CN110593897A - Prefabricated hollow concrete segment and prefabricating method - Google Patents

Prefabricated hollow concrete segment and prefabricating method Download PDF

Info

Publication number
CN110593897A
CN110593897A CN201910917327.8A CN201910917327A CN110593897A CN 110593897 A CN110593897 A CN 110593897A CN 201910917327 A CN201910917327 A CN 201910917327A CN 110593897 A CN110593897 A CN 110593897A
Authority
CN
China
Prior art keywords
segment
concrete
fiber
steel
air bag
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910917327.8A
Other languages
Chinese (zh)
Inventor
谢东武
丁文其
张清照
赵程
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongji University
Original Assignee
Tongji University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongji University filed Critical Tongji University
Priority to CN201910917327.8A priority Critical patent/CN110593897A/en
Publication of CN110593897A publication Critical patent/CN110593897A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/52Producing shaped prefabricated articles from the material specially adapted for producing articles from mixtures containing fibres, e.g. asbestos cement
    • B28B1/523Producing shaped prefabricated articles from the material specially adapted for producing articles from mixtures containing fibres, e.g. asbestos cement containing metal fibres
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B21/00Methods or machines specially adapted for the production of tubular articles
    • B28B21/56Methods or machines specially adapted for the production of tubular articles incorporating reinforcements or inserts
    • B28B21/60Methods or machines specially adapted for the production of tubular articles incorporating reinforcements or inserts prestressed reinforcements
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/086Methods of making concrete lining segments

Abstract

The invention relates to a prefabricated hollow concrete segment and a prefabricating method, which are applied to underground engineering constructed by adopting a prefabricating and assembling method, wherein the segment comprises a segment framework, an air bag arranged in the segment framework and used for forming a hollow structure and a segment main body formed by pouring concrete in a layering way, wherein the air bag is arranged along the extension direction of the segment framework and is fixed by a hook on the segment framework.

Description

Prefabricated hollow concrete segment and prefabricating method
Technical Field
The invention relates to the technical field of civil engineering, in particular to a prefabricated hollow concrete segment and a prefabricating method.
Background
Based on the characteristics of good mechanical property and economical efficiency of reinforced (fiber) concrete materials, the tunnel with the prefabricated assembled duct pieces as a bearing structure comprises rail transit, a highway tunnel, a railway tunnel, a municipal pipeline and the like, and the most commonly used duct pieces are reinforced (fiber) concrete duct pieces. Adopt the rib plate formula structure different with the steel-pipe piece, steel (fibre) concrete section of jurisdiction generally is that the entity is whole to water to it is great to cause the section of jurisdiction dead weight, assembles and receives great restriction with the section of jurisdiction size, and then causes section of jurisdiction ring and unit length tunnel section of jurisdiction seam numerous, not only influences the structure atress, moreover because the seam is numerous, has increased the risk of operation in-process tunnel percolating water, consequently the tunnel is assembled and is needed to optimize the improvement with the concrete section of jurisdiction urgently. Meanwhile, concrete cracks generated in the concrete structure construction and operation process can reduce the bearing capacity of the segment structure and influence the durability of the segment structure.
Disclosure of Invention
The invention aims to overcome the defects in the prior art and provide a prefabricated hollow concrete segment and a prefabricating method.
The purpose of the invention can be realized by the following technical scheme:
the utility model provides a prefabricated empty stomach concrete section of jurisdiction, is applied to the underground works who adopts the construction of prefabricated concatenation method, and this section of jurisdiction includes section of jurisdiction skeleton, sets up the gasbag and the fashioned section of jurisdiction main part of layering concreting that are used for forming empty stomach structure in the section of jurisdiction skeleton, the gasbag set up along section of jurisdiction skeleton extending direction to fix through the couple on the section of jurisdiction skeleton.
The duct piece main body is made of steel/fiber reinforced concrete, fiber steel/fiber reinforced concrete or fiber concrete, wherein steel/fiber bars in the steel/fiber reinforced concrete duct piece main body and the fiber steel/fiber reinforced concrete duct piece main body are duct piece stress steel/fiber bars, and steel/fiber bars in the fiber concrete duct piece main body are construction steel/fiber bars for fixing the air bag through a hook.
Prefabricated section of jurisdiction skeleton constitute by many main muscle and ligature many annular stirrups between adjacent main muscle, the gasbag setting in the space that many main muscle and stirrup surround and form.
The fixed position of the air bag avoids the segment embedded part.
The air bag accounts for 20-40% of the volume of the segment, and the distance from the outer surface of the air bag to the outer boundary of the segment meets the requirements of segment stress and the thickness of a steel bar protection layer.
The outer surface of the air bag is streamline, and the material of the air bag is rubber, PVC composite material, waterproof fabric or metal.
The fiber doped in the concrete formed by the cast segment main body adopts steel fiber and synthetic fiber, the steel fiber is carbon steel fiber, low alloy steel fiber or stainless steel fiber, and the synthetic fiber is polyacrylonitrile fiber, polypropylene fiber, polyamide fiber or polyvinyl alcohol fiber.
The duct piece framework material is a steel bar or a fiber bar.
A prefabricating method for prefabricating an open-web concrete segment comprises the following steps:
1) binding a segment framework;
2) placing an uninflated air bag at a set position in the process of binding the segment framework;
3) the air bag hook is accurately positioned, and the air bag is inflated, so that the bearing capacity and the durability of the duct piece cannot be influenced by the implantation of the air bag;
4) adopting commercial concrete to perform hollow concrete segment pouring prefabrication;
5) and (5) demolding, curing and prefabricating the hollow concrete pipe piece.
Compared with the prior art, the invention has the following advantages:
according to the method, the air bag is placed in the concrete pipe to replace solid concrete, so that the prefabricated hollow concrete pipe is obtained, the accurate positioning of the air bag is utilized to ensure that the placing of the air bag does not influence the bearing capacity and durability of a concrete pipe ring, the self weight of the pipe can be reduced, the size of the prefabricated pipe is increased, the convenience of pipe construction is improved, the construction efficiency can be effectively improved, raw materials are saved, the construction cost is saved, the resource loss is reduced, green construction is realized, and the environmental influence is reduced; along with the increase of the load caused by the increase of the tunnel excavation section, the thickness of the segment is also continuously increased, so that the research and development of the hollow concrete segment have important theoretical significance and practical value.
Drawings
Fig. 1 is an elevation view of a prefabricated open-web concrete segment.
Fig. 2 is a cross-sectional view of 1-1 in fig. 1.
Fig. 3 is a cross-sectional view of 2-2 in fig. 1.
Fig. 4 is a cross-sectional view of 3-3 of fig. 1.
Fig. 5 is a cross-sectional view of 4-4 of fig. 1.
Fig. 6 is a cross-sectional view of 5-5 of fig. 1.
Fig. 7 is a cross-sectional view of 6-6 of fig. 1.
Detailed Description
The invention is described in detail below with reference to the figures and specific embodiments.
Examples
The invention provides a prefabricated hollow concrete segment and a prefabricating method, wherein the prefabricated hollow concrete segment can be applied to underground projects constructed by adopting a prefabricating and assembling method, and the prefabricated hollow concrete segment comprises but is not limited to shield tunnels, assembled ring-type pipe-jacking tunnels, prefabricated and assembled secondary linings by a drilling and blasting method, underground pipe galleries, prefabricated and assembled underground projects, underground complexes and the like.
The structure of the prefabricated hollow concrete pipe piece is shown in figures 1-7, the prefabricated hollow concrete pipe piece comprises a pipe piece framework, an air bag arranged in the pipe piece framework and used for forming a hollow structure and a pipe piece main body formed by pouring concrete, and the air bag is fixed through a hook on the pipe piece framework.
The prefabricated hollow concrete segment can be reinforced (fiber) concrete, fiber reinforced (fiber) concrete or fiber concrete, wherein the reinforced (fiber) concrete segment adopts a classic steel (fiber) bar and concrete mechanics calculation mode, the fiber reinforced (fiber) concrete segment considers that the fiber and the steel (fiber) bar are stressed together, the steel (fiber) bar amount configured on the segment can be effectively reduced, and the fiber concrete segment completely adopts the fiber to replace the steel (fiber) bar.
According to the stress characteristics of the segment structure, an air bag is arranged in the segment and is fixed on a segment steel (fiber) rib framework by a hook; wherein the steel (fiber) bars in the reinforced concrete segment and the fiber reinforced (fiber) reinforced concrete segment are segment stress steel (fiber) bars, and the steel (fiber) bars in the fiber reinforced concrete segment are construction steel (fiber) bars for positioning the air bag.
The section of jurisdiction atress and steel bar protection layer thickness requirement are satisfied to the distance that corresponds section of jurisdiction outer boundary in gasbag boundary, the shared section of jurisdiction volume of gasbag reaches 20% ~ 40%, can reduce the concrete volume greatly, the appearance and the location of gasbag should ensure not obviously influencing the section of jurisdiction bearing capacity, and adopt the streamlined of making things convenient for concrete placement, the protective layer thickness of section of jurisdiction reinforcing bar is ensured in the location of gasbag, do not influence the durability of section of jurisdiction structure, the section of jurisdiction inner structure characteristic need be considered in the appearance of gasbag, the built-in fitting that the section of jurisdiction corresponds needs to be dodged.
The air bag material can be rubber, PVC composite material, waterproof fabric, metal or other high polymer materials and the like, has pressure resistance and puncture resistance, avoids rupture and failure in the installation, positioning and concrete pouring processes of the air bag, and has no adverse effect on the environment in the tunnel operation process.
The invention increases the concrete heat dissipation area by the built-in air bag, reduces the volume of the concrete, thereby reducing the segment cracks possibly caused by the hydration heat of the large-volume concrete, and the air bag can obviously reduce the average density of the segments, the segment size can be increased by combining the construction capability of the current tunnel construction mechanical equipment, the number of single-ring and unit-length tunnel segments is reduced, the number of single-ring and unit-length tunnel segment joints is reduced, and the risk of water leakage of the tunnel joints is reduced.
The hook for positioning the air bag has enough strength and toughness, so that the air bag is prevented from deviating in the concrete pouring process, and the segment framework can be made of materials meeting the stress requirements such as reinforcing steel bars and fiber bars.
The fiber doped in the poured concrete can adopt common non-toxic fiber in fiber concrete, such as steel fiber (including carbon steel fiber, low alloy steel fiber, stainless steel fiber and the like) and synthetic fiber (including polyacrylonitrile fiber, polypropylene fiber, polyamide fiber, polyvinyl alcohol fiber and the like), and the fiber doped in the concrete needs to consider the stress requirement besides the control requirement of the segment concrete crack, correspondingly reduces the reinforcement amount of a steel (fiber) rib framework and facilitates the binding of steel (fiber) ribs.
The prefabricating method of the prefabricated hollow concrete segment is realized by the following steps:
(1) binding a segment steel (fiber) rib framework;
(2) an air bag is arranged in the process of binding a segment steel (fiber) rib framework;
(3) the air bag hook is accurately positioned, so that the bearing capacity and the durability of the duct piece cannot be influenced by the implantation of the air bag;
(4) adopting commercial concrete or fiber concrete to perform hollow concrete segment prefabrication;
(5) and (5) demolding, curing and prefabricating the hollow concrete pipe piece.

Claims (9)

1. The utility model provides a prefabricated empty stomach concrete section of jurisdiction, is applied to the underground works who adopts the construction of prefabricated concatenation method, its characterized in that, this section of jurisdiction include section of jurisdiction skeleton, set up the gasbag and the fashioned section of jurisdiction main part of layering concreting that are used for forming empty stomach structure in the section of jurisdiction skeleton, the gasbag along section of jurisdiction skeleton extending direction setting to fix through the couple on the section of jurisdiction skeleton.
2. The prefabricated open-web concrete duct piece of claim 1, wherein the duct piece body material is steel/fiber reinforced concrete, fiber steel/fiber reinforced concrete or fiber concrete, wherein the steel/fiber bars in the steel/fiber reinforced concrete duct piece body and the fiber steel/fiber reinforced concrete duct piece body are duct piece stress steel/fiber bars, and the steel/fiber bars in the fiber concrete duct piece body are construction steel/fiber bars for fixing the air bag through hooks.
3. The precast open-web concrete segment as recited in claim 1, wherein the precast segment frame is composed of a plurality of main ribs and a plurality of annular stirrups bound between the adjacent main ribs, and the air bag is disposed in a space surrounded by the main ribs and the stirrups.
4. The precast open-web concrete segment as recited in claim 3, wherein the fixed position of the air bag is free of segment embedment.
5. The prefabricated open-web concrete segment as claimed in claim 1, wherein the air bag accounts for 20-40% of the volume of the segment, and the distance from the outer surface of the air bag to the outer boundary of the segment meets the requirements of segment stress and the thickness of a steel bar protection layer.
6. The precast open-web concrete segment as recited in claim 1, wherein the outer surface of the air bag is streamlined and made of rubber, PVC composite, impermeable fabric or metal.
7. The precast open-web concrete segment as recited in claim 2, wherein the concrete formed by casting the segment body is doped with steel fibers and synthetic fibers, the steel fibers are carbon steel fibers, low alloy steel fibers or stainless steel fibers, and the synthetic fibers are polyacrylonitrile fibers, polypropylene fibers, polyamide fibers or polyvinyl alcohol fibers.
8. The precast open-web concrete segment as recited in claim 1, wherein the segment skeleton material is steel bars or fiber bars.
9. A prefabrication method for prefabricating a hollow concrete segment is characterized by comprising the following steps:
1) binding a segment framework;
2) placing an uninflated air bag at a set position in the process of binding the segment framework;
3) the air bag hook is accurately positioned, and the air bag is inflated, so that the bearing capacity and the durability of the duct piece cannot be influenced by the implantation of the air bag;
4) adopting commercial concrete to perform hollow concrete segment pouring prefabrication;
5) and (5) demolding, curing and prefabricating the hollow concrete pipe piece.
CN201910917327.8A 2019-09-26 2019-09-26 Prefabricated hollow concrete segment and prefabricating method Pending CN110593897A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910917327.8A CN110593897A (en) 2019-09-26 2019-09-26 Prefabricated hollow concrete segment and prefabricating method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910917327.8A CN110593897A (en) 2019-09-26 2019-09-26 Prefabricated hollow concrete segment and prefabricating method

Publications (1)

Publication Number Publication Date
CN110593897A true CN110593897A (en) 2019-12-20

Family

ID=68863690

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910917327.8A Pending CN110593897A (en) 2019-09-26 2019-09-26 Prefabricated hollow concrete segment and prefabricating method

Country Status (1)

Country Link
CN (1) CN110593897A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114718599A (en) * 2022-03-29 2022-07-08 同济大学 Concrete embedded inflatable/liquid steel pipe intelligent duct piece

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2395032Y (en) * 1999-09-28 2000-09-06 成保才 Hollow pipe sheet for channel
CN202990171U (en) * 2012-12-06 2013-06-12 郑州大学 Hollow shear wall structure with crisscross and slantingly distributed ribs
CN106584654A (en) * 2016-11-16 2017-04-26 中铁工程装备集团机电工程有限公司 Production process for prefabricated reinforced concrete duct pieces
WO2017081990A1 (en) * 2015-11-11 2017-05-18 鹿島建設株式会社 Precast structure, and construction method for underground structures
CN109732772A (en) * 2018-12-30 2019-05-10 中铁十四局集团有限公司 The method for prefabricating of section of jurisdiction and section of jurisdiction

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2395032Y (en) * 1999-09-28 2000-09-06 成保才 Hollow pipe sheet for channel
CN202990171U (en) * 2012-12-06 2013-06-12 郑州大学 Hollow shear wall structure with crisscross and slantingly distributed ribs
WO2017081990A1 (en) * 2015-11-11 2017-05-18 鹿島建設株式会社 Precast structure, and construction method for underground structures
CN106584654A (en) * 2016-11-16 2017-04-26 中铁工程装备集团机电工程有限公司 Production process for prefabricated reinforced concrete duct pieces
CN109732772A (en) * 2018-12-30 2019-05-10 中铁十四局集团有限公司 The method for prefabricating of section of jurisdiction and section of jurisdiction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114718599A (en) * 2022-03-29 2022-07-08 同济大学 Concrete embedded inflatable/liquid steel pipe intelligent duct piece
CN114718599B (en) * 2022-03-29 2023-08-29 同济大学 Concrete embedded inflation/liquid steel pipe intelligent duct piece

Similar Documents

Publication Publication Date Title
CN108952759A (en) A kind of tunnel lining structure and construction method using concrete filled steel tube and superimposed sheet
CN112443337B (en) Ultra-high performance concrete-common concrete shield tunnel segment and construction method thereof
CN108442239A (en) A kind of full assembled light abutment and its construction method
CN110029599A (en) Prefabricated culvert steel connecting structure and construction method
CN109487681A (en) Erosion resistant ultra-high performance concrete constrains section assembling bridge pier and method of construction
CN110744677A (en) Prefabricated built-in light filling body concrete segment and prefabricating method
CN110593897A (en) Prefabricated hollow concrete segment and prefabricating method
CN111271087A (en) Construction method for arch prefabricated lining structure with post-cast strip connection
CN100376835C (en) Shock-resistant culvert pipe with large section and circumferential stress and preparation process thereof
CN111660409A (en) Large-span tunnel lining model prefabricating device and method in geomechanical model test
CN208328665U (en) A kind of full assembled light abutment
CN113187515B (en) Tunnel secondary lining with assembled UHPC structure as bottom die and construction method thereof
CN208718220U (en) A kind of profile steel concrete column using GFRP tendons
CN110685344A (en) Prefabricated hollow concrete pipe ring and prefabricating method
CN102536260A (en) Composite cavity component
CN105781016A (en) Cement-based composite and steel pipe combined compound column and manufacturing method thereof
CN110685343A (en) Prefabricated built-in light filling body concrete pipe ring and prefabricating method
CN113294171B (en) Corrugated steel plate and UHPC combined assembled tunnel lining structure and construction method thereof
CN215907493U (en) Assembled prefab reinforcing apparatus
CN214944311U (en) Tunnel secondary lining using assembled UHPC structure as bottom die
CN213926243U (en) Assembled pile cap for prestressed pipe pile
CN109577169A (en) A kind of assembly concrete box girder structure and construction method based on steel construction sway bracing
CN211692480U (en) Tunnel segment based on high-performance cement-based composite material
CN211524821U (en) A restraint filling type section of jurisdiction lining cutting supporting construction for shield tunnel
CN111560980A (en) 3D printing underground comprehensive pipe gallery manufacturing and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191220

RJ01 Rejection of invention patent application after publication