CN110469132A CN201910698053.8A CN201910698053A CN110469132A CN 110469132 A CN110469132 A CN 110469132A CN 201910698053 A CN201910698053 A CN 201910698053A CN 110469132 A CN110469132 A CN 110469132A
Authority
CN
China
Prior art keywords
air filter
spool
dust
foundation pit
bogie
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910698053.8A
Other languages
Chinese (zh)
Other versions
CN110469132B (en
Inventor
张桂军
陈健
徐秋明
陈许兵
车二平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201910698053.8A priority Critical patent/CN110469132B/en
Publication of CN110469132A publication Critical patent/CN110469132A/en
Application granted granted Critical
Publication of CN110469132B publication Critical patent/CN110469132B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/242Safety or protective measures preventing damage to building parts or finishing work during construction for temporarily covering the whole worksite, e.g. building, trench

Abstract

The present invention relates to the pit earthwork operation dust-proof sheds that one kind can roll unlatching, comprising: the support post of foundation pit two sides is set to along the length direction of foundation pit;The first Air Filter spool set on foundation pit side is wound with the first Air Filter on the first Air Filter spool;The bogie being located relatively above foundation pit, bogie are set between column supported on both sides, and the free end of the first Air Filter is by being pierced by and being fixed on bogie in the first Air Filter spool;Second Air Filter spool is wound with the second Air Filter on the second Air Filter spool;Drawstring, one end of drawstring are lain on the second Air Filter spool;And fixed card buckle, the both ends of fixed card buckle are around on drawstring and the Air Filter bracket that is plugged on the second Air Filter.Surround by the first Air Filter and the second Air Filter dust-proof booth structure forming semiclosed shape, dust can be effectively suppressed drifting in the present invention, above-mentioned dust-proof booth structure has the characteristics that structure is simple, install convenient.

Description

A kind of pit earthwork operation dust-proof shed rolling unlatching
Technical field
The present invention relates to a kind of dust-proof sheds, more particularly to a kind of pit earthwork operation dust-proof shed that can roll unlatching.
Background technique
Currently, either building construction or underground pipe gallery, town road and underground pipe network pipeline construction require Earthwork is carried out, when earthwork can generate a large amount of particle and dust, cause environmental pollution, endanger surrounding resident, especially It is northern dry weather, the cubic metre of earth and stone can all cause sandstone material dust to wave in air during excavation, backfill or stirring, sternly Ghost image rings air quality.
When earthwork, scene needs in operating area using sprinkling truck, fog gun, the spraying spray system of foundation pit periphery setting It unites and continues depositing dust, but often due to foundation pit working area is big, spread of spray is difficult to cover among foundation pit, this imitates dust controlling Fruit is poor, and building site PM2.5 cannot be effectively reduced and be punished by environment supervision department.
To avoid dust polluting environment, it is necessary to research and develop new dust guard.
Summary of the invention
In view of the above-mentioned problems, now providing, a kind of structure is simple, the pit earthwork operation for rolling unlatching of install convenient is used Dust-proof shed.
Specific technical solution is as follows:
A kind of pit earthwork operation dust-proof shed rolling unlatching, has the feature that, comprising:
The support post of foundation pit two sides is set to along the length direction of foundation pit;
The first Air Filter spool set on foundation pit side, the first Air Filter spool is between column supported on both sides, and first The first Air Filter is wound on Air Filter spool;
The bogie being located relatively above foundation pit, bogie is set between column supported on both sides, and bogie can be along foundation pit Length direction reciprocatingly slide, the free end of the first Air Filter in the first Air Filter spool by being pierced by and upwardly extending and be fixed on On bogie;
Second Air Filter spool, the second Air Filter spool are correspondingly arranged between left and right adjacent support post, and second is anti- The second Air Filter is wound on dirt net volume axis, the free end of the second Air Filter is by being pierced by and extending downwardly in the second Air Filter spool Above to earth's surface;
Drawstring, one end of drawstring are lain on the second Air Filter spool, and the other end extends and connects downwards along Air Filter In in weighted spherical ball;And
Fixed card buckle, the Air Filter bracket that the both ends of fixed card buckle bypass drawstring and are plugged on the second Air Filter On.
Above-mentioned pit earthwork operation dust-proof shed, also has the feature that, dust-proof shed further include: drive roll, driven Roller is sheathed on the first transmission belt, driving motor and the second transmission belt between drive roll and driven voller along the length direction of foundation pit, Drive roll and driven voller are rotationally connected on column supported on both sides, and the corresponding two sides first that are fixedly connected in both ends of bogie pass Dynamic to take, drive roll is sequentially connected by the output shaft of the second transmission belt and driving motor.
Above-mentioned pit earthwork operation dust-proof shed also has the feature that, dust-proof shed further includes fixed bracket, fixed Branch is set up on support post, and the both ends correspondence of the second Air Filter spool is hung between fixed bracket.
Above-mentioned pit earthwork operation dust-proof shed also has the feature that, left and right adjacent support post is equipped with More horizontal girds.
The beneficial effect of above scheme is:
Surrounded in the present invention by the first Air Filter and the second Air Filter to be formed semiclosed shape, dust can be effectively suppressed float Scattered dust-proof booth structure, above-mentioned dust-proof booth structure have the characteristics that structure is simple, install convenient.
Detailed description of the invention
Fig. 1 is the overall structure diagram of the pit earthwork operation dust-proof shed provided in the embodiment of the present invention;
Fig. 2 is the first partial structural schematic diagram of the pit earthwork operation dust-proof shed provided in the embodiment of the present invention;
Fig. 3 is the second partial structural diagram of the pit earthwork operation dust-proof shed provided in the embodiment of the present invention.
In attached drawing: 1, support post;2, the first Air Filter;3, bogie;4, the second Air Filter spool;5, second is dust-proof Net;6, drawstring;7, weighted spherical ball;8, fixed card buckle;9, Air Filter bracket;10, drive roll;11, driven voller;12, the first conveyer belt; 13, the second transmission belt;14, fixed bracket;15, box body.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art without creative labor it is obtained it is all its His embodiment, shall fall within the protection scope of the present invention.
It should be noted that in the absence of conflict, the feature in embodiment and embodiment in the present invention can phase Mutually combination.
The present invention will be further explained below with reference to the attached drawings and specific examples, but not as the limitation of the invention.
As shown in Figure 1 to Figure 3, the pit earthwork operation dust-proof shed provided in the embodiment of the present invention, comprising: along foundation pit Length direction be set to the support posts 1 of foundation pit two sides, left and right adjacent support post 1 be equipped with more horizontal girds 15 (with Enhance dust-proof shed overall structural strength);The first Air Filter spool set on foundation pit side, it is collateral that the first Air Filter spool is located at two It supports between column 1, the first Air Filter 2 is wound on the first Air Filter spool;The bogie 3 being located relatively above foundation pit, driving Frame 3 is set between column 1 supported on both sides, and bogie 3 can reciprocatingly slide along the length direction of foundation pit, the first Air Filter 2 from By holding by being pierced by and upwardly extending in the first Air Filter spool and be fixed on bogie 3;Second Air Filter spool 4, second is anti- Dirt net volume axis 4 is correspondingly arranged between left and right adjacent support post 1, and is wound with the second Air Filter on the second Air Filter spool 4 5, the free end of the second Air Filter 5 in the second Air Filter spool 4 by being pierced by and extending downward into above earth's surface;Drawstring 6, drawstring 6 One end lie on the second Air Filter spool 4, the other end extends downwards along Air Filter and is connected in weighted spherical ball 7;And Fixed card buckle 8, the both ends of fixed card buckle 8 around drawstring 6 and the Air Filter bracket 9 that is plugged on the second Air Filter 5 (thereon The settable spliced eye matched with 8 both ends of fixed card buckle) on.
Roll type Window curtain structure is used for reference in the present invention, utilizes the be wound in the first Air Filter spool (not shown) One Air Filter 2 and the second Air Filter 5 being wound on the second Air Filter spool 4 surround to form one with opening (so that machinery is set It is standby into and out of in the present invention the second Air Filter spool 4 and the second Air Filter 5 can also be used for reference with above-mentioned opening after construction The corresponding Air Filter of structure setting, with when constructing gap to foundation pit realize it is totally-enclosed) the dust-proof booth structure of semiclosed shape, with effective Waving for sandstone material is prevented, and then effectively solves air quality problems because caused by waving it.
The second Air Filter 5 is effectively limited by drawstring 6 and weighted spherical ball 7 in the present invention, it is avoided to put because of factors such as winds It is dynamic;In the present invention drawstring 6 and weighted spherical ball 7 can be limited by the cooperation of fixed card buckle 8 and Air Filter bracket 9.
To avoid the damage to the first Air Filter spool and driving motor such as soil block at construction environment, sandstone in the present invention, Therefore the first Air Filter spool and driving motor are built in box body 15.
To reduce interference of the Air Filter to construction machinery in the present invention, thus the first Air Filter 2 is designed to as above open Formula structure is opened, specifically, dust-proof shed further includes drive roll 10, driven voller 11, is sheathed on along the length direction of foundation pit in the present invention The first transmission belt 12, driving motor and the second transmission belt 13 between drive roll 10 and driven voller 11, the present invention in drive roll 10 And driven voller 11 is rotationally connected on column 1 supported on both sides, and the corresponding two sides first that are fixedly connected in both ends of bogie 3 are driven On band 12, drive roll 10 is sequentially connected by the second transmission belt 13 and the output shaft of driving motor (not shown), the present invention In by the forward and backward mobile forward and backward movement for driving 2 free end of the first Air Filter of the first transmission belt 12, to realize dust-proof ceiling The unlatching in portion, closure.When carrying out earth's surface construction early period, the first Air Filter 2 can be in open state in the present invention, continues when the later period The first Air Filter 2 can be closed when foundation pit operation.
Specifically, dust-proof shed further includes fixed bracket 14 in the present invention, bracket 14 is fixed in the present invention, and to hang on support vertical On column 1, the both ends of the second Air Filter spool 4 correspondence is hung between fixed bracket 14, in the present invention using fixed bracket 14 with Realize the rotation of the second Air Filter spool 4 and by the second Air Filter spool 4 rotation realize the second Air Filter 5 it is quick receive, It puts.
First Air Filter spool in dust-proof shed provided by the invention, the second Air Filter spool 4, fixed pulling rope 6 correlation set Meter is so that dust-proof shed has the advantages that quick for installation, structure detachably recycles in the present invention.
The above is only preferred embodiments of the present invention, are not intended to limit the implementation manners and the protection scope of the present invention, right For those skilled in the art, it should can appreciate that and all replace with being equal made by description of the invention and diagramatic content It changes and obviously changes obtained scheme, should all be included within the scope of the present invention.

Claims (4)

1. the pit earthwork operation dust-proof shed that one kind can roll unlatching characterized by comprising
The support post (1) of foundation pit two sides is set to along the length direction of foundation pit;
The first Air Filter spool set on the foundation pit side, the first Air Filter spool are located at support post described in two sides (1) between, the first Air Filter (2) are wound on the first Air Filter spool;
The bogie (3) being located relatively above the foundation pit, the bogie (3) are set between support post (1) described in two sides, And the bogie (3) can reciprocatingly slide along the length direction of the foundation pit, the free end of first Air Filter (2) is by described It is pierced by first Air Filter spool and upwardly extends and be fixed on the bogie (3);
Second Air Filter spool (4), the second Air Filter spool (4) are correspondingly arranged at the left and right adjacent support post (1) Between, and be wound with the second Air Filter (5) on the second Air Filter spool (4), the free end of second Air Filter (5) by It is pierced by and is extended downward into above earth's surface in the second Air Filter spool (4);
Drawstring (6), one end of the drawstring (6) are lain on the second Air Filter spool (4), the other end along Air Filter towards Lower extension is simultaneously connected on weighted spherical ball (7);And
The both ends of fixed card buckle (8), the fixed card buckle (8) around the drawstring (6) and are plugged in dust-proof positioned at described second On Air Filter bracket (9) on net (5).
2. pit earthwork operation dust-proof shed according to claim 1, which is characterized in that the dust-proof shed further include: main Dynamic roller (10), driven voller (11) are sheathed on the drive roll (10) and the driven voller (11) along the length direction of the foundation pit Between the first transmission belt (12), driving motor and the second transmission belt (13), the drive roll (10) and the driven voller (11) It is rotationally connected on support post described in two sides (1), and the both ends of the bogie (3) corresponding are fixedly connected on described in two sides the On one transmission belt (12), the drive roll (10) is driven by the output shaft of second transmission belt (13) and the driving motor Connection.
3. pit earthwork operation dust-proof shed according to claim 1, which is characterized in that the dust-proof shed further includes fixing Bracket (14), the fixed bracket (14) are set on the support post (1), the both ends pair of the second Air Filter spool (4) It should hang between the fixed bracket (14).
4. pit earthwork operation dust-proof shed according to claim 1-3, which is characterized in that left and right adjacent The support post (1) is equipped with more horizontal girds (15).
CN201910698053.8A 2019-07-31 2019-07-31 Foundation ditch earthwork operation that can roll and open is with dustproof canopy Active CN110469132B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910698053.8A CN110469132B (en) 2019-07-31 2019-07-31 Foundation ditch earthwork operation that can roll and open is with dustproof canopy

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910698053.8A CN110469132B (en) 2019-07-31 2019-07-31 Foundation ditch earthwork operation that can roll and open is with dustproof canopy

Publications (2)

Publication Number Publication Date
CN110469132A true CN110469132A (en) 2019-11-19
CN110469132B CN110469132B (en) 2021-01-19

Family

ID=68509920

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910698053.8A Active CN110469132B (en) 2019-07-31 2019-07-31 Foundation ditch earthwork operation that can roll and open is with dustproof canopy

Country Status (1)

Country Link
CN (1) CN110469132B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112495081A (en) * 2020-11-13 2021-03-16 郑州大学第一附属医院 Dustproof effectual building foundation ditch dustproof system
CN112933805A (en) * 2021-01-26 2021-06-11 新十建设集团有限公司 Building site dust device
CN113431197A (en) * 2021-06-24 2021-09-24 山西建投五岳建设工程有限公司 Movable combined type canopy and construction method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203145483U (en) * 2013-03-25 2013-08-21 歌山建设集团有限公司 Construction site construction dustproof screen device
CN205743051U (en) * 2016-05-09 2016-11-30 陈好学 A kind of construction site construction dust screen apparatus possessing Simple sliding function
CN208586925U (en) * 2018-07-09 2019-03-08 中建八局第一建设有限公司 It is a kind of reusable convenient for the dust-proof protection canopy of Single-person operation type sand basin

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203145483U (en) * 2013-03-25 2013-08-21 歌山建设集团有限公司 Construction site construction dustproof screen device
CN205743051U (en) * 2016-05-09 2016-11-30 陈好学 A kind of construction site construction dust screen apparatus possessing Simple sliding function
CN208586925U (en) * 2018-07-09 2019-03-08 中建八局第一建设有限公司 It is a kind of reusable convenient for the dust-proof protection canopy of Single-person operation type sand basin

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112495081A (en) * 2020-11-13 2021-03-16 郑州大学第一附属医院 Dustproof effectual building foundation ditch dustproof system
CN112495081B (en) * 2020-11-13 2023-11-07 郑州大学第一附属医院 Building foundation pit dustproof system with good dustproof effect
CN112933805A (en) * 2021-01-26 2021-06-11 新十建设集团有限公司 Building site dust device
CN113431197A (en) * 2021-06-24 2021-09-24 山西建投五岳建设工程有限公司 Movable combined type canopy and construction method thereof

Also Published As

Publication number Publication date
CN110469132B (en) 2021-01-19

Similar Documents

Publication Publication Date Title
CN110469132A (en) A kind of pit earthwork operation dust-proof shed rolling unlatching
CN111705807A (en) Dust settling system for excavation construction of urban long and narrow type support-free deep foundation pit
CN104567294A (en) Aerial suspension airing device for materials
CN107178226A (en) The whole self-propelled totally-enclosed green construction enclosing of formula and its construction method
CN214832708U (en) Full-automatic movable subway foundation pit protection greenhouse
CN107376550A (en) Movable spraying system and its spraying method
CN206917351U (en) The whole self-propelled totally-enclosed green construction enclosing of formula
CN208897847U (en) One kind pushing and pulling closed atomizing refuse depot entirely
CN212105396U (en) Guardrail with shielding effect
CN215882077U (en) Civil engineering building is with muddy earth agitating unit of unloading of being convenient for
CN214303184U (en) Wire netting for afforestation
CN207363315U (en) Ecological container
CN214460543U (en) Foundation pit protection shed
CN220458092U (en) Telescopic rain shelter
CN210782246U (en) Greenhouse warm in winter
CN209873935U (en) Building surface rainwater collection device in garden
CN213205201U (en) Security protection device is used in construction management construction
CN214972733U (en) Construction site raise dust spraying system
CN216553141U (en) Dustproof canopy device
CN217053375U (en) A folding dust screen for foundation ditch construction
CN212801876U (en) Tunnel water drainage structures of preventing
CN215555262U (en) Silt storage device for construction
CN215406073U (en) Deep foundation pit construction dust keeper
CN116047027B (en) Indoor simulation planting experimental device and method for high-steep rock slope
CN220386156U (en) Civil engineering construction dust fall equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant