CN110469036A - A kind of furred ceiling and its construction method - Google Patents

A kind of furred ceiling and its construction method Download PDF

Info

Publication number
CN110469036A
CN110469036A CN201910796341.7A CN201910796341A CN110469036A CN 110469036 A CN110469036 A CN 110469036A CN 201910796341 A CN201910796341 A CN 201910796341A CN 110469036 A CN110469036 A CN 110469036A
Authority
CN
China
Prior art keywords
plate
ceiling
maintenance
board
velar plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910796341.7A
Other languages
Chinese (zh)
Inventor
刘志森
刘铁锌
王聪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING HONGJIAN ENGINEERING Co Ltd
Original Assignee
BEIJING HONGJIAN ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING HONGJIAN ENGINEERING Co Ltd filed Critical BEIJING HONGJIAN ENGINEERING Co Ltd
Priority to CN201910796341.7A priority Critical patent/CN110469036A/en
Publication of CN110469036A publication Critical patent/CN110469036A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/22Connection of slabs, panels, sheets or the like to the supporting construction
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F19/00Other details of constructional parts for finishing work on buildings
    • E04F19/08Built-in cupboards; Masks of niches; Covers of holes enabling access to installations

Abstract

The present invention relates to building decoration and fitment technical field more particularly to the construction methods of a kind of furred ceiling and the furred ceiling.The furred ceiling includes ceiling board, access hole is offered on ceiling board, maintenance velar plate is covered on access hole, wherein a side is provided with protrusion to maintenance velar plate, and the setting of access hole a side is fluted, and protrusion cooperates with groove, other three side for overhauling velar plate is pingbian, lapping plate is provided at the top of maintenance velar plate, and lapping plate and ceiling board overlap, and velar plate is concordant with ceiling board is arranged for maintenance.Lapping plate can make maintenance velar plate concordant with ceiling board with protrusion mutual cooperation, therefore after the completion of installation of ceiling, maintenance velar plate can be hidden, guarantee the globality and aesthetics of furred ceiling, ceiling construction process provided in the present invention, construction technology can be simplified, suspended ceiling overhauling port can be optimized, guarantee finishing furred ceiling effect.Finishing material can also be saved simultaneously, reduce maintenance cost.

Description

A kind of furred ceiling and its construction method
Technical field
The present invention relates to building decoration and fitment technical field more particularly to the construction methods of a kind of furred ceiling and the furred ceiling.
Background technique
Existing PVC furred ceiling is mostly to be blocked by monolith PVC board realization to top, at the top of house when something goes wrong It needs to dismantle the furred ceiling of monolith, causes the problem of subsequent maintenance inconvenience, to solve the above-mentioned problems, usually adopt in work progress It is solved with suspended ceiling overhauling port is opened up, and suspended ceiling overhauling port has become essential construction content in furred ceiling engineering. Since toilet pipeline valve is more, it is therefore necessary to access hole be arranged convenient for later period maintenance, traditional access hole considers that aesthetics is made At required higher cost, need using edge strip and individual cover board.Moreover, if valve location dispersion at the top of toilet, needs to stay Multiple access holes are set, are influenced instead beautiful.
Therefore, a kind of furred ceiling is needed, to solve the above technical problems.
Summary of the invention
It is an object of the invention to propose a kind of furred ceiling, suspended ceiling overhauling port can be hidden, improve the aesthetic measure of furred ceiling.
To achieve this purpose, the present invention adopts the following technical scheme:
A kind of furred ceiling, including ceiling board are provided, access hole is offered on the ceiling board, inspection is covered on the access hole Velar plate is repaired, wherein a side is provided with protrusion to the maintenance velar plate, and access hole a side setting is fluted, described convex It rises and cooperates with the groove, other three side of the maintenance velar plate is pingbian, is provided with overlap joint at the top of the maintenance velar plate Plate, the lapping plate and the ceiling board overlap, and the maintenance velar plate is concordant with the ceiling board to be arranged.
As a kind of optimal technical scheme of above-mentioned furred ceiling, the ceiling board includes more PVC that are parallel and being bonded to each other Plate.
As a kind of optimal technical scheme of above-mentioned furred ceiling, it is described maintenance velar plate include grafting setting the first cover board and Second cover board, first cover board and the PVC board plug connection, second cover board and the PVC pass through the lapping plate Overlap joint.
As a kind of optimal technical scheme of above-mentioned furred ceiling, two lapping plates are symmetrically set to the maintenance lid At the top of plate.
As a kind of optimal technical scheme of above-mentioned furred ceiling, the lapping plate stretches out the length of the access hole deck side edge Greater than the distance between the side and the access hole.
As a kind of optimal technical scheme of above-mentioned furred ceiling, the lapping plate is by glue in the maintenance velar plate Top.
As a kind of optimal technical scheme of above-mentioned furred ceiling, the maintenance velar plate is square structure, the access hole Cover board length is twice or three times of PVC board width.
As a kind of optimal technical scheme of above-mentioned furred ceiling, the thickness of the maintenance velar plate and the thickness of the ceiling board It is identical.
The invention also provides a kind of ceiling construction methods, and for installing to furred ceiling described above, feature exists In including the following steps:
Before ceiling board installation, square access hole is opened up in maintenance position;
The clout opened up under square access hole cutting is processed into maintenance velar plate;
Maintenance velar plate is connect with lapping plate;
After ceiling board installation, velar plate will be overhauled and protruded into access hole with one end of lapping plate, the other end is inserted into groove It is interior and mobile to groove direction;
After the protrusion of maintenance velar plate is bonded completely with groove, lapping plate is overlapped in the top of the ceiling board.
The invention has the advantages that:
Furred ceiling provided in the present invention, since protrusion is arranged in the one side wall of maintenance velar plate, the relative side of access hole is set It is equipped with groove, groove and male cooperation, maintenance velar plate can be made to connect with ceiling board, and due to setting at the top of maintenance velar plate There is lapping plate, overlapped at the top of lapping plate and ceiling board, lapping plate and protrusion mutual cooperation can make to overhaul velar plate and ceiling board Concordantly, therefore after the completion of installation of ceiling, maintenance velar plate can be hidden, guarantees the globality and aesthetics of furred ceiling, that is, uses It is overall beautiful that existing multiple access holes will not influence furred ceiling.
Ceiling construction process provided in the present invention can simplify construction technology, and carry out when fluting on ground, Neng Goubao The safety for demonstrate,proving construction personnel, since maintenance velar plate is process by the clout after opening up access hole cutting, and can be excellent While changing suspended ceiling overhauling port, cost is reduced, guarantees finishing furred ceiling effect.Finishing material can also be saved simultaneously, reduce the later period Maintenance cost.
Detailed description of the invention
Fig. 1 is the cross-sectional view of furred ceiling provided in an embodiment of the present invention;
Fig. 2 is partial enlarged view at A in Fig. 1;
Fig. 3 is the top view of furred ceiling provided in an embodiment of the present invention.
In figure:
1, ceiling board;11, PVC board;2, velar plate is overhauled;21, the first cover board;22, the second cover board;3, lapping plate;4, recessed Slot;5, raised.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawings and examples.It is understood that this place is retouched The specific embodiment stated is used only for explaining the present invention rather than limiting the invention.It also should be noted that in order to just Only the parts related to the present invention are shown in description, attached drawing rather than entire infrastructure.
In the description of the present invention unless specifically defined or limited otherwise, term " connected ", " connection ", " fixation " are answered It is interpreted broadly, for example, it may be being fixedly connected, may be a detachable connection, or is integral;It can be mechanical connection, It can be electrical connection;It can be directly connected, the company inside two elements can also be can be indirectly connected through an intermediary Logical or two elements interaction relationship.For the ordinary skill in the art, can be understood with concrete condition above-mentioned The concrete meaning of term in the present invention.
In the present invention unless specifically defined or limited otherwise, fisrt feature second feature "upper" or "lower" It may include that the first and second features directly contact, also may include that the first and second features are not direct contacts but pass through it Between other characterisation contact.Moreover, fisrt feature includes the first spy above the second feature " above ", " above " and " above " Sign is right above second feature and oblique upper, or is merely representative of first feature horizontal height higher than second feature.Fisrt feature exists Second feature " under ", " lower section " and " following " include that fisrt feature is directly below and diagonally below the second feature, or is merely representative of First feature horizontal height is less than second feature.
In the description of the present embodiment, term " on ", "lower", " right side ", etc. orientation or positional relationships be based on shown in attached drawing Orientation or positional relationship, be merely for convenience of description and simplification operation, rather than the device or element of indication or suggestion meaning It must have a particular orientation, be constructed and operated in a specific orientation, therefore be not considered as limiting the invention.In addition, Term " first ", " second " are only used to distinguish between description, and have no special meaning.
A kind of furred ceiling is provided in the present embodiment, which can block access hole, and make to overhaul velar plate 2 and furred ceiling Plate 1 is coplanar with, and makes to overhaul the state that velar plate 2 is in hiding.Make user when in use, though there are more access holes all It is not easy to be found, improves the aesthetic measure of the furred ceiling.The furred ceiling is applicable to arrange line equipment and right under ceiling board 1 In the furred ceiling room that beauty requires, such as toilet, kitchen or boiled water room or laundry.
Specifically, as shown in Figure 1-3, the furred ceiling includes ceiling board 1, access hole is offered on ceiling board 1, is covered on access hole It is stamped maintenance velar plate 2, wherein a side is provided with protrusion 5, access hole a side setting fluted 4, protrusion to maintenance velar plate 2 5 with groove 4 cooperate, maintenance velar plate 2 other three side be pingbian, maintenance velar plate 2 on, with protrusion 5 relative side with The distance for the access hole side that the side is oppositely arranged is greater than raised 5 length, overhauls and is provided with lapping plate 3 at the top of velar plate 2, takes Fishplate bar 3 and ceiling board 1 overlap, the setting concordant with ceiling board 1 of maintenance velar plate 2.The access hole being wherein arranged on ceiling board 1 according to It needs to be arranged, access hole setting conveniently can be checked artificially in valve or conduit fittings.
The furred ceiling provided in the present embodiment, due to the one side wall setting protrusion 5 of maintenance velar plate 2, the opposite side of access hole Side setting fluted 4, groove 4 and protrusion 5 cooperate, and maintenance velar plate 2 can be made to connect with ceiling board 1, and due to overhauling lid It is provided with lapping plate 3 at the top of plate 2, is overlapped at the top of lapping plate 3 and ceiling board 1, lapping plate 3 cooperates with protrusion 5 can make to examine It is concordant with ceiling board 1 to repair velar plate 2, therefore after the completion of installation of ceiling, maintenance velar plate 2 can be hidden, guarantee the whole of furred ceiling Body and aesthetics, it is overall beautiful there are multiple access holes will not to influence furred ceiling.
In the present embodiment, for the ease of installing and being arranged access hole, ceiling board 1 includes more in parallel and is bonded to each other PVC board 11.Installation personnel can according to need directly at the scene carry out access hole open-work, while can also ground into Row cutting forms access hole, guarantees the safety of installation personnel.
Preferably, as shown in Figures 2 and 3, maintenance velar plate 2 includes the first cover board 21 and the second cover board of grafting setting 22,11 plug connection of the first cover board 21 and PVC board, 21 one end of the first cover board is arranged fluted 4, and the other end is provided with protrusion 5, and Second cover board 22 is overlapped with another PVC board 11 by lapping plate 3, and 22 one end of the second cover board is provided with protrusion 5, and the other end is flat Side.The protrusion 5 of first cover board 21 is inserted into the groove 4 of access hole.The protrusion 5 of second cover board 22 is inserted into first In the groove 4 of cover board 21, the grafting of the first cover board 21 and the second cover board 22 is realized.This kind setting can guarantee to overhaul velar plate 2 It is arranged in access hole 4.
Preferably, maintenance velar plate 2 is square structure, maintenance 2 length of velar plate be twice of 11 width of PVC board or Three times.Family is able to use according to situation about observed inside furred ceiling in time, guarantee there are the enough families in enough spaces to be overhauled.It should Secondary use can be carried out to the PVC board 11 cut at access hole by overhauling velar plate 2, be added to the PVC board 11 cut Work obtains maintenance velar plate 2, makes full use of existing raw material, reduces furred ceiling cost, naturally it is also possible to customize again.
Specifically, deviate from access hole in order to make maintenance velar plate 2 not sink after mounting, taken in the present embodiment Fishplate bar 3 is set as no less than two, while lapping plate 3 is uniformly distributed in the top of maintenance velar plate 2, lapping plate in the present embodiment 3 be two, and when lapping plate 3 is two, two lapping plates 3 are symmetrically set to 2 top of maintenance velar plate.In addition, in order to anti- Only maintenance velar plate 2 is insecure after installing, and in the present embodiment, the length that lapping plate 3 stretches out maintenance 2 side of velar plate is greater than the side The distance between side and access hole.It is 10cm, lapping plate 3 that lapping plate 3, which stretches out the length of maintenance 2 side of velar plate, in the present embodiment Height be chosen as 2cm, width is chosen as 3cm.
In the present embodiment, for the ease of installation, lapping plate 3 is by glue at the top of maintenance velar plate 2.It certainly can also Being installed on lapping plate 3 by way of screw fixation on maintenance velar plate 2.
It is coplanar between velar plate 2 and ceiling board 1 in order to guarantee to overhaul, prevent maintenance velar plate 2 from protruding ceiling board 1, this reality The thickness for applying maintenance velar plate 2 in example is identical as the thickness of ceiling board 1.Between maintenance velar plate 2 and ceiling board 1 after making installation It is coplanar.The aesthetic feeling for guaranteeing furred ceiling hides maintenance velar plate 2.
A kind of ceiling construction method is additionally provided in the present embodiment, for pacifying to the furred ceiling provided in the present embodiment Dress, includes the following steps:
Before S1, ceiling board 1 are installed, square access hole is opened up in maintenance position;
S2, the clout opened up under square access hole cutting is processed into maintenance velar plate 2;
S3, maintenance velar plate 2 are connect with lapping plate 3;
After S4, ceiling board 1 are installed, velar plate 2 will be overhauled and protruded into access hole with one end of lapping plate 3, the other end is inserted Enter in groove 4 and mobile to 4 direction of groove;
After S5, the protrusion 5 for overhauling velar plate 2 are bonded completely with groove 4, lapping plate 3 is overlapped in the top of ceiling board 1.
When the dismounting of velar plate 2 will be overhauled by needing, it is contrary in groove 4 along being inserted into protrusion 5 that velar plate 2 will be overhauled Direction push, make protrusion 5 with groove 4 be detached from, then by overhaul velar plate 2 protrusion 5 pull downward on, so that realizing will overlap Plate 3 and ceiling board 1 are detached from, and realize the purpose removed to maintenance velar plate 2.
The ceiling construction process provided in the present embodiment can simplify construction technology, and carry out when fluting on ground, can The safety for guaranteeing construction personnel, since maintenance velar plate 2 is process by the clout after opening up access hole cutting, and can be While optimizing suspended ceiling overhauling port, cost is reduced, guarantees finishing furred ceiling effect.Finishing material can also be saved simultaneously, after reduction Phase maintenance cost.
In addition, the above is only a better embodiment of the present invention and the applied technical principle.It will be appreciated by those skilled in the art that The invention is not limited to the specific embodiments described herein, be able to carry out for a person skilled in the art it is various it is apparent variation, It readjusts and substitutes without departing from protection scope of the present invention.Therefore, although being carried out by above embodiments to the present invention It is described in further detail, but the present invention is not limited to the above embodiments only, without departing from the inventive concept, also It may include more other equivalent embodiments, and the scope of the invention is determined by the scope of the appended claims.

Claims (9)

1. a kind of furred ceiling, which is characterized in that including ceiling board (1), offer access hole, the maintenance on the ceiling board (1) Maintenance velar plate (2) is covered on mouthful, wherein a side is provided with raised (5), the access hole one to the maintenance velar plate (2) Fluted (4) are arranged in side, and the protrusion (5) and the groove (4) cooperate, and other three side of maintenance velar plate (2) is Pingbian, maintenance velar plate (2) top are provided with lapping plate (3), and the lapping plate (3) and the ceiling board (1) overlap, institute State maintenance velar plate (2) setting concordant with the ceiling board (1).
2. furred ceiling according to claim 1, which is characterized in that the ceiling board (1) includes more in parallel and is bonded to each other PVC board (11).
3. furred ceiling according to claim 2, which is characterized in that maintenance velar plate (2) includes the first of grafting setting Cover board (21) and the second cover board (22), first cover board (21) and the PVC board (11) plug connection, second cover board (22) it is overlapped with another PVC board (11) by the lapping plate (3).
4. furred ceiling according to claim 1, which is characterized in that two lapping plates (3) are symmetrically set to the inspection It repairs at the top of velar plate (2).
5. furred ceiling according to claim 1, which is characterized in that the lapping plate (3) stretches out maintenance velar plate (2) side The length on side is greater than the distance between the side and the access hole.
6. furred ceiling according to claim 1, which is characterized in that the lapping plate (3) is by glue in the access hole The top of cover board (2).
7. furred ceiling according to claim 6, which is characterized in that the maintenance velar plate (2) is square structure, the inspection Repair twice or three times that velar plate (2) length is PVC board (11) width.
8. furred ceiling according to claim 1, which is characterized in that the thickness and the ceiling board of maintenance velar plate (2) (1) thickness is identical.
9. a kind of ceiling construction method, for being installed to the described in any item furred ceilings of claim 1-8, which is characterized in that Include the following steps:
Before ceiling board (1) installation, square access hole is opened up in maintenance position;
The clout opened up under square access hole cutting is processed into maintenance velar plate (2);
Maintenance velar plate (2) is connect with lapping plate (3);
After ceiling board (1) installation, velar plate (2) will be overhauled and protruded into access hole with the one end of lapping plate (3), other end insertion It is in groove (4) and mobile to groove (4) direction;
After the protrusion (5) of maintenance velar plate (2) is bonded completely with groove (4), lapping plate (3) is overlapped in the ceiling board (1) Top.
CN201910796341.7A 2019-08-27 2019-08-27 A kind of furred ceiling and its construction method Pending CN110469036A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910796341.7A CN110469036A (en) 2019-08-27 2019-08-27 A kind of furred ceiling and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910796341.7A CN110469036A (en) 2019-08-27 2019-08-27 A kind of furred ceiling and its construction method

Publications (1)

Publication Number Publication Date
CN110469036A true CN110469036A (en) 2019-11-19

Family

ID=68513019

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910796341.7A Pending CN110469036A (en) 2019-08-27 2019-08-27 A kind of furred ceiling and its construction method

Country Status (1)

Country Link
CN (1) CN110469036A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006028968A (en) * 2004-07-20 2006-02-02 Izu Mokuzai Ichiba:Kk Paulownia member for house
CN104481102A (en) * 2014-11-06 2015-04-01 安徽鸿路钢结构(集团)股份有限公司 Heat preserving and environmentally-friendly decorative board for external wall
CN205840105U (en) * 2016-06-30 2016-12-28 上海志豪实业有限公司 The steel joist suspended ceiling of keel piece can be hidden
CN106760414A (en) * 2017-01-17 2017-05-31 优居优住家居装饰(北京)有限公司 A kind of bathroom furred ceiling stealth access hole construction method
CN207244973U (en) * 2017-09-15 2018-04-17 北京金碧合力建筑设计工程有限公司 A kind of suspended ceiling overhauling port structure
CN109653427A (en) * 2019-01-22 2019-04-19 嘉兴富得利厨卫科技有限公司 A kind of mounting structure of Integral ceiling

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006028968A (en) * 2004-07-20 2006-02-02 Izu Mokuzai Ichiba:Kk Paulownia member for house
CN104481102A (en) * 2014-11-06 2015-04-01 安徽鸿路钢结构(集团)股份有限公司 Heat preserving and environmentally-friendly decorative board for external wall
CN205840105U (en) * 2016-06-30 2016-12-28 上海志豪实业有限公司 The steel joist suspended ceiling of keel piece can be hidden
CN106760414A (en) * 2017-01-17 2017-05-31 优居优住家居装饰(北京)有限公司 A kind of bathroom furred ceiling stealth access hole construction method
CN207244973U (en) * 2017-09-15 2018-04-17 北京金碧合力建筑设计工程有限公司 A kind of suspended ceiling overhauling port structure
CN109653427A (en) * 2019-01-22 2019-04-19 嘉兴富得利厨卫科技有限公司 A kind of mounting structure of Integral ceiling

Similar Documents

Publication Publication Date Title
CN206346452U (en) A kind of two-wire groove skirting line structure
WO2006057512A1 (en) Built-in wall water service box
WO2013110067A2 (en) Vertical wall mount system
CN108824648A (en) Space module house
CN101265747A (en) Wooden floor and method of manufacture and mounting method
CN107201798A (en) A kind of Integral ceiling fixed structure and section bar
CN110469036A (en) A kind of furred ceiling and its construction method
CN110273476A (en) A kind of assembled toilet and its installation method
CN103835458A (en) Installing assembly of external corner decorating plate
CN213990550U (en) Hidden bottom hooking structure used during photovoltaic tile roof installation
CN206376495U (en) A kind of skirting line structure
CN205259528U (en) Press mounting type wall system
CN210530225U (en) Wall clamping cloth wallboard with double female grooves
CN209509365U (en) A kind of inside-corner decoration plate mounting assembly
CN207934284U (en) a kind of waterproof curtain wall
CN206917411U (en) A kind of lockset of simple to install
CN214177215U (en) Hanging structure for photovoltaic tile roof installation
JPH11200533A (en) Room-forming panel member in which piping can be installed
CN105544908A (en) Decorative plate for wall
CN214786340U (en) Integrated toilet
CN220133237U (en) Assembled type drop-level suspended ceiling mounting structure
CN215106791U (en) Prefabricated wall structure
CN217000512U (en) Hidden building panel and metal roof
CN217400058U (en) Integrated ceiling assembling structure with assembling parts
CN203701443U (en) Purline for roof decoration

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191119

RJ01 Rejection of invention patent application after publication