CN110616707A - Post-grouting cast-in-situ bored pile construction method - Google Patents

Post-grouting cast-in-situ bored pile construction method Download PDF

Info

Publication number
CN110616707A
CN110616707A CN201910969613.9A CN201910969613A CN110616707A CN 110616707 A CN110616707 A CN 110616707A CN 201910969613 A CN201910969613 A CN 201910969613A CN 110616707 A CN110616707 A CN 110616707A
Authority
CN
China
Prior art keywords
pile
hole
grouting
pipe
reinforcement cage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910969613.9A
Other languages
Chinese (zh)
Inventor
郭俊义
杜锦强
李达疆
汪洋
连丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Electrical Construction Group Henan Engineering Co Ltd
Original Assignee
China Electrical Construction Group Henan Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Electrical Construction Group Henan Engineering Co Ltd filed Critical China Electrical Construction Group Henan Engineering Co Ltd
Priority to CN201910969613.9A priority Critical patent/CN110616707A/en
Publication of CN110616707A publication Critical patent/CN110616707A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds

Abstract

The invention discloses a post-grouting cast-in-situ bored pile construction method, which comprises the following steps: forming holes: firstly, measuring the pile position, then aligning the center of the steel casing to the center of a pile hole for vertical embedding, finally drilling to form a hole, and after the drilled hole reaches the designed depth, carrying out primary hole cleaning by using a hole cleaning drill bit; transporting the manufactured reinforcement cage to the site through a cage transporting vehicle, and placing the lower part of the reinforcement cage in place; placing the guide pipe, then carrying out secondary hole cleaning, pouring concrete for the depth of the pile within half an hour, and measuring the elevation of the pile top by using a heavy hammer or a measuring rod in time when the pile top is close to the pile top in pouring; and finally, performing post-grouting construction, wherein the post-grouting construction is to perform grouting to the pile side firstly and perform grouting to the pile bottom after the grout is initially set. The construction method has the advantages that the construction method has small harmful influence on adjacent buildings and surrounding environment, the length and the diameter of the pile can be freely changed according to design requirements, the pile end can enter a bearing layer or be embedded into a rock stratum, and the bearing capacity of a single pile is large.

Description

Post-grouting cast-in-situ bored pile construction method
One, the technical field
The invention relates to a construction method of a pile foundation, in particular to a post-grouting bored pile construction method, and belongs to the technical field of building construction.
Secondly, background art:
in pile foundation construction, a method of grouting after filling a pile is often adopted to improve the bearing capacity and the uplift resistance of the pile, and for main buildings (structures) of a power plant, a natural foundation cannot meet the requirements of strength and deformation, and an artificial foundation is needed; the foundation of the main power plant of the general power plant is buried between-5.00 m and-7.50 m, the main bearing layer of the foundation is a layer I and a layer II, and the part of the foundation is a layer II or a layer III, when the site is met and is distributed with hard silty clay with larger thickness and contains a large amount of calcium nodules, the concrete precast pile is difficult to penetrate through the hard silty clay layer.
Thirdly, the invention content:
the technical problem to be solved by the invention is as follows: the defects of the prior art are overcome, the construction method of the post-grouting bored pile is provided, the problem that the concrete precast pile is difficult to penetrate through a hard powdery clay layer is solved, and the effect of strong bearing capacity is achieved.
The technical scheme adopted by the invention for solving the technical problem is as follows:
the invention relates to a post-grouting cast-in-situ bored pile construction method, which comprises the following steps:
construction preparation:
1) selecting proper mechanical equipment such as a drilling machine, a drill bit, a protective arm sleeve and the like according to the physical characteristics of the soil layer of the construction land;
2) the concrete adopts compact sandstone materials, the cement adopted by post-grouting is PC32.5 ordinary portland cement, and the water cement ratio is 1: 2;
3) selecting reinforcing steel bars and welding rods, wherein the reinforcing steel bars are selected from phi-HPB 300, phi-HRB 335 and phi-HRB 400 grades; wherein: e43 type welding rods are adopted for the HPB300 steel bars, and E50 type welding rods are adopted for the HRB335 steel bars and the HRB400 steel bars;
the construction method comprises the following specific steps:
A. forming holes
1) Positioning and lofting: measuring and placing an axis by using a total station by adopting a wire guiding method to position a pile, drilling a hole on the measured pile position by using a steel bar, inserting a short steel bar as a mark, and curing the periphery by using concrete for 300 m;
2) manufacturing and sinking a protective cylinder: the welding seam is adopted, the inner diameter of the steel casing is 100mm larger than the pile diameter, the wall thickness is 4mm, and the height is 1.5 m; embedding the steel pile casing vertically, allowing the steel pile casing to enter undisturbed soil for 300mm, filling clay around the steel pile casing, and ensuring that the error between the center of the steel pile casing and the center of a pile hole is less than or equal to 20 mm;
3) preparing slurry: adopting high-plasticity clay or bentonite as the rotary-drilled slurry, and making slurry by using a stirrer;
4) positioning a drilling machine: the error of the drill bit aiming at the center of the pile is controlled within 50mm, the verticality of the drill rod is controlled within 0.3 percent, and the plane error and the verticality of the pile hole are ensured;
5) drilling to form a hole:
a. measuring the diameter of a drill bit, the total length of a drilling tool, the drilling hole depth and the exposed length of a drill rod;
b. during drilling, a vertical control instrument is observed to ensure the verticality of a drilled hole, the drilling is not interrupted and stopped without any reason during the hole forming, the drilling speed is paid attention to before the final hole to prevent hole collapse, the pile body is positioned below the underground water level, slurry is required to be used, the liquid level of the slurry in the hole is ensured to be not lower than the natural ground in the drilling process, for a soil layer of the hole easy to collapse, a low-speed footage is adopted, when the distance from the soil layer is 1 ~ 0.5.5 m, the footage speed is controlled to be 0.2 ~ 0.5.5 m/h, and the drilling in a decompression state is ensured;
c. cleaning the hole by using a hole cleaning drill after the hole is drilled to reach the preset depth;
b. Manufacturing, transporting and placing of reinforcement cage
1) Manufacturing a steel reinforcement cage:
a. main reinforcement: the main ribs are welded by flash welding;
b. and (3) processing the stiffening hoops and the reinforcement cage framework: winding the reinforcing steel bars into stiffening hoops with the inner diameter of a specified size by using a die, wherein the spacing of the stiffening hoops is 2m, the hooping parts are lapped and welded together by adopting a single surface, and the width of a welding seam is 0.7 d;
c. coiling and welding the centralizer: before winding, straightening the disc, winding the disc into a disc with the diameter corresponding to that of the reinforcement cage by using a mold, and winding the disc on the manufactured reinforcement cage framework according to requirements;
d. and (3) mounting a rear grouting pipe: the rear grouting pipe is a seamless steel pipe with the size of 1 inch, and is connected with the steel reinforcement cage by adopting a pipe hoop or a coupling;
2) and (3) transporting and placing the reinforcement cage:
the steel reinforcement cage is transported by a cage transporting vehicle, and cedar poles are bound in the steel reinforcement cage, so that the steel reinforcement cage is prevented from deforming in the transportation process; before the steel reinforcement cage is placed, the elevation of the steel tapping protecting cylinder is measured by a level gauge, and the length of a hanging rib or a pressing rod is calculated; when the steel reinforcement cage is placed, the steel reinforcement cage does not touch the wall of the hole and keeps vertical centering, and the cross arm of the hanging bar or the pressure lever is placed on the sleeper and cannot be pressed on the protective cylinder; calculating the ground elevation according to the same elevation, fixing the pressure rod on the orifice cross arm after the reinforcement cage is put down in place, and preventing the reinforcement cage from floating upwards or moving downwards during pouring;
C. down-placing guide pipe and secondary hole cleaning
a. Adopting phi 219 guide pipes which are connected by screw threads or flange plates and sealed by rubber rings or rubber plates; the guide pipe is placed in the middle of the lower inlet hole, and the cleaned screw thread is fastened when the guide pipe is connected;
b. after the guide pipe is placed into the hole, secondary hole cleaning is carried out, and the slurry performance is kept during hole cleaning; removing sediments at the bottom of the hole, and simultaneously avoiding reducing the silty clay; the density of the mud returned by secondary hole cleaning is less than or equal to 1.15, and the sediment at the bottom of the hole is less than or equal to 100 mm;
D. pouring of concrete
a. During primary concrete pouring, the lower end of the guide pipe is 0.3 ~ 0.5.5 m away from the bottom of the hole, a waterproof bolt is added before pouring, the depth of the bottom of the guide pipe embedded in the concrete after primary pouring is ensured to be 2m ~ 5m, the slump of the primary poured concrete is 140-160 mm of soil, and the slump of the concrete is 160-220 mm in other times;
b. during pouring, the concrete in the pipe is observed to descend and the water return condition of the orifice is observed, the ascending height of the concrete surface in the hole is measured in time, and the upper guide pipe is lifted and dismantled in sections in time; the guide pipe is embedded in the concrete, and the depth of the guide pipe is 2-6 m; when the pile top is poured, measuring the elevation of the pile top, wherein the elevation of the pile top of the poured pile is more than or equal to 0.8m, and slowly moving the guide pipe up and down after the concrete surface reaches the elevation of the over-poured length to slowly close the opening of the concrete surface;
E. post grouting construction
1) And (3) processing and mounting a rear grouting pipe:
a. the bottom grouting pipe is a 1 'seamless steel pipe, the bottom nozzle is processed into a ring shape by a plastic pipe with the pipe diameter of 1.2', and the nozzle is arranged at the bottom; the grouting pipe and the reinforcement cage are fixed by welding or binding; the upper part of the grouting pipe is 0.3m higher than the ground, and the pipe orifice is sealed by a protective cap;
b. the annular pipe of the side grouting pipe nozzle is a plastic pipe with the pipe diameter of 1.2 ″, the annular pipe is arranged 15.0m away from the pile end, the flexible nozzle pipe is connected with the grouting pipe through a tee joint, and the grouting pipe is fixedly connected with the reinforcement cage in a welding or binding mode; the upper part of the grouting pipe is 0.3m higher than the ground, and the pipe orifice is sealed by a protective cap;
2) grouting: the grouting sequence adopts slow grouting, firstly grouting to the pile side, and then grouting to the pile bottom after the grout is initially set, wherein the time interval between the grouting to the pile side and the grouting to the pile bottom is not less than 2 hours; and (4) when the grouting amount reaches 4/5 of a design value, the grouting pressure exceeds 3-4 MPa, and the grouting can be stopped after the grouting amount is stabilized for 3-10 minutes.
The construction method of the post-grouting bored pile comprises the steps of after drilling to form a hole, lifting a drill bit, replacing mud with higher density by mud with lower relative density by a mud replacement method, and keeping the original water head height in the hole during hole cleaning.
The technology of the invention has the following beneficial effects:
1. the slurry dug by the rotary drilling method is stirred and prepared by adopting high-plasticity clay or bentonite, the slurry parameters are strictly controlled in the drilling process, the collapse and the hole shrinkage of the hole wall are avoided, and the filling quality of the pile is ensured; in the drilling process, a driller can pay attention to the perpendicularity of the vertical control instrument at any time, and pay attention to the drilling speed before final hole drilling, so that the hole collapse condition is prevented.
2. The pile body of the invention is below the underground water level, the mud must be used, and the mud is supplemented into the hole in the drilling process, so that the liquid level of the mud in the hole is ensured not to be lower than the natural ground. The sediment in the mud ditch and the tank is cleaned frequently, the mud ditch and the tank are kept smooth, and the mud quality is ensured.
3. The centralizer is arranged on the reinforcement cage, so that the thickness of a protective layer can be ensured, and the hole wall is prevented from being damaged in the process of descending the reinforcement cage; in the transportation process of the reinforcement cage, fir poles are tied in the reinforcement cage, so that the reinforcement cage is prevented from being extruded and deformed in the transportation process; when the reinforcement cage is lowered to the place, the pressure lever is fixed on the orifice cross arm to prevent the reinforcement cage from floating upwards or moving downwards during pouring.
4. After the concrete surface of the invention reaches the elevation of the over-grouting length, the guide pipe should be moved up and down slowly without pulling out the pipe quickly, so that the concrete surface opening is closed slowly, and the quality defects of slurry mixing, formation of a concrete core or water seepage of a pile head and the like caused by the fact that the pipe is pulled out too quickly are prevented.
5. By utilizing the construction method for construction, the harmful influence on adjacent buildings and the surrounding environment is small, the length and the diameter of the pile can be freely changed according to the design requirement, and the pile end can enter a bearing stratum or be embedded into a rock stratum; the single pile has large bearing capacity.
Fourthly, the specific implementation mode:
the post-grouting cast-in-situ bored pile construction method comprises the following steps:
a post-grouting cast-in-situ bored pile construction method is characterized by comprising the following steps:
construction preparation:
1) selecting proper mechanical equipment such as a drilling machine, a drill bit, a protective arm sleeve and the like according to the physical characteristics of the soil layer of the construction land;
2) the concrete adopts compact sandstone materials, the cement adopted by post-grouting is PC32.5 ordinary portland cement, and the water cement ratio is 1: 2;
3) selecting reinforcing steel bars and welding rods, wherein the reinforcing steel bars are selected from phi-HPB 300, phi-HRB 335 and phi-HRB 400 grades; wherein: e43 type welding rods are adopted for the HPB300 steel bars, and E50 type welding rods are adopted for the HRB335 steel bars and the HRB400 steel bars;
the construction method comprises the following specific steps:
A. forming holes
1) Positioning and lofting: measuring and placing an axis by using a total station by adopting a wire guiding method to position a pile, drilling a hole on the measured pile position by using a steel bar, inserting a short steel bar as a mark, and curing the periphery by using concrete for 300 m;
2) manufacturing and sinking a protective cylinder: the welding seam is adopted, the inner diameter of the steel casing is 100mm larger than the pile diameter, the wall thickness is 4mm, and the height is 1.5 m; embedding the steel pile casing vertically, allowing the steel pile casing to enter undisturbed soil for 300mm, filling clay around the steel pile casing, and ensuring that the error between the center of the steel pile casing and the center of a pile hole is less than or equal to 20 mm;
3) preparing slurry: adopting high-plasticity clay or bentonite as the rotary-drilled slurry, and making slurry by using a stirrer;
4) positioning a drilling machine: the error of the drill bit aiming at the center of the pile is controlled within 50mm, the verticality of the drill rod is controlled within 0.3 percent, and the plane error and the verticality of the pile hole are ensured;
5) drilling to form a hole:
a. measuring the diameter of a drill bit, the total length of a drilling tool, the drilling hole depth and the exposed length of a drill rod;
b. during drilling, a vertical control instrument is observed to ensure the verticality of a drilled hole, the drilling is not interrupted and stopped without any reason during the hole forming, the drilling speed is paid attention to before the final hole to prevent hole collapse, the pile body is positioned below the underground water level, slurry is required to be used, the liquid level of the slurry in the hole is ensured to be not lower than the natural ground in the drilling process, for a soil layer of the hole easy to collapse, a low-speed footage is adopted, when the distance from the soil layer is 1 ~ 0.5.5 m, the footage speed is controlled to be 0.2 ~ 0.5.5 m/h, and the drilling in a decompression state is ensured;
c. cleaning the hole by using a hole cleaning drill after the hole is drilled to reach the preset depth;
b. Manufacturing, transporting and placing of reinforcement cage
1) Manufacturing a steel reinforcement cage:
a. main reinforcement: the main ribs are welded by flash welding;
b. and (3) processing the stiffening hoops and the reinforcement cage framework: winding the reinforcing steel bars into stiffening hoops with the inner diameter of a specified size by using a die, wherein the spacing of the stiffening hoops is 2m, the hooping parts are lapped and welded together by adopting a single surface, and the width of a welding seam is 0.7 d;
c. coiling and welding the centralizer: before winding, straightening the disc, winding the disc into a disc with the diameter corresponding to that of the reinforcement cage by using a mold, and winding the disc on the manufactured reinforcement cage framework according to requirements;
d. and (3) mounting a rear grouting pipe: the rear grouting pipe is a seamless steel pipe with the size of 1 inch, and is connected with the steel reinforcement cage by adopting a pipe hoop or a coupling;
B. and (3) transporting and placing the reinforcement cage:
the steel reinforcement cage is transported by a cage transporting vehicle, and cedar poles are bound in the steel reinforcement cage, so that the steel reinforcement cage is prevented from deforming in the transportation process; before the steel reinforcement cage is placed, the elevation of the steel tapping protecting cylinder is measured by a level gauge, and the length of a hanging rib or a pressing rod is calculated; when the steel reinforcement cage is placed, the steel reinforcement cage does not touch the wall of the hole and keeps vertical centering, and the cross arm of the hanging bar or the pressure lever is placed on the sleeper and cannot be pressed on the protective cylinder; calculating the ground elevation according to the same elevation, fixing the pressure rod on the orifice cross arm after the reinforcement cage is put down in place, and preventing the reinforcement cage from floating upwards or moving downwards during pouring;
C. down-placing guide pipe and secondary hole cleaning
a. Adopting phi 219 guide pipes which are connected by screw threads or flange plates and sealed by rubber rings or rubber plates; the guide pipe is placed in the middle of the lower inlet hole, and the cleaned screw thread is fastened when the guide pipe is connected;
b. after the guide pipe is placed into the hole, secondary hole cleaning is carried out, and the slurry performance is kept during hole cleaning; removing sediments at the bottom of the hole, and simultaneously avoiding reducing the silty clay; the density of the mud returned by secondary hole cleaning is less than or equal to 1.15, and the sediment at the bottom of the hole is less than or equal to 100 mm;
D. pouring of concrete
a. During primary concrete pouring, the lower end of the guide pipe is 0.3 ~ 0.5.5 m away from the bottom of the hole, a waterproof bolt is added before pouring, the depth of the bottom of the guide pipe embedded in the concrete after primary pouring is ensured to be 2m ~ 5m, the slump of the primary poured concrete is 140-160 mm, and the slump of the concrete is 160-220 mm at other times;
b. during pouring, the concrete in the pipe is observed to descend and the water return condition of the orifice is observed, the ascending height of the concrete surface in the hole is measured in time, and the upper guide pipe is lifted and dismantled in sections in time; the guide pipe is embedded in the concrete, and the depth of the guide pipe is 2-6 m; when the pile top is poured, measuring the elevation of the pile top, wherein the elevation of the pile top of the poured pile is more than or equal to 0.8m, and slowly moving the guide pipe up and down after the concrete surface reaches the elevation of the over-poured length to slowly close the opening of the concrete surface;
E. post grouting construction
1) And (3) processing and mounting a rear grouting pipe:
a. the bottom grouting pipe is a 1 'seamless steel pipe, the bottom nozzle is processed into a ring shape by a plastic pipe with the pipe diameter of 1.2', and the nozzle is arranged at the bottom; the grouting pipe and the reinforcement cage are fixed by welding or binding; the upper part of the grouting pipe is 0.3m higher than the ground, and the pipe orifice is sealed by a protective cap;
b. the annular pipe of the side grouting pipe nozzle is a plastic pipe with the pipe diameter of 1.2 ″, the annular pipe is arranged 15.0m away from the pile end, the flexible nozzle pipe is connected with the grouting pipe through a tee joint, and the grouting pipe is fixedly connected with the reinforcement cage in a welding or binding mode; the upper part of the grouting pipe is 0.3m higher than the ground, and the pipe orifice is sealed by a protective cap;
2) grouting: the grouting sequence adopts slow grouting, firstly grouting to the pile side, and then grouting to the pile bottom after the grout is initially set, wherein the time interval between the grouting to the pile side and the grouting to the pile bottom is not less than 2 hours; the grouting amount reaches 4/5 of a design value, the grouting pressure exceeds 3-4 MPa, and the grouting can be stopped after the grouting is stabilized for 3-10 minutes;
after drilling and forming holes, a drill bit is put out, the slurry with higher density is replaced by the slurry with lower relative density by a slurry replacement method, and the original water head height in the holes is kept during hole cleaning;
in the actual construction, also pay attention to:
1. the slurry is changed step by step during hole cleaning, the slurry change gradient is determined according to the geological conditions of the hole wall, and a large amount of clear water cannot be directly injected into the slurry, so that the drilling slag can rapidly sink to the bottom, and hole collapse can be caused to thicken the sediment at the bottom of the hole; the concrete pouring is to be continuously constructed, the speed is properly slowed down at the initial stage of the concrete pouring, and the speed can be properly accelerated later, so that the initial setting time of the first batch of concrete is not exceeded during the final pouring. If the concrete amount is large, the construction temperature is high, and the initial setting time of the concrete is short, a certain amount of retarder can be properly added, but the adding amount of the retarder needs to be determined through strict tests.
2. For a soil layer with easy hole collapse, when the distance between the soil layer and the soil layer is 1-0.5 m, controlling the footage speed to be 0.5m/h, ensuring drilling in a decompression state, observing the change condition of the position of slurry in the casing, and immediately supplementing slurry if slurry leakage occurs, and ensuring the water head pressure difference of the slurry; entering an easily collapsed layer, stopping drilling for 4-8 hours regardless of the slurry leakage phenomenon, and circulating the slurry continuously during the drilling stopping period to ensure that the slurry fully seeps into the well wall and fully protects the wall, thereby avoiding slurry leakage and hole collapse; and (4) adopting low-speed footage on the easily collapsed layer, controlling the speed to be 0.2-0.5 m/h, and ensuring the drilling in a decompression state. The footage is too fast, the mud wall protection time is insufficient, and the mud leakage and hole collapse are easily caused; and controlling the index of the used mud according to different stratums. When backfilling, soft layer and sand layer are drilled, the speed is strictly controlled. When the underground water level is too high, the protective cylinder should be lifted, and the water head is increased. When underground obstacles are treated, residual stones and concrete blocks must be thoroughly removed; when the hole wall is seriously collapsed, the collapse position is required to be detected, sand and clay are mixed and backfilled to the position 1-2 m above the collapse hole section, and the hole is drilled again after tamping.
3. The drill bit with the diameter protection device is selected, the diameter of the drill bit meets the requirement of the diameter of a formed hole, the drill bit is required to be frequently checked and timely repaired, the viscosity of slurry can be properly improved when the hole section easy to reduce is drilled, and the hole diameter can be enlarged by adopting a method of repeatedly sweeping the hole up and down on the part easy to reduce.
4. When the hole is formed, the density of the slurry and the sediment at the bottom of the hole are strictly controlled, and the mud blocks must be thoroughly removed when the hole is cleaned for the first time. The lifting of the guide pipe needs to be slow in the concrete pouring process, particularly when the guide pipe reaches the pile top, the guide pipe is strictly forbidden to be lifted greatly, the buried depth of the guide pipe is strictly controlled, and the material is strictly forbidden to be broken midway when single pile concrete is poured; when the guide pipe is pulled out, the buried depth of the concrete after the guide pipe is pulled out must be accurately calculated and controlled, and the pipe is strictly pulled out by experience.

Claims (2)

1. A post-grouting cast-in-situ bored pile construction method is characterized by comprising the following steps:
construction preparation:
1) selecting proper mechanical equipment such as a drilling machine, a drill bit, a protective arm sleeve and the like according to the physical characteristics of the soil layer of the construction land;
2) the concrete adopts compact sandstone materials, the cement adopted by post-grouting is PC32.5 ordinary portland cement, and the water cement ratio is 1: 2;
3) selecting reinforcing steel bars and welding rods, wherein the reinforcing steel bars are selected from phi-HPB 300, phi-HRB 335 and phi-HRB 400 grades; wherein: e43 type welding rods are adopted for the HPB300 steel bars, and E50 type welding rods are adopted for the HRB335 steel bars and the HRB400 steel bars;
the construction method comprises the following specific steps:
A. forming holes
1) Positioning: measuring and placing an axis by using a total station by adopting a wire guiding method to position a pile, drilling a hole on the measured pile position by using a steel bar, inserting a short steel bar as a mark, and curing the periphery by using concrete for 300 m;
2) manufacturing and sinking a protective cylinder: the welding seam is adopted, the inner diameter of the steel casing is 100mm larger than the pile diameter, the wall thickness is 4mm, and the height is 1.5 m; embedding the steel pile casing vertically, allowing the steel pile casing to enter undisturbed soil for 300mm, filling clay around the steel pile casing, and ensuring that the error between the center of the steel pile casing and the center of a pile hole is less than or equal to 20 mm;
3) preparing slurry: adopting high-plasticity clay or bentonite as the rotary-drilled slurry, and making slurry by using a stirrer;
4) positioning a drilling machine: the error of the drill bit aiming at the center of the pile is controlled within 50mm, the verticality of the drill rod is controlled within 0.3 percent, and the plane error and the verticality of the pile hole are ensured;
5) drilling to form a hole:
a. measuring the diameter of a drill bit, the total length of a drilling tool, the drilling hole depth and the exposed length of a drill rod;
b. during drilling, a vertical control instrument is observed to ensure the verticality of a drilled hole, the drilling is not interrupted and stopped without any reason during the hole forming, the drilling speed is paid attention to before the final hole to prevent hole collapse, the pile body is positioned below the underground water level, slurry is required to be used, the liquid level of the slurry in the hole is ensured to be not lower than the natural ground in the drilling process, for a soil layer of the hole easy to collapse, a low-speed footage is adopted, when the distance from the soil layer is 1 ~ 0.5.5 m, the footage speed is controlled to be 0.2 ~ 0.5.5 m/h, and the drilling in a decompression state is ensured;
c. cleaning the hole by using a hole cleaning drill after the hole is drilled to reach the preset depth;
b. Manufacturing, transporting and placing of reinforcement cage
1) Manufacturing a steel reinforcement cage:
a. main reinforcement: the main ribs are welded by flash welding;
b. and (3) processing the stiffening hoops and the reinforcement cage framework: winding the reinforcing steel bars into stiffening hoops with the inner diameter of a specified size by using a die, wherein the spacing of the stiffening hoops is 2m, the hooping parts are lapped and welded together by adopting a single surface, and the width of a welding seam is 0.7 d;
c. coiling and welding the centralizer: before winding, straightening the disc, winding the disc into a disc with the diameter corresponding to that of the reinforcement cage by using a mold, and winding the disc on the manufactured reinforcement cage framework according to requirements;
d. and (3) mounting a rear grouting pipe: the rear grouting pipe is a seamless steel pipe with the size of 1 inch, and is connected with the steel reinforcement cage by adopting a pipe hoop or a coupling;
B. and (3) transporting and placing the reinforcement cage:
the steel reinforcement cage is transported by a cage transporting vehicle, and cedar poles are bound in the steel reinforcement cage, so that the steel reinforcement cage is prevented from deforming in the transportation process; before the steel reinforcement cage is placed, the elevation of the steel tapping protecting cylinder is measured by a level gauge, and the length of a hanging rib or a pressing rod is calculated; when the steel reinforcement cage is placed, the steel reinforcement cage does not touch the wall of the hole and keeps vertical centering, and the cross arm of the hanging bar or the pressure lever is placed on the sleeper and cannot be pressed on the protective cylinder; calculating the ground elevation according to the same elevation, fixing the pressure rod on the orifice cross arm after the reinforcement cage is put down in place, and preventing the reinforcement cage from floating upwards or moving downwards during pouring;
C. down-placing guide pipe and secondary hole cleaning
a. Adopting phi 219 guide pipes which are connected by screw threads or flange plates and sealed by rubber rings or rubber plates; the guide pipe is placed in the middle of the lower inlet hole, and the cleaned screw thread is fastened when the guide pipe is connected;
b. after the guide pipe is placed into the hole, secondary hole cleaning is carried out, and the slurry performance is kept during hole cleaning; removing sediments at the bottom of the hole, and simultaneously avoiding reducing the silty clay; the density of the mud returned by secondary hole cleaning is less than or equal to 1.15, and the sediment at the bottom of the hole is less than or equal to 100 mm;
D. pouring of concrete
a. During primary concrete pouring, the lower end of the guide pipe is 0.3 ~ 0.5.5 m away from the bottom of the hole, a waterproof bolt is added before pouring, the depth of the bottom of the guide pipe embedded in the concrete after primary pouring is ensured to be 2m ~ 5m, the slump of the primary poured concrete is 140-160 mm, and the slump of the concrete is 160-220 mm at other times;
b. during pouring, the concrete in the pipe is observed to descend and the water return condition of the orifice is observed, the ascending height of the concrete surface in the hole is measured in time, and the upper guide pipe is lifted and dismantled in sections in time; the guide pipe is embedded in the concrete, and the depth of the guide pipe is 2-6 m; when the pile top is poured, measuring the elevation of the pile top, wherein the elevation of the pile top of the poured pile is more than or equal to 0.8m, and slowly moving the guide pipe up and down after the concrete surface reaches the elevation of the over-poured length to slowly close the opening of the concrete surface;
E. post grouting construction
1) And (3) processing and mounting a rear grouting pipe:
a. the bottom grouting pipe is a 1 'seamless steel pipe, the bottom nozzle is processed into a ring shape by a plastic pipe with the pipe diameter of 1.2', and the nozzle is arranged at the bottom; the grouting pipe and the reinforcement cage are fixed by welding or binding; the upper part of the grouting pipe is 0.3m higher than the ground, and the pipe orifice is sealed by a protective cap;
b. the annular pipe of the side grouting pipe nozzle is a plastic pipe with the pipe diameter of 1.2 ″, the annular pipe is arranged 15.0m away from the pile end, the flexible nozzle pipe is connected with the grouting pipe through a tee joint, and the grouting pipe is fixedly connected with the reinforcement cage in a welding or binding mode; the upper part of the grouting pipe is 0.3m higher than the ground, and the pipe orifice is sealed by a protective cap;
2) grouting: the grouting sequence adopts slow grouting, firstly grouting to the pile side, and then grouting to the pile bottom after the grout is initially set, wherein the time interval between the grouting to the pile side and the grouting to the pile bottom is not less than 2 hours; and (4) when the grouting amount reaches 4/5 of a design value, the grouting pressure exceeds 3-4 MPa, and the grouting can be stopped after the grouting amount is stabilized for 3-10 minutes.
2. The method for constructing a post-grouting bored pile according to claim 1, wherein: after drilling to form a hole, the drill bit is lifted out, the slurry with higher density is replaced by the slurry with lower relative density by a slurry replacement method, and the original water head height in the hole is kept during hole cleaning.
CN201910969613.9A 2019-10-12 2019-10-12 Post-grouting cast-in-situ bored pile construction method Pending CN110616707A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910969613.9A CN110616707A (en) 2019-10-12 2019-10-12 Post-grouting cast-in-situ bored pile construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910969613.9A CN110616707A (en) 2019-10-12 2019-10-12 Post-grouting cast-in-situ bored pile construction method

Publications (1)

Publication Number Publication Date
CN110616707A true CN110616707A (en) 2019-12-27

Family

ID=68925441

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910969613.9A Pending CN110616707A (en) 2019-10-12 2019-10-12 Post-grouting cast-in-situ bored pile construction method

Country Status (1)

Country Link
CN (1) CN110616707A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110985071A (en) * 2019-12-31 2020-04-10 四川交投建设工程股份有限公司 Active highway tunnel disease comprehensive treatment structure and construction method
CN114108639A (en) * 2021-11-17 2022-03-01 上海市机械施工集团有限公司 Construction method for foundation pit bottom sealing
CN115288118A (en) * 2022-08-08 2022-11-04 中铁三局集团有限公司 Construction method of large-diameter steel-concrete combined pile in high seismic intensity area
CN116145650A (en) * 2023-02-01 2023-05-23 广东省水利水电第三工程局有限公司 Cast-in-place pile construction technology

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101069815B1 (en) * 2008-12-31 2011-10-04 대림산업 주식회사 Post grouting system of Cast-in-place concrete piles and the post grouting method for increasing end bearing capacity at pile base
CN104846810A (en) * 2015-05-19 2015-08-19 常州第一建筑集团有限公司 Self-circulating posterior grouting bored pile construction method
CN105239563A (en) * 2015-10-27 2016-01-13 贵州开磷建设集团有限公司 Dry-method hole forming filling pile structure for post-grouting matched rotary drilling rig and construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101069815B1 (en) * 2008-12-31 2011-10-04 대림산업 주식회사 Post grouting system of Cast-in-place concrete piles and the post grouting method for increasing end bearing capacity at pile base
CN104846810A (en) * 2015-05-19 2015-08-19 常州第一建筑集团有限公司 Self-circulating posterior grouting bored pile construction method
CN105239563A (en) * 2015-10-27 2016-01-13 贵州开磷建设集团有限公司 Dry-method hole forming filling pile structure for post-grouting matched rotary drilling rig and construction method

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
刘纯洁等: "《城市轨道交通工程建设单位现场管理操作手册》", 30 April 2017 *
周占磊等: "后注浆灌注桩在孟加拉某电厂工程中的应用", 《电力勘测设计》 *
张琨等: "中国尊大厦超深基坑后注浆钻孔灌注桩施工技术", 《施工技术》 *
汤海潮等: "浅谈"后注浆"钻孔灌注桩施工现场监理控制要点", 《建设监理》 *
王伯慧等: "《中国钻孔灌注桩新发展》", 31 August 1999, 人民交通出版社 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110985071A (en) * 2019-12-31 2020-04-10 四川交投建设工程股份有限公司 Active highway tunnel disease comprehensive treatment structure and construction method
CN110985071B (en) * 2019-12-31 2021-02-09 四川交投建设工程股份有限公司 Active highway tunnel disease comprehensive treatment structure and construction method
CN114108639A (en) * 2021-11-17 2022-03-01 上海市机械施工集团有限公司 Construction method for foundation pit bottom sealing
CN114108639B (en) * 2021-11-17 2023-06-20 上海市机械施工集团有限公司 Construction method for foundation pit bottom sealing
CN115288118A (en) * 2022-08-08 2022-11-04 中铁三局集团有限公司 Construction method of large-diameter steel-concrete combined pile in high seismic intensity area
CN116145650A (en) * 2023-02-01 2023-05-23 广东省水利水电第三工程局有限公司 Cast-in-place pile construction technology

Similar Documents

Publication Publication Date Title
CN110230309B (en) Karst area bridge karst cave pile foundation construction method
AU2020103672A4 (en) Construction method of rotary drilling hole-forming and jet mixing cement-soil occlusion curtain piles
CN110616707A (en) Post-grouting cast-in-situ bored pile construction method
CN108442382B (en) In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
CN108894214B (en) Karst cave geological environment cast-in-place pile and pile-forming construction method thereof
WO2021082767A1 (en) Method for constructing reinforced fiber and metakaolin-based pressurized cast-in-place pile
CN102286984A (en) Water-stop curtain and construction method thereof
CN112502139A (en) Construction method for excavation of deep pit by three-axis stirring pile curtain water stop and rotary digging cast-in-place pile support
CN112323777A (en) Hollow precast pile for rock embedding and rock embedding construction method using precast pile
CN111535307B (en) Hole forming construction method for rotary drilling cast-in-place pile in reef limestone stratum
CN107587502B (en) Construction method for rotary drilling hole-forming pressure-grouting cement soil occlusion curtain pile
CN112609690A (en) Construction method of rotary drilling cast-in-place pile in sea-filling geological complex area
CN112282767A (en) Ultra-deep reinforcement construction method for shield end soil body under water-rich silty-fine sand geology
CN110777775A (en) Foundation pit structure and construction method thereof
CN113006109B (en) Construction method of waterproof curtain of foundation pit of highly permeable stratum area
CN107653889B (en) Construction method of section steel pressure-grouting cement soil curtain support pile
CN117107749A (en) Construction method of large-diameter punched bored pile under influence of sea water seepage in sea-filling land-building area
CN111456021A (en) Construction method for reversely making enclosure structure by utilizing RJP piles
CN111535305A (en) Construction method of cast-in-situ bored pile for air well
CN113685190B (en) Reinforcing system for shield to penetrate shallow soft clay and construction method
CN115584722A (en) Construction method of secant pile in water-rich rock-filling layer-containing soft soil area
CN110714459A (en) Construction method of cast-in-situ bored pile
CN108035357A (en) Filling pile construction scheme and its funnel
CN114635450A (en) Construction method for permanent steel pipe structural column of covered and excavated station
CN113914304A (en) CFG pile long spiral drill hole core pipe pumping mixture pouring pile-forming construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191227