CN107201798A CN201710647243.8A CN201710647243A CN107201798A CN 107201798 A CN107201798 A CN 107201798A CN 201710647243 A CN201710647243 A CN 201710647243A CN 107201798 A CN107201798 A CN 107201798A
Authority
CN
China
Prior art keywords
section bar
strap
fixed
clamp
buckle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710647243.8A
Other languages
Chinese (zh)
Inventor
王恒凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foshan Zhilian Yongdao Aluminum Co ltd
Original Assignee
FOSHAN NANHAI YONGDAO CONSTRUCTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FOSHAN NANHAI YONGDAO CONSTRUCTION Co Ltd filed Critical FOSHAN NANHAI YONGDAO CONSTRUCTION Co Ltd
Priority to CN201710647243.8A priority Critical patent/CN107201798A/en
Publication of CN107201798A publication Critical patent/CN107201798A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/22Connection of slabs, panels, sheets or the like to the supporting construction
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/06Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/30Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by edge details of the ceiling; e.g. securing to an adjacent wall

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Finishing Walls (AREA)

Abstract

The present invention relates to integrated ceiling decoration apparatus field, disclose a kind of Integral ceiling fixed structure, for being connected between section bar and buckle or another section bar, including the strap for setting or being connected to the fixation substrate on section bar He be connected on fixed substrate, neck of the fixed substrate provided with the fixed substrate side of opening direction, one end of the strap is provided with the clamp being connected with neck, and the other end coordinates for fixing buckle or another section bar with fixed substrate.Integral ceiling fixed structure cooperatively forms a clamping force to buckle or another section bar, so as to reach fixed effect equivalent to existing triangular keel by the connection of fixed substrate and strap.It can not only be used for individual member to be connected on section bar, may also set up in the part on section bar as profile structure, it is applied widely, further reduce the limitation of profile design.

Description

A kind of Integral ceiling fixed structure and section bar
Technical field
The present invention relates to integrated ceiling decoration apparatus field, more particularly, to a kind of Integral ceiling fixed structure and type Material.
Background technology
Integral ceiling is the combination of metal square plate and electrical equipment, point buckle module, heating module, lighting module, ventilation module Deng, with installing simple, flexible arrangement, the advantage, the main flow as toilet, kitchen furred ceiling, whole indoor such as easy to maintenance Occupy considerable status in decoration, make appropriate decoration to ceiling, indoor environment can not only be beautified, moreover it is possible to build rich Rich colorful interior space artistic image.Nowadays, with growing, full room furred ceiling, veranda suspension, the dining room of Integral ceiling industry Furred ceiling, parlor furred ceiling, passageway furred ceiling etc. are all increasingly becoming the main flow of house ornamentation.Change the dull color of plasterboard, what leak just turned yellow Puzzled, to change the deficiency that ceiling motif is dull, integrated ceiling board is just modish as market.
The main joist for including being connected with wall wall general Integral ceiling, the triangular keel that is connected with main joist more with And snap connection the buckle on triangular keel.Buckle is fixedly connected by triangular keel with main joist, and buckle with It is also to be stitched together by triangular keel between buckle, in order to fix decoration panel, triangular keel of the prior art Frequently include top and be symmetricly set in the kink at top two ends, and make kink cooperate to surround accommodating cavity, so that Decoration panel is snapped connection with triangular keel.
With the development of Integral ceiling industry, increasing indoor design has been no longer limited to couter-ceiling, and one-level is hung Top or two grades of furred ceilings turn into the preference of designer and user.One-level furred ceiling is the furred ceiling of only one of which level, that is, two flat Low one-level is only done in face, moulding;Two grades of furred ceilings are the furred ceilings of two levels, that is, have three planes.To prevent the side of next layer plane It is excessively dull lofty at edge, just occur in that for decorating the decoration bar sections such as two grades of beams with moulding.Existing two grades of beams etc. are decorated Section bar is typically fixed also by triangular keel with buckle, because the top of triangular keel is wider, and which also limits setting for two grades of beams Meter, causes its lower end decorative cover size not reduce, so as to cause the ratio of whole two grades of beams uncoordinated, have impact on Integral decoration Effect.
The content of the invention
In view of this, the present invention for overcome at least one described in above-mentioned prior art not enough there is provided a kind of structure it is capable and vigorous, Occupy little space, accurate positioning, fixing intensity are high, the Integral ceiling fixed structure that is easily installed.
In order to solve above-mentioned technical problem, the present invention uses following technical proposals:
A kind of Integral ceiling fixed structure, for being connected between section bar and buckle or another section bar, including sets or connects The fixation substrate being connected on section bar and the strap being connected on fixed substrate, the fixed substrate is provided with opening towards admittedly Determine the neck of substrate side, one end of the strap is provided with the clamp being connected with neck, the other end and fixed substrate Coordinate for fixing buckle or another section bar.
The Integral ceiling fixed structure of the present invention passes through fixed substrate and strap equivalent to existing triangular keel Connection cooperatively forms a clamping force to buckle or another section bar, so as to reach fixed effect.Due to the present invention it is special Structure so that its lateral dimension is general equivalent to same longitudinal size triangular keel, structure is capable and vigorous, greatly reduce its occupancy Space so that the design of the section bar such as two grades of beams is more flexible, structure is more reasonable.In addition, the present invention can not only be used for independent structure Part is connected on section bar, may also set up in the part on section bar as profile structure, applied widely, further reduces section bar The limitation of design.
For convenience of the assembling between fixed substrate and strap, it is additionally provided with the fixed substrate under the neck Side, the groove apart set with fixed substrate lower end, the groove formation avoid the avoidance space of the strap other end.It is fixed In substrate and strap assembling process, the other end of strap is avoided in groove, the strap other end and fixed base Interaction force between plate is reduced, or even forms free gap between the two, and interaction force is zero, the card on strap Plate just can be easily inserted in the neck on fixed substrate, the phase mutual friction between strap and fixed substrate is reduced, so as to subtract The possibility of few mutual scratch, in turn ensure that the quality of section bar while improving efficiency of assembling.Buckle or another section bar are installed During, due to restriction effect of the neck to clamp anyway so that strap is swung, its other end is in its natural state Squeezing into for the position remained in groove, buckle or another section bar is outside into one with fixed base plate shape to strap respectively And active force in opposite direction so that strap swings out certain angle and occurs micro-strain, and now strap has Have a backswing to the trend in groove, strap and fixed substrate respectively to the buckle squeezed into or another section bar formation one to Interior reaction force, so as to reach the effect of fixed buckle or another section bar.Further, since the strap other end is in natural shape Anyway swing and be all located in groove under state so that buckle or another section bar squeeze into or extract it is all more difficult so that Improve fixing intensity, it is ensured that connection validity.
The neck includes bottom plate, upper side wall, lower wall, upper clamp and lower clamp, the one of the upper side wall and lower wall The two ends of end difference connecting bottom board, the upper clamp of other end connection of the upper side wall, the lower card of other end connection of the lower wall Plate.When buckle or another section bar squeeze into the crack of strap and fixed substrate, the other end of strap will be forced to swing One angle, can form interaction force between clamp and neck, the lower end of clamp props up the inner side of lower clamp, the upper end of clamp Withstand bottom plate, although so it is also ensured that the clamping force of Integral ceiling fixed structure, but when receiving external force effect, clamp It may be moved up and down in neck, be unfavorable for integrally-built stability, therefore, the other end of the lower clamp is provided with card Projection inside groove, it is described raised for withstanding the clamp, by strap after the effect of buckle or the power of another section bar Certain angle is swung, while clamp also swings respective angles, is protruded out into the angle that clamp bottom is formed with strap, i.e., Make to be acted on by external force, clamp can not also be moved up and down with respect to neck, so that the free degree that strap is moved up and down is limited, Improve the stability of Integral ceiling fixed structure.
The strap includes the first flat board and the second flat board at an acute angle each other, and described first flat board one end connects One end of the second flat board is connect, other end connection clamp, the other end of second flat board coordinates for clip with fixed substrate Plate or another section bar, or avoid in the groove.Angle between first flat board and the second flat board is acute angle, is improved The chuck strength of buckle fixture.
The other end of second flat board is provided with S-shaped plate or arc, and the S-shaped plate or arc coordinate with fixed substrate For fixing buckle or another section bar, or avoid in the groove.The cooperation of S-shaped plate or arc and fixed substrate, just In the crack of buckle or the insertion of another section bar between the two, facilitate the installation of buckle or another section bar, while the setting of S templates The intensity of strap in this place can also be improved so that the structure is more compact effective.
In order to improve the assembly precision between strap and fixed substrate, improve Integral ceiling fixed structure to buckle or The clamping force of another section bar, the clamp is L shaped plate, includes the transverse slat and riser of interconnection, one end of the strap The side for deviating from transverse slat on riser is connected to, and with transverse slat at a distance of setting, the transverse slat end and the neck bottom or described Bottom plate cooperates.In buckle or another section bar installation process, because buckle or another section bar get into strap and fixed base In fit clearance between plate, the strap other end is swung out after a low-angle, and the end of clamp upper cross plate will be propped up Neck inwall, it is to avoid the strap other end continues to swing out, it is ensured that can give buckle between strap and fixed substrate Or the enough clamping forces of another section bar, it is ensured that fixation and positioning that buckle or another section bar are stablized.Due to the setting of transverse slat, So that contact line and the distance between axis of oscillation increase of strap of clamp and neck inwall, improve strap with Assembly precision between fixed substrate, while the requirement on machining accuracy to neck can also be reduced, reduces processing cost, strap It will be withstood after swinging low-angle by bottom plate, now the strap other end is still located in groove, it is ensured that strap has Enough clamping forces, improve the stability maintenance of buckle or another section bar.
The fixed substrate opposite side is provided with the interface arrangment of T-shaped, the lower end of the T-shaped and fixed substrate connection, described Interface arrangment is used to be connected with the corner code groove on another section bar.
It is a further object to provide a kind of section bar, the section bar includes the fixed part and decoration being connected with each other Above-mentioned Integral ceiling fixed structure is set or is connected with portion, the fixed part, and the section bar is unloaded can make after strap For corner section bar.Due to setting or being connected to above-mentioned Integral ceiling fixed structure on the fixed part of section bar so that the section bar can be with It is directly connected to buckle, it is not necessary to extra that both are connected using triangular keel, remains for holding also without pre- on section bar Receive the space of triangular keel, therefore the size of section bar lower end decorative cover can be reduced so that profile structure is more coordinated, and design is more To be flexible.Further, since strap can be unloaded, when it is unloaded from section bar, the side of section bar fixed part becomes smooth, Wall can be close to or wall setting of getting up, now, the effect of section bar is applied widely just equivalent to corner section bar.Further Light trough is additionally provided with ground, the fixed part and/or ornamental portion, for fixed light band, the section bar is unloaded after strap can be with It is used as corner light sectional material.
The present invention has the advantages that compared with prior art:
1st, the lateral dimension of Integral ceiling fixed structure of the present invention is general equivalent to same longitudinal size triangular keel, structure essence Space that is brave, greatly reducing its occupancy so that the design of the section bar such as two grades of beams is more flexible, structure is more reasonable.
2nd, the present invention can not only be used for individual member and be connected on section bar, may also set up on section bar as the one of profile structure Part, it is applied widely, further reduce the limitation of profile design.
3rd, in fixed substrate and strap assembling process, the other end of strap is avoided in groove, strap On clamp just can be easily inserted in the neck on fixed substrate, reduce the phase mutual friction between strap and fixed substrate, So as to reduce the possibility of mutual scratch, the quality of section bar is in turn ensure that while improving efficiency of assembling.Buckle or another is installed During section bar, due to restriction effect of the neck to clamp anyway so that strap is swung, its other end is in nature The position in groove is remained under state, when buckle or another section bar are squeezed into, strap and fixed substrate will be to them Formed clamping action so that buckle or another section bar squeeze into or extract all more difficulty, so as to improve fixing intensity, it is ensured that Connect validity.
4th, due to setting or being connected to above-mentioned Integral ceiling fixed structure on the fixed part of section bar so that the section bar can be straight Buckle is connect in succession, it is not necessary to extra that both are connected using triangular keel, remain for accommodating also without pre- on section bar The space of triangular keel, therefore the size of section bar lower end decorative cover can be reduced so that profile structure is more coordinated, and design is more Flexibly.
5th, because strap can be unloaded, when it is unloaded from section bar, the side of section bar fixed part becomes smooth, can Be close to wall or get up wall set, now, the effect of section bar is applied widely just equivalent to corner section bar.
Brief description of the drawings
Fig. 1 is the structural representation of the Integral ceiling fixed structure of embodiment 1;
Fig. 2 is the Integral ceiling fixed structure assembled state schematic diagram of embodiment 1;
Fig. 3 is the Integral ceiling fixed structure of embodiment 1 and buckle installment state schematic diagram;
Fig. 4 is the enlarged diagram in A portions in Fig. 1;
Fig. 5 is the connection diagram of the Integral ceiling fixed structure of embodiment 1 and buckle;
Fig. 6 is the structural representation of the Integral ceiling fixed structure of embodiment 2;
Fig. 7 is the use state schematic diagram of the Integral ceiling fixed structure of embodiment 2;
Fig. 8 is that traditional two grades of beams increase schematic diagram;
Fig. 9 is the structural representation of 3 two grades of top-type materials of embodiment;
Figure 10 is the structural representation on two grades of tops of tradition;
Figure 11 is the structural representation of 4 two grades of top-type materials of embodiment;
Figure 12 is the micro- staggered floor construction schematic diagram of embodiment 5;
Figure 13 is the corner modulated structure schematic diagram of embodiment 5;
Description of reference numerals:Fixed substrate 100, neck 110, bottom plate 111, upper side wall 112, lower wall 113, upper clamp 114, under Clamp 115, projection 1151, groove 120, interface arrangment 130, strap 200, clamp 210, transverse slat 211, riser 212, first Flat board 220, the second flat board 230, S-shaped plate 231, corner code groove 310, lower end decoration panel 320, side decoration panel 330, light bar card Groove 340, attachment structure 350, top plate 360, buckle 410, last layer buckle 411, next layer of buckle 412, traditional two grades of beams 420, Increase part 430, triangular keel 440, corner section bar 450.
Embodiment
Accompanying drawing being given for example only property explanation, it is impossible to be interpreted as the limitation to this patent;In order to more preferably illustrate the present embodiment, accompanying drawing A little parts have omission, zoomed in or out, and do not represent the size of actual product;To those skilled in the art, accompanying drawing In some known features and its explanation may omit and will be understood by;Described in accompanying drawing position relationship be used for be given for example only Property explanation, it is impossible to be interpreted as the limitation to this patent.The present invention is described in further details with reference to specific embodiment.
Embodiment 1
As shown in figure 1, a kind of Integral ceiling fixed structure, for being connected between section bar and buckle 410 or another section bar, It is described solid including the strap 200 for setting or being connected to the fixation substrate 100 on section bar He be connected on fixed substrate 100 Substrate 100 is determined provided with opening towards the neck 110 of the fixed side of substrate 100, and one end of the strap 200 is provided with and card The clamp 210 that groove 110 is connected, the other end coordinates for fixing buckle 410 or another section bar with fixed substrate 100.
The Integral ceiling fixed structure of the present embodiment is equivalent to existing triangular keel 440, by fixed substrate 100 and admittedly The connection of clamp plate 200 cooperatively forms a clamping force to buckle 410 or another section bar, so as to reach fixed effect.By In the special construction of the present invention so that its lateral dimension is general equivalent to same longitudinal size triangular keel 440, structure essence Space that is brave, greatly reducing its occupancy so that the design of the section bar such as two grades of beams is more flexible, structure is more reasonable.In addition, this Invention can not only be used for individual member and be connected on section bar, may also set up in the part on section bar as profile structure, be applicable model Enclose wide, further the limitation of reduction profile design.
For convenience of the assembling between fixed substrate 100 and strap 200, it is additionally provided with and is located on the fixed substrate 100 The lower section of neck 110, the groove 120 apart set with the fixed lower end of substrate 100, the formation of groove 120 avoid geometrical clamp The avoidance space of the other end of plate 200.As shown in Fig. 2 in fixed substrate 100 and the assembling process of strap 200, strap 200 other end is avoided in groove 120, and the interaction force between the other end of strap 200 and fixed substrate 100 subtracts It is few, or even free gap is formed between the two, interaction force is zero, and the clamp 210 on strap 200 just can be easily inserted In neck 110 on fixed substrate 100, the phase mutual friction between strap 200 and fixed substrate 100 is reduced, so as to reduce The possibility of mutual scratch, in turn ensure that the quality of section bar while improving efficiency of assembling.As shown in figure 3, install buckle 410 or During another section bar, due to restriction effect of the neck 110 to clamp 210 anyway so that strap 200 is swung, The position that its other end is remained in groove 120 in its natural state, buckle 410 or another section bar are squeezed into respectively to solid One outside and in opposite direction active force of clamp plate 200 and the fixed formation of substrate 100 so that strap 200 swings out one Determine angle and occur micro-strain, now strap 200 has a backswing to the trend in groove 120, strap 200 With fixed substrate 100 respectively to the buckle 410 squeezed into or another section bar one inside reaction force of formation, so as to reach clip The effect of plate 410 or another section bar.Further, since anyway the other end of strap 200 swings all positions in its natural state In in groove 120 so that buckle 410 or another section bar are squeezed into or extracted all more difficult, so as to improve fixing intensity, protect Card connection validity.
As shown in figure 4, the neck 110 includes bottom plate 111, upper side wall 112, lower wall 113, upper clamp 114 and lower card The two ends of connecting bottom board 111 are distinguished in one end of plate 115, the upper side wall 112 and lower wall 113, the upper side wall 112 it is another The upper clamp 114 of end connection, the lower clamp 115 of other end connection of the lower wall 113.When buckle 410 or another section bar are squeezed into admittedly During the crack of clamp plate 200 and fixed substrate 100, the other end of strap 200 will be forced to swing an angle, clamp 210 Interaction force can be formed between neck 110, the lower end of clamp 210 props up the inner side of lower clamp 115, the upper end of clamp 210 Withstand bottom plate 111, although so it is also ensured that the clamping force of Integral ceiling fixed structure, but when receiving external force effect, Clamp 210 may be moved up and down in neck 110, be unfavorable for integrally-built stability, therefore, the lower clamp 115 is another One end is provided with the projection 1151 inside neck 110, and described raised 1151 are used to withstand the clamp 210, by buckle 410 Or strap 200 swings certain angle after the effect of the power of another section bar, while clamp 210 also swings respective angles, it is raised 1151 enter in the angle that the bottom of clamp 210 is formed with strap 200, even if being acted on by external force, clamp 210 also can not phase Neck 110 is moved up and down, so as to limit the free degree that strap 200 is moved up and down, Integral ceiling fixed knot is improved The stability of structure.
As shown in figure 5, the strap 200 includes the first flat board 220 and the second flat board at an acute angle each other 230, described one end of first flat board 220 connects one end of the second flat board 230, other end connection clamp 210, second flat board 230 other end coordinates with fixed substrate 100 and is used to fix buckle 410 or another section bar, or avoids in the groove 120 It is interior.Angle between the flat board 230 of first flat board 220 and second is acute angle, and the clamping for improving the fixture of buckle 410 is strong Degree.
The other end of second flat board 230 is provided with S-shaped plate 231, and the S-shaped plate 231 coordinates with fixed substrate 100 and is used for Fixed buckle 410 or another section bar, or avoid in the groove 120.The cooperation of S-shaped plate 231 and fixed substrate 100, just In the crack of buckle 410 or the insertion of another section bar between the two, facilitate the installation of buckle 410 or another section bar, while S templates Setting can also improve the intensity of strap 200 in this place so that the structure more it is compact effectively.Although the present embodiment is The other end of two flat boards 230 improves the intensity of strap 200 in this place by the way of S-shaped plate 231 is set, but actual raw Identical purpose can also be reached in production using the structure of arc.
In order to improve the assembly precision between strap 200 and fixed substrate 100, Integral ceiling fixed structure pair is improved The clamping force of buckle 410 or another section bar, the clamp 210 is L shaped plate, includes the transverse slat 211 and riser 212 of interconnection, One end of the strap 200 is connected to the side for deviating from transverse slat 211 on riser 212, and with transverse slat 211 at a distance of setting, institute The end of transverse slat 211 is stated to cooperate with the bottom of neck 110 or the bottom plate 111.With reference to Fig. 5, buckle 410 or another section bar In installation process, got into due to buckle 410 or another section bar in the fit clearance between strap 200 and fixed substrate 100, The other end of strap 200 is swung out after a low-angle, and the end of the upper cross plate 211 of clamp 210 will be propped up in neck 110 Wall, it is to avoid the other end of strap 200 continues to swing out, it is ensured that being capable of give-commission between strap 200 and fixed substrate 100 Plate 410 or the enough clamping forces of another section bar, it is ensured that fixation and positioning that buckle 410 or another section bar are stablized.Due to horizontal stroke The setting of plate 211 so that the distance between axis of oscillation of contact line and strap 200 of clamp 210 and the inwall of neck 110 Increase, improves the assembly precision between strap 200 and fixed substrate 100, while the processing to neck 110 can also be reduced Required precision, reduces processing cost, and strap 200 will be withstood after swinging low-angle by bottom plate 111, now strap 200 other ends are still located in groove 120, it is ensured that strap 200 has enough clamping forces, improve buckle 410 or another The stability maintenance of section bar.
Embodiment 2
The present embodiment and the difference of embodiment 1 are, as shown in fig. 6, the opposite side of fixed substrate 100 is provided with the clamping of T-shaped Structure 130, the lower end of the T-shaped is connected with fixed substrate 100, and the interface arrangment 130 is used for and the corner brace on another section bar Groove 310 is connected.
As shown in fig. 7, two grades of beams 420 of tradition can connect any buckle 410 by the present embodiment Integral ceiling fixed structure, Higher purpose is reached, now, the upper end of buckle 410 for increasing can arrange in pairs or groups any limit angle section 450 for installing one Layer buckle 410, the method that part 430 is increased for two grades of beams is increased compared to being used in conventional method(As shown in Figure 8), it is more beneficial for Solve the problems, such as the receipts side of last layer buckle 410.
Embodiment 3
As shown in figure 9, a kind of two grades of top-type materials, include the fixed part and ornamental portion of interconnection, the fixed part includes implementing Integral ceiling fixed structure described in example 1 and the corner code groove 310 for increasing part 430 for connecting, the corner code groove 310 are connected to institute The upper end of fixation substrate 100 of Integral ceiling fixed structure is stated, the ornamental portion includes lower end and decorates panel 320 and side decorative cover Plate 330, lower end decoration panel 320 one end connection side decorative cover plate 330, the other end is connected the lower end of substrate 100.
Two grades of top-type materials of the present embodiment are due to the Integral ceiling fixed knot being provided with its fixed part described in embodiment 1 Structure so that the section bar can be directly connected to buckle 410, it is not necessary to extra that both are connected using triangular keel 440, type Also without the space for remaining for accommodating triangular keel 440 in advance on material, understood with reference to Fig. 9 and Figure 10, two grades of top-types of the present embodiment The size a of the lower end decoration panel 320 of material is substantially reduced compared to the size b of the lower end decoration panel 320 of two grades of top-type materials of tradition, So that profile structure is more coordinated, design more flexible.
In addition, light bar neck 340 can also be set in space between Integral ceiling fixed structure and ornamental portion, constitute out Two grades of top-type materials of light.
Embodiment 4
As shown in figure 11, a kind of two grades of top-type materials, include the fixed part and ornamental portion of interconnection, and the fixed part includes implementing Integral ceiling fixed structure, light bar neck 340 and attachment structure 350 described in example 1, the lower end of light bar neck 340 connect institute The upper end of fixation substrate 100 of Integral ceiling fixed structure is stated, upper end connects the bindiny mechanism, and the attachment structure 350 is used for Last layer buckle 410 is connected, the ornamental portion includes lower end decoration panel 320 and side decoration panel 330, the lower end decoration The one end of panel 320 connects side decorative cover plate 330, and the other end is connected the lower end of substrate 100.
Two grades of top-type materials of the present embodiment are due to the Integral ceiling fixed knot being provided with its fixed part described in embodiment 1 Structure so that the section bar can be directly connected to buckle 410, it is not necessary to extra that both are connected using triangular keel 440, type Also without the space for remaining for accommodating triangular keel 440 in advance on material, the lower end decoration panel 320 of two grades of top-type materials of the present embodiment Size be substantially reduced compared to the size of the lower end decoration panel 320 of two grades of top-type materials of tradition so that profile structure is more coordinated, Design is more flexible.
Embodiment 5
As shown in Figure 12 ~ 13, a kind of dual-purpose section bar of micro- staggered floor or corner lamp includes the fixed part and ornamental portion of interconnection, institute Stating ornamental portion includes lower end decoration panel 320, side decoration panel 330 and top plate 360, and the top plate 360 is decorated positioned at lower end The top of panel 320, described lower end decoration one end of panel 320 and the one end of top plate 360 are connected respectively to side decoration panel 330 Two ends, the lower end decoration other end of panel 320 and the other end of top plate 360 are connected respectively to fixed part side, the fixed part It is described including the Integral ceiling fixed structure described in embodiment 1 and the corner code groove 310 being connected to above Integral ceiling fixed structure The strap 200 of Integral ceiling fixed structure is located at the opposite side of fixed part, and the corner code groove 310 increases part for connection 430.Light bar neck 340 is provided with the space that the fixed part is collectively formed with ornamental portion.
As shown in figure 12, Integral ceiling fixed structure is used to fix next layer of buckle 410, last layer button in the present embodiment Plate 410 is overlapped and the top of top plate 360, the overall micro- staggered floor construction of composition.
In addition, removing after strap 200, as shown in figure 13, the section bar of the present embodiment is also used as corner lamp and used.
Obviously, the above embodiment of the present invention is only intended to clearly illustrate example of the present invention, and is not pair The restriction of embodiments of the present invention.For those of ordinary skill in the field, may be used also on the basis of the above description To make other changes in different forms.There is no necessity and possibility to exhaust all the enbodiments.It is all this Any modifications, equivalent substitutions and improvements made within the spirit and principle of invention etc., should be included in the claims in the present invention Protection domain within.

Claims (9)

1. a kind of Integral ceiling fixed structure, for being connected between section bar and buckle or another section bar, it is characterised in that Including the strap for setting or being connected to the fixation substrate on section bar He be connected on fixed substrate, set on the fixed substrate There is neck of the opening towards fixed substrate side, one end of the strap is provided with the clamp being connected with neck, another End coordinates for fixing buckle or another section bar with fixed substrate.
2. Integral ceiling fixed structure according to claim 1, it is characterised in that be additionally provided with and be located on the fixed substrate At a distance of the groove set below the neck, with fixed substrate lower end, the groove formation avoids keeping away for the strap other end Allow space.
3. Integral ceiling fixed structure according to claim 2, it is characterised in that the neck include bottom plate, upper side wall, The two ends of connecting bottom board are distinguished in one end of lower wall, upper clamp and lower clamp, the upper side wall and lower wall, the upper side wall The upper clamp of other end connection, the lower clamp of other end connection of the lower wall, the other end of the lower clamp is provided with neck Internal projection, it is described raised for withstanding the clamp.
4. Integral ceiling fixed structure according to claim 1, it is characterised in that the strap is included each other First flat board and the second flat board at an acute angle, described first flat board one end connects one end of the second flat board, and the other end connects clamp, The other end of second flat board coordinates with fixed substrate and is used to fix buckle or another section bar, or avoids in the groove It is interior.
5. Integral ceiling fixed structure according to claim 4, it is characterised in that the other end of second flat board is provided with S-shaped plate or arc, the S-shaped plate or arc coordinate for fixing buckle or another section bar, or avoidance with fixed substrate In in the groove.
6. the Integral ceiling fixed structure according to any one of claim 1 ~ 5, it is characterised in that the clamp is L shaped plate, Transverse slat and riser including interconnection, one end of the strap are connected to the side for deviating from transverse slat on riser, and with horizontal stroke Plate is at a distance of setting, and the transverse slat end cooperates with the neck bottom or the bottom plate.
7. the Integral ceiling fixed structure according to any one of claim 1 ~ 5, it is characterised in that the fixed substrate is another Side is provided with the interface arrangment of T-shaped, and the lower end of the T-shaped is used for and another section bar with fixed substrate connection, the interface arrangment Corner code groove connection.
8. a kind of section bar, it is characterised in that set or connect on fixed part and ornamental portion including interconnection, the fixed part Just like the Integral ceiling fixed structure described in any one of claim 1 ~ 7.
9. section bar according to claim 8, it is characterised in that light trough is additionally provided with the fixed part and/or ornamental portion, is used In fixed light band.
CN201710647243.8A 2017-08-01 2017-08-01 A kind of Integral ceiling fixed structure and section bar Pending CN107201798A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710647243.8A CN107201798A (en) 2017-08-01 2017-08-01 A kind of Integral ceiling fixed structure and section bar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710647243.8A CN107201798A (en) 2017-08-01 2017-08-01 A kind of Integral ceiling fixed structure and section bar

Publications (1)

Publication Number Publication Date
CN107201798A true CN107201798A (en) 2017-09-26

Family

ID=59911534

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710647243.8A Pending CN107201798A (en) 2017-08-01 2017-08-01 A kind of Integral ceiling fixed structure and section bar

Country Status (1)

Country Link
CN (1) CN107201798A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442604A (en) * 2018-04-10 2018-08-24 安徽科蓝特铝业有限公司 A kind of keel furred ceiling aluminium alloy extrusions
CN109441061A (en) * 2018-12-20 2019-03-08 海盐美赫电器科技有限公司 A kind of telescopic edge closing bar
CN109653427A (en) * 2019-01-22 2019-04-19 嘉兴富得利厨卫科技有限公司 A kind of mounting structure of Integral ceiling
CN112681601A (en) * 2020-08-11 2021-04-20 浙江宝仕龙集成家居股份有限公司 Beam-slab connecting structure and suspended ceiling using same
CN113585593A (en) * 2021-08-11 2021-11-02 广东省锦绣明天建材有限公司 Corner mounting structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007257954A (en) * 2006-03-22 2007-10-04 Toshiba Lighting & Technology Corp Frame body and lighting fixture
CN205299419U (en) * 2016-01-13 2016-06-08 刘祥 Ceiling lamp device easy to assemble
CN106677401A (en) * 2017-01-24 2017-05-17 佛山市卓尔盛金属制品有限公司 Keel-line lamp
CN207376937U (en) * 2017-08-01 2018-05-18 佛山市南海永道建材有限公司 A kind of Integral ceiling fixed structure and section bar

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007257954A (en) * 2006-03-22 2007-10-04 Toshiba Lighting & Technology Corp Frame body and lighting fixture
CN205299419U (en) * 2016-01-13 2016-06-08 刘祥 Ceiling lamp device easy to assemble
CN106677401A (en) * 2017-01-24 2017-05-17 佛山市卓尔盛金属制品有限公司 Keel-line lamp
CN207376937U (en) * 2017-08-01 2018-05-18 佛山市南海永道建材有限公司 A kind of Integral ceiling fixed structure and section bar

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442604A (en) * 2018-04-10 2018-08-24 安徽科蓝特铝业有限公司 A kind of keel furred ceiling aluminium alloy extrusions
CN109441061A (en) * 2018-12-20 2019-03-08 海盐美赫电器科技有限公司 A kind of telescopic edge closing bar
CN109653427A (en) * 2019-01-22 2019-04-19 嘉兴富得利厨卫科技有限公司 A kind of mounting structure of Integral ceiling
CN109653427B (en) * 2019-01-22 2024-03-12 嘉兴富得利厨卫科技有限公司 Mounting structure of integrated furred ceiling
CN112681601A (en) * 2020-08-11 2021-04-20 浙江宝仕龙集成家居股份有限公司 Beam-slab connecting structure and suspended ceiling using same
CN113585593A (en) * 2021-08-11 2021-11-02 广东省锦绣明天建材有限公司 Corner mounting structure

Similar Documents

Publication Publication Date Title
CN107201798A (en) A kind of Integral ceiling fixed structure and section bar
CN205557972U (en) Reassembling type corner furred ceiling layer
CN107268867B (en) Decorative line keel
CN104179282A (en) Suspended ceiling
CN204898991U (en) Reassembling type corner furred ceiling layer
CN104164937B (en) A kind of suspended ceiling
CN207376937U (en) A kind of Integral ceiling fixed structure and section bar
CN205954981U (en) Connection of use can be made up and piece is increased
CN204609243U (en) There is the smallpox secondary ceiling decoration bar of decorative lighting function
CN108301578A (en) A kind of installation node of cladding panel
CN205296531U (en) Suspended ceiling mounting structure
CN205296538U (en) A compound connecting piece for integrated furred ceiling of double entry
CN209509365U (en) A kind of inside-corner decoration plate mounting assembly
CN103276843B (en) Ceiling structure
CN107327055B (en) Exposed frame system of glass curtain wall
CN207905191U (en) The connection structure of column and ornamental strip
CN204665181U (en) A kind of furred ceiling light trough structure
CN205742685U (en) Variola illumination Os Draconis
CN206337776U (en) A kind of decorating structure of metope
CN205171796U (en) Integrated suspension ceiling duplex structure
CN105133771B (en) Decoration auxiliary girder, decoration beam connection, decoration girder construction connected vertically
CN208293869U (en) A kind of light and shade frame mixing ceiling system
CN219033743U (en) Side keel and decorative line mounting structure
CN208545936U (en) A kind of novel decorative line easy to install
CN219808559U (en) Combined ceiling

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190508

Address after: 528237 Xiwan Village, Guanyao, Liubian First Industrial Zone, Shishan Town, Nanhai District, Foshan City, Guangdong Province

Applicant after: Foshan Zhilian Yongdao Aluminum Co.,Ltd.

Address before: 528244 Xiwan Village, Guanyao, Liubian First Industrial Zone, Shishan Town, Nanhai District, Foshan City, Guangdong Province

Applicant before: FOSHAN CITY YONGDAO CONSTRUCTION MATERIALS CO.,LTD.

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170926