CN110424486A - A kind of construction method of nonstandard diaphragm wall - Google Patents

A kind of construction method of nonstandard diaphragm wall Download PDF

Info

Publication number
CN110424486A
CN110424486A CN201910630871.4A CN201910630871A CN110424486A CN 110424486 A CN110424486 A CN 110424486A CN 201910630871 A CN201910630871 A CN 201910630871A CN 110424486 A CN110424486 A CN 110424486A
Authority
CN
China
Prior art keywords
mud
wall
nonstandard
construction
diaphragm wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910630871.4A
Other languages
Chinese (zh)
Inventor
王欢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Sui Shi Civil Polytron Technologies Inc
Original Assignee
Guangzhou Sui Shi Civil Polytron Technologies Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Sui Shi Civil Polytron Technologies Inc filed Critical Guangzhou Sui Shi Civil Polytron Technologies Inc
Priority to CN201910630871.4A priority Critical patent/CN110424486A/en
Publication of CN110424486A publication Critical patent/CN110424486A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/187Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F5/00Dredgers or soil-shifting machines for special purposes
    • E02F5/02Dredgers or soil-shifting machines for special purposes for digging trenches or ditches

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses a kind of construction methods of nonstandard diaphragm wall, specifically includes the following steps: S1, according to the excavation of foundation pit depth of modern city project, the diaphram wall of 800mm, 900mm and 1000mm thickness is selected to be analyzed respectively, calculate the vertical ocean property grade beam method that code requirement is recommended, using consolidated quick index, fender post deformation, internal force calculating are all made of water and soil point and calculate principle, are calculated according to the construction operating condition drafted;The present invention relates to Diaphragm Wall fields.The construction method of the nonstandard diaphragm wall, it can guarantee the effect of whole construction, improve the quality of nonstandard diaphragm wall, and whole construction procedure is simplified, some raw material in construction are saved, mud is made according to practical soil property, it ensure that grooving quality and speed, the labor intensity of staff is reduced to a certain extent, and reduces the cost of integral construction, it is practical.

Description

A kind of construction method of nonstandard diaphragm wall
Technical field
The present invention relates to Diaphragm Wall field, specially a kind of construction method of nonstandard diaphragm wall.
Background technique
Diaphram wall is that foundation engineering uses a kind of trench machine on the ground, along all side axis of deep excavation project Line excavates out a long and narrow deep trouth under the conditions of mud off, after clear slot, steel reinforcement cage is hung in slot, then uses tremie method Underwater concreting with tremie method builds up a unit groove section, so carries out paragraph by paragraph, builds up continuous reinforced concrete wall together in underground Wall, as intercept water, antiseepage, load-bearing, water-retaining structure, the diaphram wall width of standard be generally 600mm, 800mm, 1000mm and 1200mm, and there is matched fore shaft to change and grab bucket with chute forming machine, construction is greatly facilitated in this way, but due to applying , there is the construction method of some nonstandard diaphragm walls in the difference of work situation, and the consideration in energy conservation, but existing The construction method construction effect of nonstandard diaphragm wall is general, and construction procedure is cumbersome, adds somewhat to work people The labor intensity of member.
Traditional nonstandard diaphragm wall, it is impossible to ensure that the effect of whole construction, reduces non-standard underground and connect The quality of continuous wall, whole construction is cumbersome, wastes some raw material in construction, it is difficult to guarantee grooving quality and speed, one Determine the labor intensity for increasing staff in degree, and increases the cost of integral construction, it is not very practical.
Summary of the invention
(1) the technical issues of solving
In view of the deficiencies of the prior art, it the present invention provides a kind of construction method of nonstandard diaphragm wall, solves The bad and at high cost problem of nonstandard diaphragm wall construction effect.
(2) technical solution
In order to achieve the above object, the present invention is achieved by the following technical programs: a kind of nonstandard diaphragm wall Construction method, specifically includes the following steps:
S1, according to the excavation of foundation pit depth of modern city project, select the underground company of 800mm, 900mm and 1000mm thickness respectively Continuous wall is analyzed, and the vertical ocean property grade beam method that code requirement is recommended is calculated, using consolidated quick index, fender post deformation, Internal force calculating is all made of water and soil point and calculates principle, is calculated according to the construction operating condition drafted;
S2, it is excavated by triumphant sharp rod-type hydraulic grab chute forming machine to mud stone top surface, rushes rock with dedicated block stamp using rock machine is rushed It to design slot bottom absolute altitude, then changes block stamp into plane set-hammer and repairs slot, after repairing slot qualification, slurry is changed at clear bottom, after acceptance(check), using 1 150t crawler crane and 1 80t crawler crane lift placement steel reinforcement cage, steel reinforcement cage weight about 32t, the integral manufacturing on steel reinforcement cage platform Tremie is placed in molding, secondary to change slurry, after acceptance(check), pours underwater concrete immediately;
S3, after pouring beginning in S2, answer it is compact continuously carry out, forbid midway stop work, to be prevented in filling process Concrete mix overflows from funnel top or falls into outside funnel bottom hole, in filling process, it should be noted that under observation tube inner concrete Drop and water level in borehole go up and down situation, timely measured hole inner concrete face height, to ensure stake top quality, when filling concrete to stake When top, superfilled 800-1000mm is answered, to guarantee after cutting laitance, concrete quality can meet design requirement at stake item absolute altitude;
S4, the particularity due to nonstandard diaphragm wall, conventional grab bucket are reequiped, main utilize of grabbing bucket 800mm thickness diaphram wall standard bucket two sides are welded with certain thickness sawtooth pattern iron plate, but in the case of soil property is harder, take an examination It grabs native ability relative drop caused by considering after reequiping and efficiency is caused to reduce, then wedge type locking notch pipe is re-worked again;
S5, the design that mud match ratio is carried out according to this engineering geological condition cutting method and purposes etc., determine reasonable Mud match ratio, the mud used in construction of diaphragm wall in lithostratigraphy are as follows: bentonite, bonding agent, dispersing agent and tap water It is formed through rational proportion, it is desirable that viscosity is appropriate, and specific gravity meets the requirements, and stability is good, and filtering fluid loss is small, and it is short that mudcake forms the time And thin and flexible, while requiring to reinforce the mud management in work progress, quality of mud fluid detection is carried out on time, is adjusted in time Mud index is handled nonadjustable discarded poor mud, in time so that it is guaranteed that slurry trench stability;
After S6, construction of guide wall are good, using GPS-2000 type drilling machine at the both ends of each slot section and centre along diaphram wall It is longitudinal respectively bore a hole should be first in place by drilling machine before drilling, with level detecting pad is steady, leveling, the theodolite being mutually with two Adjust drilling rod verticality, in boring procedure, 5 meters of every drilling depth are detected a hole wall verticality with ultrasound wall instrument, and discovery is inclined Difference adjusts immediately, and to guarantee to be not more than at hole perpendicularity 1300, drilling depth is diaphragm wall projected depth, detects whole hole again and hangs down Straight degree, the backward shift that meets the requirements are bored next slot section and are excavated after the guide hole of each slot section is drilled using hydraulic grab bucket grooving machine To the above soil layer of mixed rock, chute forming machine is in place, grooving center line is confirmed, with two theodolite inspection adjustment guide rods and grab bucket for top surface Verticality is less than 2%, and checks that all auxiliary facilities are intact, can start grooving, before grooving, pays attention to one side grooving one While mud is continuously replenished, keeps mud face leading wall top face or less 300-500mm, guarantee the mud pressure in slot section, to prevent upper Collapse hole excavates precision in addition to the dipmeter automatic measurement carried with chute forming machine, every digging depth 5m or so is used during grooving Ultrasound wall instrument measures the verticality of a cell wall, if required precision is not achieved, adjustment correction in time, until mud stone top surface;
S7, in S6 after grooving, allow in slot section after mud sediment 30 minutes, it is heavy that Cao bottom gently picked up with hydraulic grab Then slag picks up remaining sediment with vacuum pump, after monitor station lattice, using crawler crane erection joint pipe, installation course It is middle to correct its verticality with theodolite, and slowly put down, underground continuous wall groove segment and the cleaning of slot section seam are using autocratic wire brush Clean with water, wire brush be fixed on chute forming machine grab bucket on, be close to concrete surface pull back and forth up and down, until pull out wire brush on without Until spare.
Preferably, in the S2 triumphant benefit rod-type hydraulic grab chute forming machine model LS-418J.
Preferably, the depth segment of conduit Transducers Embedded in Concrete is preferably controlled in 2-6m in the S3, the correct promotion for commanding conduit And dismounting.
Preferably, mud processing method is to guarantee the important link of quality of mud fluid in the S5, using RM-2000 type 2m mud Slurry blender is stirred, and when mud configuration, is first configured two tanks, is then sampled inspections, is determining the conjunction of mud property parameter After requiring, it can be produced in batches.
Preferably, due to criteria of right and wrong diaphram wall in the S7, therefore junction block is using the compromise joint of customization processing Pipe, side are semicircle, and another is convex, merogenesis connection, and 8 meters of every section length is pulled out using self-control pulling power traction, seam cleaning Work should be completed at clear bottom after grooving before changing slurry.
(3) beneficial effect
The present invention provides a kind of construction methods of nonstandard diaphragm wall.Have following the utility model has the advantages that this is non-standard The construction method of diaphram wall selects 800mm, 900mm by S1, according to the excavation of foundation pit depth of modern city project respectively It is analyzed with the diaphram wall of 1000mm thickness, calculates the vertical ocean property grade beam method that code requirement is recommended, it is fast using consolidation Index is cut, fender post deformation, internal force calculating are all made of water and soil point and calculate principle, calculated according to the construction operating condition drafted;S2, lead to It crosses triumphant sharp rod-type hydraulic grab chute forming machine to excavate to mud stone top surface, rushes rock to design slot bottom mark with dedicated block stamp using rock machine is rushed Then height changes block stamp into plane set-hammer and repairs slot, after repairing slot qualification, slurry is changed at clear bottom, after acceptance(check), using 1 150t crawler crane and 1 Platform 80t crawler crane lifts placement steel reinforcement cage, and steel reinforcement cage weight about 32t, integral manufacturing forms on steel reinforcement cage platform, places coagulation Native conduit, it is secondary to change slurry, after acceptance(check), underwater concrete is poured immediately;The effect that can guarantee whole construction, improves The quality of nonstandard diaphragm wall, and whole construction procedure is simplified, save some raw material in construction, mud root Factually border soil property is made, and ensure that grooving quality and speed, reduces the labor intensity of staff to a certain extent, and Reduce the cost of integral construction, it is practical.
Specific embodiment
Below in conjunction with the embodiment of the present invention, technical solution of the present invention is clearly and completely described, it is clear that institute The embodiment of description is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, Every other embodiment obtained by those of ordinary skill in the art without making creative efforts, belongs to this hair The range of bright protection.
The embodiment of the present invention provides a kind of technical solution: a kind of construction method of nonstandard diaphragm wall specifically includes Following steps:
S1, according to the excavation of foundation pit depth of modern city project, select the underground company of 800mm, 900mm and 1000mm thickness respectively Continuous wall is analyzed, and the vertical ocean property grade beam method that code requirement is recommended is calculated, using consolidated quick index, fender post deformation, Internal force calculating is all made of water and soil point and calculates principle, is calculated according to the construction operating condition drafted;
S2, it is excavated by triumphant sharp rod-type hydraulic grab chute forming machine to mud stone top surface, rushes rock with dedicated block stamp using rock machine is rushed It to design slot bottom absolute altitude, then changes block stamp into plane set-hammer and repairs slot, after repairing slot qualification, slurry is changed at clear bottom, after acceptance(check), using 1 150t crawler crane and 1 80t crawler crane lift placement steel reinforcement cage, steel reinforcement cage weight about 32t, the integral manufacturing on steel reinforcement cage platform Tremie is placed in molding, secondary to change slurry, after acceptance(check), pours underwater concrete immediately;
S3, after pouring beginning in S2, answer it is compact continuously carry out, forbid midway stop work, to be prevented in filling process Concrete mix overflows from funnel top or falls into outside funnel bottom hole, in filling process, it should be noted that under observation tube inner concrete Drop and water level in borehole go up and down situation, timely measured hole inner concrete face height, to ensure stake top quality, when filling concrete to stake When top, superfilled 800-1000mm is answered, to guarantee after cutting laitance, concrete quality can meet design requirement at stake item absolute altitude;
S4, the particularity due to nonstandard diaphragm wall, conventional grab bucket are reequiped, main utilize of grabbing bucket 800mm thickness diaphram wall standard bucket two sides are welded with certain thickness sawtooth pattern iron plate, but in the case of soil property is harder, take an examination It grabs native ability relative drop caused by considering after reequiping and efficiency is caused to reduce, then wedge type locking notch pipe is re-worked again;
S5, the design that mud match ratio is carried out according to this engineering geological condition cutting method and purposes etc., determine reasonable Mud match ratio, the mud used in construction of diaphragm wall in lithostratigraphy are as follows: bentonite, bonding agent, dispersing agent and tap water It is formed through rational proportion, it is desirable that viscosity is appropriate, and specific gravity meets the requirements, and stability is good, and filtering fluid loss is small, and it is short that mudcake forms the time And thin and flexible, while requiring to reinforce the mud management in work progress, quality of mud fluid detection is carried out on time, is adjusted in time Mud index is handled nonadjustable discarded poor mud, in time so that it is guaranteed that slurry trench stability;
After S6, construction of guide wall are good, using GPS-2000 type drilling machine at the both ends of each slot section and centre along diaphram wall It is longitudinal respectively bore a hole should be first in place by drilling machine before drilling, with level detecting pad is steady, leveling, the theodolite being mutually with two Adjust drilling rod verticality, in boring procedure, 5 meters of every drilling depth are detected a hole wall verticality with ultrasound wall instrument, and discovery is inclined Difference adjusts immediately, and to guarantee to be not more than at hole perpendicularity 1300, drilling depth is diaphragm wall projected depth, detects whole hole again and hangs down Straight degree, the backward shift that meets the requirements are bored next slot section and are excavated after the guide hole of each slot section is drilled using hydraulic grab bucket grooving machine To the above soil layer of mixed rock, chute forming machine is in place, grooving center line is confirmed, with two theodolite inspection adjustment guide rods and grab bucket for top surface Verticality is less than 2%, and checks that all auxiliary facilities are intact, can start grooving, before grooving, pays attention to one side grooving one While mud is continuously replenished, keeps mud face leading wall top face or less 300-500mm, guarantee the mud pressure in slot section, to prevent upper Collapse hole excavates precision in addition to the dipmeter automatic measurement carried with chute forming machine, every digging depth 5m or so is used during grooving Ultrasound wall instrument measures the verticality of a cell wall, if required precision is not achieved, adjustment correction in time, until mud stone top surface;
S7, in S6 after grooving, allow in slot section after mud sediment 30 minutes, it is heavy that Cao bottom gently picked up with hydraulic grab Then slag picks up remaining sediment with vacuum pump, after monitor station lattice, using crawler crane erection joint pipe, installation course It is middle to correct its verticality with theodolite, and slowly put down, underground continuous wall groove segment and the cleaning of slot section seam are using autocratic wire brush Clean with water, wire brush be fixed on chute forming machine grab bucket on, be close to concrete surface pull back and forth up and down, until pull out wire brush on without Until spare.
In the present invention, the model LS-418J of triumphant benefit rod-type hydraulic grab chute forming machine in S2.
In the present invention, the depth segment of conduit Transducers Embedded in Concrete is preferably controlled in 2-6m in S3, the correct promotion for commanding conduit and It removes.
In the present invention, mud processing method is to guarantee the important link of quality of mud fluid in S5, using RM-2000 type 2m mud Blender is stirred, and when mud configuration, is first configured two tanks, is then sampled inspection, determine mud property parameter in accordance with After it is required that, it can be produced in batches.
In the present invention, due to criteria of right and wrong diaphram wall in S7, therefore junction block uses the compromise joint pipe of customization processing, Side is semicircle, and another is convex, and merogenesis connects, 8 meters of every section length, is pulled out using self-control pulling power traction, seam fettler Make to complete before changing slurry at clear bottom after grooving.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment Intrinsic element.In the absence of more restrictions.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (5)

1. a kind of construction method of nonstandard diaphragm wall, it is characterised in that: specifically includes the following steps:
S1, according to the excavation of foundation pit depth of modern city project, select the diaphram wall of 800mm, 900mm and 1000mm thickness respectively It is analyzed, calculates the vertical ocean property grade beam method that code requirement is recommended, using consolidated quick index, fender post deformation, internal force Calculating is all made of water and soil point and calculates principle, is calculated according to the construction operating condition drafted;
S2, it is excavated by triumphant sharp rod-type hydraulic grab chute forming machine to mud stone top surface, rushes rock to setting with dedicated block stamp using rock machine is rushed Slot bottom absolute altitude is counted, then block stamp is changed into plane set-hammer and repairs slot, after repairing slot qualification, slurry is changed at clear bottom, after acceptance(check), using 1 150t Crawler crane and 1 80t crawler crane lift placement steel reinforcement cage, steel reinforcement cage weight about 32t, on steel reinforcement cage platform integral manufacturing at Type places tremie, secondary to change slurry, after acceptance(check), pours underwater concrete immediately;
S3, after pouring beginning in S2, answer it is compact continuously carry out, forbid midway stop work, coagulation is prevented in filling process Native mixture overflows from funnel top or falls into outside funnel bottom hole, in filling process, it should be noted that the decline of observation tube inner concrete and Water level in borehole goes up and down situation, timely measured hole inner concrete face height, to ensure stake top quality, when filling concrete to stake top When, superfilled 800-1000mm is answered, to guarantee after cutting laitance, concrete quality can meet design requirement at stake item absolute altitude;
S4, the particularity due to nonstandard diaphragm wall, conventional grab bucket are reequiped, and grab bucket mainly utilizes 800mm Thick diaphram wall standard bucket two sides are welded with certain thickness sawtooth pattern iron plate, but in the case of soil property is harder, are considered as changing It grabs native ability relative drop caused by after dress and efficiency is caused to reduce, then wedge type locking notch pipe is re-worked again;
S5, the design that mud match ratio is carried out according to this engineering geological condition cutting method and purposes etc., determine reasonable mud Match ratio, the mud used in construction of diaphragm wall in lithostratigraphy are as follows: bentonite, bonding agent, dispersing agent and tap water economic cooperation Reason matches, it is desirable that viscosity is appropriate, and specific gravity meets the requirements, and stability is good, and filtering fluid loss is small, and it is short and thin that mudcake forms the time And flexible, while requiring to reinforce the mud management in work progress, quality of mud fluid detection is carried out on time, adjusts mud in time Index is handled nonadjustable discarded poor mud, in time so that it is guaranteed that slurry trench stability;
After S6, construction of guide wall are good, using GPS-2000 type drilling machine at the both ends of each slot section and centre along diaphram wall longitudinal direction Respectively boring a hole should be first in place by drilling machine before drilling, with level detecting pad is steady, leveling, is adjusted with two theodolites being mutually Good drilling rod verticality, in boring procedure, 5 meters of every drilling depth are detected a hole wall verticality with ultrasound wall instrument, and discovery deviation is vertical It adjusts, to guarantee to be not more than at hole perpendicularity 1300, drilling depth is diaphragm wall projected depth, and it is vertical to detect whole hole again Degree, the backward shift that meets the requirements bores next slot section, after the guide hole of each slot section is drilled, is excavated and is pushed up using hydraulic grab bucket grooving machine To the above soil layer of mixed rock, chute forming machine is in place, confirms grooving center line, with two theodolite inspection adjustment guide rods and grabs bucket vertical in face Straight degree, is less than 2%, and check that all auxiliary facilities are intact, can start grooving, before grooving, pay attention to. while grooving Mud is continuously replenished, keeps mud face leading wall top face or less 300-500mm, guarantees the mud pressure in slot section, to prevent above collapsing Precision is excavated in addition to the dipmeter automatic measurement carried with chute forming machine, every digging depth 5m or so, Yao Yongchao during grooving in hole Cement bond logging wall instrument measures the verticality of a cell wall, if required precision is not achieved, adjustment correction in time, until mud stone top surface;
S7, in S6 after grooving, allow in slot section after mud sediment 30 minutes, Cao bottom sediment gently picked up with hydraulic grab, Then remaining sediment is picked up with vacuum pump, after monitor station lattice, using crawler crane erection joint pipe, use in installation course Theodolite corrects its verticality, and slowly puts down, and underground continuous wall groove segment is cleared up with slot section seam and cleaned with water using autocratic wire brush, Wire brush is fixed in chute forming machine grab bucket, is close to concrete surface and is pulled back and forth up and down, until pulling out on wire brush without spare Until.
2. a kind of construction method of nonstandard diaphragm wall according to claim 1, it is characterised in that: triumphant in the S2 The model LS-418J of sharp rod-type hydraulic grab chute forming machine.
3. a kind of construction method of nonstandard diaphragm wall according to claim 1, it is characterised in that: led in the S3 The depth segment of pipe Transducers Embedded in Concrete is preferably controlled in 2-6m, the correct promotion and dismounting for commanding conduit.
4. a kind of construction method of nonstandard diaphragm wall according to claim 1, it is characterised in that: mud in the S5 Slurry processing method is to guarantee the important link of quality of mud fluid, is stirred using RM-2000 type 2m slurry mixer, mud configuration When, two tanks are first configured, inspection is then sampled, after determining that mud property parameter meets the requirements, can be produced in batches.
5. a kind of construction method of nonstandard diaphragm wall according to claim 1, it is characterised in that: in the S7 by Then nonstandard diaphragm wall, therefore junction block uses the compromise joint pipe of customization processing, side is semicircle, and another is convex Shape, merogenesis connection, 8 meters of every section length are pulled out using self-control pulling power traction, and seam cleaning work should be before slurry be changed at clear bottom after the grooving It completes.
CN201910630871.4A 2019-07-12 2019-07-12 A kind of construction method of nonstandard diaphragm wall Pending CN110424486A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910630871.4A CN110424486A (en) 2019-07-12 2019-07-12 A kind of construction method of nonstandard diaphragm wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910630871.4A CN110424486A (en) 2019-07-12 2019-07-12 A kind of construction method of nonstandard diaphragm wall

Publications (1)

Publication Number Publication Date
CN110424486A true CN110424486A (en) 2019-11-08

Family

ID=68409333

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910630871.4A Pending CN110424486A (en) 2019-07-12 2019-07-12 A kind of construction method of nonstandard diaphragm wall

Country Status (1)

Country Link
CN (1) CN110424486A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110820723A (en) * 2019-11-22 2020-02-21 中铁开发投资集团有限公司 Construction control method for underground diaphragm wall of deep and large foundation pit support structure of station
CN111827262A (en) * 2020-07-31 2020-10-27 广西建工集团建筑工程总承包有限公司 Construction method of fold-line-shaped irregular underground continuous wall
CN114482011A (en) * 2022-01-10 2022-05-13 中建五局土木工程有限公司 Combined construction method of super-thick plain soil filling-strong water permeable round gravel composite stratum deep and wide underground continuous wall

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010203115A (en) * 2009-03-03 2010-09-16 Railway Technical Res Inst Method for collecting groundwater in construction of underground structure by cut-and-cover
CN102852158A (en) * 2012-09-25 2013-01-02 浙江省地质矿产工程公司 Construction method for nonstandard diaphragm wall
CN105887887A (en) * 2016-01-27 2016-08-24 济南城建集团有限公司 Underwater concrete grouting pile top elevation control construction method
CN106759288A (en) * 2016-11-29 2017-05-31 昆山顶牛市政建设有限公司 One kind building bored pile construction method
KR101925597B1 (en) * 2018-02-06 2019-02-20 주식회사 유탑엔지니어링건축사사무소 Underground continuous wall grouting waterproofing method
CN109680676A (en) * 2018-12-26 2019-04-26 中铁二十五局集团第五工程有限公司 A kind of ventilating shaft building enclosure and its construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010203115A (en) * 2009-03-03 2010-09-16 Railway Technical Res Inst Method for collecting groundwater in construction of underground structure by cut-and-cover
CN102852158A (en) * 2012-09-25 2013-01-02 浙江省地质矿产工程公司 Construction method for nonstandard diaphragm wall
CN105887887A (en) * 2016-01-27 2016-08-24 济南城建集团有限公司 Underwater concrete grouting pile top elevation control construction method
CN106759288A (en) * 2016-11-29 2017-05-31 昆山顶牛市政建设有限公司 One kind building bored pile construction method
KR101925597B1 (en) * 2018-02-06 2019-02-20 주식회사 유탑엔지니어링건축사사무소 Underground continuous wall grouting waterproofing method
CN109680676A (en) * 2018-12-26 2019-04-26 中铁二十五局集团第五工程有限公司 A kind of ventilating shaft building enclosure and its construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110820723A (en) * 2019-11-22 2020-02-21 中铁开发投资集团有限公司 Construction control method for underground diaphragm wall of deep and large foundation pit support structure of station
CN111827262A (en) * 2020-07-31 2020-10-27 广西建工集团建筑工程总承包有限公司 Construction method of fold-line-shaped irregular underground continuous wall
CN114482011A (en) * 2022-01-10 2022-05-13 中建五局土木工程有限公司 Combined construction method of super-thick plain soil filling-strong water permeable round gravel composite stratum deep and wide underground continuous wall

Similar Documents

Publication Publication Date Title
WO2022096024A1 (en) Construction method for super-long small-diameter hole bored pile
CN107524138B (en) Construction method of ultra-deep foundation pit underground diaphragm wall
CN102425160A (en) Construction engineering pile method combining rotary drilling rig with manual bottom expanding
CN110424486A (en) A kind of construction method of nonstandard diaphragm wall
CN110185844A (en) Shallow earthing pipe-jacking with large diameter construction method
CN105275381A (en) Drilling construction method for water-rich cobble stratum by utilizing impact drill
CN108842819A (en) A kind of urban track traffic cable run method for tunnel construction
CN110984221A (en) Construction method for reinforcing end socket at initial end of air shaft and guide wall structure
CN108301403A (en) Subway drilling cast-in-place pile construction method
CN112281857A (en) Deep foundation pit excavation construction method
CN111364444A (en) Shallow-buried rock stratum section diaphragm wall grooving construction method
CN109137885A (en) A kind of construction method of underground continuous wall
CN104164881A (en) Piling wall overlapping cantilever foundation pit support construction method and structure
CN111455977A (en) Underground continuous wall construction method
CN110158630A (en) A kind of deep covering layer area large-span arch bridge annular ground continuous wall base
CN114263168A (en) Construction method of rock-socketed diaphragm wall of stratum water-stopping enclosure structure
CN112695763A (en) Deep sludge stratum foundation pit excavation method
CN206721870U (en) A kind of long auger guncreting pile steel reinforcement cage
CN204174625U (en) The superimposed cantilever foundation pit supporting construction of a kind of piling wall
CN111608210A (en) Construction method of pressure bearing type anti-floating anchor rod in water-saturated silt stratum
CN211898541U (en) Guide wall structure for reinforced structure of air shaft initial end head
CN110725163B (en) Composite roadbed device based on existing rail transit roadbed and pile construction method
CN209293012U (en) A kind of construction of diaphragm wall structure
CN218148483U (en) Tower crane foundation structure
CN110344418A (en) The structure and its construction technology of support system in a kind of deep basal pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20191108

WD01 Invention patent application deemed withdrawn after publication