CN110541501A - Vertical piece connecting device of assembled concrete shear force wall - Google Patents

Vertical piece connecting device of assembled concrete shear force wall Download PDF

Info

Publication number
CN110541501A
CN110541501A CN201910946236.7A CN201910946236A CN110541501A CN 110541501 A CN110541501 A CN 110541501A CN 201910946236 A CN201910946236 A CN 201910946236A CN 110541501 A CN110541501 A CN 110541501A
Authority
CN
China
Prior art keywords
wall
fixedly connected
plug
limiting plate
assembled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201910946236.7A
Other languages
Chinese (zh)
Inventor
张东岭
宋荣方
王欢
余术刚
刘新阳
王玉振
包纯
李春锋
王梓旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Vocational College of Water Conservancy and Environment
Original Assignee
Henan Vocational College of Water Conservancy and Environment
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Vocational College of Water Conservancy and Environment filed Critical Henan Vocational College of Water Conservancy and Environment
Priority to CN201910946236.7A priority Critical patent/CN110541501A/en
Publication of CN110541501A publication Critical patent/CN110541501A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)

Abstract

The invention discloses an assembled concrete shear wall vertical splicing and connecting device which comprises a wall to be assembled and an assembled wall, wherein a male plug is arranged on one side of the wall to be assembled, a female slot is prefabricated on the assembled wall, a connecting plug is fixedly connected to the wall to be assembled, a return baffle is arranged at the head of the connecting plug, a limiting plate is arranged on the connecting plug on the inner side of the return baffle, the limiting plate is rotatably connected with the connecting plug, and the limiting plate and the return baffle are connected through a spring; female slot has been seted up with the same high position of public plug in assembly wall one side, and the oral area of female slot inner chamber is fixed to be provided with the conflict piece that cooperatees and use with the limiting plate, and when public plug inserted female slot, the fender is returned to the returning can cross the conflict and advance female slot soon, and the limiting plate needs to take place rotatoryly to waiting to assemble the wall direction when crossing the conflict soon, and the bottom of female slot is through passing through spring coupling slide block. The invention solves the problems that the position between two shear walls is deviated and the installation is troublesome when the vertical splicing and connecting of the assembled concrete shear walls are convenient.

Description

vertical piece connecting device of assembled concrete shear force wall
Technical Field
The invention relates to the technical field of constructional engineering, in particular to a vertical abutted seam connecting device for an assembled concrete shear wall.
background
The fabricated building is a building assembled by prefabricated parts at a construction site, and is called as a fabricated building. The shear wall is also called as wind resisting wall or earthquake resisting wall, and structure wall. The wall body of the house or the structure mainly bears horizontal load and vertical load (gravity) caused by wind load or earthquake action. The shear wall is divided into a plane shear wall and a cylinder shear wall. The plane shear wall is used in reinforced concrete frame structure, plate lifting structure and flat slab system. In order to increase the rigidity, strength and collapse resistance of the structure, the reinforced concrete shear wall can be cast in situ or prefabricated in some parts. The cast-in-place shear wall, the peripheral beams and the columns are simultaneously poured, and the integrity is good. The cylinder shear wall is used in high-rise buildings, high-rise structures and suspension structures and is formed by enclosing partition walls of elevator rooms, staircases, equipment and auxiliary rooms, the cylinder wall is a cast-in-place reinforced concrete wall body, the rigidity and the strength of the cast-in-place reinforced concrete wall body are higher than those of a plane shear wall body and can bear larger horizontal load, when the assembled shear wall is subjected to vertical splicing, a connecting device is required to be used for connecting the assembled shear wall, and the existing assembled concrete shear wall vertical splicing connecting device has the following defects:
1. Before the shear walls are connected in a splicing manner, the two shear walls are not preliminarily fixed, but are directly fixed generally, and because the shear walls are directly fixed by positioning once in an assembly manner, the upper parts and the lower parts of the two shear walls cannot be completely leveled during fixing, so that the splicing quality of the shear walls cannot meet the requirement and the splicing efficiency is low;
2. The joint of the two shear walls is not well sealed, and water leakage and air leakage can occur after assembly.
Disclosure of Invention
Aiming at the defects of the prior art, the invention provides a vertical splicing and connecting device for an assembled concrete shear wall, which solves the problems that the position between two shear walls is deviated when the vertical splicing and connecting device for the assembled concrete shear wall is spliced, the installation of the shear walls is troublesome, and the two shear walls are not well sealed.
in order to achieve the purpose, the invention is realized by the following technical scheme: a vertical splicing and connecting device for an assembled concrete shear wall comprises the assembled wall and the assembled wall, wherein a male plug is arranged on one side of the assembled wall, a female slot is prefabricated in the assembled wall, the male plug comprises a connecting plug, a limiting plate and a return baffle, the connecting plug is fixedly connected to the assembled wall, the return baffle is arranged at the head of the connecting plug, the limiting plate is arranged on the connecting plug on the inner side of the return baffle, the limiting plate is rotatably connected with the connecting plug, and the limiting plate and the return baffle are connected through a spring; female slot has been seted up with the same high position of public plug in assembly wall one side, and the oral area of female slot inner chamber is fixed to be provided with the conflict piece that cooperatees and use with the limiting plate, and when public plug inserted female slot, the fender is returned to the returning can cross the conflict and advance female slot soon, and the limiting plate needs to take place rotatoryly to waiting to assemble the wall direction when crossing the conflict soon, and the bottom of female slot is through passing through spring coupling slide block.
As a preferred scheme of the invention, the return stop comprises a stop plug and a stop head, both sides of the connecting plug are rotatably connected with limiting plates through rotating pieces, the stop plug is fixedly connected to the connecting plug on each limiting plate side, the end part of the stop plug is fixedly connected with the stop head on the limiting plate side, one end of the spring is fixedly connected with one side of the limiting plate, and the other end of the spring is fixedly connected with the stop plug; the portion of female slot inner chamber just is located and fixes setting up the touch multitouch with the position correspondence department of male limiting plate, the equal fixedly connected with chute board in one side of touch multitouch, two sliding connection slider between the chute board to the equal fixed connection spring pipe in top and the bottom of slider one side.
as another preferable scheme of the present invention, one side of the wall to be assembled is fixedly connected with a fixing plate, one side of the assembling wall is fixedly connected with fixing grooves used in cooperation with the fixing plate, and the number of the fixing plates and the number of the fixing grooves are two.
As another preferable scheme of the present invention, a clamping block is fixedly connected to one side of the fixing groove, a clamping groove matched with the clamping block is formed in one side of the fixing plate, and a buffer block matched with the fixing plate is fixedly connected to one side of the fixing groove and located above and below the clamping block.
as a further preferable scheme of the invention, the top and the bottom of one side of the surface of the wall to be assembled are both fixedly connected with a calibration transverse plate, and the top and the bottom of one side of the surface of the wall to be assembled are fixedly connected with a fixing sleeve matched with the calibration transverse plate for use.
As another further preferable scheme of the invention, the surface of the fixed sleeve is fixedly connected with a threaded sleeve, the internal thread of the threaded sleeve is connected with a pointed half-threaded inserted bar, one end of the threaded inserted bar penetrates through the fixed sleeve and extends into the fixed sleeve, and the surface of the calibration transverse plate is provided with a jack matched with the threaded inserted bar for use.
As a still further preferable aspect of the present invention, a rubber partition is fixedly connected to one side of the wall to be assembled, and one side of the rubber partition is in contact with one side of the wall to be assembled.
As a further preferable scheme of the invention, the other side of the sliding block is fixedly connected with a cushion block which is matched with the connecting plug for use.
The invention provides a vertical abutted seam connecting device for an assembled concrete shear wall. The method has the following beneficial effects:
(1) The vertical abutted seam connecting device for the fabricated concrete shear wall is fixedly connected with a spring through one side of a blocking block, one end of the spring is fixedly connected with one side of a limiting plate, female slots are formed in the top and the bottom of one side of the fabricated wall, abutting blocks matched with the limiting plate for use are fixedly connected to the top and the bottom of an inner cavity of the female slot, sliding groove plates are fixedly connected to the top and the bottom of the inner cavity of the female slot and positioned on one side of the abutting blocks, a sliding block is connected between the two sliding groove plates in a sliding manner, spring pipes are fixedly connected to the top and the bottom of one side of the sliding block, one end of each spring pipe is fixedly connected with one side of the inner cavity of the female slot, a clamping block is fixedly connected to one side of a fixing groove, a clamping groove matched with the clamping block for use is formed in one side of the fixing plate, and buffer, before carrying out the piece joint connection to the shear force wall, can be quick tentatively fix two shear force walls to make vertical deviation can not appear between two shear force walls, upper portion flushes completely with the lower part, can be quick when carrying out final fixing fix two shear force walls.
(2) this vertical piece connecting device of assembled concrete shear force wall, top and the equal fixedly connected with calibration diaphragm in bottom through treating assembly wall surface one side, the top and the fixed cover that bottom fixedly connected with and calibration diaphragm matched with and use of assembly wall surface one side, the fixed surface fixedly connected with thread bush of fixed cover, the inside threaded connection of thread bush has the screw inserted bar, the one end of screw inserted bar runs through fixed cover and extends to the inside of fixed cover, the jack that cooperatees and uses with the screw inserted bar is seted up on the surface of calibration diaphragm, fix the upper portion and the lower part of two shear force walls simultaneously, it does not incline to have guaranteed to treat the installation of assembly wall, thereby the shear force wall has carried out fine fixing, its normal use has been guaranteed.
(3) This vertical piece connecting device of assembled concrete shear force wall, through waiting one side fixedly connected with rubber partition of assembly wall, one side of rubber partition contacts with one side of assembly wall, has carried out fine protection to the piece department of two shear force walls, has carried out fine sealing to piece department simultaneously.
drawings
The invention is described in further detail below with reference to the accompanying drawings:
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a cross-sectional view of a female slot and retaining slot arrangement in accordance with the present invention;
FIG. 3 is an enlarged view of a portion of the invention at A in FIG. 2;
FIG. 4 is an enlarged view of a portion of the present invention at B of FIG. 2;
FIG. 5 is an enlarged view of a portion of the invention at C of FIG. 1;
Fig. 6 is a bottom view of the internal structure of fig. 5 of the present invention.
in the figure: 1. a wall to be assembled; 2. assembling a wall; 3. a connecting plug; 4. a limiting plate; 5. blocking; 6. a stopper; 7. a spring; 8. a female slot; 9. a contact block; 10. a chute plate; 11. a slider; 12. a spring tube; 13. a fixing plate; 14. fixing grooves; 15. calibrating a transverse plate; 16. fixing a sleeve; 17. a threaded sleeve; 18. a threaded bayonet; 19. a jack; 20. a rubber partition plate; 21. a clamping block; 22. a card slot; 23. a buffer block; 24. and a cushion block.
Detailed Description
With reference to fig. 1 to 6, the present invention provides a technical solution: the utility model provides a vertical piece connecting device of assembled concrete shear force wall, is including waiting to assemble wall 1 and assembly wall 2, waits to assemble the equal fixedly connected with connecting plug 3 in top and the bottom of 1 one side of wall, and connecting plug 3's top and bottom all rotate through rotating and are connected with limiting plate 4, rotate the connecting piece specifically can be as articulated part. A blocking plug 5 is fixedly connected with the top and the bottom of the connecting plug 3 and positioned at one side of the limiting plate 4, a blocking head 6 matched with the limiting plate 4 for use is fixedly connected with one side of the blocking plug 5, a spring 7 is fixedly connected with one side of the blocking plug 5, one end of the spring 7 is fixedly connected with one side of the limiting plate 4, a female slot 8 is arranged at the top and the bottom of one side of the assembly wall 2, a touch block 9 matched with the limiting plate 4 for use is fixedly connected with the top and the bottom of the inner cavity of the female slot 8, a sliding groove plate 10 is fixedly connected with the top and the bottom of the inner cavity of the female slot 8 and positioned at one side of the touch block 9, a sliding block 11 is slidably connected between the, and the top and the bottom of slider 11 one side all fixedly connected with spring pipe 12, the outside of spring pipe 12 is the rubber leather sheath, and the inside of rubber leather sheath contains expanding spring, one end of spring pipe 12 and one side fixed connection of female slot 8 inner chamber. Treat one side fixedly connected with fixed plate 13 of assembly wall 1, one side fixedly connected with of assembly wall 2 and fixed plate 13 cooperate the fixed slot 14 that uses, and the quantity of fixed plate 13 and fixed slot 14 is two, further strengthens the stability of treating assembly wall 1 and assembly wall 2 initial joint.
Treat the equal fixedly connected with calibration diaphragm 15 in top and the bottom of assembly wall 1 surface one side, the top and the bottom fixedly connected with of assembly wall 2 surface one side cooperate with the fixed cover 16 that uses with calibration diaphragm 15, the fixed surface fixedly connected with thread bush 17 of fixed cover 16, the inside threaded connection of thread bush 17 has screw inserted bar 18, the one end of screw inserted bar 18 runs through fixed cover 16 and extends to the inside of fixed cover 16, calibration diaphragm 15's surface is seted up and is cooperated jack 19 that uses with screw inserted bar 18. The calibration cross plate 15 is fixed by welding with embedded steel bars in the wall 1 to be assembled, so that the stability of the calibration cross plate 15 can be improved, and the fixing sleeve 16 is also arranged.
treat one side fixedly connected with rubber baffle 20 of assembly wall 1, rubber baffle 20 is the flexible rubber material, there is fine leakproofness, the phenomenon that leaks appears between two shear force walls that can be fine prevent, one side of rubber baffle 20 and one side contact of assembly wall 2, one side fixedly connected with fixture block 21 of fixed slot 14, draw-in groove 22 with fixture block 21 matched with use is seted up to one side of fixed plate 13, one side of fixed slot 14 just is located the top of fixture block 21 and the equal fixedly connected with in below buffer block 23 that cooperatees and use with fixed plate 13, buffer block 23 is the rubber material, the opposite side fixedly connected with of slider 11 cooperatees and uses cushion 24 with connecting plug 3, cushion 24 is the rubber cushion.
When the assembling wall is used, when the wall 1 to be assembled and the wall 2 to be assembled are assembled and connected, an operator can align the fixing plate 13 with the fixing groove 14, insert the fixing plate 13 into the fixing groove 14, and then preliminarily position the upper and lower positions of the wall 1 to be assembled and the wall 2 to be assembled, when the fixing plate 13 is inserted into the fixing groove 14, the limiting plate 4 can enter the female slot 8, so that the limiting plate 4 is abutted by the abutting block 9 and the limiting plate 4 is abutted by the stopper 6, the limiting plate 4 is clamped between the abutting block 9 and the stopper 6, the connecting plug 3 can be clamped inside the female slot 8, and further the left and right positions of the wall 1 to be assembled and the wall 2 are limited to a certain degree, at the moment, the operator can rotate the threaded insert rod 18 into the threaded sleeve 17, the threaded sleeve 17 and the fixing sleeve 16 are welded and fixed together, and after the threaded insert rod 18 is rotated into the jack 19, therefore, the wall 1 to be assembled and the wall 2 to be assembled are calibrated and fixed, namely, the wall 1 to be assembled can keep a specific gap with the wall 2 to be assembled, and then the overall mutual position between the wall 1 to be assembled and the wall 2 to be assembled can be further calibrated, so that the pre-designed matching is met. Certainly, after the wall 1 to be assembled is fixed, cement solidification can be performed on the wall, a hole is generally formed in the wall and is communicated with a channel in the wall, cement mortar flows to a gap and then is solidified through grouting into the hole, the prefabricated wall is further fixed, and after the wall 1 to be assembled and the wall 2 to be assembled are solidified, the calibration transverse plate 15 and the fixing sleeve 16 can be partially detached.
The vertical abutted seam connecting device for the fabricated concrete shear wall is characterized in that a spring 7 is fixedly connected to one side of a blocking block 5, one end of the spring 7 is fixedly connected to one side of a limiting plate 4, female slots 8 are respectively formed in the top and the bottom of one side of an assembled wall 2, abutting blocks 9 matched with the limiting plate 4 for use are respectively fixedly connected to the top and the bottom of the inner cavity of the female slot 8, sliding groove plates 10 are respectively fixedly connected to the top and the bottom of the inner cavity of the female slot 8 and positioned on one side of the abutting blocks 9, a sliding block 11 is slidably connected between the two sliding groove plates 10, spring tubes 12 are respectively fixedly connected to the top and the bottom of one side of the sliding block 11, one end of each spring tube 12 is fixedly connected to one side of the inner cavity of the female slot 8, a clamping block 21 is fixedly connected to one side of a fixing groove 14, a clamping groove 22 matched with the clamping block 21 for use is formed in one side of the fixing groove 14 and positioned, before splicing and connecting the shear walls, the two shear walls can be quickly and preliminarily fixed, so that vertical deviation between the two shear walls cannot occur, the upper part and the lower part are completely flush, the two shear walls can be quickly and quickly fixed when final fixing is carried out, the top and the bottom of one side of the surface of the wall 1 to be assembled are fixedly connected with a calibration transverse plate 15, the top and the bottom of one side of the surface of the wall 2 to be assembled are fixedly connected with a fixed sleeve 16 matched with the calibration transverse plate 15, the surface of the fixed sleeve 16 is fixedly connected with a threaded sleeve 17, the internal thread of the threaded sleeve 17 is connected with a threaded insert rod 18, a pointed half thread of the threaded insert rod 18 is conveniently inserted into a jack 19, one end of the threaded insert rod 18 penetrates through the fixed sleeve 16 and extends into the fixed sleeve 16, the surface of the calibration transverse plate 15 is provided with a jack 19 matched, the unthreaded part of the front end of the threaded insert rod 18 enters the insert hole 19, and the upper part and the lower part of the two prefabricated shear walls are simultaneously fixed, so that the shear walls are well fixed. Through waiting to assemble one side fixedly connected with rubber baffle 20 of wall 1, one side of rubber baffle 20 and the contact of one side of assembly wall 2 have carried out fine protection to the piece department of two shear force walls, have carried out fine sealing to piece department simultaneously.

Claims (8)

1. The utility model provides a vertical piece connecting device of assembled concrete shear force wall, is waiting to assemble wall and assembly wall including waiting to assemble wall, waits to assemble a wall side and is provided with public plug, and the prefabrication has female slot, its characterized in that on the assembly wall: the male plug comprises a connecting plug, a limiting plate and a return gear, the connecting plug is fixedly connected to a wall to be assembled, the return gear is arranged at the head of the connecting plug, the limiting plate is arranged on the connecting plug at the inner side of the return gear, the limiting plate is rotatably connected with the connecting plug, and the limiting plate is connected with the return gear through a spring; female slot has been seted up with the same high position of public plug in assembly wall one side, and the oral area of female slot inner chamber is fixed to be provided with the conflict piece that cooperatees and use with the limiting plate, and when public plug inserted female slot, the fender is returned to the returning can cross the conflict and advance female slot soon, and the limiting plate needs to take place rotatoryly to waiting to assemble the wall direction when crossing the conflict soon, and the bottom of female slot is through passing through spring coupling slide block.
2. The vertical splicing and connecting device for the fabricated concrete shear wall according to claim 1, characterized in that: the return baffle comprises a baffle plug and a baffle head, both sides of the connecting plug are rotatably connected with a limiting plate through rotating pieces, the connecting plug on each limiting plate side is fixedly connected with the baffle plug, the end part of the baffle plug is fixedly connected with the baffle head on the limiting plate side, one end of the spring is fixedly connected with one side of the limiting plate, and the other end of the spring is fixedly connected with the baffle plug; the portion of female slot inner chamber just is located and fixes setting up the touch multitouch with the position correspondence department of male limiting plate, the equal fixedly connected with chute board in one side of touch multitouch, two sliding connection slider between the chute board to the equal fixed connection spring pipe in top and the bottom of slider one side.
3. The vertical splicing and connecting device for the fabricated concrete shear wall according to claim 1, characterized in that: treat one side fixedly connected with fixed plate of assembly wall, one side fixedly connected with of assembly wall and the fixed slot that the fixed plate cooperateed and uses, the quantity of fixed plate and fixed slot is two.
4. The vertical abutted seam connecting device for the fabricated concrete shear wall according to claim 3, wherein: one side fixedly connected with fixture block of fixed slot, the draw-in groove of using with the fixture block cooperatees is seted up to one side of fixed plate, one side of fixed slot just is located the equal fixedly connected with in top and the below of fixture block and the buffer block that the fixed plate cooperatees and uses.
5. The vertical splicing and connecting device for the fabricated concrete shear wall according to claim 1, characterized in that: treat the equal fixedly connected with calibration diaphragm in top and the bottom of assembly wall surface one side, the top and the bottom fixedly connected with of assembly wall surface one side and the fixed cover that the calibration diaphragm cooperateed and uses.
6. The vertical splicing joint connecting device for the fabricated concrete shear wall according to claim 5, wherein: the fixed surface of cover is connected with the thread bush, the inside threaded connection of thread bush has the half screw-thread inserted bar of pointed end, the one end of screw-thread inserted bar runs through fixed cover and extends to the inside of fixed cover, the jack that cooperatees and use with the screw-thread inserted bar is seted up on the surface of calibration diaphragm.
7. The vertical splicing and connecting device for the fabricated concrete shear wall according to claim 1, characterized in that: one side of the wall to be assembled is fixedly connected with a rubber partition plate, and one side of the rubber partition plate is in contact with one side of the wall to be assembled.
8. The vertical splicing and connecting device for the fabricated concrete shear wall according to claim 1, characterized in that: and the other side of the sliding block is fixedly connected with a cushion block matched with the connecting plug for use.
CN201910946236.7A 2019-10-03 2019-10-03 Vertical piece connecting device of assembled concrete shear force wall Withdrawn CN110541501A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910946236.7A CN110541501A (en) 2019-10-03 2019-10-03 Vertical piece connecting device of assembled concrete shear force wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910946236.7A CN110541501A (en) 2019-10-03 2019-10-03 Vertical piece connecting device of assembled concrete shear force wall

Publications (1)

Publication Number Publication Date
CN110541501A true CN110541501A (en) 2019-12-06

Family

ID=68715331

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910946236.7A Withdrawn CN110541501A (en) 2019-10-03 2019-10-03 Vertical piece connecting device of assembled concrete shear force wall

Country Status (1)

Country Link
CN (1) CN110541501A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112144911A (en) * 2020-11-11 2020-12-29 陕西理工大学 Civil construction reinforced wall and reinforcing method thereof
CN112900657A (en) * 2021-01-23 2021-06-04 北京新兴保信建设工程有限公司 Assembled building wall body seal structure
CN113718986A (en) * 2021-09-02 2021-11-30 开封大学 Simplify assembled wall component of construction
CN114150793A (en) * 2021-11-22 2022-03-08 惠瑞净化科技(江苏)有限公司 Light keel light partition wall system for lithium battery clean room
CN115822128A (en) * 2023-02-23 2023-03-21 成都建工第六建筑工程有限公司 Assembly type wall body structure and construction method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112144911A (en) * 2020-11-11 2020-12-29 陕西理工大学 Civil construction reinforced wall and reinforcing method thereof
CN112900657A (en) * 2021-01-23 2021-06-04 北京新兴保信建设工程有限公司 Assembled building wall body seal structure
CN112900657B (en) * 2021-01-23 2021-11-23 北京新兴保信建设工程有限公司 Assembly type building
CN113718986A (en) * 2021-09-02 2021-11-30 开封大学 Simplify assembled wall component of construction
CN113718986B (en) * 2021-09-02 2022-08-09 开封大学 Simplify assembled wall component of construction
CN114150793A (en) * 2021-11-22 2022-03-08 惠瑞净化科技(江苏)有限公司 Light keel light partition wall system for lithium battery clean room
CN115822128A (en) * 2023-02-23 2023-03-21 成都建工第六建筑工程有限公司 Assembly type wall body structure and construction method

Similar Documents

Publication Publication Date Title
CN110541501A (en) Vertical piece connecting device of assembled concrete shear force wall
CA3106047C (en) Prefabricated wall and assembly structure for prefabricated building, and construction method therefor
WO2017197853A1 (en) Insulation precast wall and prefabricated building
CN101608480B (en) Manufacturing method of precast concrete short-limb shear wall provided with door windows
CN205400024U (en) Instrument formula external scaffolding bolt that can dismantle used repeatedly links wall spare
CN211499913U (en) Low-energy-consumption prefabricated house
CN104863290A (en) Combined wall formed by single prefabricated wall sections and construction method
CN114135023B (en) Assembly type building outer wall and construction method
CN104294920A (en) Joint assembly of U-shaped steel reinforced concrete combined beam and special-shaped concrete-filled steel tube column and manufacturing method of joint assembly
CN210857610U (en) Vertical piece connecting device of assembled concrete shear force wall
CN106284852A (en) A kind of reinforcing bar connector of plane position adjustable
CN110424534B (en) Prefabricated assembled type reinforced-free concrete frame and construction method thereof
CN106013763A (en) Flat iron fastener type external scaffold wall connecting piece
CN219569255U (en) Light multifunctional prefabricated wall
CN111561075A (en) Precast concrete shear wall building structure and construction method thereof
CN111456233A (en) Prefabricated assembled concrete beam column joint structure and construction method thereof
CN203034615U (en) Novel outer sleeve tube type connecting node of cold-bending rectangular steel tube column and H-shaped steel girder
CN214834737U (en) Plug-in type board primary and secondary keel fast-assembling early-dismantling ear-shaped connecting piece
CN113638506A (en) Precast concrete ground beam-frame column connecting joint and construction method thereof
CN218027860U (en) Underground engineering wall body connecting device by reverse operation method
CN216616291U (en) Floor combination steel secondary beam node structure
CN216109030U (en) Precast concrete ground beam-shear force wall connected node
CN219508852U (en) Closed prefabricated cover plate of basement outer wall post-pouring strip
CN215802325U (en) Precast concrete ground beam-frame column connected node
CN214117104U (en) Assembled building shear wall structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20191206

WW01 Invention patent application withdrawn after publication