of the 61850-8 protocol to the remote machine of the station control layer, and the remote machine converts the MMS manufacturing message of the 61850-8 protocol into telecontrol protocol data;
A6)远动机将远动协议数据发送给智能调试设备的远动站仿真模块;A6) The telemotor sends the telecontrol protocol data to the telecontrol station simulation module of the intelligent debugging device;
A7)智能调试设备将远动站仿真模块接收的远动协议数据中的遥测数据和SV报文中的遥测数据进行比对分析,如果两者匹配则判定测试合格,跳转执行步骤A8);如果两者不匹配,则判定测试不合格,若重复测试次数小于最大重复测试次数T则跳转执行步骤A5),否则跳转执行步骤A8);A7) The intelligent debugging equipment compares and analyzes the telemetry data in the telecontrol protocol data received by the telecontrol station emulation module and the telemetry data in the SV message. If the two match, it is determined that the test is qualified, and jump to step A8); If the two do not match, it is determined that the test is unqualified. If the number of repeated tests is less than the maximum number of repeated tests T, then jump to step A5), otherwise jump to step A8);
A8)记录测试不合格的信息,智能调试设备控制智能验收信号仿真装置停止输出,且在等待无效信号时间T0后跳转执行步骤A9);A8) Record the unqualified information of the test, the intelligent debugging equipment controls the intelligent acceptance signal simulation device to stop outputting, and jump to step A9 after waiting for the invalid signal time T0);
A9)智能调试设备判断遥测测试方案是否仍有待测的下一个测试点,若仍有待测的下一个测试点则选择下一个测试点作为当前的测试点后跳转执行步骤A2);否则结束测试。A9) The intelligent debugging device judges whether the telemetry test plan still has the next test point to be tested. If there is still the next test point to be tested, select the next test point as the current test point and then jump to step A2); otherwise End the test.
优选地,步骤A1)中无效信号时间T0的初始化时间为2秒、有效信号时间T1的初始化时间为30秒。Preferably, in step A1), the initialization time of the invalid signal time T0 is 2 seconds, and the initialization time of the valid signal time T1 is 30 seconds.
优选地,所述最大重复测试次数T为3。Preferably, the maximum number of repeated tests T is 3.
优选地,本发明还包括应用于遥信试验的自动闭环测试的步骤,详细步骤包括:Preferably, the present invention also includes the steps of automatic closed-loop testing applied to the remote signaling test, and the detailed steps include:
B1)拟定遥信测试方案,初始化设定智能验收信号仿真装置持续输出无效信号时间T0、有效信号时间T1;从遥信测试方案中选择一个测试点作为当前的测试点;B1) Draw up a remote signaling test plan, initialize and set the intelligent acceptance signal simulation device to continuously output invalid signal time T0 and valid signal time T1; select a test point from the remote signal test plan as the current test point;
B2)针对当前的测试点,智能验收信号仿真装置默认输出无效信号,在延迟无效信号时间T0后控制控制智能验收信号仿真装置向智能变电站的间隔层网络发送GOOSE报文作为测试报文且持续输出有效信号时间T1;B2) For the current test point, the intelligent acceptance signal simulation device outputs an invalid signal by default. After delaying the invalid signal time T0, the intelligent acceptance signal simulation device is controlled to send a GOOSE message to the bay layer network of the smart substation as a test message and continue to output Valid signal time T1;
B3)位于智能变电站间隔层的智能测控装置采集GOOSE报文并进行计算处理,将数据转换成61850-8协议的 MMS制造报文传给站控层网络;B3) The intelligent measurement and control device located at the interval layer of the smart substation collects GOOSE messages and performs calculation and processing, and converts the data into MMS manufacturing messages of the 61850-8 protocol and transmits them to the station control layer network;
B4)智能调试设备在站控层网络监听的61850-8协议的MMS制造报文进行解析,获取相应GGIO节点中的数据,并将GGIO节点中的数据与GOOSE报文中的遥信数据进行比对分析,如果两者匹配则判定测试合格,跳转执行步骤B5);如果两者不匹配,则判定测试不合格,若重复测试次数小于最大重复测试次数T则跳转执行步骤B2),否则跳转执行步骤B8);B4) The intelligent debugging device analyzes the MMS manufacturing message of the 61850-8 protocol monitored by the station control layer network, obtains the data in the corresponding GGIO node, and compares the data in the GGIO node with the remote signaling data in the GOOSE message For the analysis, if the two match, it is judged that the test is qualified, and jump to step B5); if the two do not match, it is judged that the test is unqualified, if the number of repeated tests is less than the maximum number of repeated tests T, then jump to step B2), otherwise Jump to step B8);
B5)站控层网络继续将61850-8协议的MMS制造报文传给站控层的远动机,远动机将61850-8协议的MMS制造报文转换为远动协议数据;B5) The station control layer network continues to transmit the MMS manufacturing message of the 61850-8 protocol to the remote machine of the station control layer, and the remote machine converts the MMS manufacturing message of the 61850-8 protocol into telecontrol protocol data;
B6)远动机将远动协议数据发送给智能调试设备的远动站仿真模块;B6) The telemotor sends the telecontrol protocol data to the telecontrol station simulation module of the intelligent debugging equipment;
B7)智能调试设备将远动站仿真模块接收的远动协议数据中的遥信数据和SV报文中的遥信数据进行比对分析,如果两者匹配则判定测试合格,跳转执行步骤B8);如果两者不匹配,则判定测试不合格,若重复测试次数小于最大重复测试次数T则跳转执行步骤B5),否则跳转执行步骤B8);B7) The intelligent debugging equipment compares and analyzes the remote signaling data in the telecontrol protocol data received by the telecontrol station simulation module and the remote signaling data in the SV message. If the two match, it is determined that the test is qualified, and jump to step B8 ); if the two do not match, it is judged that the test is unqualified, if the number of repeated tests is less than the maximum number of repeated tests T, then jump to step B5); otherwise, jump to step B8);
B8)记录测试不合格的信息,智能调试设备控制智能验收信号仿真装置停止输出,且在等待无效信号时间T0后跳转执行步骤B9);B8) Record the unqualified information of the test, the intelligent debugging equipment controls the intelligent acceptance signal simulation device to stop outputting, and jump to step B9 after waiting for the invalid signal time T0);
B9)智能调试设备判断遥信测试方案是否仍有待测的下一个测试点,若仍有待测的下一个测试点则选择下一个测试点作为当前的测试点后跳转执行步骤B2);否则结束测试。B9) The intelligent debugging device judges whether there is still the next test point to be tested in the remote signaling test plan. If there is still the next test point to be tested, select the next test point as the current test point and then jump to step B2); Otherwise end the test.
优选地,步骤B1)中无效信号时间T0的初始化时间为2秒、有效信号时间T1的初始化时间为30秒。Preferably, in step B1), the initialization time of the invalid signal time T0 is 2 seconds, and the initialization time of the valid signal time T1 is 30 seconds.
优选地,所述最大重复测试次数T为3。Preferably, the maximum number of repeated tests T is 3.
优选地,本发明还包括应用于遥控试验的自动闭环测试的步骤,详细步骤包括:Preferably, the present invention also includes the step of being applied to the automatic closed-loop test of the remote control test, and the detailed steps include:
C1)拟定遥控测试方案,初始化设定智能调试设备的远动站仿真模块持续输出无效信号时间T0、有效信号时间T1;从遥控测试方案中选择一个测试点作为当前的测试点;C1) Draw up a remote control test plan, initialize and set the remote station simulation module of the intelligent debugging equipment to continuously output invalid signal time T0 and valid signal time T1; select a test point from the remote control test plan as the current test point;
C2)针对当前的测试点,智能调试设备的远动站仿真模块默认输出无效信号,在延迟无效信号时间T0后预置当前的测试点单点选择后并执行分闸或者合闸的操作并延迟有效信号时间T1,并将远动协议遥控报文发送给位于站控层的远动机;C2) For the current test point, the remote station simulation module of the intelligent debugging equipment outputs an invalid signal by default, and after delaying the invalid signal time T0, preset the current test point single-point selection and perform the opening or closing operation and delay The effective signal time is T1, and the remote control message of the telecontrol protocol is sent to the telemotor at the station control layer;
C3)位于站控层的远动机将远动协议遥控报文转换为61850-8协议的MMS制造报文传给站控层网络;C3) The telemotor located at the station control layer converts the telecontrol protocol telecontrol message into the MMS manufacturing message of the 61850-8 protocol and transmits it to the station control layer network;
C4)智能调试设备在站控层网络监听的61850-8协议的MMS制造报文进行解析,获取相应CSIW节点中的数据,并将CSIW节点中的数据与远动站仿真模块中当前的测试点的遥控状态行比对分析,如果两者匹配则判定测试合格,跳转执行步骤C5);如果两者不匹配,则判定测试不合格,若重复测试次数小于最大重复测试次数T则跳转执行步骤C2),否则跳转执行步骤C8);C4) The intelligent debugging equipment analyzes the MMS manufacturing message of the 61850-8 protocol monitored by the station control layer network, obtains the data in the corresponding CSIW node, and compares the data in the CSIW node with the current test point in the remote station simulation module The comparison and analysis of the remote control status line, if the two match, it is judged that the test is qualified, and the jump is executed to step C5); Step C2), otherwise skip to step C8);
C5)站控层网络继续将61850-8协议的MMS制造报文传给位于间隔层的智能测控装置,智能测控装置将61850-8协议的MMS制造报文转换成GOOSE报文协议数据;C5) The station control layer network continues to transmit the MMS manufacturing message of the 61850-8 protocol to the intelligent measurement and control device located in the bay layer, and the intelligent measurement and control device converts the MMS manufacturing message of the 61850-8 protocol into GOOSE message protocol data;
C6)位于间隔层的智能测控装置将转换后的GOOSE报文协议数据通过间隔层网络发给智能验收信号仿真装置接收;C6) The intelligent measurement and control device located at the bay layer sends the converted GOOSE message protocol data to the intelligent acceptance signal simulation device through the bay layer network for reception;
C7)智能调试设备将智能验收信号仿真装置接收的GOOSE报文协议数据和智能调试设备的远动站仿真模块中当前的测试点的遥控状态行比对分析,如果两者匹配则判定测试合格,跳转执行步骤C8);如果两者不匹配,则判定测试不合格,若重复测试次数小于最大重复测试次数T则跳转执行步骤C5),否则跳转执行步骤C8);C7) The intelligent debugging equipment compares and analyzes the GOOSE message protocol data received by the intelligent acceptance signal simulation device and the remote control status of the current test point in the remote control station simulation module of the intelligent debugging equipment. If the two match, it is determined that the test is qualified. Jump to step C8); if the two do not match, it is determined that the test is unqualified, if the number of repeated tests is less than the maximum number of repeated tests T, then jump to step C5); otherwise, jump to step C8);
C8)记录测试不合格的信息,智能调试设备的远动站仿真模块等待无效信号时间T0后跳转执行步骤C9);C8) Record the unqualified information of the test, and the remote control station simulation module of the intelligent debugging equipment waits for the invalid signal time T0 and then jumps to step C9);
C9)智能调试设备判断遥控测试方案是否仍有待测的下一个测试点,若仍有待测的下一个测试点则选择下一个测试点作为当前的测试点后跳转执行步骤C2);否则结束测试。C9) The intelligent debugging device judges whether the remote control test plan still has the next test point to be tested, if there is still the next test point to be tested, select the next test point as the current test point and then jump to step C2); otherwise End the test.
优选地,步骤C1)中无效信号时间T0的初始化时间为2秒、有效信号时间T1的初始化时间为30秒。Preferably, in step C1), the initialization time of the invalid signal time T0 is 2 seconds, and the initialization time of the valid signal time T1 is 30 seconds.
优选地,所述最大重复测试次数T为3。Preferably, the maximum number of repeated tests T is 3.
和现有技术相比,本发明智能变电站自动化设备智能调试系统具有下述优点:本发明智能变电站自动化设备智能调试系统包括智能调试设备和智能验收信号仿真装置,所述智能调试设备分别与智能验收信号仿真装置、智能变电站的站控层网络、智能变电站站控层的远动机双向数据连接,所述智能验收信号仿真装置分别与智能变电站的间隔层网络、过程层网络双向数据连接,能够利用纵向跨层网络数据分析,实现全站遥信、遥测、遥控预置试验的自动闭环测试,可用于实现对间隔层设备、站控层设备的各个功能指标和性能指标的综合自动测试,以便直观、准确的定位出故障原因和故障位置、提高智能站验收质量和效率,保证智能站的可靠运行。本发明能够规避智能变电站现场验收对测试人员在自动化通讯协议等方面的要求极高的问题,对测试人员技术门槛要求低,测试效率高。Compared with the prior art, the intelligent debugging system of intelligent substation automation equipment of the present invention has the following advantages: the intelligent debugging system of intelligent substation automation equipment of the present invention includes intelligent debugging equipment and intelligent acceptance signal simulation device, and the intelligent debugging equipment is respectively connected with intelligent acceptance The signal simulation device, the station control layer network of the smart substation, and the two-way data connection of the remote machine of the smart substation station control layer, the smart acceptance signal simulation device is respectively connected with the interval layer network and the process layer network of the smart substation for two-way data connection, and can utilize vertical Cross-layer network data analysis, realize automatic closed-loop test of remote signaling, telemetry, and remote control preset test of the whole station, and can be used to realize comprehensive automatic test of various functional indicators and performance indicators of equipment at bay layer and station control layer, so as to be intuitive, Accurately locate the cause and location of the fault, improve the acceptance quality and efficiency of the intelligent station, and ensure the reliable operation of the intelligent station. The invention can avoid the problem that the on-site acceptance of the intelligent substation has extremely high requirements on testers in aspects such as automation communication protocols, has low requirements on the technical threshold of the testers, and has high test efficiency.
和现有技术相比,本发明智能变电站自动化设备智能调试系统应用方法具有下述优点:本发明智能变电站自动化设备智能调试系统应用方法为本发明智能变电站自动化设备智能调试系统的应用,其能够给利用纵向跨层网络数据分析,实现全站遥信/遥测/遥控预置试验的自动闭环测试,实现对间隔层设备、站控层设备的各个功能指标和性能指标的综合自动测试,并能直观、准确的定位出故障原因和故障位置,提高智能站验收质量和效率,保证智能站的可靠运行,而且能够规避智能变电站现场验收对测试人员在自动化通讯协议等方面的要求极高的问题,对测试人员技术门槛要求低,测试效率高。Compared with the prior art, the application method of the intelligent debugging system of the intelligent substation automation equipment of the present invention has the following advantages: the application method of the intelligent debugging system of the intelligent substation automation equipment of the present invention is the application of the intelligent debugging system of the intelligent substation automation equipment of the present invention, which can give Using vertical cross-layer network data analysis, the automatic closed-loop test of the whole station remote signal/telemetry/remote control preset test is realized, and the comprehensive automatic test of each functional index and performance index of the equipment at the bay layer and the station control layer is realized, and it can be intuitively , Accurately locate the cause and location of the fault, improve the acceptance quality and efficiency of the smart station, ensure the reliable operation of the smart station, and avoid the problem that the on-site acceptance of the smart substation places extremely high requirements on the testers in terms of automation communication protocols. Testers have low technical threshold requirements and high testing efficiency.
附图说明Description of drawings
为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following will briefly introduce the drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description are only These are some embodiments of the present invention. Those skilled in the art can also obtain other drawings based on these drawings without creative work.
图1为本发明实施例的系统结构示意图。FIG. 1 is a schematic diagram of the system structure of an embodiment of the present invention.
图2为本发明实施例中遥测试验的自动闭环测试方法流程图。Fig. 2 is a flowchart of an automatic closed-loop test method for a telemetry test in an embodiment of the present invention.
图3为本发明实施例中遥信试验的自动闭环测试方法流程图。Fig. 3 is a flowchart of an automatic closed-loop test method for a remote signaling test in an embodiment of the present invention.
图4为本发明实施例中遥控试验的自动闭环测试方法流程图。Fig. 4 is a flow chart of the automatic closed-loop test method of the remote control test in the embodiment of the present invention.
图5为本发明实施例中智能验收信号仿真装置的输出信号图。Fig. 5 is an output signal diagram of the intelligent acceptance signal simulation device in the embodiment of the present invention.
具体实施方式Detailed ways
为使本发明实施例的目的、技术方案和优点更加清楚,下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments It is a part of embodiments of the present invention, but not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without creative efforts fall within the protection scope of the present invention.
如图1所示,本实施例的智能变电站自动化设备智能调试系统包括智能调试设备和智能验收信号仿真装置,智能调试设备分别与智能验收信号仿真装置、智能变电站的站控层网络、智能变电站站控层的远动机双向数据连接,智能验收信号仿真装置分别与智能变电站的间隔层网络、过程层网络双向数据连接。本实施例中,智能调试设备具体为安装有智能调试软件以及远动仿真模块的计算机设备;智能验收信号仿真装置具体采用南京丹迪克科技开发有限公司的DK-34B4型智能验收测试信号仿真装置。As shown in Figure 1, the intelligent commissioning system for intelligent substation automation equipment in this embodiment includes intelligent commissioning equipment and intelligent acceptance signal simulation device, and the intelligent commissioning equipment is connected with the intelligent acceptance signal simulation device, the station control layer network of the intelligent substation, and the intelligent substation station respectively. The two-way data connection of the remote machine at the control layer, and the two-way data connection between the intelligent acceptance signal simulation device and the bay layer network and process layer network of the smart substation respectively. In this embodiment, the intelligent debugging equipment is specifically a computer device equipped with intelligent debugging software and a telecontrol simulation module; the intelligent acceptance signal simulation device specifically adopts the DK-34B4 intelligent acceptance test signal simulation device of Nanjing Dandic Technology Development Co., Ltd.
参见图1,智能调试设备通过控制智能验收信号仿真装置、通过过程层,向间隔层的智能保护设备、智能测控设备发送SV信号以及GOOSE状态信号并持续T0有效信号时间,间隔层的智能保护设备和智能测控设备接收到该信号后分析和处理,并通过站控层网络的DL/T860.8 MMS报文向远动机发送相应的数据和状态信息,最终数据传到智能调试设备中的远动仿真模块。测试过程中,智能调试系统会在站控层网络中进行实时监听分析间隔层和站控层设备的通讯报文,得到相应的中间数据,智能测试系统将结合过程层数据(仿真装置SV、GOOSE数据)、站控层数据(MMS制造报文解析数据)以及远动数据(104报文解析数据),与智能调试系统测试方案设置参数进行分析比对, 如果在某个环节发现异常,将直接定位显示相应的异常信息。同理,远动仿真模块也可仿真远动主站直接下发遥控命令,实现对整个站端的遥控执行过程进行检测。Referring to Figure 1, the intelligent debugging equipment sends SV signals and GOOSE status signals to the intelligent protection equipment and intelligent measurement and control equipment in the interval layer by controlling the intelligent acceptance signal simulation device and the process layer, and lasts for T0 effective signal time, and the intelligent protection equipment in the interval layer After receiving the signal, the intelligent measurement and control equipment analyzes and processes it, and sends the corresponding data and status information to the remote machine through the DL/T860.8 MMS message of the station control layer network, and finally the data is transmitted to the remote machine in the intelligent debugging equipment simulation module. During the test process, the intelligent debugging system will monitor and analyze the communication messages of the interval layer and the station control layer equipment in real time in the station control layer network, and obtain the corresponding intermediate data. The intelligent test system will combine the process layer data (simulation device SV, GOOSE Data), station control layer data (MMS manufacturing message analysis data) and telecontrol data (104 message analysis data), analyze and compare with the parameters set in the test plan of the intelligent debugging system. If any abnormality is found in a certain link, it will directly Locate and display the corresponding exception information. In the same way, the telecontrol simulation module can also simulate the telecontrol master station to directly issue remote control commands to realize the detection of the remote control execution process of the entire station.
本实施例还提供一种前述智能变电站自动化设备智能调试系统的应用方法,包括应用于遥测试验的自动闭环测试的步骤,如图2所示,详细步骤包括:This embodiment also provides an application method of the intelligent debugging system of the aforementioned intelligent substation automation equipment, including the steps of automatic closed-loop testing applied to the telemetry test, as shown in Figure 2, the detailed steps include:
A1)拟定遥测测试方案,初始化设定智能验收信号仿真装置持续输出无效信号时间T0、有效信号时间T1;从遥测测试方案中选择一个测试点作为当前的测试点;A1) Draw up a telemetry test plan, initialize and set the intelligent acceptance signal simulation device to continuously output invalid signal time T0 and valid signal time T1; select a test point from the telemetry test plan as the current test point;
A2)针对当前的测试点(例如某测试点Ua=57V、Ia=5A),智能验收信号仿真装置默认输出无效信号,在延迟无效信号时间T0后控制控制智能验收信号仿真装置向智能变电站的过程层网络发送SV报文作为测试报文且持续输出有效信号时间T1;A2) For the current test point (such as a certain test point Ua=57V, Ia=5A), the intelligent acceptance signal simulation device outputs an invalid signal by default, and controls the process of sending the intelligent acceptance signal simulation device to the smart substation after delaying the invalid signal time T0 Layer network sends SV message as a test message and continues to output valid signal time T1;
A3)位于智能变电站间隔层的智能测控装置采集SV报文并进行计算处理,将数据转换成61850-8协议(DL/T860.8)的MMS制造报文传给站控层网络;A3) The intelligent measurement and control device located at the bay layer of the smart substation collects SV messages and performs calculation and processing, and converts the data into MMS manufacturing messages of the 61850-8 protocol (DL/T860.8) and transmits them to the station control layer network;
A4)站控层误差计算:智能调试设备在站控层网络监听的61850-8协议的MMS制造报文进行解析,获取相应MMXU节点中的数据,并将MMXU节点中的数据与SV报文中的遥测数据进行比对分析,如果两者匹配则判定测试合格,跳转执行步骤A5);如果两者不匹配,则判定测试不合格,若重复测试次数小于最大重复测试次数T(即重复测试次数N满足:1<=N<=T)则跳转执行步骤A2),否则跳转执行步骤A8);A4) Error calculation at the station control layer: the intelligent debugging device analyzes the MMS manufacturing message of the 61850-8 protocol monitored by the station control layer network, obtains the data in the corresponding MMXU node, and compares the data in the MMXU node with the SV message The telemetry data is compared and analyzed, if the two match, it is judged that the test is qualified, and the execution is skipped to step A5); The number of times N satisfies: 1<=N<=T), then jump to step A2), otherwise jump to step A8);
A5)站控层网络继续将61850-8协议的MMS制造报文传给站控层的远动机,远动机将61850-8协议的MMS制造报文转换为远动协议数据(104协议数据);A5) The station control layer network continues to transmit the MMS manufacturing message of the 61850-8 protocol to the remote machine of the station control layer, and the remote machine converts the MMS manufacturing message of the 61850-8 protocol into telecontrol protocol data (104 protocol data);
A6)远动机将远动协议数据(104协议数据)发送给智能调试设备的远动站仿真模块;A6) The telecontroller sends the telecontrol protocol data (104 protocol data) to the telecontrol station simulation module of the intelligent debugging device;
A7)远传误差计算:智能调试设备将远动站仿真模块接收的远动协议数据(104协议数据)中的遥测数据和SV报文中的遥测数据进行比对分析,如果两者匹配则判定测试合格,跳转执行步骤A8);如果两者不匹配,则判定测试不合格,若重复测试次数小于最大重复测试次数T(即重复测试次数N满足:1<=N<=T)则跳转执行步骤A5),否则跳转执行步骤A8);A7) Remote transmission error calculation: the intelligent debugging device compares and analyzes the telemetry data in the telecontrol protocol data (104 protocol data) received by the telecontrol station simulation module and the telemetry data in the SV message, and judges if the two match If the test is qualified, skip to step A8); if the two do not match, it is determined that the test is unqualified, and if the number of repeated tests is less than the maximum number of repeated tests T (that is, the number of repeated tests N satisfies: 1<=N<=T) then skip Go to step A5), otherwise skip to step A8);
A8)记录测试不合格的信息,智能调试设备控制智能验收信号仿真装置停止输出,且在等待无效信号时间T0后跳转执行步骤A9);记录测试不合格的信息还可进一步根据需要对测试不合格的信息进行分析;A8) Record the unqualified information of the test, the intelligent debugging device controls the intelligent acceptance signal simulation device to stop outputting, and jump to step A9 after waiting for the invalid signal time T0; record the unqualified information of the test, and further correct the unqualified test according to the needs Qualified information for analysis;
A9)智能调试设备判断遥测测试方案是否仍有待测的下一个测试点,若仍有待测的下一个测试点则选择下一个测试点作为当前的测试点后跳转执行步骤A2);否则结束测试。A9) The intelligent debugging device judges whether the telemetry test plan still has the next test point to be tested. If there is still the next test point to be tested, select the next test point as the current test point and then jump to step A2); otherwise End the test.
参见前述步骤A1)-步骤A9)可知,本实施例方法可以提高检定效率、缩短全程检定时间并对不合格项给出重测;保证每个测试点在单次检测过程中有不少于重复测试次数N次机会重采终端测量值,重复性较好,假若测试过程中有一次采集的测量值判断合格了则认为此测试点检测合格;对于检测过程中首次检测不合格的测试点仍有最大重复测试次数T次机会进行重测,避免测试过程突发情况影响测试结果;只要第一次判断出测量值合格,即使测试点持续输出时间未用完,也跳出该测试点进入下一个测试点检测。Referring to the aforementioned steps A1)-step A9), it can be seen that the method of this embodiment can improve the verification efficiency, shorten the whole verification time and provide retests for unqualified items; ensure that each test point has no less than repeated The number of tests N times will re-acquire the terminal measurement value, and the repeatability is good. If the measurement value collected once during the test is judged to be qualified, the test point is considered to be qualified; The maximum number of repeated tests is T times to retest to avoid unexpected situations in the test process from affecting the test results; as long as the measured value is judged to be qualified for the first time, even if the continuous output time of the test point is not used up, it will jump out of the test point and enter the next test point detection.
本实施例中,步骤A1)中无效信号时间T0的初始化时间为2秒、有效信号时间T1的初始化时间为30秒。智能验收信号仿真装置的输出信号如图5所示,分别输出无效信号、有效信号、无效信号,且有效信号持续时间为T1。In this embodiment, the initialization time of the invalid signal time T0 in step A1) is 2 seconds, and the initialization time of the valid signal time T1 is 30 seconds. The output signals of the intelligent acceptance signal simulation device are shown in Fig. 5, which respectively output invalid signals, valid signals, and invalid signals, and the duration of the valid signals is T1.
本实施例中,最大重复测试次数T为3,下同。In this embodiment, the maximum number of repeated tests T is 3, the same below.
本实施例还包括应用于遥信试验的自动闭环测试的步骤,如图3所示,详细步骤包括:The present embodiment also includes the steps of the automatic closed-loop test applied to the remote signal test, as shown in Figure 3, the detailed steps include:
B1)拟定遥信测试方案,初始化设定智能验收信号仿真装置持续输出无效信号时间T0、有效信号时间T1;从遥信测试方案中选择一个测试点作为当前的测试点;B1) Draw up a remote signaling test plan, initialize and set the intelligent acceptance signal simulation device to continuously output invalid signal time T0 and valid signal time T1; select a test point from the remote signal test plan as the current test point;
B2)针对当前的测试点(例如某测试点开出1输出常开变为常闭、翻转时间1S),智能验收信号仿真装置默认输出无效信号,在延迟无效信号时间T0后控制控制智能验收信号仿真装置向智能变电站的间隔层网络发送GOOSE报文作为测试报文且持续输出有效信号时间T1;B2) For the current test point (for example, a certain test point opens 1 output normally open to normally closed, and the flipping time is 1S), the intelligent acceptance signal simulation device outputs an invalid signal by default, and controls the intelligent acceptance signal after delaying the invalid signal time T0 The simulation device sends a GOOSE message to the bay layer network of the smart substation as a test message and continuously outputs a valid signal time T1;
B3)位于智能变电站间隔层的智能测控装置采集GOOSE报文并进行计算处理,将数据转换成61850-8协议(DL/T860.8)的 MMS制造报文传给站控层网络;B3) The intelligent measurement and control device located at the interval layer of the smart substation collects GOOSE messages and performs calculation and processing, and converts the data into MMS manufacturing messages of the 61850-8 protocol (DL/T860.8) and transmits them to the station control layer network;
B4)站控层遥信判断:智能调试设备在站控层网络监听的61850-8协议的MMS制造报文进行解析,获取相应GGIO节点中的数据,并将GGIO节点中的数据与GOOSE报文中的遥信数据进行比对分析,如果两者匹配则判定测试合格,跳转执行步骤B5);如果两者不匹配,则判定测试不合格,若重复测试次数小于最大重复测试次数T(即重复测试次数N满足:1<=N<=T)则跳转执行步骤B2),否则跳转执行步骤B8);B4) Remote signaling judgment at the station control layer: the intelligent debugging device analyzes the MMS manufacturing message of the 61850-8 protocol monitored by the station control layer network, obtains the data in the corresponding GGIO node, and compares the data in the GGIO node with the GOOSE message Compare and analyze the remote signaling data in , if the two match, it is judged that the test is qualified, and jump to step B5); if the two do not match, it is judged that the test is unqualified, if the number of repeated tests is less than the maximum number of repeated tests The number of repeated tests N satisfies: 1<=N<=T), then jump to step B2), otherwise jump to step B8);
B5)站控层网络继续将61850-8协议(DL/T860.8)的MMS制造报文传给站控层的远动机,远动机将61850-8协议的MMS制造报文转换为远动协议数据(104协议数据);B5) The station control layer network continues to transmit the MMS manufacturing message of the 61850-8 protocol (DL/T860.8) to the remote machine of the station control layer, and the remote machine converts the MMS manufacturing message of the 61850-8 protocol into a telecontrol protocol data (104 protocol data);
B6)远动机将远动协议数据(104协议数据)发送给智能调试设备的远动站仿真模块;B6) The telecontroller sends the telecontrol protocol data (104 protocol data) to the telecontrol station simulation module of the intelligent debugging device;
B7)远传遥信判断:智能调试设备将远动站仿真模块接收的远动协议数据(104协议数据)中的遥信数据和SV报文中的遥信数据进行比对分析,如果两者匹配则判定测试合格,跳转执行步骤B8);如果两者不匹配,则判定测试不合格,若重复测试次数小于最大重复测试次数T(即重复测试次数N满足:1<=N<=T)则跳转执行步骤B5),否则跳转执行步骤B8);B7) Telecommunication judgment: the intelligent debugging equipment compares and analyzes the remote signaling data in the telecontrol protocol data (104 protocol data) received by the telecontrol station emulation module and the remote signaling data in the SV message. If they match, it is determined that the test is qualified, and jump to step B8); if the two do not match, it is determined that the test is unqualified, if the number of repeated tests is less than the maximum number of repeated tests T (that is, the number of repeated tests N satisfies: 1<=N<=T ) then jump to step B5), otherwise jump to step B8);
B8)记录测试不合格的信息,智能调试设备控制智能验收信号仿真装置停止输出,且在等待无效信号时间T0后跳转执行步骤B9);记录测试不合格的信息还可进一步根据需要对测试不合格的信息进行分析;B8) Record the unqualified information of the test, the intelligent debugging device controls the intelligent acceptance signal simulation device to stop outputting, and jump to step B9 after waiting for the invalid signal time T0; record the unqualified information of the test and further correct the unqualified test according to the needs Qualified information for analysis;
B9)智能调试设备判断遥信测试方案是否仍有待测的下一个测试点,若仍有待测的下一个测试点则选择下一个测试点作为当前的测试点后跳转执行步骤B2);否则结束测试。B9) The intelligent debugging device judges whether there is still the next test point to be tested in the remote signaling test plan. If there is still the next test point to be tested, select the next test point as the current test point and then jump to step B2); Otherwise end the test.
参见前述步骤B1)-步骤B9)可知,本实施例方法可以提高检定效率、缩短全程检定时间并对不合格项给出重测;保证每个测试点在单次检测过程中有不少于重复测试次数N次机会重采终端测量值,重复性较好,假若测试过程中有一次采集的测量值判断合格了则认为此测试点检测合格;对于检测过程中首次检测不合格的测试点仍有最大重复测试次数T次机会进行重测,避免测试过程突发情况影响测试结果;只要第一次判断出测量值合格,即使测试点持续输出时间未用完,也跳出该测试点进入下一个测试点检测。Referring to the aforementioned steps B1)-Step B9), it can be seen that the method of this embodiment can improve the verification efficiency, shorten the whole verification time and provide retests for unqualified items; ensure that each test point has no less than repeated The number of tests N times will re-acquire the terminal measurement value, and the repeatability is good. If the measurement value collected once during the test is judged to be qualified, the test point is considered to be qualified; The maximum number of repeated tests is T times to retest to avoid unexpected situations in the test process from affecting the test results; as long as the measured value is judged to be qualified for the first time, even if the continuous output time of the test point is not used up, it will jump out of the test point and enter the next test point detection.
本实施例中,步骤B1)中无效信号时间T0的初始化时间为2秒、有效信号时间T1的初始化时间为30秒。In this embodiment, the initialization time of the invalid signal time T0 in step B1) is 2 seconds, and the initialization time of the valid signal time T1 is 30 seconds.
本实施例还包括应用于遥控试验的自动闭环测试的步骤,如图4所示,详细步骤包括:The present embodiment also includes the steps of the automatic closed-loop test applied to the remote control test, as shown in Figure 4, the detailed steps include:
C1)拟定遥控测试方案,初始化设定智能调试设备的远动站仿真模块持续输出无效信号时间T0、有效信号时间T1;从遥控测试方案中选择一个测试点作为当前的测试点;C1) Draw up a remote control test plan, initialize and set the remote station simulation module of the intelligent debugging equipment to continuously output invalid signal time T0 and valid signal time T1; select a test point from the remote control test plan as the current test point;
C2)针对当前的测试点(例如某测试点点表YK1预置、单点执行合闸),智能调试设备的远动站仿真模块默认输出无效信号,在延迟无效信号时间T0后预置当前的测试点单点选择后并执行分闸或者合闸的操作并延迟有效信号时间T1,并将远动协议遥控报文发送给位于站控层的远动机;以某测试点点表YK1预置、单点执行合闸为例,则依据遥控测试方案,延迟T1时间后控制智能调试设备的远动仿真模块预置某点单点选择后并执行合闸操作,并延迟T1时间,仿真远动主站将104协议遥控报文发送给远动机。C2) For the current test point (such as a certain test point table YK1 preset, single-point execution closing), the remote station simulation module of the intelligent debugging device outputs an invalid signal by default, and presets the current test after delaying the invalid signal time T0 After selecting a single point, perform the opening or closing operation and delay the effective signal time T1, and send the telecontrol protocol telecontrol message to the telemotor at the station control layer; a certain test point table YK1 preset, single point Take closing as an example, according to the remote control test plan, after delaying T1 time, the telecontrol simulation module that controls the intelligent debugging equipment presets a single point and performs the closing operation, and delays T1 time, and the simulation telecontrol master station will The 104 protocol remote control message is sent to the remote machine.
C3)位于站控层的远动机将远动协议遥控报文(104协议遥控报文)转换为61850-8协议(DL/T860.8)的MMS制造报文传给站控层网络;C3) The telemotor at the station control layer converts the telecontrol protocol remote control message (104 protocol remote control message) into the MMS manufacturing message of the 61850-8 protocol (DL/T860.8) and transmits it to the station control layer network;
C4)站控层遥控判断:智能调试设备在站控层网络监听的61850-8协议的MMS制造报文进行解析,获取相应CSIW节点中的数据,并将CSIW节点中的数据与远动站仿真模块中当前的测试点的遥控状态行比对分析,如果两者匹配则判定测试合格,跳转执行步骤C5);如果两者不匹配,则判定测试不合格,若重复测试次数小于最大重复测试次数T(即重复测试次数N满足:1<=N<=T)则跳转执行步骤C2),否则跳转执行步骤C8);C4) Remote control judgment of the station control layer: the intelligent debugging device analyzes the MMS manufacturing message of the 61850-8 protocol monitored by the station control layer network, obtains the data in the corresponding CSIW node, and simulates the data in the CSIW node with the remote station The remote control status of the current test point in the module is compared and analyzed. If the two match, the test is judged to be qualified, and the jump is executed to step C5); if the two do not match, the test is judged to be unqualified. The number of times T (that is, the number of repeated tests N satisfies: 1<=N<=T), then jump to step C2); otherwise, jump to step C8);
C5)站控层网络继续将61850-8协议的MMS制造报文传给位于间隔层的智能测控装置,智能测控装置将61850-8协议的MMS制造报文转换成GOOSE报文协议数据(GOOSE发布报文);C5) The station control layer network continues to transmit the MMS manufacturing message of the 61850-8 protocol to the intelligent measurement and control device located at the interval layer, and the intelligent measurement and control device converts the MMS manufacturing message of the 61850-8 protocol into the GOOSE message protocol data (published by GOOSE message);
C6)位于间隔层的智能测控装置将转换后的GOOSE报文协议数据(GOOSE发布报文)通过间隔层网络发给智能验收信号仿真装置接收;C6) The intelligent measurement and control device located at the bay layer sends the converted GOOSE message protocol data (GOOSE release message) to the intelligent acceptance signal simulation device through the bay layer network for reception;
C7)过程层遥控判断:智能调试设备将智能验收信号仿真装置接收的GOOSE报文协议数据(GOOSE订阅报文)和智能调试设备的远动站仿真模块中当前的测试点的遥控状态行比对分析,如果两者匹配则判定测试合格,跳转执行步骤C8);如果两者不匹配,则判定测试不合格,若重复测试次数小于最大重复测试次数T(即重复测试次数N满足:1<=N<=T)则跳转执行步骤C5),否则跳转执行步骤C8);C7) Process level remote control judgment: the intelligent debugging equipment compares the GOOSE message protocol data (GOOSE subscription message) received by the intelligent acceptance signal simulation device with the remote control status of the current test point in the remote control station simulation module of the intelligent debugging equipment Analysis, if the two match, it is determined that the test is qualified, and jump to step C8); if the two do not match, it is determined that the test is unqualified, if the number of repeated tests is less than the maximum number of repeated tests T (that is, the number of repeated tests N satisfies: 1< =N<=T), then jump to step C5), otherwise jump to step C8);
C8)记录测试不合格的信息,智能调试设备的远动站仿真模块等待无效信号时间T0后跳转执行步骤C9);记录测试不合格的信息还可进一步根据需要对测试不合格的信息进行分析;C8) Record the unqualified information of the test, the remote station simulation module of the intelligent debugging equipment waits for the invalid signal time T0 and then jump to step C9); record the unqualified information of the test, and further analyze the unqualified information according to the needs ;
C9)智能调试设备判断遥控测试方案是否仍有待测的下一个测试点,若仍有待测的下一个测试点则选择下一个测试点作为当前的测试点后跳转执行步骤C2);否则结束测试。C9) The intelligent debugging device judges whether the remote control test plan still has the next test point to be tested, if there is still the next test point to be tested, select the next test point as the current test point and then jump to step C2); otherwise End the test.
参见前述步骤C1)-步骤C9)可知,本实施例方法可以提高检定效率、缩短全程检定时间并对不合格项给出重测;保证每个测试点在单次检测过程中有不少于重复测试次数N次机会重采终端测量值,重复性较好,假若测试过程中有一次采集的测量值判断合格了则认为此测试点检测合格;对于检测过程中首次检测不合格的测试点仍有最大重复测试次数T次机会进行重测,避免测试过程突发情况影响测试结果;只要第一次判断出测量值合格,即使测试点持续输出时间未用完,也跳出该测试点进入下一个测试点检测。Referring to the aforementioned steps C1)-step C9), it can be seen that the method of this embodiment can improve the verification efficiency, shorten the whole verification time and provide retests for unqualified items; ensure that each test point has no less than repeated The number of tests N times will re-acquire the terminal measurement value, and the repeatability is good. If the measurement value collected once during the test is judged to be qualified, the test point is considered to be qualified; The maximum number of repeated tests is T times to retest to avoid unexpected situations in the test process from affecting the test results; as long as the measured value is judged to be qualified for the first time, even if the continuous output time of the test point is not used up, it will jump out of the test point and enter the next test point detection.
本实施例中,步骤C1)中无效信号时间T0的初始化时间为2秒、有效信号时间T1的初始化时间为30秒。In this embodiment, the initialization time of the invalid signal time T0 in step C1) is 2 seconds, and the initialization time of the valid signal time T1 is 30 seconds.
综上所述,本实施例智能调试设备连接和控制智能验收信号仿真装置,可实现过程层、间隔层、站控层的有机连接,同时实现远动仿真功能,可以实现从智能仿真装置加量,然后通过间隔层设备、站控层网络、站控层设备、远动网络等环节后返回到智能测试系统,构成一个有机的闭环。测试过程中,智能调试设备科同步分析各网络中的DL/T860.8报文(MMS制造报文)和远动104报文(远动协议数据),并结合智能验收信号仿真装置的输入输出(SV、GOOSE报文),实现对整个系统的闭环测试,若在全站系统的某个环节出现异常或者错误,智能系统将自动实时定位和显示,并形成相应记录和结论。此外,本实施例还提供了一种实现智能变电站遥测、遥信、遥控等试验的自动闭环测试方法,利用纵向跨层网络数据分析,实现全站遥信、遥测、遥控预置试验的自动闭环测试,实现对间隔层设备、站控层设备的各个功能指标和性能指标的综合自动测试,并能直观、准确的定位出故障原因和故障位置,提高智能站验收质量和效率,保证智能站的可靠运行。To sum up, the intelligent debugging equipment in this embodiment connects and controls the intelligent acceptance signal simulation device, which can realize the organic connection of the process layer, the interval layer, and the station control layer, and realize the telecontrol simulation function at the same time, and can realize the increase in volume from the intelligent simulation device. , and then return to the intelligent test system after going through the interval layer equipment, station control layer network, station control layer equipment, telecontrol network and other links, forming an organic closed loop. During the test, the intelligent debugging equipment section synchronously analyzes the DL/T860.8 message (MMS manufacturing message) and
以上所述仅是本发明的优选实施方式,本发明的保护范围并不仅局限于上述实施例,凡属于本发明思路下的技术方案均属于本发明的保护范围。应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理前提下的若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。The above descriptions are only preferred implementations of the present invention, and the protection scope of the present invention is not limited to the above-mentioned embodiments, and all technical solutions under the idea of the present invention belong to the protection scope of the present invention. It should be pointed out that for those skilled in the art, some improvements and modifications without departing from the principles of the present invention should also be regarded as the protection scope of the present invention.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910764363.5A CN110632410B (en) | 2019-08-19 | 2019-08-19 | A kind of intelligent debugging system of intelligent substation automation equipment and application method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910764363.5A CN110632410B (en) | 2019-08-19 | 2019-08-19 | A kind of intelligent debugging system of intelligent substation automation equipment and application method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110632410A true CN110632410A (en) | 2019-12-31 |
CN110632410B CN110632410B (en) | 2021-10-01 |
Family
ID=68970449
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910764363.5A Active CN110632410B (en) | 2019-08-19 | 2019-08-19 | A kind of intelligent debugging system of intelligent substation automation equipment and application method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110632410B (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111193322A (en) * | 2020-01-02 | 2020-05-22 | 国网北京市电力公司 | Dispatching system and method of transformer substation |
CN111610397A (en) * | 2020-05-26 | 2020-09-01 | 中国电力科学研究院有限公司 | An automatic closed-loop testing system and method |
CN111654111A (en) * | 2020-06-15 | 2020-09-11 | 国网宁夏电力有限公司电力科学研究院 | A GOOSE simulation test method for secondary system of intelligent substation |
CN112165444A (en) * | 2020-08-10 | 2021-01-01 | 国网安徽省电力有限公司 | Automatic comparison and verification system and method for remote signaling and remote measuring quantity of telecontrol machine of intelligent substation |
CN113872321A (en) * | 2021-09-03 | 2021-12-31 | 国网湖南省电力有限公司 | Monitoring information detection method and device for uninterrupted transformation of monitoring equipment in substations |
CN117471934A (en) * | 2023-10-09 | 2024-01-30 | 广东工业大学 | Simulation methods and computer equipment for multifunctional measurement and control devices |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103123758A (en) * | 2012-11-28 | 2013-05-29 | 大同电力高级技工学校 | Dispatching automation digital physical hybrid simulation training system |
CN103246283A (en) * | 2013-05-16 | 2013-08-14 | 上海电力学院 | Closed loop testing method of power plant side automatic voltage control system |
CN104502748A (en) * | 2014-12-03 | 2015-04-08 | 国家电网公司 | Transformer station integrated automatic test system |
CN105116248A (en) * | 2015-08-05 | 2015-12-02 | 国家电网公司 | Automatic closed-loop test method for intelligent transformer station relay protection equipment |
CN105159282A (en) * | 2015-09-01 | 2015-12-16 | 国家电网公司 | Process level simulation system and closed-loop testing method of intelligent transformer substation measuring and control device |
CN105242164A (en) * | 2015-08-21 | 2016-01-13 | 国电南瑞科技股份有限公司 | Automatic detection system and method of secondary virtual loop of intelligent transformer station |
CN106712001A (en) * | 2016-12-30 | 2017-05-24 | 国网浙江省电力公司绍兴供电公司 | Data modeling method for network message recording analysis device |
CN107257304A (en) * | 2017-07-31 | 2017-10-17 | 国电南瑞科技股份有限公司 | Telemechanical is exempted to a configuration testing system |
CN107317399A (en) * | 2017-08-09 | 2017-11-03 | 南京国电南自电网自动化有限公司 | Intelligent substation visualization is automatic to dot system and method |
CN107515344A (en) * | 2017-10-18 | 2017-12-26 | 南京能云电力科技有限公司 | Test system and method for a kind of whole station information intelligent of digital transformer substation to point |
CN110071577A (en) * | 2019-05-10 | 2019-07-30 | 国家电网有限公司 | Supervisory control of substation information acceptance method and system |
-
2019
- 2019-08-19 CN CN201910764363.5A patent/CN110632410B/en active Active
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103123758A (en) * | 2012-11-28 | 2013-05-29 | 大同电力高级技工学校 | Dispatching automation digital physical hybrid simulation training system |
CN103246283A (en) * | 2013-05-16 | 2013-08-14 | 上海电力学院 | Closed loop testing method of power plant side automatic voltage control system |
CN104502748A (en) * | 2014-12-03 | 2015-04-08 | 国家电网公司 | Transformer station integrated automatic test system |
CN105116248A (en) * | 2015-08-05 | 2015-12-02 | 国家电网公司 | Automatic closed-loop test method for intelligent transformer station relay protection equipment |
CN105242164A (en) * | 2015-08-21 | 2016-01-13 | 国电南瑞科技股份有限公司 | Automatic detection system and method of secondary virtual loop of intelligent transformer station |
CN105159282A (en) * | 2015-09-01 | 2015-12-16 | 国家电网公司 | Process level simulation system and closed-loop testing method of intelligent transformer substation measuring and control device |
CN106712001A (en) * | 2016-12-30 | 2017-05-24 | 国网浙江省电力公司绍兴供电公司 | Data modeling method for network message recording analysis device |
CN107257304A (en) * | 2017-07-31 | 2017-10-17 | 国电南瑞科技股份有限公司 | Telemechanical is exempted to a configuration testing system |
CN107317399A (en) * | 2017-08-09 | 2017-11-03 | 南京国电南自电网自动化有限公司 | Intelligent substation visualization is automatic to dot system and method |
CN107515344A (en) * | 2017-10-18 | 2017-12-26 | 南京能云电力科技有限公司 | Test system and method for a kind of whole station information intelligent of digital transformer substation to point |
CN110071577A (en) * | 2019-05-10 | 2019-07-30 | 国家电网有限公司 | Supervisory control of substation information acceptance method and system |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111193322A (en) * | 2020-01-02 | 2020-05-22 | 国网北京市电力公司 | Dispatching system and method of transformer substation |
CN111610397A (en) * | 2020-05-26 | 2020-09-01 | 中国电力科学研究院有限公司 | An automatic closed-loop testing system and method |
CN111654111A (en) * | 2020-06-15 | 2020-09-11 | 国网宁夏电力有限公司电力科学研究院 | A GOOSE simulation test method for secondary system of intelligent substation |
CN111654111B (en) * | 2020-06-15 | 2023-05-23 | 国网宁夏电力有限公司电力科学研究院 | GOOSE simulation test method for secondary system of intelligent substation |
CN112165444A (en) * | 2020-08-10 | 2021-01-01 | 国网安徽省电力有限公司 | Automatic comparison and verification system and method for remote signaling and remote measuring quantity of telecontrol machine of intelligent substation |
CN113872321A (en) * | 2021-09-03 | 2021-12-31 | 国网湖南省电力有限公司 | Monitoring information detection method and device for uninterrupted transformation of monitoring equipment in substations |
CN117471934A (en) * | 2023-10-09 | 2024-01-30 | 广东工业大学 | Simulation methods and computer equipment for multifunctional measurement and control devices |
CN117471934B (en) * | 2023-10-09 | 2024-04-19 | 广东工业大学 | Simulation method and computer equipment for multifunctional measurement and control device |
Also Published As
Publication number | Publication date |
---|---|
CN110632410B (en) | 2021-10-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110632410A (en) | An intelligent debugging system for intelligent substation automation equipment and its application method | |
CN202533519U (en) | Fully automatic closed loop test system of protective relaying device | |
CN102901881B (en) | On-site debugging method for digital substation | |
CN102622234B (en) | Development system and method for automatic test case | |
CN104155970A (en) | Intelligent substation monitoring host closed loop test system and test method thereof | |
CN108020742A (en) | The live Auto-Test System and method of distribution feeder automation | |
CN105262211B (en) | The synchronous online self-diagnosing method of a kind of distribution main website and terminal | |
CN103176084A (en) | Intelligent substation simulation system in panoramic replace mode and integration testing method for intelligent substation simulation system | |
CN111552271A (en) | A systematic test method for regional stability control and joint debugging | |
CN111046543A (en) | Intelligent substation test simulation method | |
CN110568284A (en) | Intelligent substation one-key sequential control automatic test verification method, device and system | |
CN106921522A (en) | Intelligent substation network message record analysis device networked information model inspection device | |
CN105094120A (en) | Testing device capable of simulating action behaviors of primary equipment | |
CN105759150B (en) | A kind of test system and method for substation secondary device prefabricated cabin | |
CN111708700B (en) | Intelligent remote machine closed loop comprehensive test method | |
CN104638761B (en) | A method for verifying the connection of GOOSE virtual terminals based on message monitoring and message simulation | |
CN113092130A (en) | Method for simulating conformance test of electric automobile and vehicle-mounted terminal | |
CN109861886B (en) | GOOSE double-network receiving mechanism testing system | |
CN111103495A (en) | Automatic test system and method for field debugging of cross-interval relay protection equipment | |
CN204392274U (en) | A kind of intelligent substation test system | |
CN103699760A (en) | Multilayer closed-loop main station detection data source simulation method | |
CN110212532A (en) | A kind of portable power network schedule automation simulation checking system | |
CN205864449U (en) | Charging equipment of electric automobile communication protocol consistency test device | |
CN101232408B (en) | Method and system for testing stability of mass of numeral subscriber line port for chain building and breaking | |
CN105044552A (en) | Fault diagnosis method, system and device for distribution network automation system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |