CN110528519A - A kind of new epeirogenetic of rubble mounding for sea-reclamation long spire pilot hole add the construction method of hammer piling - Google Patents

A kind of new epeirogenetic of rubble mounding for sea-reclamation long spire pilot hole add the construction method of hammer piling Download PDF

Info

Publication number
CN110528519A
CN110528519A CN201910716697.5A CN201910716697A CN110528519A CN 110528519 A CN110528519 A CN 110528519A CN 201910716697 A CN201910716697 A CN 201910716697A CN 110528519 A CN110528519 A CN 110528519A
Authority
CN
China
Prior art keywords
default
pile sinking
tubular pole
new
epeirogenetic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910716697.5A
Other languages
Chinese (zh)
Inventor
王鹏
程由奎
郭新亮
朱全象
郭媛
曾奇胜
贾龙飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang 20 Smelter Construction Co Ltd
China MCC20 Group Corp Ltd
Original Assignee
Zhejiang 20 Smelter Construction Co Ltd
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang 20 Smelter Construction Co Ltd, China MCC20 Group Corp Ltd filed Critical Zhejiang 20 Smelter Construction Co Ltd
Priority to CN201910716697.5A priority Critical patent/CN110528519A/en
Publication of CN110528519A publication Critical patent/CN110528519A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/18Reclamation of land from water or marshes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • E02D7/06Power-driven drivers
    • E02D7/10Power-driven drivers with pressure-actuated hammer, i.e. the pressure fluid acting directly on the hammer structure
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling
    • E21B7/043Directional drilling for underwater installations

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Paleontology (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Fluid Mechanics (AREA)
  • Ocean & Marine Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention belongs to new epeirogenetic piling construction field, long spire pilot hole adds the construction method of hammer piling with providing a kind of new epeirogenetic of rubble mounding for sea-reclamation, include: comprising steps of S1: being drilled by full-sleeve long-spiral drilling machine in the default pile sinking position for presetting new land, be drilled into default pile sinking height S2: being hammered default tubular pole to the default pile sinking height in the drilling of default pile sinking position by Driven Piles machine.Compared with prior art, the present invention has the advantages that passing through the characteristic for being directed to the new epeirogenetic ground different soil of rubble mounding for sea-reclamation, the construction method of effective pilot hole pile sinking, reach in the new epeirogenetic of rubble mounding for sea-reclamation place, realize the smooth pile sinking of PHC tubular pole, and improve construction efficiency, it is ensured that construction quality.

Description

A kind of new epeirogenetic of rubble mounding for sea-reclamation long spire pilot hole add the construction method of hammer piling
Technical field
A kind of the invention belongs to new epeirogenetic piling construction field, and in particular to rubble mounding for sea-reclamation new epeirogenetic ground long spire pilot hole Add the construction method of hammer piling.
Background technique
When with bordering on the sea area or the new epeirogenetic of neritic area progress, mainly by the way of rubble mounding for sea-reclamation, expand land-based area field Then ground area is developed and is built in the land newly made.
When the new epeirogenetic of rubble mounding for sea-reclamation carries out pretensioned prestressed concrete pipe pile (PHC tubular pole) construction on the ground, due to field Ground backfilling material predominantly cuts into a mountain rubble and block stone, has an adverse effect for the meeting of the pile sinking of PHC tubular pole, especially fills out passing through During rock layers, since backfill rubble block sizes are not of uniform size, for the PHC of the backfill layer of the new epeirogenetic overground part of rubble mounding for sea-reclamation Tube pile construction, the layer are strong rammer gravelly soil, return lift thickness disunity, according to direct hammer piling, penetrating resistance is big, pile sinking It is relatively difficult, when encountering intensive and larger boulder, it is easy to happen deviation of pipe pile, it is difficult to lead to pile sinking, or even pile crown occurs and breaks Damage phenomenon.
Summary of the invention
The technical problem to be solved by the present invention is to be directed to the status of the prior art, and provide a kind of new epeirogenetic of rubble mounding for sea-reclamation Ground long spire pilot hole adds the construction method of hammer piling.
The technical scheme of the invention to solve the technical problem is: a kind of with proposing the new epeirogenetic of rubble mounding for sea-reclamation long spiral shell Rotation pilot hole adds the construction method of hammer piling, comprising steps of
S1: it is drilled, is drilled into default in the default pile sinking position for presetting new land by full-sleeve long-spiral drilling machine Pile sinking height;
S2: default tubular pole is hammered to the default pile sinking height in the drilling of default pile sinking position by Driven Piles machine.
In the construction method that in a kind of above-mentioned new epeirogenetic of rubble mounding for sea-reclamation long spire pilot hole adds hammer piling, step S1 packet It includes:
S11: default pile sinking position is obtained;
S12: obtaining default tubular pole diameter, chooses corresponding drill bit according to default tubular pole diameter;
S13: according to the thickness of the new epeirogenetic ground jackstone backfill layer of rubble mounding for sea-reclamation, corresponding pilot hole steel sleeve is selected;
S14: adjustment drilling machine, bit location, so that bit location vertically stands on default pile sinking position;
S15: default pile sinking height is obtained, is drilled at default pile sinking position;
S16: it is drilled at default pile sinking position to default pile sinking height.
In the construction method that in a kind of above-mentioned new epeirogenetic of rubble mounding for sea-reclamation long spire pilot hole adds hammer piling, the step S16 further include:
S161: borehole perpendicularity is detected when drilling to 0.5m to 1m depth;
Judge whether borehole perpendicularity is vertical;
Depth is corresponded to as default pile sinking height if so, continuing downward pore-forming, if it is not, stopping pore-forming and repeating step S14。
In the construction method that in a kind of above-mentioned new epeirogenetic of rubble mounding for sea-reclamation long spire pilot hole adds hammer piling, the step S16 further include:
S162: drill bit, pilot hole steel sleeve are taken out when drilling depth reaches default pile sinking height;
S163: detection check borehole depth, bore diameter and borehole perpendicularity;
S164: in backfilling in drilling into rubble.
In the construction method that in a kind of above-mentioned new epeirogenetic of rubble mounding for sea-reclamation long spire pilot hole adds hammer piling, the step S2 includes:
S21: corresponding Driven Piles machine is selected according to default tubular pole diameter;
S22: adjusting Driven Piles seat in the plane and set, so that Driven Piles machine is vertically stood on above bore position;
S23: default tubular pole is put into drilling;
S24, tubular pole is pushed by Driven Piles machine.
In the construction method that in a kind of above-mentioned new epeirogenetic of rubble mounding for sea-reclamation long spire pilot hole adds hammer piling, the step S24 includes:
S241: tubular pole is depressed by Driven Piles machine vertically downward;
S242: judge whether default tubular pole plan-position is in pre-determined stability state;
S243: default tubular pole is continuously beaten, until default tubular pole falls into presetting in drilling and sinks if so, hammering and filling the machine that hits Stake height.
In the construction method that in a kind of above-mentioned new epeirogenetic of rubble mounding for sea-reclamation long spire pilot hole adds hammer piling, the step S243 includes:
S2431: hammering impinges upon when continuously beating default tubular pole, real-time judge tubular pole remain high height whether be less than it is default Limiting altitude;
S2432: if so, welding another default tubular pole in default tubular pole upper end, and step S241 is repeated, until tubular pole height It is consistent with default pile sinking height.
Compared with the prior art, the advantages of the present invention are as follows: by for the new epeirogenetic ground different soil of rubble mounding for sea-reclamation Characteristic, the construction method of effective pilot hole pile sinking have reached in the new epeirogenetic of rubble mounding for sea-reclamation place, have realized PHC tubular pole Smooth pile sinking, and improve construction efficiency, it is ensured that construction quality.
Detailed description of the invention
Fig. 1 be the new epeirogenetic of this rubble mounding for sea-reclamation long spire pilot hole add the construction method flow chart one of hammer piling;
Fig. 2 be the new epeirogenetic of this rubble mounding for sea-reclamation long spire pilot hole add the construction method flowchart 2 of hammer piling;
Fig. 3 be the new epeirogenetic of this rubble mounding for sea-reclamation long spire pilot hole add the construction method flow chart 3 of hammer piling;
Fig. 4 be the new epeirogenetic of this rubble mounding for sea-reclamation long spire pilot hole add the construction method flow chart four of hammer piling;
Fig. 5 be the new epeirogenetic of this rubble mounding for sea-reclamation long spire pilot hole add the construction method flow chart five of hammer piling;
Fig. 6 be the new epeirogenetic of this rubble mounding for sea-reclamation long spire pilot hole add the construction method flow chart six of hammer piling;
Fig. 7 be the new epeirogenetic of this rubble mounding for sea-reclamation long spire pilot hole add the construction method flow chart seven of hammer piling;
Fig. 8 is drilling construction schematic diagram.
Specific embodiment
Following is a specific embodiment of the present invention in conjunction with the accompanying drawings, technical scheme of the present invention will be further described, However, the present invention is not limited to these examples.
As shown in Figure 1, the new epeirogenetic of this rubble mounding for sea-reclamation long spire pilot hole add the construction method of hammer piling, comprising steps of
S1: it is drilled, is drilled into default in the default pile sinking position for presetting new land by full-sleeve long-spiral drilling machine Pile sinking height;
S2: default tubular pole is hammered to the default pile sinking height in the drilling of default pile sinking position by Driven Piles machine.
Pass through drilling machine on the ground at default pile sinking position in new epeirogenetic to drill, backfill layer in new epeirogenetic ground be drilled, in turn Facilitate and tubular pole is sunk into default pile sinking position, facilitate pile sinking, prevents the intensive or biggish rock for backfilling layer in new epeirogenetic ground Influence sinking to for tubular pole.
As shown in Fig. 2, Fig. 3, Fig. 4 and Fig. 8, further, step S1 includes:
S11: default pile sinking position is obtained;
S12: obtaining default tubular pole diameter, chooses corresponding drill bit according to default tubular pole diameter;
S13: according to the thickness of the new epeirogenetic ground jackstone backfill layer of rubble mounding for sea-reclamation, corresponding pilot hole steel sleeve is selected;
S14: adjustment drilling machine, bit location, so that bit location vertically stands on default pile sinking position;
S15: default pile sinking height is obtained, is drilled at default pile sinking position;
S16: it is drilled at default pile sinking position to default pile sinking height.
The diameter that pile sinking position and pile sinking height and tubular pole are determined according to the size of design drawing when pile sinking position, sinks After stake height and tubular pole diameter determine, corresponding drill bit is chosen by the diameter of pile sinking height and identified tubular pole and is drawn Drill bit and the rigid casing of pilot hole are built at default pile sinking position by hole steel sleeve vertically, and pilot hole steel sleeve is sheathed on brill when drilling On head and the two rotates sinking simultaneously, and soil block, rock rise delivery port with helical blade, until drilling depth reaches and presets Pile sinking height is mutually simultaneously stopped.
Further, step S16 further include:
S161: borehole perpendicularity is detected when drilling to 0.5m to 1m depth;
Judge whether borehole perpendicularity is vertical;
Depth is corresponded to as default pile sinking height if so, continuing downward pore-forming, if it is not, stopping pore-forming and repeating step S14。
When drill bit and pilot hole steel sleeve drill, then the depth of 0.5~1.0m of subdrilling detects the verticality of institute's drilling bore hole, If the verticality of drilling meets the requirements, drill bit and pilot hole steel sleeve work on, if the verticality of drilling is undesirable, It then needs to readjust the angle at drill bit and default pile sinking position, prevents drilling run-off the straight and lead to not pile sinking.
Further, step S16 further include:
S162: drill bit, pilot hole steel sleeve are taken out when depth of pore forming reaches default pile sinking height;
S163: detection check borehole depth, bore diameter and borehole perpendicularity;
S164: in backfilling in drilling into rubble.
After jackstone backfill layer completes drawing hole construction, to avoid closing on the influence of stake position drawing hole construction, and stake position is closed on The influence of subsequent hammer piling, while in order to avoid pilot hole collapse hole and security risk is reduced, stake is carried out using small particle gravelly soil Hole backfill, to reinforce the finished product protection to drilling, the diameter of small particle gravelly soil should can guarantee in 10mm between 50mm Drilling will not collapse, and can not influence tubular pole and sink to.
As shown in Fig. 5, Fig. 6, Fig. 7, further, step S2 includes:
S21: corresponding Driven Piles machine is selected according to default tubular pole diameter;
S22: adjusting Driven Piles seat in the plane and set, so that Driven Piles machine is vertically stood on above bore position;
S23: default tubular pole is put into drilling;
S24, tubular pole is pushed by Driven Piles machine.
After selecting corresponding hammering to install according to default tubular pole diameter, Driven Piles machine guide rod is adjusted, is allowed to perpendicular to default At pile sinking position, then tubular pole is lifted by crane, tubular pole lower end aligned drill center is inserted just, while being mutually 90 degree with two theodolites Angle, cooperation Driven Piles machine align stake, manage drilling, Driven Piles machine and tubular pole will by Driven Piles machine in after a vertical line At stake indentation to default pile sinking position;
Further, step S24 includes:
S241: tubular pole is depressed by Driven Piles machine vertically downward;
S242: judge whether default tubular pole plan-position is in pre-determined stability state;
S243: default tubular pole is continuously beaten, until default tubular pole falls into presetting in drilling and sinks if so, hammering and filling the machine that hits Stake height.
Driven Piles prow first presses downward to tubular pole, so that tubular pole keeps vertically being pressed into drilling under the pressure of Driven Piles machine It is interior, static pressure type pile sinking is carried out, after the plan-position of tubular pole, verticality obtain correctly adjusting and stablize, enables tubing vertical Be inserted into drilling, guarantee tubing it is subsequent continuously hammered when inclination in angle will not occur, recurrence is connected with Driven Piles machine Continuous strike tubular pole, carries out paddle type mill pile sinking.
Further, step S243 includes:
S2431: hammering impinges upon when continuously beating default tubular pole, real-time judge tubular pole remain high height whether be less than it is default Limiting altitude;
S2432: if so, welding another default tubular pole in default tubular pole upper end, and step S241 is repeated, until tubular pole height It is consistent with default pile sinking height.
In construction, default pile sinking height is higher, such as, with high tubular pole, is easy to cause tubular pole using with default pile sinking height Run-off the straight during hammering, and the working depth of Driven Piles machine requires also increase accordingly, and leads to cost and difficulty of construction Increasing continuously hammered to tubular pole upper end in a upper tubular pole and do not fallen within drilling so the tubular pole for needing to select length shorter When interior height is identical as predetermined limit height, stops hammering and welding accesses another tubular pole in tubular pole upper end, then repeat Step S241, until tubular pole height is consistent with default pile sinking height.
Tubular pole, which remains high predetermined limit height, should be 500mm, when pile extension, remove completely to welding position, with mechanical Derusting executes " steel-pipe pile flux-cored wire CO2 Welding Machine Welder to welding current, voltage, speed of welding etc. Skill regulation ", interface position deforms if any clashing and breaking or has local damage deformation after hammering, burr occurs etc., it to be modified, close It is welded again after lattice, pile extension counterpart misalignment should be less than 2mm, and local gap should be tamped greater than 2mm's using steel plate.
Pile extension throat depth increases 2mm than conventional, and weld seam answers continuous full, appearance pore-free, slag inclusion, stings meat depth Less than 0.5mm and it should be less than a quarter of full circumference, postwelding removes slag, after pile extension weld, waits 3 minutes necessary cold But time, the epoxide coal bituminous anti-decaying paint of pile extension position brushing quick-dry type of tubular pole, again into indentation tubular pole operation after parching.
Specific embodiment described herein is only an example for the spirit of the invention.The neck of technology belonging to the present invention The technical staff in domain can make various modifications or additions to the described embodiments or replace by a similar method Generation, defined range that however, it does not deviate from the spirit of the invention.

Claims (7)

1. a kind of new epeirogenetic of rubble mounding for sea-reclamation long spire pilot hole add the construction method of hammer piling, which is characterized in that comprising steps of
S1: it is drilled by full-sleeve long-spiral drilling machine in the default pile sinking position for presetting new land, is drilled into default pile sinking Highly;
S2: default tubular pole is hammered to the default pile sinking height in the drilling of default pile sinking position by Driven Piles machine.
2. the new epeirogenetic of a kind of rubble mounding for sea-reclamation according to claim 1 long spire pilot hole add the construction method of hammer piling, It is characterized in that, the step S1 includes:
S11: default pile sinking position is obtained;
S12: obtaining default tubular pole diameter, chooses corresponding drill bit according to default tubular pole diameter;
S13: according to the thickness of the new epeirogenetic ground jackstone backfill layer of rubble mounding for sea-reclamation, corresponding pilot hole steel sleeve is selected;
S14: adjustment drilling machine, bit location, so that bit location vertically stands on default pile sinking position;
S15: default pile sinking height is obtained, is drilled at default pile sinking position;
S16: it is drilled at default pile sinking position to default pile sinking height.
3. the new epeirogenetic of a kind of rubble mounding for sea-reclamation according to claim 2 long spire pilot hole add the construction method of hammer piling, It is characterized in that, the step S16 further include:
S161: borehole perpendicularity is detected when drilling to 0.5m to 1m depth;
Judge whether borehole perpendicularity is vertical;
Depth is corresponded to as default pile sinking height if so, continuing downward pore-forming, if it is not, stopping pore-forming and repeating step S14.
4. the new epeirogenetic of a kind of rubble mounding for sea-reclamation according to claim 2 long spire pilot hole add the construction method of hammer piling, It is characterized in that, the step S16 further include:
S162: drill bit, pilot hole steel sleeve are taken out when drilling depth reaches default pile sinking height;
S163: detection check borehole depth, bore diameter and borehole perpendicularity;
S164: in backfilling in drilling into rubble.
5. the new epeirogenetic of a kind of rubble mounding for sea-reclamation according to claim 1 long spire pilot hole add the construction method of hammer piling, It is characterized in that, the step S2 includes:
S21: corresponding Driven Piles machine is selected according to default tubular pole diameter;
S22: adjusting Driven Piles seat in the plane and set, so that Driven Piles machine is vertically stood on above bore position;
S23: default tubular pole is put into drilling;
S24, tubular pole is pushed by Driven Piles machine.
6. the new epeirogenetic of a kind of rubble mounding for sea-reclamation according to claim 5 long spire pilot hole add the construction method of hammer piling, It is characterized in that, the step S24 includes:
S241: tubular pole is depressed by Driven Piles machine vertically downward;
S242: judge whether default tubular pole plan-position is in pre-determined stability state;
S243: default tubular pole is continuously beaten, until default tubular pole falls into the default pile sinking height in drilling if so, hammering dress and hitting a machine Degree.
7. the new epeirogenetic of a kind of rubble mounding for sea-reclamation according to claim 6 long spire pilot hole add the construction method of hammer piling, It is characterized in that, the step S243 includes:
S2431: hammering impinges upon when continuously beating default tubular pole, and real-time judge tubular pole remains whether high height is less than predetermined limit Highly;
S2432: if so, welding another default tubular pole in default tubular pole upper end, and step S241 is repeated, up to tubular pole height and in advance If pile sinking height is consistent.
CN201910716697.5A 2019-08-05 2019-08-05 A kind of new epeirogenetic of rubble mounding for sea-reclamation long spire pilot hole add the construction method of hammer piling Pending CN110528519A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910716697.5A CN110528519A (en) 2019-08-05 2019-08-05 A kind of new epeirogenetic of rubble mounding for sea-reclamation long spire pilot hole add the construction method of hammer piling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910716697.5A CN110528519A (en) 2019-08-05 2019-08-05 A kind of new epeirogenetic of rubble mounding for sea-reclamation long spire pilot hole add the construction method of hammer piling

Publications (1)

Publication Number Publication Date
CN110528519A true CN110528519A (en) 2019-12-03

Family

ID=68661424

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910716697.5A Pending CN110528519A (en) 2019-08-05 2019-08-05 A kind of new epeirogenetic of rubble mounding for sea-reclamation long spire pilot hole add the construction method of hammer piling

Country Status (1)

Country Link
CN (1) CN110528519A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111139860A (en) * 2020-01-17 2020-05-12 上海公路桥梁(集团)有限公司 Riprap layer pile and fixing method thereof
CN113802555A (en) * 2021-09-23 2021-12-17 中国二十冶集团有限公司 Comprehensive construction method for large-area prestressed pipe piles in existing open-air storage yard area

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101158159A (en) * 2007-10-31 2008-04-09 刘小檀 Whole-course hole-preguiding hammering entering-rock PHC pile tube construction process
CN105735277A (en) * 2016-04-19 2016-07-06 黑龙江龙华岩土工程有限公司 Hammering type pile machine mixing and jet grouting device and pile forming method thereof
CN105887813A (en) * 2016-05-07 2016-08-24 深圳市宏业基基础工程有限公司 Large-diameter super-long pile construction method in karst area through full-casing pipe full rotating and rotary drilling
JP2016205111A (en) * 2014-11-11 2016-12-08 隆夫 中野 Precast pile embedding method
KR20170002355A (en) * 2016-12-27 2017-01-06 한국가스공사 Drawing apparatus for phc pile and drawing method for for phc pile thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101158159A (en) * 2007-10-31 2008-04-09 刘小檀 Whole-course hole-preguiding hammering entering-rock PHC pile tube construction process
JP2016205111A (en) * 2014-11-11 2016-12-08 隆夫 中野 Precast pile embedding method
CN105735277A (en) * 2016-04-19 2016-07-06 黑龙江龙华岩土工程有限公司 Hammering type pile machine mixing and jet grouting device and pile forming method thereof
CN105887813A (en) * 2016-05-07 2016-08-24 深圳市宏业基基础工程有限公司 Large-diameter super-long pile construction method in karst area through full-casing pipe full rotating and rotary drilling
KR20170002355A (en) * 2016-12-27 2017-01-06 한국가스공사 Drawing apparatus for phc pile and drawing method for for phc pile thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
姚伟林: "浅析引孔锤击桩法施工技术", 《福建建材》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111139860A (en) * 2020-01-17 2020-05-12 上海公路桥梁(集团)有限公司 Riprap layer pile and fixing method thereof
CN113802555A (en) * 2021-09-23 2021-12-17 中国二十冶集团有限公司 Comprehensive construction method for large-area prestressed pipe piles in existing open-air storage yard area

Similar Documents

Publication Publication Date Title
US7854572B2 (en) Piling machine with high-pressure jet spiral bit and its piling method
CN103806840B (en) One-way spiral half soil compaction drill bit and one-way spiral half Squeezing Soil Pile construction technology
CN110043190B (en) Method for building vertical well large-diameter chamber
CN109537583A (en) A kind of slip casting plant pile construction method of PHC tubular pole
CN110528519A (en) A kind of new epeirogenetic of rubble mounding for sea-reclamation long spire pilot hole add the construction method of hammer piling
CN105780763A (en) Construction method of medium-hole vibrating casing wall protection type long spiral cast-in-situ bored pile
CN106522213A (en) Rotary jet grouting bar inserting type mini pile construction method
CN109024719B (en) Pile side disturbance resistance-reducing building inclination correcting method
CN111456737B (en) Shaft construction method for preventing collapse in construction period under unfavorable geological conditions
CN103015408A (en) Cast-in-place pile synchronous casing hole-forming constructing method
CN112901074B (en) Rock-socketed drilling pore-forming technology of offshore large-diameter inclined pile rotary digging machine
CN204919533U (en) Drilling bored concrete pile hosqe bit
CN203769662U (en) One-way spiral semi-soil-squeezing drill bit
CN207260138U (en) High-pressure rotary-spray stirs the drilling rod of bearing pile and has its device
JP5698316B2 (en) Construction method of foundation pile
CN112983258A (en) Down-the-hole hammer rapid hole forming construction method for unconsolidated rock stratum geology
CN105714832B (en) A kind of large size prefabricated building enclosure of deep basal pit and construction method
CN112554176A (en) Full-casing twisted pipe follow-up rotary drilling pore-forming construction method
CN205444192U (en) Bridge stake is towards pile driving construction system
CN204225100U (en) The construction equipment of concrete pile
CN204252120U (en) The construction equipment of concrete pile
CN106120790A (en) The special equipment of the compacted guncreting pile of high frequency and method
CN114991670A (en) Pile forming method for large-diameter high-pressure jet grouting pile in complex soil layer
CN214993840U (en) Well-digging vibration pile sinking system for prefabricated inclined piles
CN104153355A (en) Concrete pile construction equipment and method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191203

RJ01 Rejection of invention patent application after publication