CN110630029A - Wall body opening underpinning device and using method - Google Patents
Wall body opening underpinning device and using method Download PDFInfo
- Publication number
- CN110630029A CN110630029A CN201910873784.1A CN201910873784A CN110630029A CN 110630029 A CN110630029 A CN 110630029A CN 201910873784 A CN201910873784 A CN 201910873784A CN 110630029 A CN110630029 A CN 110630029A
- Authority
- CN
- China
- Prior art keywords
- wall
- cross
- upright columns
- underpinning device
- horizontal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0274—Temporary shoring of wall opening
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
The invention relates to the technical field of building construction, and particularly discloses a wall body holing underpinning device and a using method thereof, wherein the wall body holing underpinning device comprises upright columns, horizontal braces and cross braces, wherein at least two groups of upright columns are vertically arranged, the bottoms of the upright columns are provided with jacks, and an anti-skidding cushion layer is arranged between the jacks and the contact surfaces of the upright columns; the horizontal supports are vertically arranged at the top of each group of the upright columns; the cross brace is vertically arranged at the top of the horizontal brace, and the cross brace is provided with a plurality of cross braces. According to the invention, by arranging the horizontal support and the cross support, the stress area of the bearing wall is effectively increased, the pressure is uniformly distributed on the horizontal support and the cross support, the height requirement of the underpinning device can be adjusted by using the jack, the problem of transformation of the bearing wall is effectively solved, and the bearing wall has the characteristics of simple structure, convenience in assembly, reusability and the like.
Description
Technical Field
The invention relates to the technical field of building construction, in particular to a wall body opening underpinning device and a using method thereof.
Background
With the development of social economy, the original spatial layout of some old buildings cannot meet the use requirements of people, and reinforcement design and modification are needed, for example, an office or a dormitory with a small space is required to be changed into a restaurant or a conference room with a large space. The existing old building is mostly a brick-concrete structure, and in order to meet the requirement of a large bay, the original bearing wall needs to be dismantled.
In the process of constructing and transforming the bottom layer or the multi-layer large space structure of the traditional house, the method of designing the reinforced concrete underpinning beam at the bottom ring beam or the plate bottom is often adopted for transforming and underpinning design. The design and construction method requires strict and uniform time for construction steps at each stage, the perpendicularity and the crack level of the wall body are abnormal easily before the concrete underpinning beam is poured, and the cracks and the deflection of the wall and the underpinning beam are beyond the standard limit after the concrete is poured. This is mainly because, when the concrete underpinning beam is set and poured, the non-uniformity and strength of the concrete material do not reach the designed strength completely, so that the wall is easy to crack when the upper wall load is transmitted to the underpinning beam, the beam deflection is too large, the underpinning procedure is delayed, and the serious person causes the interruption or failure of the wall reconstruction.
Meanwhile, different house reconstruction requires underpinning devices with different heights, the assembly or adjustment of some devices is very complex, and the assembly and adjustment of the devices before construction consume a large amount of time, so that the construction efficiency is influenced.
Disclosure of Invention
Aiming at the defects in the prior art, the invention provides a wall body holing underpinning device and a use method thereof, and the wall body holing underpinning device is simple in structure, reasonable in method and convenient to popularize.
A wall body opening underpinning device comprises upright columns, horizontal braces and transverse braces, wherein at least two groups of upright columns are vertically arranged, jacks are installed at the bottoms of the upright columns, and anti-skid cushion layers are arranged between the jacks and contact surfaces of the upright columns; the horizontal supports are vertically arranged at the top of each group of the upright columns; the cross brace is vertically arranged at the top of the horizontal brace, and the cross brace is provided with a plurality of cross braces.
Preferably, the jack is a self-locking jack.
Preferably, each group of the upright posts is at least two.
Preferably, the length of the horizontal support is 2-3 meters.
Preferably, the length of the wale is 0.5 to 1 meter.
Preferably, the height of the upright post is 1-2.5 m.
Preferably, the use method of the wall body hole opening underpinning device comprises the following steps:
(1) before construction, removing obstacles near a wall to be dismantled, and planning an area to be dismantled by using ink lines;
(2) cutting holes at intervals of 0.5-1 meter on the wall body to be removed, and inserting the cross braces into the holes;
(3) vertically arranging the upright columns at four corners of the wall body to be dismantled, wherein jacks are respectively arranged at the bottoms of the upright columns;
(4) installing the horizontal support between the cross support and the upright post;
(5) adjusting the height of the jack to enable the upright column, the horizontal support and the cross support to be effectively supported and connected;
(6) and (4) removing the wall to be removed, and removing the underpinning device after the support columns are reestablished under the wall.
The invention has the beneficial effects that:
according to the invention, by arranging the horizontal support and the cross support, the stress area of the bearing wall is effectively increased, the pressure is uniformly distributed on the horizontal support and the cross support, the height requirement of the underpinning device can be adjusted by using the jack, the problem of transformation of the bearing wall is effectively solved, and the bearing wall has the characteristics of simple structure, convenience in assembly, reusability and the like.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings needed to be used in the embodiments will be briefly described below, it should be understood that the following drawings only illustrate some embodiments of the present invention, and should not be considered as limiting the scope, and for those skilled in the art, other related drawings can be obtained according to the drawings without inventive efforts.
FIG. 1 is a schematic view of a mounting structure for use with the present invention;
FIG. 2 is a side view of the present invention;
1-a wall to be dismantled, 2-upright posts, 3-jacks, 4-horizontal braces and 5-cross braces.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention easier to clearly understand, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all embodiments of the present invention. The components of embodiments of the present invention generally described and illustrated in the figures herein may be arranged and designed in a wide variety of different configurations.
As shown in fig. 1 and 2, a wall body opening underpinning device comprises upright posts 2, horizontal braces 4 and cross braces 5, wherein at least two groups of upright posts 2 are vertically arranged, each group of upright posts 2 is at least two, the height of each upright post 2 is 1-2.5 m, a jack 3 is arranged at the bottom of each upright post 2, an anti-skid cushion layer is arranged between the jack 3 and the contact surface of each upright post 2, the anti-skid cushion can increase the friction force of the contact surface, and the jack 3 is a self-locking jack 3; the horizontal support 4 is vertically arranged at the top of each group of upright posts 2, and the length of the horizontal support 4 is 2-3 m; the cross braces 5 are vertically arranged at the tops of the horizontal braces 4, the number of the cross braces 5 is several, and the length of each cross brace 5 is 0.5-1 meter.
In one embodiment of the invention, two groups of upright posts 2 are vertically arranged, wherein each group of upright posts 2 comprises two upright posts, the height of each upright post 2 is 1.5 meters, and the length of each horizontal support 4 is 2 meters.
A use method of a wall body opening underpinning device comprises the following steps:
(1) before construction, removing obstacles near a wall body 1 to be dismantled, and marking an area to be dismantled by using ink lines, wherein the area to be dismantled comprises cross braces 5 and a wall surface to be dismantled;
(2) cutting holes at intervals of 0.5 m on the wall body to be removed, inserting the cross braces 5 into the holes, wherein the width and the height of the holes are slightly larger than those of the cross braces 5 for convenient operation;
(3) vertically arranging upright columns 2 at four corners of a wall body 1 to be disassembled, and respectively installing jacks 3 at the bottoms of the upright columns 2;
(4) installing a horizontal support 4 between a cross support 5 and the upright post 2;
(5) the height of the jack 3 is adjusted to ensure that the upright post 2, the horizontal support 4 and the cross support 5 are effectively supported and connected;
(6) and (3) dismantling the wall body 1 to be dismantled, and dismantling the underpinning device after the support column is reestablished under the wall body.
In another embodiment of the invention, the following setup and method are followed: four groups of upright columns 2 are vertically arranged, each group of upright columns 2 is two, the height of each upright column 2 is 2 meters, the length of each horizontal support 4 is 2.5 meters, in the using method, holes are cut on the wall body to be removed every 1 meter, the same effect can be achieved, and the problem of underpinning of the bearing wall during opening is solved.
According to the invention, by arranging the horizontal support and the transverse support, the stress area of the bearing wall is effectively increased, the pressure is uniformly distributed on the horizontal support and the transverse support, the height requirement of the underpinning device can be adjusted by using the jack, the problem of transformation of the bearing wall is effectively solved, and the bearing wall has the characteristics of simple structure, convenience in assembly, reusability and the like.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the present invention, and any modifications, equivalents and improvements made within the spirit and principle of the present invention should be included in the scope of the present invention.
Claims (7)
1. A wall body opening underpinning device is characterized by comprising upright columns, horizontal braces and cross braces, wherein at least two groups of upright columns are vertically arranged, jacks are installed at the bottoms of the upright columns, and anti-skid cushion layers are arranged between the jacks and contact surfaces of the upright columns; the horizontal supports are vertically arranged at the top of each group of the upright columns; the cross brace is vertically arranged at the top of the horizontal brace, and the cross brace is provided with a plurality of cross braces.
2. A wall opening underpinning device as claimed in claim 1, wherein: the jack is a self-locking jack.
3. A wall opening underpinning device as claimed in claim 1, wherein: each group of the upright posts is at least two.
4. A wall opening underpinning device as claimed in claim 1, wherein: the length of the horizontal support is 2-3 meters.
5. A wall opening underpinning device as claimed in claim 1, wherein: the length of the cross brace is 0.5-1 meter.
6. A wall opening underpinning device as claimed in claim 1, wherein: the height of the upright post is 1-2.5 m.
7. A method for using a wall hole opening underpinning device as claimed in claim 1, wherein the method comprises the following steps:
(1) before construction, removing obstacles near a wall to be dismantled, and planning an area to be dismantled by using ink lines;
(2) cutting holes at intervals of 0.5-1 meter on the wall body to be removed, and inserting the cross braces into the holes;
(3) vertically arranging the upright columns at four corners of the wall body to be dismantled, wherein jacks are respectively arranged at the bottoms of the upright columns;
(4) installing the horizontal support between the cross support and the upright post;
(5) adjusting the height of the jack to enable the upright column, the horizontal support and the cross support to be effectively supported and connected;
(6) and (4) removing the wall to be removed, and removing the underpinning device after the support columns are reestablished under the wall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910873784.1A CN110630029A (en) | 2019-09-17 | 2019-09-17 | Wall body opening underpinning device and using method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910873784.1A CN110630029A (en) | 2019-09-17 | 2019-09-17 | Wall body opening underpinning device and using method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110630029A true CN110630029A (en) | 2019-12-31 |
Family
ID=68971447
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910873784.1A Pending CN110630029A (en) | 2019-09-17 | 2019-09-17 | Wall body opening underpinning device and using method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110630029A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111472566A (en) * | 2020-04-13 | 2020-07-31 | 中建三局集团有限公司 | Underpinning device and underpinning method for joist pull column |
CN111980439A (en) * | 2020-07-21 | 2020-11-24 | 上海建工一建集团有限公司 | Wall bearing replacement device and wall bearing replacement construction method |
CN112282408A (en) * | 2020-09-05 | 2021-01-29 | 中建二局基础设施建设投资有限公司 | Municipal garden landscape house old enclosure wall body reinforcing structure and hole opening method |
US20210164247A1 (en) * | 2015-04-29 | 2021-06-03 | Jeffery Kennedy | Lintel Lift Apparatus and Method |
CN113235971A (en) * | 2021-05-19 | 2021-08-10 | 山东大学 | Large-area dismantling device and process for wall structure of subway station |
CN114293804A (en) * | 2021-12-27 | 2022-04-08 | 上海建工二建集团有限公司 | Underpinning structure and method for masonry load-bearing wall opening |
CN114319921A (en) * | 2021-12-27 | 2022-04-12 | 上海建工四建集团有限公司 | Construction method and support assembly for rammed earth wall moisture-proof layer |
US12123207B2 (en) * | 2023-06-30 | 2024-10-22 | Lintel Lift, Llc | Lintel lift apparatus and method |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001220901A (en) * | 2000-02-10 | 2001-08-17 | Dynamic Design:Kk | Base isolation structuring method for existing building |
JP2002242452A (en) * | 2001-02-14 | 2002-08-28 | Shimizu Corp | Construction method for opening part in existing masonry construction wall |
CN101429819A (en) * | 2007-11-07 | 2009-05-13 | 上海天演建筑物移位工程有限公司 | Wall and column underpinning method |
JP2011017187A (en) * | 2009-07-09 | 2011-01-27 | Toda Constr Co Ltd | Base-isolating method for existing building |
CN104652839A (en) * | 2015-01-30 | 2015-05-27 | 中国矿业大学 | Method for reducing height of reinforced concrete frame structure |
CN104863380A (en) * | 2015-05-20 | 2015-08-26 | 中建三局第二建设工程有限责任公司 | Overall replacement system for original building shock-insulation support and construction method |
CN205654123U (en) * | 2016-03-18 | 2016-10-19 | 浙江恒誉建设有限公司 | Building system of underpining |
CN106088641A (en) * | 2016-06-03 | 2016-11-09 | 河海大学 | Load bearing wall underpinning structure and method |
CN106836839A (en) * | 2016-11-29 | 2017-06-13 | 大连久鼎祥瑞特种工程技术研究院有限公司 | Fabric structure jacking increasing layer method |
CN208586936U (en) * | 2018-04-25 | 2019-03-08 | 苏州中固建筑科技股份有限公司 | A kind of control protects brick mixed building joist and demolishes walls constructing device |
-
2019
- 2019-09-17 CN CN201910873784.1A patent/CN110630029A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001220901A (en) * | 2000-02-10 | 2001-08-17 | Dynamic Design:Kk | Base isolation structuring method for existing building |
JP2002242452A (en) * | 2001-02-14 | 2002-08-28 | Shimizu Corp | Construction method for opening part in existing masonry construction wall |
CN101429819A (en) * | 2007-11-07 | 2009-05-13 | 上海天演建筑物移位工程有限公司 | Wall and column underpinning method |
JP2011017187A (en) * | 2009-07-09 | 2011-01-27 | Toda Constr Co Ltd | Base-isolating method for existing building |
CN104652839A (en) * | 2015-01-30 | 2015-05-27 | 中国矿业大学 | Method for reducing height of reinforced concrete frame structure |
CN104863380A (en) * | 2015-05-20 | 2015-08-26 | 中建三局第二建设工程有限责任公司 | Overall replacement system for original building shock-insulation support and construction method |
CN205654123U (en) * | 2016-03-18 | 2016-10-19 | 浙江恒誉建设有限公司 | Building system of underpining |
CN106088641A (en) * | 2016-06-03 | 2016-11-09 | 河海大学 | Load bearing wall underpinning structure and method |
CN106836839A (en) * | 2016-11-29 | 2017-06-13 | 大连久鼎祥瑞特种工程技术研究院有限公司 | Fabric structure jacking increasing layer method |
CN208586936U (en) * | 2018-04-25 | 2019-03-08 | 苏州中固建筑科技股份有限公司 | A kind of control protects brick mixed building joist and demolishes walls constructing device |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20210164247A1 (en) * | 2015-04-29 | 2021-06-03 | Jeffery Kennedy | Lintel Lift Apparatus and Method |
US11692363B2 (en) * | 2015-04-29 | 2023-07-04 | Lintel Lift, Llc | Lintel lift apparatus and method |
US20230340794A1 (en) * | 2015-04-29 | 2023-10-26 | Lintel Lift, Llc | Lintel Lift Apparatus and Method |
CN111472566A (en) * | 2020-04-13 | 2020-07-31 | 中建三局集团有限公司 | Underpinning device and underpinning method for joist pull column |
CN111980439A (en) * | 2020-07-21 | 2020-11-24 | 上海建工一建集团有限公司 | Wall bearing replacement device and wall bearing replacement construction method |
CN112282408A (en) * | 2020-09-05 | 2021-01-29 | 中建二局基础设施建设投资有限公司 | Municipal garden landscape house old enclosure wall body reinforcing structure and hole opening method |
CN113235971A (en) * | 2021-05-19 | 2021-08-10 | 山东大学 | Large-area dismantling device and process for wall structure of subway station |
WO2022241750A1 (en) * | 2021-05-19 | 2022-11-24 | 山东大学 | Large-area dismantling device for wall body structure of subway station and process therefor |
CN114293804A (en) * | 2021-12-27 | 2022-04-08 | 上海建工二建集团有限公司 | Underpinning structure and method for masonry load-bearing wall opening |
CN114319921A (en) * | 2021-12-27 | 2022-04-12 | 上海建工四建集团有限公司 | Construction method and support assembly for rammed earth wall moisture-proof layer |
US12123207B2 (en) * | 2023-06-30 | 2024-10-22 | Lintel Lift, Llc | Lintel lift apparatus and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110630029A (en) | Wall body opening underpinning device and using method | |
CN104863380B (en) | Overall replacement system for original building shock-insulation support and construction method | |
KR100968068B1 (en) | Multi-Horizontal Structure Member Forming Method | |
CN105220769A (en) | Large area bolt-ball net frame integral top lifting construction method | |
GB2371313A (en) | Partially prefabricated waffle slab | |
CN104652842A (en) | Building integral deviation correcting and raising lifting method and equipment thereof | |
CN108342984B (en) | Soft foundation trestle for mudflat and installation and sedimentation method thereof | |
CN214941057U (en) | Container prefabricated house and container prefabricated house elevation adjusting device that distributes in bank | |
CN111502027B (en) | Inverted cone jacking method for large-span grid structure | |
CN211922969U (en) | Umbrella-shaped elevated structure supporting frame for integrated module house | |
CN209779693U (en) | Construction supporting device | |
CN202441075U (en) | Supporting frame for big cantilever steel member installation | |
CN203225074U (en) | Advertising board of net rack structure | |
JPH08338155A (en) | Method making existing building into base isolation construction | |
CN206870081U (en) | A kind of prefabricated case beam bed die steel supporting component | |
CN105040991B (en) | The supporting construction and method for supporting of large-span steel segmental hoisting | |
CN110821223A (en) | Method for solving micro-vibration by adopting micro-vibration support in clean workshop | |
CN206205447U (en) | The fixing device of prefabricated component | |
CN218965749U (en) | Modular counter-force pedestal channel and anchor hole mounting structure | |
CN112459516B (en) | Construction method for increasing net height of existing building | |
CN221194450U (en) | Can have enough to meet need assembled construction elevator safety channel | |
CN111674684B (en) | Device for transporting and stacking prefabricated floor slab components and using method thereof | |
CN211974466U (en) | Reusable steel structure temporary support frame conversion joint | |
CN218991024U (en) | Newly-added bracket structure of concrete beam column | |
CN203846794U (en) | Adjustable support |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191231 |