CN110429548A - A kind of framework of steel reinforcement and its method for arranging of the prefabricated cover board of cable duct corner - Google Patents

A kind of framework of steel reinforcement and its method for arranging of the prefabricated cover board of cable duct corner Download PDF

Info

Publication number
CN110429548A
CN110429548A CN201910809654.1A CN201910809654A CN110429548A CN 110429548 A CN110429548 A CN 110429548A CN 201910809654 A CN201910809654 A CN 201910809654A CN 110429548 A CN110429548 A CN 110429548A
Authority
CN
China
Prior art keywords
stress
steel bar
steel
cable duct
cover board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910809654.1A
Other languages
Chinese (zh)
Other versions
CN110429548B (en
Inventor
朱梦伟
王学明
吴彤
杨磊
石磊
王虎长
张媛
文凡
刘军
尚艳军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northwest Electric Power Design Institute of China Power Engineering Consulting Group
Original Assignee
Northwest Electric Power Design Institute of China Power Engineering Consulting Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northwest Electric Power Design Institute of China Power Engineering Consulting Group filed Critical Northwest Electric Power Design Institute of China Power Engineering Consulting Group
Priority to CN201910809654.1A priority Critical patent/CN110429548B/en
Publication of CN110429548A publication Critical patent/CN110429548A/en
Application granted granted Critical
Publication of CN110429548B publication Critical patent/CN110429548B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/02Installations of electric cables or lines in or on the ground or water laid directly in or on the ground, river-bed or sea-bottom; Coverings therefor, e.g. tile
    • H02G9/025Coverings therefor, e.g. tile

Abstract

The framework of steel reinforcement and production method of a kind of prefabricated cover board of cable duct corner provided by the invention, steel bar layer in prefabricated cover board is constituted using several positioning stirrups and several steel bar stress groups, steel bar stress group is people's font structure, the big one end of preform lid board width is arranged in open end, the small one end of preform lid board width is arranged in the other end of steel bar stress, this makes it possible to the pre-buried quantity of reinforcing bar for reducing the small one end of preform lid board width, it can guarantee the number of steel bars of the big one end of prefabricated cover plate diameter simultaneously, therefore it can guarantee the reliability that the bonding of the pure land is mixed between reinforcing bar, improve the intensity of prefabricated cover board.

Description

A kind of framework of steel reinforcement and its method for arranging of the prefabricated cover board of cable duct corner
Technical field
The present invention relates to power line cables civil engineering fields, and in particular to a kind of prefabricated cover board of cable duct corner Framework of steel reinforcement and its method for arranging.
Background technique
With the growth of national economy, the raising of living standards of the people, urban development is getting faster, more and more cities The transmission and distribution networks that cobweb formula is taken leave of in development carry out overhead line and land policy.More and more overhead lines are by electric power electricity Cable replaces, and cable duct laying is one of main overhead cabling method.
Cable channel cover plate is the important component part of cable duct, at cable duct turning, will be generated " one one big It is small " sector cable trench cover.When cable duct width is more than certain range, the width at trapezoidal cable duct both ends can be differed very Greatly, a wide end bar is excessively dilute, and the concrete between reinforcing bar and reinforcing bar may generate local failure;An or narrow end bar Overstocked, concrete, which is difficult to pour, to vibrate, and the reliable bond of the concrete between reinforcing bar is difficult to ensure.Give city cable power transmission and distribution The long-term safety of system and stable operation bring hidden danger.
In order to overcome existing technological deficiency, the present invention has developed a kind of reinforcing bar of the prefabricated cover board of cable duct corner Skeleton and its method for arranging.
Summary of the invention
The non-uniform problem of cover board steel bar arrangement is pre-payed for corner in the prior art, the present invention provides a kind of cable duct turn The framework of steel reinforcement and its method for arranging of prefabricated cover board at angle, under conditions of guaranteeing to meet stress, reasonable few reinforcing bar Quantity improves the adhesion strength of concrete, and then improves the intensity of cover board.
The present invention is to be achieved through the following technical solutions:
A kind of framework of steel reinforcement of the prefabricated cover board of cable duct corner, if including several spaced positioning stirrups and Dry spaced steel bar stress group, positioning stirrup are ring structure, and circumferential section is the extending direction of cable duct, stress steel The length direction of muscle group is the width direction of cable duct;
The inside of positioning stirrup is arranged in steel bar stress group, and steel bar stress group is herringbone structure, and steel bar stress group is opened Mouth end is located at the big side of preform lid board width, and the other end of steel bar stress group is located at the small side of preform lid board width.
Preferably, the steel bar stress group includes two symmetrically arranged steel bar stresses, and each steel bar stress includes first Stress section and the second stress section, the first stress section are connect by bending section with the second stress section;
First stress section of two steel bar stresses is close to, and the second stress section of two steel bar stresses is symmetricly set on overlapping The two sides of two the first stress sections make steel bar stress group form herringbone structure.
Preferably, the distance between two second stress sections in the steel bar stress group and two neighboring stress steel Spacing between muscle group meets reinforcement constitution requirement.
Preferably, the bending angle of the bending section is 30-60 °.
Preferably, the spacing between the two neighboring positioning stirrup is 120-180mm.
The present invention also provides a kind of method for arranging of the framework of steel reinforcement of the prefabricated cover board of cable duct corner, including it is following Step:
1) according to the shape of cable duct corner, the template of prefabricated cover board is built;
2) it is spaced apart several positioning stirrups in a template, positions the circumferential section of stirrup and the extending direction phase of cable duct Together;
3) the connection reinforcing bar for placing a linear structure respectively at four inflection points of positioning stirrup, several positioning stirrups are connected It connects, forms rectangle reinforcement cage structure;
4) several steel bar stresses are placed in the inside of steel reinforcement cage, the length direction of steel bar stress is the width along cable duct Direction, the first stress section are located at the small one end of template width, and the second stress section is located at the big one end of template width, and two neighboring Steel bar stress is symmetrical arranged;
5) overlapping of the first stress section of two neighboring steel bar stress is tied up, forms steel bar stress group, by steel bar stress It organizes and is tied up at the top of steel reinforcement cage.
Preferably, spacing and the second stress in step 5, between the first stress section of two neighboring steel bar stress group Spacing between section, meets reinforcement constitution requirement.
It is embedding in the prefabricated cover board to have above-mentioned steel the present invention also provides a kind of prefabricated cover board of cable duct corner Tendons skeleton.
Compared with prior art, the invention has the following beneficial technical effects:
A kind of framework of steel reinforcement of the prefabricated cover board of cable duct corner provided by the invention, if including several positioning stirrups and Dry steel bar stress group is constituted, and steel bar stress group is people's font structure, and the big one end of preform lid board width, stress is arranged in open end The small one end of preform lid board width is arranged in the other end of reinforcing bar, and this makes it possible to the steel for reducing the small one end of preform lid board width The pre-buried quantity of muscle, while can guarantee the number of steel bars of the big one end of prefabricated cover plate diameter, therefore can guarantee to mix between reinforcing bar The reliability of the bonding of the pure land improves the intensity of prefabricated cover board.
The production method of framework of steel reinforcement provided by the invention, by template from bottom to top successively be laid with positioning stirrup and Steel bar stress group need to make it meet the detailing requiments of reinforcing bar when being laid with steel bar stress group, since steel bar stress uses bending structure, Therefore " two-in-one " and muscle processing can be carried out to the small end of prefabricated cover board, and two neighboring steel bar stress is made to form chevron shaped knot Structure reduces the quantity of reinforcing bar, finally in casting concrete, can be avoided the concrete between reinforcing bar and generates local failure, or Concrete is difficult to pour the problem of vibrating, while improving the reliability of concrete binding between reinforcing bar, improves cable channel cover plate Intensity, guarantee safety, reliability and the durability of prefabricated cover board, guarantee city cable electrical power trans mission/distribution system long-term safety and Stable operation.
Detailed description of the invention
Fig. 1 is the bottom layer of the reinforcing steel layout drawing of cable trench prefabricating cover board of the present invention;
Fig. 2 is the structural schematic diagram of steel bar stress group of the present invention;
Fig. 3 is the sectional view of the prefabricated cover board big end of the present invention;
Fig. 4 is the sectional view of the prefabricated cover board small end of the present invention.
In figure: 1, steel bar stress group;2, stirrup is positioned;3, template;4, steel bar stress;5, the first stress section;6, bending segment; 7, the second stress section.
Specific embodiment
Present invention will be described in further detail below with reference to the accompanying drawings, described to be explanation of the invention rather than limit It is fixed.
Refering to fig. 1, a kind of framework of steel reinforcement of the prefabricated cover board of cable duct corner, including several spaced positioning Stirrup and several spaced steel bar stress groups, positioning stirrup 2 are ring structure, and the circumferential section for positioning stirrup is cable The extending direction of ditch, steel bar stress group 1 are located at the inside of positioning stirrup 2, and angularly uniformly distributed, the length side of steel bar stress group 1 To for the of same size of cable duct, make the bottom for positioning stirrup 2 and steel bar stress group 1 in cross arranged crosswise.
Steel bar stress group 1 is herringbone structure, and the open end of steel bar stress group is located at the big side of preform lid board width, by The other end of power reinforcing bar group is located at the small side of preform lid board width.
Referring to Fig.2, the steel bar stress group 1 of the herringbone structure, including two symmetrically arranged steel bar stresses 4, each Reinforcing bar includes the first stress section 5 and the second stress section 7, and one end of the first stress section 5 passes through bending section 6 and the second stress section 7 One end.
First stress section 5 of two steel bar stresses 4 is connected by tying up overlapping, forms an overall structure, and two second Stress section 7 is symmetricly set on the two sides of two the first stress sections 5 of overlapping, forms U-type groove between two the second stress sections 7, into And steel bar stress group 1 is made to form herringbone structure.
The first about 5 stress section overlapping of two steel bar stresses 4 is connected or horizontally overlapping connected.
One end of bending section 6 is connect with the first stress section 5, and the other end is connect with the second stress section 7, the first stress section 5, folding Curved segment 6 and the second stress section 7 are overall structure, and the reinforcing bar of You Yigen linear structure carries out bending twice and formed, and bending angle is 30-60 °, the angle of bending section 6 and the first stress section 5 or the second stress section 7 is 30-60 °.
The distance between two second stress sections 7 in the steel bar stress group 1 and two neighboring steel bar stress group it Between spacing, it is necessary to meet reinforcement constitution requirement.
Spacing between the two neighboring positioning stirrup 2 is 120-180mm.
A kind of framework of steel reinforcement of the prefabricated cover board of cable duct corner provided by the invention, if including several positioning stirrups and Dry steel bar stress group is constituted, and steel bar stress group is people's font structure, and the big one end of preform lid board width, stress is arranged in open end The small one end of preform lid board width is arranged in the other end of reinforcing bar, and this makes it possible to the steel for reducing the small one end of preform lid board width The pre-buried quantity of muscle, while can guarantee the number of steel bars of the big one end of prefabricated cover plate diameter, therefore can guarantee to mix between reinforcing bar The reliability of the bonding of the pure land improves the intensity of prefabricated cover board.
Refering to Fig. 3 and 4, the present invention also provides the arrangement sides of the framework of steel reinforcement of the prefabricated cover board of above-mentioned cable duct corner Method, comprising the following steps:
1) according to the shape of cable duct corner, the template 3 of prefabricated cover board is built, need to guarantee that 3 inner wall of template is flat and smooth, Template 3 connects reliably.
2) arrangement positioning stirrup, the positioning stirrup 2 of several ring structures is spaced apart in template plate, positions stirrup Circumferential section is identical as the extending direction of cable duct, and the quantity for positioning stirrup 2 is determined according to the length of prefabricated cover board.
Two neighboring positioning stirrup spacing is 120mm-180mm.
2 specification of positioning stirrup is determined by cable channel cover plate shear calculation.
3) the connection reinforcing bar for placing a linear structure respectively at four inflection points of positioning stirrup 2, by several positioning stirrups Connection forms rectangle reinforcement cage structure.
4) refering to Fig. 3, several steel bar stresses 4 are placed in the inside of steel reinforcement cage, the length direction of steel bar stress is along electricity The width direction of cable ditch, the first stress section 5 are located at the small one end of template width, and the second stress section 7 is located at big one of template width End, and two neighboring steel bar stress 4 is symmetrical arranged.
5) refering to Fig. 4, the first stress section 5 overlapping of two neighboring steel bar stress is tied up, steel bar stress group 1 is formed, then It will be tied up at the top of steel bar stress group and steel reinforcement cage.
The spacing between spacing and the second stress section 7 between first stress section 5 of two neighboring steel bar stress group, Meet reinforcement constitution requirement.
The steel bar stress group 1 takes herringbone pattern, guarantees that the bar spacing of preform lid board ends all meets reinforcing bar Detailing requiments.
1 specification of steel bar stress group is determined by cable channel cover plate flexural calculation.
6) casting concrete in template 3 completes the production of prefabricated cover board after concrete setting.
The production method of the framework of steel reinforcement of the prefabricated cover board of cable duct corner provided by the invention, by template from It is successively laid with positioning stirrup and steel bar stress group on down, it need to be made to meet the detailing requiments of reinforcing bar when being laid with steel bar stress group, Since steel bar stress group uses chevron shaped structure, " two-in-one " and muscle processing can be carried out to the small end of prefabricated cover board, is subtracted The quantity of reinforcing bar is lacked, finally in casting concrete, the concrete that can be avoided between reinforcing bar generates local failure or concrete It is difficult to pour the problem of vibrating, while improving the reliability of concrete binding between reinforcing bar, improve the intensity of cable channel cover plate, Guarantee safety, reliability and the durability of prefabricated cover board, guarantee the long-term safety of city cable electrical power trans mission/distribution system and stablizes fortune Row.
A kind of prefabricated cover board of cable duct corner, the concrete layer including fanning ring type structure are embedding in concrete layer Above-mentioned framework of steel reinforcement.
The above content is merely illustrative of the invention's technical idea, and this does not limit the scope of protection of the present invention, all to press According to technical idea proposed by the present invention, any changes made on the basis of the technical scheme each falls within claims of the present invention Protection scope within.

Claims (8)

1. a kind of framework of steel reinforcement of the prefabricated cover board of cable duct corner, which is characterized in that spaced fixed including several Position stirrup (2) and several spaced steel bar stress groups (1), positioning stirrup (2) are ring structure, and circumferential section is cable The extending direction of ditch, the length direction of steel bar stress group (1) are the width direction of cable duct;
In the inside of positioning stirrup (2), steel bar stress group (1) is herringbone structure, steel bar stress group for steel bar stress group (1) setting (1) open end is located at the big side of preform lid board width, and it is small that the other end of steel bar stress group (1) is located at preform lid board width Side.
2. the framework of steel reinforcement of the prefabricated cover board of cable duct corner according to claim 1, which is characterized in that the stress steel Muscle group (1) includes two symmetrically arranged steel bar stresses (4), and each steel bar stress includes the first stress section (5) and the second stress Section (7), the first stress section (5) are connect by bending section (6) with the second stress section (7);
First stress section (5) of two steel bar stresses (4) is close to, and the second stress section (7) of two steel bar stresses is symmetricly set on The two sides of two the first stress sections (5) of overlapping make steel bar stress group (1) to form herringbone structure.
3. the framework of steel reinforcement of the prefabricated cover board of cable duct corner according to claim 2, which is characterized in that the stress steel Spacing between the distance between two second stress sections (7) in muscle group (1) and two neighboring steel bar stress group meets Reinforcement constitution requirement.
4. the framework of steel reinforcement of the prefabricated cover board of cable duct corner according to claim 2, which is characterized in that the bending section (6) bending angle is 30-60 °.
5. the framework of steel reinforcement of the prefabricated cover board of cable duct corner according to claim 1, which is characterized in that described adjacent two Spacing between a positioning stirrup (2) is 120-180mm.
6. a kind of method for arranging of the framework of steel reinforcement of the prefabricated cover board of the cable duct corner any one of claim 1-5, It is characterized in that, comprising the following steps:
1) according to the shape of cable duct corner, the template (3) of prefabricated cover board is built;
2) it is spaced apart several positioning stirrups (2) in a template, positions the circumferential section of stirrup and the extending direction phase of cable duct Together;
3) the connection reinforcing bar for placing a linear structure respectively at four inflection points of positioning stirrup (2), several positioning stirrups are connected It connects, forms rectangle reinforcement cage structure;
4) several steel bar stresses (4) are placed in the inside of steel reinforcement cage, the length direction of steel bar stress is the width along cable duct Direction, the first stress section (5) are located at the small one end of template width, and the second stress section (7) is located at the big one end of template width, and phase Adjacent two steel bar stresses (4) are symmetrical arranged;
5) overlapping of the first stress section (5) of two neighboring steel bar stress is tied up, is formed steel bar stress group (1), by stress steel It is tied up at the top of muscle group and steel reinforcement cage.
7. the arrangement of the framework of steel reinforcement of the prefabricated cover board for stating cable duct corner of cable duct corner according to claim 6 Method, which is characterized in that the spacing and second in step 5, between the first stress section (5) of two neighboring steel bar stress group Spacing between stress section (7), meets reinforcement constitution requirement.
8. a kind of prefabricated cover board of cable duct corner, which is characterized in that embedding in the prefabricated cover board to have the right that 1-5 is required to appoint Framework of steel reinforcement described in one.
CN201910809654.1A 2019-08-29 2019-08-29 Reinforcement skeleton of prefabricated cover plate at corner of cable trench and arrangement method of reinforcement skeleton Active CN110429548B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910809654.1A CN110429548B (en) 2019-08-29 2019-08-29 Reinforcement skeleton of prefabricated cover plate at corner of cable trench and arrangement method of reinforcement skeleton

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910809654.1A CN110429548B (en) 2019-08-29 2019-08-29 Reinforcement skeleton of prefabricated cover plate at corner of cable trench and arrangement method of reinforcement skeleton

Publications (2)

Publication Number Publication Date
CN110429548A true CN110429548A (en) 2019-11-08
CN110429548B CN110429548B (en) 2024-02-06

Family

ID=68418103

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910809654.1A Active CN110429548B (en) 2019-08-29 2019-08-29 Reinforcement skeleton of prefabricated cover plate at corner of cable trench and arrangement method of reinforcement skeleton

Country Status (1)

Country Link
CN (1) CN110429548B (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AR074784A4 (en) * 2009-12-17 2011-02-09 Cupa Materiales Sa PREFABRICATED PANEL WITH SIDE VIEW TYPE FOR WALL CONSTRUCTION, WITH ANCHORAGE AND MANUFACTURING PROCESS
CN202989953U (en) * 2012-12-20 2013-06-12 湖南送变电勘察设计咨询有限公司 High-strength light anticorrosion concrete base prefabricating assembling cable trench
CN204221939U (en) * 2014-11-03 2015-03-25 国家电网公司 A kind of precast concrete cable channel cover plate mold system
CN104878872A (en) * 2015-05-19 2015-09-02 华南理工大学 Ultra-high performance concrete cover plate with truss structure framework and production method of ultra-high performance concrete cover plate
CN104878874A (en) * 2015-05-19 2015-09-02 华南理工大学 Pier head reinforced ultra-high performance concrete cover plate and production method thereof
CN105178514A (en) * 2015-08-17 2015-12-23 陈胜民 Three-arch three-fillet triangle type efficient high-strength thread reinforcing bar and using method thereof
KR20160119623A (en) * 2015-04-06 2016-10-14 (주)나우기술 PC Concrete Structure of Variable section Reinforce for Increse Stiffness with Projecting Cable and Truss Structure
CN106049763A (en) * 2016-07-27 2016-10-26 中国建筑第八工程局有限公司 Ribbed rebar with cross ribs staggered
CN108560796A (en) * 2018-04-17 2018-09-21 昆明理工大学 A kind of concrete T type rib Covered with Angles prefabricated panel and its superimposed sheet of making
CN210129724U (en) * 2019-08-29 2020-03-06 中国电力工程顾问集团西北电力设计院有限公司 Steel reinforcement framework of prefabricated apron and prefabricated apron of cable pit corner

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AR074784A4 (en) * 2009-12-17 2011-02-09 Cupa Materiales Sa PREFABRICATED PANEL WITH SIDE VIEW TYPE FOR WALL CONSTRUCTION, WITH ANCHORAGE AND MANUFACTURING PROCESS
CN202989953U (en) * 2012-12-20 2013-06-12 湖南送变电勘察设计咨询有限公司 High-strength light anticorrosion concrete base prefabricating assembling cable trench
CN204221939U (en) * 2014-11-03 2015-03-25 国家电网公司 A kind of precast concrete cable channel cover plate mold system
KR20160119623A (en) * 2015-04-06 2016-10-14 (주)나우기술 PC Concrete Structure of Variable section Reinforce for Increse Stiffness with Projecting Cable and Truss Structure
CN104878872A (en) * 2015-05-19 2015-09-02 华南理工大学 Ultra-high performance concrete cover plate with truss structure framework and production method of ultra-high performance concrete cover plate
CN104878874A (en) * 2015-05-19 2015-09-02 华南理工大学 Pier head reinforced ultra-high performance concrete cover plate and production method thereof
CN105178514A (en) * 2015-08-17 2015-12-23 陈胜民 Three-arch three-fillet triangle type efficient high-strength thread reinforcing bar and using method thereof
CN106049763A (en) * 2016-07-27 2016-10-26 中国建筑第八工程局有限公司 Ribbed rebar with cross ribs staggered
CN108560796A (en) * 2018-04-17 2018-09-21 昆明理工大学 A kind of concrete T type rib Covered with Angles prefabricated panel and its superimposed sheet of making
CN210129724U (en) * 2019-08-29 2020-03-06 中国电力工程顾问集团西北电力设计院有限公司 Steel reinforcement framework of prefabricated apron and prefabricated apron of cable pit corner

Also Published As

Publication number Publication date
CN110429548B (en) 2024-02-06

Similar Documents

Publication Publication Date Title
CN208533764U (en) A kind of panel structure
CN207582764U (en) A kind of close spelling laminated floor slab connecting joint structure of end fluting
CN104032869B (en) A kind of Prefabricated stacking floor and precast construction method thereof
CN105839818A (en) Integral concrete prefabricated wallboard free of lateral die assembly as well as assembling structure and assembling method thereof
CN203238780U (en) Prefabricated stirrup cage of beam column core area
CN108678220A (en) A kind of concrete shear force wall of steel bar template integrative installation technology
CN108643585A (en) Precast concrete sandwich heat preservation Side fascia and its preparation construction method
CN110429548A (en) A kind of framework of steel reinforcement and its method for arranging of the prefabricated cover board of cable duct corner
CN210129724U (en) Steel reinforcement framework of prefabricated apron and prefabricated apron of cable pit corner
CN106087881B (en) A kind of precast concrete box-structure and cast-in-place concrete convolution Sluice Pier structure and its construction technology
CN209669918U (en) For the lattice barricade in geological disaster engineering
CN209163167U (en) A kind of precast floor slab connecting node construction
CN112942658B (en) Prefabricated bottom plate preparation method, prefabricated bottom plate structure and construction method thereof
CN206655359U (en) A kind of precast concrete overlapped shear wall
CN109339223A (en) A kind of connecting node and its construction method of column and steel lid beam
CN206607689U (en) Precast beam and wallboard connecting structure and building
CN211499382U (en) Composite floor slab, building and frame for preparing composite floor slab
CN208142800U (en) A kind of small precast bracket of fixed multi-pipeline spacing
CN109024241B (en) Prefabricated assembled arch box and connecting method thereof
CN208329274U (en) A kind of prestressing without bondn steel reinforced concrete wall
CN208763209U (en) The assembled integral concrete frame structure of beam-ends connection
CN110359352A (en) A kind of prefabricated assembled T beam and construction method
CN206513097U (en) A kind of new omnipotent auxiliary cross-arm of " D " composite
CN110029729A (en) A kind of the splicing node and construction method of prefabricated reinforced concrete girder and secondary beam
CN218648554U (en) Novel cable cross river laying structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant