CN110616602B - Sedimentation control device and method for construction of pipe jacking and downward passing existing operation railway - Google Patents
Sedimentation control device and method for construction of pipe jacking and downward passing existing operation railway Download PDFInfo
- Publication number
- CN110616602B CN110616602B CN201910877480.2A CN201910877480A CN110616602B CN 110616602 B CN110616602 B CN 110616602B CN 201910877480 A CN201910877480 A CN 201910877480A CN 110616602 B CN110616602 B CN 110616602B
- Authority
- CN
- China
- Prior art keywords
- screen
- settlement
- control unit
- laser
- sleeper
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2/00—General structure of permanent way
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B35/00—Applications of measuring apparatus or devices for track-building purposes
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2204/00—Characteristics of the track and its foundations
- E01B2204/06—Height or lateral adjustment means or positioning means for slabs, sleepers or rails
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Machines For Laying And Maintaining Railways (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
The invention discloses a settlement control device and a settlement control method for construction of a pipe jacking downwards through an existing operation railway, wherein a settlement measuring unit is arranged on a sleeper, a laser pen is used for positioning on a screen scale, when the sleeper sinks or bulges, the screen scale on the corresponding position can rise or fall, so that the irradiation position of the laser pen is changed, and the screen scale sends change data to a control unit to collect the deformation of the sleeper; the invention can pass the construction condition of the existing railway under the jacking pipe, ensure the flatness of the track, and avoid the influence on vehicles on the track caused by the settlement or the uplift of the surface during construction.
Description
Technical Field
The invention belongs to the field of pipe jacking construction, and particularly relates to a settlement control device and method for construction of pipe jacking downward-penetrating existing operation railways.
Background
In recent years, the traffic infrastructure has not been developed before, more and more railways, highways, subways and pipe culverts are put into construction, so that the situation that the existing construction runs down or strides over the existing building is inevitable in the construction of many projects, and the situation that the existing operation railway runs down through the top pipe is a typical form.
The push pipe is worn existing operation railway down and is often caused adverse effect, if cause existing operation railway track subside too big, threaten operation safety, the existence of top traffic load also causes adverse effect to the construction of below push pipe in addition, increases the construction degree of difficulty, seriously slows down the construction progress. At present, some auxiliary construction measures are developed for the pipe jacking to pass through the existing operation railway, such as reducing the train operation frequency, reducing the train operation speed, reinforcing the soil body below the railway through grouting, and the like, and the existing measures have certain effects but also have inherent defects, such as influence on the train operation plan and even train delay caused by reducing the train operation frequency or the train operation speed; the soil body is reinforced by grouting, grouting pressure control is poor, so that the grouting effect is poor or the grouting pressure is too high to cause track uplift, and certain threat is brought to driving. With more and more infrastructure facilities, the condition that the jacking pipe downwards passes through the existing railway is more and more, and at present, a better settlement control method for the jacking pipe downwards passing through the existing operating railway does not exist.
Disclosure of Invention
The invention aims to overcome the defects and provides a settlement control device and a settlement control method for construction of a pipe jacking downward-penetrating existing operation railway, which can ensure smooth upper railway tracks in the pipe jacking construction process and ensure the operation safety of a train.
In order to achieve the aim, the settlement control device for construction of the existing operation railway with the jacking pipe passing downwards comprises a settlement measuring unit and a settlement control unit;
the settlement measuring unit comprises a base point, a plurality of laser pens and a plurality of screen scales, wherein the base point is fixed on the ground which is not affected by construction settlement, all the screen scales are distributed on the sleeper, all the laser pens are fixed on the base point, and the laser pens point to the corresponding screen scales;
the settlement control unit comprises a plurality of air bags arranged in a soil body below the sleeper, the air bags are connected with corresponding air charging devices, all the air charging devices are connected with the control unit, and the control unit is connected with all the screen scales;
the screen scale is used for acquiring the position information of the laser pen pointing to the screen scale and sending the position information to the control unit;
the control unit is used for controlling the corresponding inflating device to inflate or deflate according to the position information sent by the screen scale, so that the screen scale is always at a zero point.
The base point is connected with all the laser pens through the supporting rod.
The heights of all the screen scales are different, and the heights of the laser pens corresponding to all the screen scales are adjusted through the vertical rods.
The number of the air bags is the same as that of the screen scales, and each air bag is arranged below the corresponding screen scale.
Each air bag is connected with a pressure gauge, and the working condition of the air bag is judged through the pressure gauge.
The air bag is made of high-strength rubber materials, and the requirement of bearing capacity transmitted from the upper part is met.
A method for arranging a settlement control device for construction of a jacking pipe downwards penetrating through an existing operation railway comprises the following steps:
selecting a base point on the ground which is not influenced by settlement, and installing a laser pen on the base point;
step two, vertically installing a vertical rod on the sleeper, and installing a screen scale on the top of the vertical rod;
adjusting the laser pens and the screen scales to enable each laser pen to correspond to one screen scale, and connecting the screen scales with the control unit;
excavating a soil body below the sleeper, placing a plurality of independent air bags in the soil body, connecting the air charging devices of all the air bags with the control unit, and backfilling the soil body below the sleeper;
and step five, inflating the air bag in advance to keep the track straight, and adjusting each screen scale to enable the laser emitted by the laser pen to point to a zero point.
In the first step, a support rod is arranged on the base and extends to one side of the track, and all the laser pens are longitudinally fixed at the end part of the support rod.
And in the second step, a cross rod is arranged at the top of the vertical rod, the cross rod is far away from the track, the traveling crane is not influenced, and the screen scale is arranged at the end part of the cross rod.
Compared with the prior art, the settlement measuring unit is arranged on the sleeper, the laser pen is used for positioning on the screen scale, when the sleeper collapses or bulges, the screen scale on the corresponding position can ascend or descend, so that the irradiation position of the laser pen is changed, the screen scale sends the change data to the control unit, and the deformation of the sleeper is collected; the invention can pass the construction condition of the existing railway under the jacking pipe, ensure the flatness of the track, and avoid the influence on vehicles on the track caused by the settlement or the uplift of the surface during construction.
The laying method of the invention firstly lays the settlement measuring units, then lays the settlement control units, and finally carries out zero alignment on the settlement measuring units when the settlement control units support the sleepers, thus finishing the laying. The laying method is simple, the construction efficiency is high, the laying method can be quickly laid in a construction area, the influence on vehicles on the track is small, and the influence of ground settlement caused by pipe jacking construction on train operation can be prevented through the laying of the settlement control unit.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a side schematic view of the present invention;
wherein, 1, a base point; 2. a support bar; 3. a laser pen; 4. a screen scale; 5. an air bag; 6. a track; 7. a sleeper.
Detailed Description
The invention will be further explained with reference to the drawings.
Referring to fig. 1 and 2, a settlement control device for construction of a pipe jacking under an existing operating railway comprises a settlement measuring unit and a settlement control unit;
the settlement measuring unit comprises a base point 1, a plurality of laser pens 3 and a plurality of screen scales 4, wherein the base point 1 is fixed on the ground which is not affected by settlement, all the screen scales 4 are distributed on a sleeper 7, all the laser pens 3 are fixed on the base point 1, the base point 1 is connected with all the laser pens 3 through a support rod 2, the laser pens 3 point to the corresponding screen scales 4, the heights of the screen scales 4 are different, and the heights of the laser pens corresponding to the screen scales 4 are adjusted through vertical rods;
the settlement control unit comprises a plurality of air bags 5 arranged in the soil below the sleeper 7, the number of the air bags 5 is the same as that of the screen scales 4, each air bag 5 is arranged below the corresponding screen scale 4, the air bags 5 are connected with corresponding air charging devices, the air bags 5 are connected with pressure gauges, all the air charging devices are connected with a control unit, and the control unit is connected with all the screen scales 4;
the screen scale 4 is used for acquiring the position information of the laser pen 3 pointing to the screen scale 4 and sending the position information to the control unit;
the control unit is used for controlling the corresponding inflating device to perform inflation or deflation work according to the position information sent by the screen scale 4.
A method for arranging a settlement control device for construction of a jacking pipe downwards penetrating through an existing operation railway comprises the following steps:
firstly, selecting a base point 1 on the ground which is not affected by settlement, installing a support rod 2 on the base 1, extending the support rod 2 to one side of a track 6, and longitudinally fixing all laser pens 3 at the end part 2 of the support rod 2;
step two, vertically installing vertical rods on the sleepers 7, installing cross rods on the tops of the vertical rods, enabling the cross rods to be far away from the tracks 6, not affecting traveling, and installing the screen scales 4 at the end parts of the cross rods;
adjusting the laser pens 3 and the screen scales 4 to enable each laser pen 3 to correspond to one screen scale 4, and connecting the screen scales 4 with the control unit;
excavating a soil body below the sleeper 7, placing a plurality of independent air bags 5 in the soil body, connecting the air charging devices of all the air bags 5 with a control unit, and backfilling the soil body below the sleeper 7;
and step five, pre-inflating the air bag 5 to keep the track 6 straight, and adjusting each screen scale 4 to enable the laser emitted by the laser pen 3 to point to a zero point.
When the ground below the sleeper 7 is sent to subside or rise, the sleeper 7 on the corresponding position drives the screen scale 4 to move downwards or upwards, and the laser pen 3 is fixed on the base point 1, so the position of the laser pen 3 irradiated on the screen scale 4 can generate corresponding change, the screen display 4 acquires the change of the irradiation position of the laser pen 3 and sends the changed position to the control unit, the control unit judges the sleeper 7 corresponding to the changed position and the air bag 5 corresponding to the sleeper 7 according to the received information, and controls the inflating device to inflate or exhaust the air bag 5, so that the sleeper 7 on the corresponding position is restored to the initial position.
Claims (4)
1. A settlement control device for construction of a pipe jacking downward-penetrating existing operation railway is characterized by comprising a settlement measuring unit and a settlement control unit;
the settlement measuring unit comprises a base point (1), a plurality of laser pens (3) and a plurality of screen scales (4), the base point (1) is fixed on the ground which is not affected by settlement, vertical rods are vertically arranged on the sleepers (7), the height of each screen scale (4) is different, the height of each screen scale (4) is adjusted through the vertical rods corresponding to the laser pens, the screen ruler is characterized in that a cross rod is installed at the top of a vertical rod, the cross rod is far away from a track (6), the screen ruler (4) is installed at the end of the cross rod, all the screen ruler (4) are distributed on a sleeper (7), all laser pens (3) are fixed on a base point (1), the laser pens (3) point to the corresponding screen ruler (4), a support rod (2) is installed on a base (1), the base point (1) is connected with all the laser pens (3) through the support rod (2), the support rod (2) extends to one side of the track (6), and all the laser pens (3) are longitudinally fixed at the end (2) of the support rod (2);
the settlement control unit comprises a plurality of air bags (5) arranged in the soil body below the sleeper (7), the air bags (5) are connected with corresponding air charging devices, all the air charging devices are connected with the control unit, and the control unit is connected with all the screen scales (4);
the screen scale (4) is used for collecting the position information of the laser pen (3) pointing to the screen scale (4) and sending the position information to the control unit;
the control unit is used for controlling the corresponding inflating device to perform inflation or deflation work according to the position information sent by the screen scale (4);
the number of the air bags (5) is the same as that of the screen scales (4), and each air bag (5) is arranged below the corresponding screen scale (4);
the air bag (5) is connected with a pressure gauge.
2. The method for arranging the settlement control device for construction of jacking pipe downwards passing through the existing operation railway as claimed in claim 1, which is characterized by comprising the following steps:
step one, selecting a base point (1) on the ground which is not affected by settlement, and installing a laser pen (2) on the base point (1);
step two, vertically installing a vertical rod on the sleeper (7), and installing a screen scale (4) on the top of the vertical rod;
adjusting the laser pens (3) and the screen scales (4) to enable each laser pen (3) to correspond to one screen scale (4), and connecting the screen scales (4) with the control unit;
fourthly, excavating the soil body below the sleeper (7), placing a plurality of independent air bags (5) in the soil body, connecting the air charging devices of all the air bags (5) with the control unit, and backfilling the soil body below the sleeper (7);
and fifthly, inflating the air bag (5) in advance to keep the track (6) straight, and adjusting each screen scale (4) to enable the laser emitted by the laser pen (3) to point to a zero point.
3. The method for arranging the settlement control device for pipe jacking under the existing operating railway construction as claimed in claim 2, wherein in the first step, the support rod (2) is installed on the base (1), the support rod (2) extends to one side of the track (6), and all the laser pens (3) are longitudinally fixed at the end part of the support rod (2).
4. The method for arranging the settlement control devices for pipe jacking and downward passing existing operating railway construction as claimed in claim 3, wherein in the second step, the cross bar is arranged at the top of the vertical bar, the cross bar is far away from the track (6) and does not affect the traveling, and the screen scale (4) is arranged at the end part of the cross bar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910877480.2A CN110616602B (en) | 2019-09-17 | 2019-09-17 | Sedimentation control device and method for construction of pipe jacking and downward passing existing operation railway |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910877480.2A CN110616602B (en) | 2019-09-17 | 2019-09-17 | Sedimentation control device and method for construction of pipe jacking and downward passing existing operation railway |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110616602A CN110616602A (en) | 2019-12-27 |
CN110616602B true CN110616602B (en) | 2021-09-28 |
Family
ID=68923492
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910877480.2A Active CN110616602B (en) | 2019-09-17 | 2019-09-17 | Sedimentation control device and method for construction of pipe jacking and downward passing existing operation railway |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110616602B (en) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2354930A1 (en) * | 1973-11-02 | 1975-05-22 | Holzmann Philipp Ag | Tunnel in ground subject to mining subsidence - has relatively moving reinforced concrete sections and plastic enclosure |
CH701566A1 (en) * | 2010-02-08 | 2011-01-14 | Prof Dr Kalman Kovari | Method for early recognition of building-site subsidence during construction of underground railways in urban area, involves transferring produced and previously evaluated measured values to persons working in working face area |
CN102146648A (en) * | 2011-03-14 | 2011-08-10 | 西南交通大学 | High-speed railway structure settlement monitoring device and monitoring method |
CN102635040A (en) * | 2012-04-23 | 2012-08-15 | 中铁三局集团有限公司 | Method for reducing track construction settlement during construction of undercrossing existing railway |
CN106049193A (en) * | 2016-05-17 | 2016-10-26 | 中国铁道科学研究院铁道建筑研究所 | Center line deviation rectifying method for ballastless track of high-speed railway of roadbed segment |
CN106702834A (en) * | 2016-12-28 | 2017-05-24 | 中国铁道科学研究院铁道建筑研究所 | Midline deviation rectifying method for sedimentary offset ballastless track |
CN107964843A (en) * | 2017-12-06 | 2018-04-27 | 中铁二院工程集团有限责任公司 | A kind of high-speed railway Karst Subgrade construction and its restorative procedure for having warning function |
CN108385452A (en) * | 2018-04-19 | 2018-08-10 | 山东建筑大学 | A kind of raising adjustment mechanism, system and method for administering subgrade settlement |
CN109973099A (en) * | 2019-04-08 | 2019-07-05 | 华东交通大学 | A kind of monitoring method of bridge-type shield rail vertical displacement amount |
Family Cites Families (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2767562B2 (en) * | 1995-03-07 | 1998-06-18 | 東京フアブリック工業株式会社 | Height adjustment support method of rail anti-vibration sleepers |
JP3909294B2 (en) * | 2003-01-31 | 2007-04-25 | 株式会社エス・ジー・エス | Settlement measurement method |
AU2008229932B2 (en) * | 2008-06-03 | 2010-04-01 | Precision Alignment Holdings Pty Ltd | Laser Alignment Device for use with a Drill Rig |
KR101200917B1 (en) * | 2012-07-24 | 2012-11-13 | (주)대우건설 | Protector including measuring instrument |
CN105089698A (en) * | 2014-05-13 | 2015-11-25 | 中国铁道科学研究院城市轨道交通中心 | Settlement control method in process of enabling subway tunnel to penetrate through existing railway |
CN104912562B (en) * | 2015-06-30 | 2017-04-12 | 中铁一局集团有限公司 | Construction method for deformation control over existing operation tunnel crossing under shield |
CN105259942A (en) * | 2015-11-03 | 2016-01-20 | 中国矿业大学(北京) | Existing line settlement control system and method based on slip casting technology |
CN105547243B (en) * | 2015-12-16 | 2018-10-09 | 中国科学院半导体研究所 | The method that laser directly measures subgrade settlement |
CN105862874B (en) * | 2016-04-14 | 2017-09-19 | 浙江科技学院 | A kind of means of defence for controlling closing foundation ditch construction of structures to deform |
CN109425314A (en) * | 2017-09-02 | 2019-03-05 | 湖南北斗星空自动化科技有限公司 | A method of track plates angularity is detected using laser displacement range measurement principle |
CN107815935B (en) * | 2017-10-31 | 2020-04-10 | 广州铁路科技开发有限公司 | Real-time monitoring method and system for geometric state of high-speed railway track |
CN107780309A (en) * | 2017-11-21 | 2018-03-09 | 长安大学 | A kind of sedimentation applied to track eliminates system and method in real time |
KR20180134786A (en) * | 2018-11-25 | 2018-12-19 | 김준모 | The Construction Method of Underpinning under the Rock Conditions. |
-
2019
- 2019-09-17 CN CN201910877480.2A patent/CN110616602B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2354930A1 (en) * | 1973-11-02 | 1975-05-22 | Holzmann Philipp Ag | Tunnel in ground subject to mining subsidence - has relatively moving reinforced concrete sections and plastic enclosure |
CH701566A1 (en) * | 2010-02-08 | 2011-01-14 | Prof Dr Kalman Kovari | Method for early recognition of building-site subsidence during construction of underground railways in urban area, involves transferring produced and previously evaluated measured values to persons working in working face area |
CN102146648A (en) * | 2011-03-14 | 2011-08-10 | 西南交通大学 | High-speed railway structure settlement monitoring device and monitoring method |
CN102635040A (en) * | 2012-04-23 | 2012-08-15 | 中铁三局集团有限公司 | Method for reducing track construction settlement during construction of undercrossing existing railway |
CN106049193A (en) * | 2016-05-17 | 2016-10-26 | 中国铁道科学研究院铁道建筑研究所 | Center line deviation rectifying method for ballastless track of high-speed railway of roadbed segment |
CN106702834A (en) * | 2016-12-28 | 2017-05-24 | 中国铁道科学研究院铁道建筑研究所 | Midline deviation rectifying method for sedimentary offset ballastless track |
CN107964843A (en) * | 2017-12-06 | 2018-04-27 | 中铁二院工程集团有限责任公司 | A kind of high-speed railway Karst Subgrade construction and its restorative procedure for having warning function |
CN108385452A (en) * | 2018-04-19 | 2018-08-10 | 山东建筑大学 | A kind of raising adjustment mechanism, system and method for administering subgrade settlement |
CN109973099A (en) * | 2019-04-08 | 2019-07-05 | 华东交通大学 | A kind of monitoring method of bridge-type shield rail vertical displacement amount |
Also Published As
Publication number | Publication date |
---|---|
CN110616602A (en) | 2019-12-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106245529B (en) | Railway tee girder safely and fast falls beam method | |
CN110195382B (en) | Roadbed structure and method for lifting track structure by adopting same | |
CN106049193A (en) | Center line deviation rectifying method for ballastless track of high-speed railway of roadbed segment | |
CN106702834A (en) | Midline deviation rectifying method for sedimentary offset ballastless track | |
CN103757993A (en) | System and method for high-speed railway subgrade settlement restoration | |
CN109778611B (en) | Deviation rectifying method for ballastless track structure in railway tunnel | |
CN206886602U (en) | A kind of highway bridge construction drilling platform | |
CN102733317A (en) | Plane rotation construction technique for steel truss girder for existing bridge spanning construction | |
CN107059506A (en) | A kind of plate-type ballastless track track plates replacing options | |
CN109235292A (en) | Railroad bridge changes beam process and changes girder system system | |
CN106948228A (en) | A kind of plate-type ballastless track track plates fast replacement system and method | |
CN108387384A (en) | A kind of railway track and wheel hub high-frequency percussion loading simulator | |
CN110616602B (en) | Sedimentation control device and method for construction of pipe jacking and downward passing existing operation railway | |
CN205576749U (en) | Pontic roof beam structure promotes and rackwork | |
CN115711822A (en) | Impact test device capable of adjusting confining pressure and impact test method | |
CN106498976A (en) | A kind of inter-city passenger rail underpass of freeways open-cut group pushes up support and change method | |
CN112176793A (en) | Repairing method for ballastless track settlement | |
CN111236089A (en) | Uneven jacking system and uneven jacking construction method for existing bridge superstructure | |
CN109338831A (en) | A kind of non-fragment orbit method for correcting error based on rope saw cut | |
CN109355986A (en) | A kind of non-fragment orbit sedimentation regulation method based on rope saw cut | |
CN106192621A (en) | High-speed railway track plate lays precision high-speed adjustment device and method | |
CN211605992U (en) | Novel weak current support for rail transit | |
CN111576130A (en) | Road and bridge connection control system and construction method thereof | |
CN205711575U (en) | A kind of half span type for CRTS III plate-type non-fragment orbit repairs structure | |
CN206874289U (en) | Just lining construction hydraulic template trolley |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |