CN110439841A - Stabilization air flow system for the test of external-wall heat-insulation material combustion simulation - Google Patents

Stabilization air flow system for the test of external-wall heat-insulation material combustion simulation Download PDF

Info

Publication number
CN110439841A
CN110439841A CN201910763398.7A CN201910763398A CN110439841A CN 110439841 A CN110439841 A CN 110439841A CN 201910763398 A CN201910763398 A CN 201910763398A CN 110439841 A CN110439841 A CN 110439841A
Authority
CN
China
Prior art keywords
wind speed
blower
air flow
flow system
facade
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910763398.7A
Other languages
Chinese (zh)
Inventor
王守江
张和平
程旭东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
University of Science and Technology of China USTC
Original Assignee
University of Science and Technology of China USTC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by University of Science and Technology of China USTC filed Critical University of Science and Technology of China USTC
Priority to CN201910763398.7A priority Critical patent/CN110439841A/en
Publication of CN110439841A publication Critical patent/CN110439841A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F04POSITIVE - DISPLACEMENT MACHINES FOR LIQUIDS; PUMPS FOR LIQUIDS OR ELASTIC FLUIDS
    • F04DNON-POSITIVE-DISPLACEMENT PUMPS
    • F04D25/00Pumping installations or systems
    • F04D25/16Combinations of two or more pumps ; Producing two or more separate gas flows
    • F04D25/166Combinations of two or more pumps ; Producing two or more separate gas flows using fans
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F04POSITIVE - DISPLACEMENT MACHINES FOR LIQUIDS; PUMPS FOR LIQUIDS OR ELASTIC FLUIDS
    • F04DNON-POSITIVE-DISPLACEMENT PUMPS
    • F04D27/00Control, e.g. regulation, of pumps, pumping installations or pumping systems specially adapted for elastic fluids
    • F04D27/004Control, e.g. regulation, of pumps, pumping installations or pumping systems specially adapted for elastic fluids by varying driving speed
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N31/00Investigating or analysing non-biological materials by the use of the chemical methods specified in the subgroup; Apparatus specially adapted for such methods
    • G01N31/12Investigating or analysing non-biological materials by the use of the chemical methods specified in the subgroup; Apparatus specially adapted for such methods using combustion
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B10/00Integration of renewable energy sources in buildings
    • Y02B10/30Wind power

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Physics & Mathematics (AREA)
  • Molecular Biology (AREA)
  • Combustion & Propulsion (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • General Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Immunology (AREA)
  • Pathology (AREA)
  • Aerodynamic Tests, Hydrodynamic Tests, Wind Tunnels, And Water Tanks (AREA)

Abstract

The invention discloses a kind of stabilization air flow systems of external-wall heat-insulation material combustion simulation test comprising blower, air monitoring unit and blast velocity control unit;Air monitoring unit is used to monitor the wind speed of predetermined position;Blast velocity control unit is used to receive the control electric signal of air monitoring unit transmission, and the revolving speed of blower is controlled according to the control signal.Above-mentioned predeterminated position is disposed proximate to the windward side of facade.Using when, air monitoring unit monitors predetermined position wind speed, monitor the actual wind speed at facade, and control electric signal is converted into wind speed and is sent to blast velocity control unit, blast velocity control unit controls blower according to above-mentioned control electric signal, and the wind speed at facade is made to reach test requirements document.Obviously, which can adjust the revolving speed of blower according to the actual wind speed at facade, to make the wind speed at facade up to stability number, meet test requirements document.

Description

Stabilization air flow system for the test of external-wall heat-insulation material combustion simulation
Technical field
The present invention relates to Mechanical Industry Technology fields, more specifically to one kind for external-wall heat-insulation material burning mould The stabilization air flow system of quasi- test.
Background technique
For the fire safety performance of scientific evaluation external-wall heat-insulation material, external-wall heat-insulation material combustion simulation examination need to be carried out It tests, the facade of specific setting simulation, and external-wall heat-insulation material is made to burn on facade.Facade is by phase Even and orthogonal main wall and secondary wall are constituted, the wide 3.0m of main wall, high 9.0m, the wide 2.0m of secondary wall, high 9.0m, flame front when burning Product is spent up to 45 ㎡, flame temperature up to 600 degree -800, the flame when external-wall heat-insulation material is fired to the high 9m in the top of experimental provision Height can reach 12m.As above test carries out in outdoor spacious open place, but natural wind wind speed is unstable in outdoor environment Fixed and uncontrollable, it is difficult to reach the wind speed requirement of this test: experiment wall overall surface is required to reach by uniformly distributed wind speed To stable two kinds of wind speed 5m/s and 10m/s.
In conclusion making facade surface by equal how in outdoor carry out external-wall heat-insulation material combustion experiment Even stable wind speed reaches the stabilization wind speed requirement of simulation test, is those skilled in the art's urgent problem to be solved.
Summary of the invention
In view of this, the present invention provides a kind of stabilization air flow system for the test of external-wall heat-insulation material combustion simulation, The revolving speed of blower can be adjusted according to the actual wind speed at facade, so that reaching the wind speed at facade stablizes number Value, meets test requirements document.
To achieve the above object, the invention provides the following technical scheme:
A kind of stabilization air flow system for the test of external-wall heat-insulation material combustion simulation, comprising:
Blower, the blower setting on the support frame, are used to dry to facade;
Air monitoring unit, for monitoring the wind speed of predetermined position;
Blast velocity control unit, the control electric signal sent for receiving the air monitoring unit, and according to control electricity Signal controls the blower.
Preferably, in aforementioned stable air flow system, the blower be it is multiple, each blower is set gradually along the vertical direction On support frame as described above.
Preferably, in aforementioned stable air flow system, the air monitoring unit includes:
Air monitoring stake, the air monitoring stake are arranged between the facade and the blower.
Preferably, in aforementioned stable air flow system, two wind speed transducers, the two difference are equipped in the wind speed measurement stake It is transferred to blast velocity control unit respectively for acquiring away from the wind speed at ground 1m, 4m, then after being converted into control electric signal with wind speed.
Preferably, in aforementioned stable air flow system, the blast velocity control unit includes:
Power distribution isolator, the power distribution isolator are used to receive the control electric signal that the air monitoring unit is sent;
Fan frequency converter, the fan frequency converter are connected with the power distribution isolator, for according to the air monitoring list The revolving speed of blower described in the control electric signal adjust automatically that member is sent.
Preferably, in aforementioned stable air flow system, the power distribution isolator be it is multiple, and each power distribution isolator respectively with The different fan frequency converters is connected.
Preferably, in aforementioned stable air flow system, support frame as described above includes:
Pedestal;
The main body rack of assembly on the base, the blower are fixed on the main body rack.
Preferably, in aforementioned stable air flow system, the pedestal is equipped with universal wheel, and the universal wheel is with locking dress It sets.
The present invention provides a kind of stabilization air flow system of external-wall heat-insulation material combustion simulation test comprising blower, wind speed Monitoring unit and blast velocity control unit;Air monitoring unit is used to monitor the wind speed of predetermined position;Blast velocity control unit is used for The control electric signal that air monitoring unit is sent is received, and controls the revolving speed of blower according to the control signal.Above-mentioned predeterminated position It is disposed proximate to the windward side of facade.
When using stable air flow system as above, air monitoring unit monitors predetermined position wind speed, that is, monitors to build Actual wind speed at alien invasion, and control electric signal is converted into wind speed and is sent to blast velocity control unit, blast velocity control unit root Blower is controlled according to above-mentioned control electric signal, the wind speed at facade is made to reach test requirements document.
As above the principle for stablizing air flow system is as follows: the stabilization wind speed that facade uniformly requires in testing ground is by certainly Right wind superposition manual intervention wind (i.e. blower air-supply) is realized, that is, does not reach requirement wind when testing the natural wind speed that metope is subject to Blower is blown automatically according to wind speed difference when fast, and when natural wind speed reaches requirement wind speed, blower reduces air output automatically, to reach To experiment wall surface by the effect for stablizing wind speed;According to fan characteristic, " air quantity, wind speed and the revolving speed of blower are directly proportional passes System ", the revolving speed of blower is bigger, and air quantity, the wind speed of blower will be bigger, so this programme realizes control by control rotation speed of fan The wind speed of blower air-supply.
Obviously, the stabilization air flow system as above for the test of external-wall heat-insulation material combustion simulation can be according to facade The actual wind speed at place adjusts the revolving speed of blower, to make the wind speed at facade up to stability number, meets test requirements document.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with It obtains other drawings based on these drawings.
Fig. 1 is the control principle drawing of stable air flow system provided in an embodiment of the present invention;
Fig. 2 is the overlooking structure diagram of support frame provided in an embodiment of the present invention;
Fig. 3 is the schematic cross-sectional view of A-A in Fig. 2;
Fig. 4 is the schematic cross-sectional view of B-B in Fig. 2;
Fig. 5 is the installation diagram of support frame provided in an embodiment of the present invention and blower;
Fig. 6 is stable air flow system provided in an embodiment of the present invention and structural schematic diagram;
Wherein, in Fig. 1-Fig. 6:
Wind speed transducer ST;Fan frequency converter BP;Power distribution isolator SY3, SY2;Support frame 101;Pedestal 111;Main body branch Frame 112;Drawstring 113;Blower 102;Air monitoring stake 103.
Specific embodiment
The embodiment of the invention discloses a kind of stabilization air flow system for the test of external-wall heat-insulation material combustion simulation, energy Enough actual wind speeds according at facade adjust the revolving speed of blower, so that reaching the wind speed at facade stablizes number Value, meets test requirements document.
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Fig. 1-Fig. 3 is please referred to, the embodiment of the present invention provides a kind of stabilization wind speed of external-wall heat-insulation material combustion simulation test Device comprising blower 102, air monitoring unit and blast velocity control unit;Air monitoring unit is for monitoring predetermined position Wind speed;Blast velocity control unit is used to receive the control electric signal of air monitoring unit transmission, and is controlled according to the control signal The revolving speed of blower 102.Above-mentioned predeterminated position is disposed proximate to the windward side of facade.The structure of facade with it is existing Technology is identical, including main wall and secondary wall.
When using stable air flow system as above, air monitoring unit monitors predetermined position wind speed, that is, monitors to build Actual wind speed at alien invasion, and control electric signal is converted into wind speed and is sent to blast velocity control unit, blast velocity control unit root Blower 102 is controlled according to above-mentioned control electric signal, the wind speed at facade is made to reach test requirements document.
As above the principle for stablizing air flow system is as follows: the stabilization wind speed that facade uniformly requires in testing ground is by certainly Right wind superposition manual intervention wind (i.e. blower 102 is blown) is realized, that is, wants when the natural wind speed that experiment metope is subject to is not achieved Blower 102 is blown automatically according to wind speed difference when seeking wind speed, and when natural wind speed reaches requirement wind speed, blower 102 is reduced automatically and sent Air quantity is stablized wind speed to achieve the effect that test wall surface;According to 102 characteristic of blower " air quantity of blower 102, wind speed and Revolving speed is proportional ", the revolving speed of blower 102 is bigger, and air quantity, the wind speed of blower 102 will be bigger, so this programme passes through It controls 102 revolving speed of blower and realizes the wind speed that control blower 102 is blown.
Obviously, the stabilization air flow system as above for the test of external-wall heat-insulation material combustion simulation can be according to facade The actual wind speed at place adjusts the revolving speed of blower 102, to make the wind speed at facade up to stability number, meets test and wants It asks.
Specifically, in aforementioned stable air flow system, blower 102 be it is multiple, each blower 102 is successively set on along the vertical direction On support frame 101.More specifically, blower 102 is set as 5, and 102 uniform intervals 1.9m of each blower is fixed on support frame 101 On.
Air monitoring unit includes air monitoring stake 103, and air monitoring stake 103 is arranged in facade and blower 102 Between.Specifically, (front surface of facade refers to main wall to front surface 1m of the air monitoring stake 103 apart from facade The upper surface towards secondary wall side), the side outside 0.3m away from facade, is the air monitoring with thermal radiation resistant function Stake 103, high 4.5m.
Be equipped with two wind speed transducer ST in wind speed measurement stake, two wind speed transducer ST be respectively used to acquisition away from ground 1m, Wind speed at 4m, then it is transferred to blast velocity control unit respectively in the form of wind speed is converted into control electric signal.
As above stablize in air flow system, blast velocity control unit includes:
Power distribution isolator, power distribution isolator are used to receive the control electric signal of air monitoring unit transmission;
Fan frequency converter BP, fan frequency converter BP are connected with above-mentioned power distribution isolator, for being sent out according to air monitoring unit The revolving speed of the control electric signal adjust automatically blower 102 sent.
Power distribution isolator is multiple, and each power distribution isolator is connected from different fan frequency converter BP respectively.Specifically, matching Electric isolator is 2, and the two is respectively used to receive the control electric signal that two wind speed transducer ST are sent, wherein with for adopting Collect the corresponding power distribution isolator of wind speed transducer ST away from wind speed at the 4m of ground, three blowers for controlling and being located above 102 three fan frequency converter BP being respectively cooperating with;Match with for acquiring away from the wind speed transducer ST of wind speed is corresponding at the 1m of ground Electric isolator, for controlling two fan frequency converter BP being respectively cooperating with underlying two blowers 102, as shown in Figure 1.
It tests metope (i.e. above-mentioned facade) lower half portion and acquires in application, power distribution isolator SY2 is responsible for receiving Wind velocity signal the 2 Fans frequency converter B P positioned at lower half are distributed to relation of equal quantity, by fan frequency converter BP according to wind speed The revolving speed of 2 Fans 102 of the control electric signal adjust automatically lower half that monitoring unit is sent, to control under experiment surface Actual wind speed suffered by half part
Power distribution isolator SY3 is responsible for the wind velocity signal that reception experiment metope top half acquisition comes and is distributed to relation of equal quantity 3 Fans frequency converter B P of the blower fan group upper half, the control electric signal sent by fan frequency converter BP according to air monitoring unit The revolving speed of adjust automatically blower 102, to control actual wind speed suffered by experiment surface top half.
Preferably, in aforementioned stable air flow system, support frame 101 is set as including pedestal 111 and being assemblied on pedestal 111 Main body rack 112, blower 102 is fixed on main body rack 112.In the program, support frame 101 divides for pedestal 111 and main body 112 two parts of bracket, the two can manufacture respectively, reduce production difficulty, transport, store after can also mutually splitting the two, section Save space.
Specifically, blower 102 is set as being bolted on main body rack 112, main body rack 112 and pedestal 111 Using hinge engaging structure, installation convenient for safeguarding, and compact overall structure stability is good.In order to improve main body rack 112 and bottom The assembly reliability of seat 111, support frame 101 are set as further including drawstring 113, and main body rack 112 is fixed in one end of drawstring 113 Top, the other end is fixed on pedestal 111, and drawstring 113 is in tension.
Preferably, in aforementioned stable air flow system, pedestal 111 is equipped with universal wheel, and universal wheel has locking device, with root Any mobile package unit is required according to different wind directions, to change wind direction.
Specifically, the parameter of blower 102 is as follows in aforementioned stable air flow system: power of motor 18.5kw, revolving speed 1450r/ Min, wind pressure 1490-2032pa, exhaust air rate 15826-29344m/h, certainly, according to the actual wind speed of external environment, blower 102 Parameter may also be configured to other values, the present embodiment does not limit.
Stable air flow system provided in this embodiment at outdoor is away from ignition point 5m, kindling face height 10m, width 3.5m with In interior natural environment, it is entirely capable of output directional and the continuously adjustable wind for stablizing wind speed 4m/s-10m/s, blower 102 and support frame 101 can bear 250 degree of continuous heat-resisting operations in 4 hours.In addition in the stable air flow system, wind-speed sample and electrical control implementation are closed Ring control, has energy conservation, blast velocity control accurate, the fast advantage of reaction speed, and the test for stablizing wind speed is required suitable for indoor and outdoor Occasion.
Each embodiment in this specification is described in a progressive manner, the highlights of each of the examples are with other The difference of embodiment, the same or similar parts in each embodiment may refer to each other.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest scope of cause.

Claims (8)

1. a kind of stabilization air flow system for the test of external-wall heat-insulation material combustion simulation characterized by comprising
Blower, the blower setting on the support frame, are used to dry to facade;
Air monitoring unit, for monitoring the wind speed of predetermined position;
Blast velocity control unit, the control electric signal sent for receiving the air monitoring unit, and according to the control electric signal Control the blower.
2. stable air flow system according to claim 1, which is characterized in that the blower is multiple, each blower edge Vertical direction is successively set on support frame as described above.
3. stable air flow system according to claim 1, which is characterized in that the air monitoring unit includes:
Air monitoring stake, the air monitoring stake are arranged between the facade and the blower.
4. stable air flow system according to claim 3, which is characterized in that be equipped with two wind speed in the wind speed measurement stake Transmitter, the two is respectively used to acquire the wind speed away from ground 1m, 4m, then transmits respectively after being converted into control electric signal with wind speed Give blast velocity control unit.
5. stable air flow system according to claim 1, which is characterized in that the blast velocity control unit includes:
Power distribution isolator, the power distribution isolator are used to receive the control electric signal that the air monitoring unit is sent;
Fan frequency converter, the fan frequency converter are connected with the power distribution isolator, for being sent out according to the air monitoring unit The revolving speed of blower described in the control electric signal adjust automatically sent.
6. stable air flow system according to claim 5, which is characterized in that the power distribution isolator is multiple, and each Power distribution isolator is connected from the different fan frequency converters respectively.
7. stable air flow system according to claim 1, which is characterized in that support frame as described above includes:
Pedestal;
The main body rack of assembly on the base, the blower are fixed on the main body rack.
8. stable air flow system according to claim 7, which is characterized in that the pedestal is equipped with universal wheel, and described ten thousand Locking device is had to wheel.
CN201910763398.7A 2019-08-19 2019-08-19 Stabilization air flow system for the test of external-wall heat-insulation material combustion simulation Pending CN110439841A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910763398.7A CN110439841A (en) 2019-08-19 2019-08-19 Stabilization air flow system for the test of external-wall heat-insulation material combustion simulation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910763398.7A CN110439841A (en) 2019-08-19 2019-08-19 Stabilization air flow system for the test of external-wall heat-insulation material combustion simulation

Publications (1)

Publication Number Publication Date
CN110439841A true CN110439841A (en) 2019-11-12

Family

ID=68436266

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910763398.7A Pending CN110439841A (en) 2019-08-19 2019-08-19 Stabilization air flow system for the test of external-wall heat-insulation material combustion simulation

Country Status (1)

Country Link
CN (1) CN110439841A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04252898A (en) * 1991-01-28 1992-09-08 Fujitsu Ltd Fan rotation monitoring circuit
CN202057708U (en) * 2011-04-27 2011-11-30 重庆迪洋仪表有限责任公司 Power distribution isolator
CN106526069A (en) * 2016-12-22 2017-03-22 公安部四川消防研究所 Environment wind field simulation unit and environment wind field simulation system applied to fireproof performance test of building exterior wall
CN206349646U (en) * 2017-01-13 2017-07-21 北京兴达奇热工控制设备有限公司 A kind of distribution isolating device
CN108320650A (en) * 2018-04-23 2018-07-24 中国科学技术大学 A kind of lower ship open top cabin fire test simulator of ambient wind effect
CN209145939U (en) * 2018-10-26 2019-07-23 广州科劳斯实验室仪器设备有限公司 A kind of multi-joint blower fan control system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04252898A (en) * 1991-01-28 1992-09-08 Fujitsu Ltd Fan rotation monitoring circuit
CN202057708U (en) * 2011-04-27 2011-11-30 重庆迪洋仪表有限责任公司 Power distribution isolator
CN106526069A (en) * 2016-12-22 2017-03-22 公安部四川消防研究所 Environment wind field simulation unit and environment wind field simulation system applied to fireproof performance test of building exterior wall
CN206349646U (en) * 2017-01-13 2017-07-21 北京兴达奇热工控制设备有限公司 A kind of distribution isolating device
CN108320650A (en) * 2018-04-23 2018-07-24 中国科学技术大学 A kind of lower ship open top cabin fire test simulator of ambient wind effect
CN209145939U (en) * 2018-10-26 2019-07-23 广州科劳斯实验室仪器设备有限公司 A kind of multi-joint blower fan control system

Similar Documents

Publication Publication Date Title
US9683554B2 (en) Acoustic noise monitoring system for a wind turbine
EP3193013B1 (en) Anti-icing and deicing method and device for high-power wind turbine blades
CN202204680U (en) All fresh air handling system for aircraft engine performance testing device
WO2021230188A1 (en) Indoor environment adjustment method and indoor environment adjustment system
CN110439841A (en) Stabilization air flow system for the test of external-wall heat-insulation material combustion simulation
CN109264205A (en) A kind of communication equipment box that can be adjusted according to Changes in weather
CN113539047A (en) Linkage type parallelization ecological environment simulation device and system
CN114674979A (en) On-spot carbon emission detection device of operation based on 5G and unmanned aerial vehicle
CN210486312U (en) Drying device of diode production usefulness
CN208001691U (en) A kind of new energy green house of vegetables temperature-adjusting device
CN208253579U (en) A kind of novel air-fuel Self Matching top adjustment is than box-type gas temperature adjustment burner
CN108571734B (en) Control device for garbage combustion temperature
CN213580013U (en) Pneumatic heat-vibration combined test device for flat model with adjustable attack angle
CN203901904U (en) Polyethylene separation plate and glass fiber compounding machine
CN220038910U (en) Portable automatic temperature control's firing equipment
CN102944145B (en) A kind of small arms test aspect ratio is the low speed free jet equipment of 180: 1
CN102937817B (en) Stationary temperature and constant air pressure control device and method of lithium ion battery pole piece drying baker
CN211043431U (en) Multifunctional integrated wind element calibrating device
CN206818817U (en) Tropical deterioration room
CN207674656U (en) A kind of power cable connector conditions warrant device
CN111786279A (en) Real-time monitoring system applied to low-voltage power distribution cabinet
CN111638735A (en) Constant-volume combustion bomb heating device and method
CN204216453U (en) A kind of reactor with T-shaped core insulation against ground prosthetic device
CN201666490U (en) High and low temperature protective device for laser performance
CN207831817U (en) dryer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191112

RJ01 Rejection of invention patent application after publication