CN110528497A - A kind of construction method of hidden hole drilling cooperation impact drill continuous wall trench underground - Google Patents

A kind of construction method of hidden hole drilling cooperation impact drill continuous wall trench underground Download PDF

Info

Publication number
CN110528497A
CN110528497A CN201810498268.0A CN201810498268A CN110528497A CN 110528497 A CN110528497 A CN 110528497A CN 201810498268 A CN201810498268 A CN 201810498268A CN 110528497 A CN110528497 A CN 110528497A
Authority
CN
China
Prior art keywords
hole
rock
rushes
construction
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810498268.0A
Other languages
Chinese (zh)
Inventor
武玉山
侯鹏
于磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian Railway Engineering Co Ltd of China Railway Seventh Group Co Ltd
Original Assignee
Xian Railway Engineering Co Ltd of China Railway Seventh Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian Railway Engineering Co Ltd of China Railway Seventh Group Co Ltd filed Critical Xian Railway Engineering Co Ltd of China Railway Seventh Group Co Ltd
Priority to CN201810498268.0A priority Critical patent/CN110528497A/en
Publication of CN110528497A publication Critical patent/CN110528497A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/187Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Earth Drilling (AREA)

Abstract

The construction method of the hidden hole drilling cooperation impact drill continuous wall trench underground of embodiment according to the present invention, pass through arrangement hole position step, hidden hole drilling construction guidance hole step, hydraulic grab bucket grooving machine grabs soil layer, it rushes stake machine and rushes rock step, the clear bottom pore formation step of filter sand carries out construction operation, by first making pilot hole with hidden hole drilling, soil layer cleaning is carried out with hydraulic grab bucket grooving machine again, on the basis of conventional construction method, create ground-connecting-wall combination grooving new process, on the one hand high-intensitive inclined-plane granitic formation ground-connecting-wall construction hammer partially is solved, bit freezing, the problems such as grooving low efficiency, the safety of ground-connecting-wall construction is ensured simultaneously, quality, progress, improve effect, cost is saved.

Description

A kind of construction method of hidden hole drilling cooperation impact drill continuous wall trench underground
Technical field
The present invention relates to a kind of construction methods of hidden hole drilling cooperation impact drill continuous wall trench underground.
Background technique
Diaphram wall has extensive use in China, wherein in 100Mpa with the geological conditions of ramp granite Under, the construction method of continuous wall trench underground mainly has: one is using the processing method to inclination competent bed, including to inclining Oblique place rockfills, and pours strong concrete etc., then with the direct grooving of impact drill, this method is at high cost and the inclined hole effect of processing is poor; Another kind is using the method for impact drill cooperation chute forming machine construction, and this method is easy to appear hammer, bit freezing partially, long construction period, function Imitate it is low, ground-connecting-wall grooving quality it is difficult to ensure that.
Therefore, under inclined-plane high intensity granite geological conditions, how to innovate one kind both can solve ground-connecting-wall work progress In difficult points such as hammer, bit freezing partially, and can improve construction effect, reduce construction period construction method be those skilled in the art urgently The technical problem solved.
Summary of the invention
The present invention is directed at least solve one of the problems of the prior art.
It is an object of the invention to propose a kind of construction method of hidden hole drilling cooperation impact drill continuous wall trench underground.
The construction method of the hidden hole drilling cooperation impact drill continuous wall trench underground of embodiment according to the present invention, the construction Method includes:
Arrangement hole position step: marking out hole site to be drilled with by spray painting mode on leading wall, every row hole site to be drilled it Between spacing be 500mm, pitch-row is 1.5m between the hole site to be drilled marked led on wall, equal in a phase slot section two sides The 1m that extends outwardly carries out bore operation, in the second stage of slot section two sides away from progress bore operation at I-steel 1.25m;
Hidden hole drilling construction guidance hole step: constructor operates down-the-hole drill to appropriate location, according to centre behind first two sides Sequence is constructed through row, by way of increasing air pressure to diamond drilling rod, creeps into rock stratum rapidly;Hydraulic grab bucket grooving machine crawl soil Layer: for the impact force and closing force that constructor adjusts hydraulic grab to pick up each layer of strong-weathered rock or more, constructor examines prison Examining system is rectified a deviation, the hydraulic grab bucket grooving machine will paste immediately when X-axis or Y-axis either direction deviation are more than permissible value The wall of leading for facing foundation pit side enters slot, and should fill into fresh mud in time, to maintain to lead mud liquid level stabilizing in wall, the hydraulic grab Chute forming machine stops at once to scar, and slot bottom is made to remain basically stable;
Rush stake machine and rush rock step: after the hydraulic grab bucket grooving machine fulfils assignment, constructor's operation rushes stake machine to rock to be rushed Position, pile monkey are unified for 3.8t, are constantly impacted by pile monkey to scar, change rock stratum internal structure, are allowed to split Gap accelerates slotter construction for the later period and creates favorable conditions;
The clear bottom pore formation step of filter sand: constructor should carry out filter sand to slot section, 15 steel pipe of diameter is inserted into slot, away from bottom hole 0.3-0.8m terminates rubber hose on steel pipe, and hose other end connects sand removing machine.
The construction method of the hidden hole drilling cooperation impact drill continuous wall trench underground of embodiment according to the present invention, by first using Hidden hole drilling makees pilot hole, then carries out soil layer cleaning with hydraulic grab bucket grooving machine, on the basis of conventional construction method, creates ground Even wall combines grooving new process, on the one hand solves high-intensitive inclined-plane granitic formation ground-connecting-wall construction hammer, bit freezing, grooving effect partially The low problem of rate, while ensuring the safety, quality of ground-connecting-wall construction, progress, effect is improved, cost has been saved.
In the present embodiment, single groove segment grooving period was averagely foreshortened to 60 days by 130 days, and single width slot grooving cost is average 9.83 ten thousand yuan are reduced, grooving efficiency is substantially increased, reduces costs;Full bid section amounts to 45 width, reduces by 4,420,000 yuan of cost, whole The body duration shortens about 2 months.
Preferentially, the arrangement hole position step further include: when sipes section is 0.8m, constructor is with 3 row of quincuncial arrangement Hole site to be drilled.
Preferentially, hidden hole drilling construction guidance hole step further include: impact drill rushes rock: constructor at least uses 2 CJ80 impact drill rushes rock pore-forming, in diaphragm wall rotation angle position, outward half of hole location should be bored, to guarantee diaphragm wall integrality more.
Preferentially, the stake machine that rushes rushes rock step further include: after constructor, which at least completes 1 main aperture, rushes rock operation, increases If sediment separator.
Preferentially, the stake machine that rushes rushes rock step further include:
Slip consistency needs are arranged according to code requirement, to guarantee that rushing broken rock grain is suspended in slot;
Mud guarantees to recycle for 24 hours in slot, to prevent from being suspended in the sinking that slot rushes broken rock grain;
Scarfing cinder is carried out using preset time period, weldering is hammered into shape, rockfill or via hole works.
Specific embodiment
Below with reference to embodiment, the present invention is further explained.In the following detailed description, it is only retouched by way of explanation Certain exemplary embodiments of the invention are stated.Undoubtedly, those skilled in the art will recognize, without departing from In the case where the spirit and scope of the present invention, the described embodiments may be modified in various different ways.Therefore, Description is regarded as illustrative in nature, and is not intended to limit the scope of the claims.
The construction method of the hidden hole drilling cooperation impact drill continuous wall trench underground of embodiment according to the present invention, by first using Hidden hole drilling makees pilot hole, then carries out soil layer cleaning with chute forming machine, finally rushes the technical solution of rock grooving with impact drill to realize, Concrete construction method is as follows:
Arrangement hole position step: marking out hole site to be drilled with by spray painting mode on leading wall, every row hole site to be drilled it Between spacing be 500mm, pitch-row is 1.5m between the hole site to be drilled marked led on wall, equal in a phase slot section two sides The 1m that extends outwardly carries out bore operation, in the second stage of slot section two sides away from progress bore operation at I-steel 1.25m;
Preferentially, when sipes section is 0.8m, constructor is with 3 row of quincuncial arrangement hole site to be drilled.
Hidden hole drilling construction guidance hole step: constructor operates down-the-hole drill to appropriate location, according to centre behind first two sides Sequence is constructed through row, by way of increasing air pressure to diamond drilling rod, creeps into rock stratum rapidly;
Preferentially, guarantee that drilling and shadoof are deflated alternately in construction, blow out inner hole deposition slag, guarantee that drilling rod smoothly bores Into avoiding bit freezing.The verticality that drilling rod is observed in construction avoids inclined hole from causing bit freezing, or forms useless hole.Mud level control exists Lead 0.8m under wall.The construction of hidden hole drilling increases the free face of rock stratum, accelerates fission of the later period rock stratum after being impacted by pile monkey Rate.
Preferentially, impact drill rushes rock: constructor at least rushes rock pore-forming using 2 CJ80 impact drills, in diaphragm wall corner portion Position outward should bore half of hole location, to guarantee diaphragm wall integrality more.
Hydraulic grab bucket grooving machine grabs soil layer: the impact force and closing force of constructor's adjusting hydraulic grab are severely-weathered to pick up More than rock each layer, constructor examine monitoring system, when X-axis or Y-axis either direction deviation are more than permissible value ± 10cm, stand It rectifies a deviation, the hydraulic grab bucket grooving machine, which will paste, to be faced the wall of leading of foundation pit side and enter slot, and should fill into fresh mud in time, with dimension It holds and leads mud liquid level stabilizing in wall, the hydraulic grab bucket grooving machine to scar stops at once, and slot bottom is made to remain basically stable;
Preferentially, the impact force of hydraulic grab and closing force are enough to pick up each layer of strong-weathered rock or more, during grooving, The verticality of strict control grab bucket and plan-position, especially fluting stage.Examine monitoring system, X, Y-axis either direction When deviation is more than permissible value, rectify a deviation immediately.Grab bucket patch, which faces foundation pit side and leads wall, enters slot, and mechanically actuated is steady.And it mends in time Enter fresh mud, mud liquid level stabilizing in wall is led in maintenance.It grabs bucket and stops to scar, and slot bottom is made to remain basically stable.Using 2 CJ80 Impact drill rushes rock pore-forming, leads and marks each bore position on wall, and pitch-row is 1.5 meters, outward to bore half in diaphragm wall rotation angle position more Hole location, to guarantee diaphragm wall integrality.The slot section successively completed to hidden hole drilling construction is constructed.Chute forming machine is arranged in night and applies Work reduces mechanical equipment on daytime jam situation.
Rush stake machine and rush rock step: after the hydraulic grab bucket grooving machine fulfils assignment, constructor's operation rushes stake machine to rock to be rushed Position, pile monkey are 3.8t, are constantly impacted by pile monkey to scar, to change rock stratum internal structure, are allowed to split Gap accelerates slotter construction for the later period and creates favorable conditions;
Preferentially, stroke is controlled in impact process within 1.5 meters, and pays attention to preventing from fanning the air hammering and put rope into shape excessively, is reduced Cell wall is disturbed.Wirerope is observed in impact process, and whether there is or not abrasions, hammer into shape such as card and hard draw should be avoided, act rashly, prevent hammer.
Further, slot section punching quantity is optimized, slot section five main apertures of construction, pore-forming sequence is first two side connectors Hole, then intermediate hole location, last constructed residual hole location.After at least completing 1 main aperture, sediment separator is added, timely desanding increases Pile monkey reduces the filter sand time when construction of later period slotter to effective impact force of rock stratum, reduces what sand screen was plugged Possibility.
Further, according to on-site actual situations, following 3 work steps are sequentially completed:
Slip consistency needs to require to be arranged according to code for construction and acceptance of subway engineering (GB50299-1999), to protect Card rushes broken rock grain and is suspended in slot, recycles outlet as early as possible by mud, and reduction is secondary to rush rock, improves punching efficiency;
Mud guarantees to recycle for 24 hours in slot, prevents from being suspended in the sinking that slot rushes broken rock grain, improves punching efficiency;
Use preset time period benefit, it may be preferable that selection night shift time (23:00-06:00) carry out scarfing cinder, weldering hammer, rockfill or Via hole work, improves punching on daytime efficiency.
The clear bottom pore formation step of filter sand: constructor should carry out filter sand to slot section, 15 steel pipe of diameter is inserted into slot, away from bottom hole 0.3-0.8m terminates rubber hose on steel pipe, and hose other end connects sand removing machine.
Preferentially, after having repaired slot section, it is necessary to carry out filter sand to slot section, sling insertion diameter 15cm steel with crawler crane in slot Pipe and air-compressor air duct (air-compressor air duct is connect lower with steel pipe), steel pipe upper end is connect with sand filter, away from bottom hole 0.3-0.8m, Rubber hose is terminated on steel pipe, hose other end connects sand removing machine, utilizes reacting cycle principle, the mud and sediment (stone, sand) of slot bottom It is separated by steel pipe inspiration sand removing machine, achievees the purpose that the clear bottom of desanding, constructor one every 2m is filtered mono- conduit position Sand.
The construction of hidden hole drilling do pilot hole on the one hand solve in punch process bore partially caused by ground-connecting-wall grooving it is of poor quality, On the other hand the problem of period length is increased the free face of rock stratum by drilling in advance, accelerates the fission that later period pile monkey rushes rock Rate improves and rushes rock efficiency.
Therefore rock stratum construction guidance hole and free face first are done with hidden hole drilling, then are in time removed native stone disintegrating slag with chute forming machine, Then scar is cleaved with rushing stake machine, the ground-connecting-wall trenching construction suitable for various extremely hard inclined-plane rock stratum.

Claims (5)

1. a kind of construction method of hidden hole drilling cooperation impact drill continuous wall trench underground, which is characterized in that the construction method packet It includes:
Arrangement hole position step: marking out hole site to be drilled with by spray painting mode on leading wall, between every row hole site to be drilled Spacing is 500mm, and pitch-row is 1.5m between the hole site to be drilled marked led on wall, in a phase slot section two sides to extension It stretches 1m and carries out bore operation, in the second stage of slot section two sides away from progress bore operation at I-steel 1.25m;
Hidden hole drilling construction guidance hole step: constructor operates down-the-hole drill to appropriate location, according to sequence intermediate behind first two sides It constructs through row, by way of increasing air pressure to diamond drilling rod, creeps into rock stratum rapidly;
Hydraulic grab bucket grooving machine grab soil layer: constructor adjust hydraulic grab impact force and closing force with pick up strong-weathered rock with Upper each layer, constructor examine monitoring system, when X-axis or Y-axis either direction deviation are more than permissible value, are entangled immediately Partially, the hydraulic grab bucket grooving machine, which will paste, faces the wall of leading of foundation pit side and enters slot, and should fill into fresh mud in time, to maintain to lead in wall Mud liquid level stabilizing, the hydraulic grab bucket grooving machine to scar stops at once, and slot bottom is made to remain basically stable;
Rush stake machine and rush rock step: after the hydraulic grab bucket grooving machine fulfils assignment, constructor's operation rushes stake machine to rock position to be rushed, Pile monkey is 3.8t, is constantly impacted by pile monkey to scar, to change rock stratum internal structure, is allowed to crack occur, is Later period accelerates slotter construction and creates favorable conditions;
The clear bottom pore formation step of filter sand: constructor should carry out filter sand to slot section, diameter 15cm steel pipe is inserted into slot, away from bottom hole 0.3- 0.8m terminates rubber hose on steel pipe, and hose other end connects sand removing machine.
2. the construction method of hidden hole drilling cooperation impact drill continuous wall trench underground according to claim 1, it is characterised in that: The arrangement hole position step further include: when sipes section is 0.8m, constructor is with 3 row of quincuncial arrangement hole site to be drilled.
3. the construction method of hidden hole drilling cooperation impact drill continuous wall trench underground according to claim 2, it is characterised in that: Hidden hole drilling construction guidance hole step further include: impact drill rushes rock: constructor at least using 2 CJ80 impact drills rush rock at Hole outward should bore half of hole location, to guarantee diaphragm wall integrality in diaphragm wall rotation angle position more.
4. the construction method of hidden hole drilling cooperation impact drill continuous wall trench underground according to claim 1-3, Be characterized in that: the stake machine that rushes rushes rock step further include: after constructor, which at least completes 1 main aperture, rushes rock operation, adds silt Separator.
5. the construction method of hidden hole drilling cooperation impact drill continuous wall trench underground according to claim 4, it is characterised in that: The stake machine that rushes rushes rock step further include:
Slip consistency needs are arranged according to code requirement, to guarantee that rushing broken rock grain is suspended in slot;
Mud guarantees to recycle for 24 hours in slot, to prevent from being suspended in the sinking that slot rushes broken rock grain;
Scarfing cinder is carried out using preset time period, weldering is hammered into shape, rockfill or via hole works.
CN201810498268.0A 2018-05-23 2018-05-23 A kind of construction method of hidden hole drilling cooperation impact drill continuous wall trench underground Pending CN110528497A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810498268.0A CN110528497A (en) 2018-05-23 2018-05-23 A kind of construction method of hidden hole drilling cooperation impact drill continuous wall trench underground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810498268.0A CN110528497A (en) 2018-05-23 2018-05-23 A kind of construction method of hidden hole drilling cooperation impact drill continuous wall trench underground

Publications (1)

Publication Number Publication Date
CN110528497A true CN110528497A (en) 2019-12-03

Family

ID=68656320

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810498268.0A Pending CN110528497A (en) 2018-05-23 2018-05-23 A kind of construction method of hidden hole drilling cooperation impact drill continuous wall trench underground

Country Status (1)

Country Link
CN (1) CN110528497A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111608572A (en) * 2020-06-02 2020-09-01 甘肃五环公路工程有限公司 Down-the-hole drill and impact drill matched pile foundation pore-forming construction method
CN114086571A (en) * 2021-11-23 2022-02-25 上海远方基础工程有限公司 Rock entering grooving construction method by matching small-diameter down-the-hole hammer with groove milling machine

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892676A (en) * 2010-07-23 2010-11-24 中铁四局集团第五工程有限公司 Percussive drilling construction process for diaphragm wall passing through rock-filled layer in reclamation area
CN102797252A (en) * 2012-09-13 2012-11-28 中铁十二局集团第七工程有限公司 Construction method of underground continuous walls
CN103953027A (en) * 2014-04-22 2014-07-30 浙江省地质矿产工程公司 Method for constructing underground continuous wall in base rock
CN106381865A (en) * 2016-08-31 2017-02-08 徐州徐工基础工程机械有限公司 Drilling and milling combination construction method applicable to hard rock grooving

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892676A (en) * 2010-07-23 2010-11-24 中铁四局集团第五工程有限公司 Percussive drilling construction process for diaphragm wall passing through rock-filled layer in reclamation area
CN102797252A (en) * 2012-09-13 2012-11-28 中铁十二局集团第七工程有限公司 Construction method of underground continuous walls
CN103953027A (en) * 2014-04-22 2014-07-30 浙江省地质矿产工程公司 Method for constructing underground continuous wall in base rock
CN106381865A (en) * 2016-08-31 2017-02-08 徐州徐工基础工程机械有限公司 Drilling and milling combination construction method applicable to hard rock grooving

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
中铁二局股份有限公司: "《高速铁路施工技术 隧道工程分册》", 30 November 2013, 中国铁道出版社 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111608572A (en) * 2020-06-02 2020-09-01 甘肃五环公路工程有限公司 Down-the-hole drill and impact drill matched pile foundation pore-forming construction method
CN114086571A (en) * 2021-11-23 2022-02-25 上海远方基础工程有限公司 Rock entering grooving construction method by matching small-diameter down-the-hole hammer with groove milling machine

Similar Documents

Publication Publication Date Title
CN112554177B (en) Construction method of ultra-long small-diameter cast-in-situ bored pile
CN104947690B (en) Grooving construction method for embedding underground continuous wall into rock
CN110528498A (en) A kind of construction method of the continuous wall trench underground of granite geology
CN103046931B (en) Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
CN104264689B (en) The construction method that grooving, pore-forming and large diameter pile are replaced by multiple Small Diameter Pile
CN110158582A (en) A method of trestle steel pipe pile is set on intectate riverbed
CN102654056A (en) Shield construction method for clearing obstacles by punching rock stratum section
CN105155516B (en) The method of construction drill bored concrete pile before making an overall screening underground obstacle
CN203584301U (en) Hole guide equipment
CN106194193A (en) The auxiliary excavation method of a kind of group hole, big cross section vertical shaft non-explosion large aperture
CN104047542A (en) Pipe hammer system of percussion drill for rock-socketed inclined pile and impact construction method of rock-socketed inclined pile
CN203114170U (en) In-hole hammer drilling embedding rock-socketed prestressed pipe pile device
CN110528497A (en) A kind of construction method of hidden hole drilling cooperation impact drill continuous wall trench underground
CN208121835U (en) Inclined building correcting and then reinforcing structure
CN105862862A (en) Salvage method for large-diameter pile buried hammer
CN101055047A (en) A process for horizontal directional drill passing through and tampering casing for separating gravel
CN102561944A (en) Porous occlusive pile drilling machine and construction technology thereof
CN108005659B (en) A kind of diving excavation construction method for the construction of city vertical shaft
CN109630179A (en) The permanent fore shaft of return air shafts and wind cave piling wall combined construction method
CN104763332A (en) Percussive-rotary drilling method and system for horizontal directional drilling crossing
CN110805307A (en) Underground continuous wall removing method
CN113026688B (en) System for expanding piles to form wall by using foundation rocks at bottom of concrete guide wall foundation
CN113373915B (en) Method for reinforcing steel column pile structure
CN214832833U (en) Open caisson mechanical construction device penetrating rock stratum
CN113006010B (en) Method for reinforcing concrete guide wall foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191203

RJ01 Rejection of invention patent application after publication