CN110424344A - A kind of hydraulic mobile jumbo of Varied section and operating method - Google Patents

A kind of hydraulic mobile jumbo of Varied section and operating method Download PDF

Info

Publication number
CN110424344A
CN110424344A CN201910701691.0A CN201910701691A CN110424344A CN 110424344 A CN110424344 A CN 110424344A CN 201910701691 A CN201910701691 A CN 201910701691A CN 110424344 A CN110424344 A CN 110424344A
Authority
CN
China
Prior art keywords
trolley
hydraulic cylinder
vehicle frame
hydraulic
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910701691.0A
Other languages
Chinese (zh)
Inventor
王孝海
林宏
康建荣
彭亚
罗刚
陈敏
吴世斌
黄纪村
王纪丰
刘凡
冉景江
彭培龙
张相明
吴兴民
冯博
靳阔军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 5 Co Ltd
China Three Gorges Projects Development Co Ltd CTG
Original Assignee
Sinohydro Bureau 5 Co Ltd
China Three Gorges Projects Development Co Ltd CTG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 5 Co Ltd, China Three Gorges Projects Development Co Ltd CTG filed Critical Sinohydro Bureau 5 Co Ltd
Priority to CN201910701691.0A priority Critical patent/CN110424344A/en
Publication of CN110424344A publication Critical patent/CN110424344A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B8/00Details of barrages or weirs ; Energy dissipating devices carried by lock or dry-dock gates
    • E02B8/06Spillways; Devices for dissipation of energy, e.g. for reducing eddies also for lock or dry-dock gates

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention provides a kind of hydraulic mobile jumbo of Varied section and operating methods, the top rolling support of trolley track is equipped with multiple groups rail wheel, the rail wheel is fixedly mounted on wheel supporting frame, trolley vehicle frame is equipped with by elevating mechanism on the wheel supporting frame, the bottom of the trolley vehicle frame is equipped with the trolley power device mobile for trolley, the top of the trolley vehicle frame is across being fixedly installed with more extension sleeves, there is telescopic rod in the inside of the extension sleeve by being slidably installed, telescopic hydraulic cylinder is installed between the extension sleeve and telescopic rod, the outer end face of the telescopic hydraulic cylinder is fixedly installed with the template for pouring, demoulding hydraulic cylinder for demoulding is installed between the template and trolley vehicle frame.The trolley can be realized a variety of lining cutting figure constructions of cavern's concrete, and cavern's lining construction duration has been effectively ensured, has reduced large number of equipment investment and cost of labor.

Description

A kind of hydraulic mobile jumbo of Varied section and operating method
Technical field
The present invention relates to the constructions of cavern's lining concrete, and in particular to a kind of hydraulic mobile jumbo of Varied section and operation side Method.
Background technique
White crane beach power station flood Discharge tunnel Project mainly includes 3 flood discharging tunnels, and every flood discharging tunnel is by inlet transition, upper flat Section, dragon fall endpiece composition.Dragon falls tail and is made of wet odd curved section, slope section and ogee section.Wet surprise curve mode is Z=X2/500+ 0.015X, slope section are the connection changeover portion between wet odd curve and anti-arc, 1# and 2# flood discharging tunnel ramp slope 1:4,3# flood discharge Hole ramp slope is that 1:3.72. ogee section is located at slope section downstream, anti-arc radius 300m.The anti-arc of 1#, 2# flood discharging tunnel directly connects Defrlector bucket, 3# flood discharging tunnel are limited between anti-arc end and bucket lip by orographic condition and increase flat section under one section, lower flat section bottom Slope 8%.
Every dragon of flood discharging tunnel falls tail and arranges 3 aerators, and aerator position is sudden expansion structure, and it is disconnected to share 7 kinds of lining cutting Face,.Wet odd curved section is connect before flood discharging tunnel 1# aerator, is followed by slope section, bottom board slope is changed to 1:4.52 by 1:4 after lining, The crown gradient is changed to 1:3.7216 by 1:4, since to become slope pile No. inconsistent for crown and bottom plate, cause flow section height by 18m is raised to 19.61m, is changing into linear distribution.Flow section width is by 15m, mutation to 15.7m, unilateral side amplification 35cm.
Flood discharging tunnel 2# aerator is located in the middle part of slope section, and bottom board slope is 1:3.7216 after lining, and the crown gradient is by 1: 3.7216 are changed to 1:2.45, since crown and bottom plate change slope pile No. are inconsistent, flow section height are caused to be raised to by 18m 19.50m being changing into linear distribution.Flow section width is by 15.7m, mutation to 16.2m, unilateral side amplification 25cm.
Reversed segmental arc before flood discharging tunnel 3# aerator is followed by lower flat section, and bottom board slope is 8% after lining, and the crown gradient is become by 8% Change to 1:4.83, since crown and bottom plate change slope pile No. are inconsistent, cause flow section height to be raised to 19.5m by 18m, change Linear distribution.Flow section width is by 16.2m, mutation to 16.5m, unilateral side amplification 15cm.
According to previous experiences, China hydroelectric project flood discharging tunnel dragon falls tail concrete construction generally using more set trolleys, difference Working face starts concrete construction simultaneously, and each working face lining trolley size is inconsistent;Lining trolley is generally by volume Machine travel walking is raised, each lining section arranges a lining trolley, then equipment cost is excessively high, and trolley walking utilizes elevator Machine is drawn, and security risk is higher, and security risk is larger.
Summary of the invention
In order to solve the above technical problems, the present invention provides a kind of hydraulic mobile jumbo of Varied section, which can be realized hole The a variety of lining cutting figures construction of room concrete, has been effectively ensured cavern's lining construction duration, reduce large number of equipment investment and manually at This.
In order to realize above-mentioned technical characteristic, the object of the present invention is achieved like this: a kind of hydraulic voluntarily platform of Varied section Vehicle, it includes the trolley track being fixed on tunnel floor plate, and the top rolling support of the trolley track is equipped with multiple groups track Wheel, the rail wheel are fixedly mounted on wheel supporting frame, are equipped with trolley vehicle by elevating mechanism on the wheel supporting frame Frame, the bottom of the trolley vehicle frame are equipped with the trolley power device mobile for trolley, the top of the trolley vehicle frame across More extension sleeves are fixedly installed with, there is telescopic rod in the inside of the extension sleeve by being slidably installed, the telescopic Telescopic hydraulic cylinder is installed between cylinder and telescopic rod, the outer end face of the telescopic hydraulic cylinder is fixedly installed with the mould for pouring Plate is equipped with the demoulding hydraulic cylinder for demoulding between the template and trolley vehicle frame.
Further, the trolley track is fixedly mounted in the concrete foundation of tunnel floor plate by anchor bolt.
Further, the trolley vehicle frame uses truss structure, is fixed on the upstream side wall of trolley vehicle frame for climbing The operation ladder component climbed, the operation ladder component include operation ladder, and the operation ladder is fixed by ladder connection frame It is mounted on trolley vehicle frame, the periphery of the operation ladder is equipped with ladder handrail.
Further, the elevating mechanism includes being hinged on the raise-lower hydraulic cylinder body of wheel supporting top of the trellis, the liter The piston rod top end of drop hydraulic cylinder is hinged on trolley vehicle frame and drives its lifting.
Further, the back bearing diagonal knot for enhancing its stability is fixed on the downstream side wall of the trolley vehicle frame Structure.
Further, the trolley power device includes the climbing hydraulic cylinder for being fixed on trolley bottom of frame, the climbing The cylinder body pedestal of hydraulic cylinder is hinged on the bottom of trolley vehicle frame, and the piston-rod end of the climbing hydraulic cylinder is hinged with track holding Mechanism, the track hold-fast body merges with trolley track matching is clamped it;It is installed on the wheel supporting frame useful Rail device is embraced in what is fixed to it.
Further, cross conveyor, the cross conveyor packet are fixedly installed at the top of the trolley vehicle frame Lateral transfer rack is included, one end of the lateral transfer rack is hinged on the bottom of trolley vehicle frame by pin shaft, and the transverse direction is defeated Send the other end of rack by lift adjustment they sup-port at the top of trolley vehicle frame.
Further, the top of the trolley vehicle frame and be located at downstream by inclined support bar support overhanging work is installed Platform;The bottom of the trolley vehicle frame is supported by the support leg for being supported to entire trolley.
Further, the raise-lower hydraulic cylinder body of the elevating mechanism, trolley power device climbing hydraulic cylinder, telescopic hydraulic Cylinder and demoulding hydraulic cylinder are all connected with hydraulic power unit, and the hydraulic power unit is fixedly mounted on pumping plant support frame, the pumping plant branch Support is fixedly mounted on trolley vehicle frame by support base, and maintenance ladder, the maintenance are connected on the side wall of the trolley vehicle frame The two sides of ladder are equipped with maintenance ladder guardrails.
The hydraulic mobile jumbo of Varied section described in any one carries out the operating method of side wall lining construction, he includes following step It is rapid:
Step 1: entire trolley is supported on trolley track by rail wheel;
Step 2: according to the height of the height adjustment raise-lower hydraulic cylinder body of tunnel, and then the height of regulating platform vehicle carriage, and then make Its tunnel for adapting to different height;
Step 3: according to the width adjusting telescopic hydraulic cylinder and demoulding hydraulic cylinder of tunnel, and then template movement being pushed to pour to needs Abutment wall, then it is poured;
Step 4: after the side wall lining to this storehouse surface pours completion, demoulding starts trolley power device, passes through hydraulic cylinder of climbing It drives above-mentioned trolley to move integrally, and enters next storehouse surface;
Step 5: when lining cutting end face changes, i.e., when side wall lining trolley need to carry out Varied section function at this time, telescopic hydraulic Cylinder and demoulding hydraulic cylinder work at the same time, and stroke is shunk according to range, and trolley is mobile, need lining cutting portion when trolley is moved to When position, telescopic hydraulic cylinder and demoulding hydraulic cylinder are extended simultaneously, after reaching design section, are stopped working, then carry out to it It pours;
Step 6: pouring completion to this section and then carry out pouring for next storehouse surface.
The method have the advantages that:
1, it can be used in Varied section tunnel concrete liner pouring construction by using the mobile jumbo of above structure, it being capable of basis Different section sizes adjusts the extension elongation of the template of trolley, and then guarantees the pouring construction of tapered side wall lining.
2, ensure that the stability of trolley track support by above-mentioned structure, so ensure that trolley follow-up operation can By property, the safety of operation ensure that.
3, it ensure that its structural strength by using truss structure, ensure that by the operation ladder component of setting in operation In the process, operating personnel can be climbed by operation ladder to the top of trolley vehicle frame, and then convenient working personnel carry out it Maintenance.
4, it is mainly used for realizing the descending operation of entire trolley by above-mentioned elevating mechanism, and then adapts to different height Tunnel section is able to drive entire trolley vehicle frame by lifting hydraulic cylinder body and is risen, and then change it in operation process Highly.
5, by above-mentioned cross conveyor, it is mainly used for the lateral transfer of concrete, and then cooperates and realize abutment wall lining The construction of block, and passed through by the section that lift adjustment support rod can adapt it to different gradient according to the size of the gradient Lift adjustment support rod is adjusted to change the tilt angle of lateral transfer rack, it is made to remain horizontal, ensure that can incite somebody to action Concrete carries out lateral transfer, and then realizes pouring for lining side wall.
6, by above-mentioned hydraulic system, driving raise-lower hydraulic cylinder body, the climbing hydraulic cylinder, telescopic hydraulic cylinder that can synchronize And demoulding hydraulic cylinder realizes the automatic synchronization work between each different components in turn, finally ensure that its normal work.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples.
Fig. 1 is side view of the invention.
Fig. 2 is main view of the invention.
In figure: trolley track 1, concrete foundation 3, embraces rail device 4, wheel supporting frame 5, rail wheel 6, climbing at anchor bolt 2 Hydraulic cylinder 7, track hold-fast body 8, maintenance ladder guardrails 9, maintenance ladder 10, support leg 11, pumping plant support frame 12, support base 13, trolley vehicle frame 14, raise-lower hydraulic cylinder body 15, back structure with oblique member 16, truss structure 17, inclined support bar 18, overhanging work Platform 19, lift adjustment support rod 20, lateral transfer rack 21, pin shaft 22, ladder connection frame 23, ladder handrail 24, operation ladder 25, template 26, demoulding hydraulic cylinder 27, side wall lining to be poured 28, telescopic rod 29, extension sleeve 30.
Specific embodiment
Embodiments of the present invention are described further with reference to the accompanying drawing.
Embodiment 1:
Referring to Fig. 1-2, a kind of hydraulic mobile jumbo of Varied section, it includes the trolley track 1 being fixed on tunnel floor plate, and described The top rolling support in track road 1 is equipped with multiple groups rail wheel 6, and the rail wheel 6 is fixedly mounted on wheel supporting frame 5, institute It states and trolley vehicle frame 14 is equipped with by elevating mechanism on wheel supporting frame 5, the bottom of the trolley vehicle frame 14 is equipped with for platform The mobile trolley power device of vehicle, the top of the trolley vehicle frame 14 are described to stretch across being fixedly installed with more extension sleeves 30 There is telescopic rod 29 in the inside of contracting sleeve 30 by being slidably installed, and is equipped with and stretches between the extension sleeve 30 and telescopic rod 29 Contracting hydraulic cylinder 31, the outer end face of the telescopic hydraulic cylinder 31 are fixedly installed with the template 26 for pouring, the template 26 and platform Demoulding hydraulic cylinder 27 for demoulding is installed between vehicle carriage 14.It can be used in becoming by using the mobile jumbo of above structure The stretching of section tunnel concrete liner pouring construction, the template 26 that trolley can be adjusted according to different section sizes is long Degree, and then guarantee the pouring construction of tapered side wall lining.During Specific construction, it can be driven by trolley power device Entire trolley is moved along 1 automatic running of trolley track, after moving to the side wall lining position for needing to pour to it, by flexible Hydraulic cylinder 31 and demoulding hydraulic cylinder 27 stretch out, and then template 26 are close to lining side wall, then carry out pouring for side wall lining and apply Work.
Further, the trolley track 1 is fixedly mounted in the concrete foundation 3 of tunnel floor plate by anchor bolt 2. It ensure that the stability that trolley track 1 supports by above-mentioned structure, and then ensure that the reliability of trolley follow-up operation, guarantee The safety of operation.
Further, the trolley vehicle frame 14 uses truss structure, fixes on the upstream side wall of trolley vehicle frame 14 useful In the operation ladder component of climbing, the operation ladder component includes operation ladder 25, and the operation ladder 25 is connected by ladder It connects frame 23 to be fixedly mounted on trolley vehicle frame 14, the periphery of the operation ladder 25 is equipped with ladder handrail 24.By using purlin Frame structure ensure that its structural strength, ensure that in operation process, operating personnel can by the operation ladder component of setting The top of trolley vehicle frame 14 is arrived by the climbing of operation ladder 25, and then convenient working personnel overhaul it.
Further, the elevating mechanism includes being hinged on the raise-lower hydraulic cylinder body 15 at 5 top of wheel supporting frame, described The piston rod top end of raise-lower hydraulic cylinder body 15 is hinged on trolley vehicle frame 14 and drives its lifting.Pass through above-mentioned elevating mechanism master Will be for realizing the descending operation of entire trolley, and then the tunnel section for adapting to different height passes through lifting in operation process Hydraulic cylinder 15 is able to drive entire trolley vehicle frame 14 and is risen, and then changes its height.
Further, the back bearing diagonal for enhancing its stability is fixed on the downstream side wall of the trolley vehicle frame 14 Structure 16.The structural strength of trolley vehicle frame 14 can greatly be enhanced by above-mentioned back structure with oblique member 16, and then guaranteed Its structural stability.
Further, the trolley power device includes the climbing hydraulic cylinder 7 for being fixed on 14 bottom of trolley vehicle frame, described to climb The cylinder body pedestal of slope hydraulic cylinder 7 is hinged on the bottom of trolley vehicle frame 14, the hinged rail of piston-rod end of the climbing hydraulic cylinder 7 Road hold-fast body 8, the track hold-fast body 8 merges with the matching of trolley track 1 is clamped it;The wheel supporting frame 5 On be equipped with for it is fixed embrace rail device 4.By above-mentioned trolley power device, it is mainly used for driving entire trolley vehicle frame 14 movement can be moved entirely trolley vehicle frame 14 in operation process by climbing hydraulic cylinder 7 along trolley track, and Entire trolley vehicle frame 14 can be fixed by track hold-fast body 8 and an armful rail device 4 later in place mobile.
Further, the top of the trolley vehicle frame 14 is fixedly installed with cross conveyor, the cross conveyor Including lateral transfer rack 21, one end of the lateral transfer rack 21 is hinged on the bottom of trolley vehicle frame 14 by pin shaft 22, The other end of the lateral transfer rack 21 is supported on the top of trolley vehicle frame 14 by lift adjustment support rod 20.By above-mentioned Cross conveyor, be mainly used for the lateral transfer of concrete, and then cooperate the construction for realizing side wall lining, and pass through liter Falling tone section support rod 20 can adapt it to the section of different gradient, according to the size of the gradient, by adjusting lift adjustment support Bar 20 changes the tilt angle of lateral transfer rack 21, it is made to remain horizontal, ensure that concrete can be carried out it is horizontal To conveying, and then realize pouring for lining side wall.
Further, the top of the trolley vehicle frame 14 and be located at downstream by inclined support bar 18 support overhanging is installed Workbench 19;The bottom of the trolley vehicle frame 14 is supported by the support leg 11 for being supported to entire trolley.By above-mentioned Overhanging workbench 19 can convenient working personnel stand, and then be convenient for its integral construction.
Further, the raise-lower hydraulic cylinder body 15 of the elevating mechanism, trolley power device climbing hydraulic cylinder 7, flexible Hydraulic cylinder 31 and demoulding hydraulic cylinder 27 are all connected with hydraulic power unit, and the hydraulic power unit is fixedly mounted on pumping plant support frame 12, The pumping plant support frame 12 is fixedly mounted on trolley vehicle frame 14 by support base 13, is connected on the side wall of the trolley vehicle frame 14 Ladder 10 is overhauled, the two sides of the maintenance ladder 10 are equipped with maintenance ladder guardrails 9.Pass through above-mentioned hydraulic system, Neng Goutong Driving raise-lower hydraulic cylinder body 15, climbing hydraulic cylinder 7, telescopic hydraulic cylinder 31 and the demoulding hydraulic cylinder 27 of step realize each difference in turn Automatic synchronization work between component finally ensure that its normal work.
Further, the voluntarily climbing driving higher HYDRAULIC CONTROL SYSTEM of a set of professional performance of the automatic trolley, Pressure 23Mpa.Using the hydraulic cylinder of 4 GE250/140-700 specialized factories, hydraulic control system adds hand using Electromagnetic Control Valve is controlled, has point-to-point, single operation, two one group respective control measure such as operation, four one group of simultaneously operating;Due to the gradient Suddenly, in order to observe conveniently, and the independent remote control operation of energy of each oil cylinder is configured.
Embodiment 2:
The hydraulic mobile jumbo of Varied section described in any one carries out the operating method of side wall lining construction, he the following steps are included:
Step 1: entire trolley is supported on trolley track 1 by rail wheel 6;
Step 2: according to the height of the height adjustment raise-lower hydraulic cylinder body 15 of tunnel, and then the height of regulating platform vehicle carriage 14, into And adapt it to the tunnel of different height;
Step 3: according to the width adjusting telescopic hydraulic cylinder 31 and demoulding hydraulic cylinder 27 of tunnel, and then pushing template 26 to be moved to need to The abutment wall to be poured, then it is poured;
Step 4: after the side wall lining to this storehouse surface pours completion, demoulding starts trolley power device, passes through hydraulic cylinder of climbing The above-mentioned trolley of 7 drivings moves integrally, and enters next storehouse surface;
Step 5: when lining cutting end face changes, i.e., when side wall lining trolley need to carry out Varied section function at this time, telescopic hydraulic Cylinder 31 and demoulding hydraulic cylinder 27 work at the same time, and stroke is shunk according to range, and trolley is mobile, need to serve as a contrast when trolley is moved to When building position, telescopic hydraulic cylinder 31 and demoulding hydraulic cylinder 27 are extended simultaneously, after reaching design section, are stopped working, then It is poured;
Step 6: pouring completion to this section and then carry out pouring for next storehouse surface.

Claims (10)

1. a kind of hydraulic mobile jumbo of Varied section, it is characterised in that: it includes the trolley track (1) being fixed on tunnel floor plate, The top rolling support of the trolley track (1) is equipped with multiple groups rail wheel (6), and the rail wheel (6) is fixedly mounted on wheel On support frame (5), it is equipped with trolley vehicle frame (14) on the wheel supporting frame (5) by elevating mechanism, the trolley vehicle frame (14) bottom is equipped with the trolley power device mobile for trolley, and the top of the trolley vehicle frame (14) is across fixed installation There are more extension sleeves (30), the inside of the extension sleeve (30) has telescopic rod (29) by being slidably installed, described to stretch It is equipped between contracting sleeve (30) and telescopic rod (29) telescopic hydraulic cylinder (31), the outer end face of the telescopic hydraulic cylinder (31) is fixed Template (26) for pouring is installed, the liquid parting for demoulding is installed between the template (26) and trolley vehicle frame (14) Cylinder pressure (27).
2. the hydraulic mobile jumbo of a kind of Varied section according to claim 1, it is characterised in that: the trolley track (1) passes through Anchor bolt (2) is fixedly mounted in the concrete foundation (3) of tunnel floor plate.
3. the hydraulic mobile jumbo of a kind of Varied section according to claim 1, it is characterised in that: the trolley vehicle frame (14) uses Truss structure is fixed with the operation ladder component for climbing, the operation ladder on the upstream side wall of trolley vehicle frame (14) Component includes operation ladder (25), and the operation ladder (25) is fixedly mounted on trolley vehicle frame (14) by ladder connection frame (23) On, the periphery of the operation ladder (25) is equipped with ladder handrail (24).
4. the hydraulic mobile jumbo of a kind of Varied section according to claim 1, it is characterised in that: the elevating mechanism includes hinged On raise-lower hydraulic cylinder body (15) at the top of wheel supporting frame (5), the piston rod top end of the raise-lower hydraulic cylinder body (15) is hinged On trolley vehicle frame (14) and drive its lifting.
5. the hydraulic mobile jumbo of a kind of Varied section according to claim 1, it is characterised in that: under the trolley vehicle frame (14) The back structure with oblique member (16) for enhancing its stability is fixed on trip side wall.
6. the hydraulic mobile jumbo of a kind of Varied section according to claim 1, it is characterised in that: the trolley power device includes It is fixed on the climbing hydraulic cylinder (7) of trolley vehicle frame (14) bottom, the cylinder body pedestal of climbing hydraulic cylinder (7) is hinged on trolley vehicle The piston-rod end of the bottom of frame (14), climbing hydraulic cylinder (7) is hinged with track hold-fast body (8), and the track is held tightly Mechanism (8) matches to merge with trolley track (1) is clamped it;It is equipped on the wheel supporting frame (5) for solid to it Fixed embraces rail device (4).
7. the hydraulic mobile jumbo of a kind of Varied section according to claim 1, it is characterised in that: the top of the trolley vehicle frame (14) Portion is fixedly installed with cross conveyor, and the cross conveyor includes lateral transfer rack (21), the cross conveyor One end of frame (21) is hinged on the bottom of trolley vehicle frame (14), the other end of the lateral transfer rack (21) by pin shaft (22) The top of trolley vehicle frame (14) is supported on by lift adjustment support rod (20).
8. the hydraulic mobile jumbo of a kind of Varied section according to claim 1, it is characterised in that: the top of the trolley vehicle frame (14) Portion is simultaneously equipped with overhanging workbench (19) by inclined support bar (18) support positioned at downstream;The bottom of the trolley vehicle frame (14) It is supported by the support leg (11) for being supported to entire trolley.
9. the hydraulic mobile jumbo of a kind of Varied section according to claim 1, it is characterised in that: the lifting liquid of the elevating mechanism Cylinder pressure body (15), the climbing hydraulic cylinder (7) of trolley power device, telescopic hydraulic cylinder (31) and demoulding hydraulic cylinder (27) all with it is hydraulic Pumping plant is connected, and the hydraulic power unit is fixedly mounted on pumping plant support frame (12), and the pumping plant support frame (12) passes through support base (13) it is fixedly mounted on trolley vehicle frame (14), maintenance ladder (10), the inspection is connected on the side wall of the trolley vehicle frame (14) The two sides for repairing ladder (10) are equipped with maintenance ladder guardrails (9).
10. carrying out the operation side of side wall lining construction using the hydraulic mobile jumbo of Varied section described in claim 1-9 any one Method, it is characterised in that he the following steps are included:
Step 1: entire trolley is supported on trolley track (1) by rail wheel (6);
Step 2: according to the height of the height adjustment raise-lower hydraulic cylinder body (15) of tunnel, and then the height of regulating platform vehicle carriage (14) Degree, and then adapt it to the tunnel of different height;
Step 3: according to the width adjusting telescopic hydraulic cylinder (31) and demoulding hydraulic cylinder (27) of tunnel, and then template (26) being pushed to move The abutment wall for needing to pour is moved, then it is poured;
Step 4: after the side wall lining to this storehouse surface pours completion, demoulding starts trolley power device, passes through hydraulic cylinder of climbing (7) it drives above-mentioned trolley to move integrally, and enters next storehouse surface;
Step 5: when lining cutting end face changes, i.e., when side wall lining trolley need to carry out Varied section function at this time, telescopic hydraulic Cylinder (31) and demoulding hydraulic cylinder (27) work at the same time, and stroke is shunk according to range, and trolley is mobile, when trolley is moved to When needing lining cutting position, telescopic hydraulic cylinder (31) and demoulding hydraulic cylinder (27) are extended simultaneously, after reaching design section, are stopped Work, then it is poured;
Step 6: pouring completion to this section and then carry out pouring for next storehouse surface.
CN201910701691.0A 2019-07-31 2019-07-31 A kind of hydraulic mobile jumbo of Varied section and operating method Pending CN110424344A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910701691.0A CN110424344A (en) 2019-07-31 2019-07-31 A kind of hydraulic mobile jumbo of Varied section and operating method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910701691.0A CN110424344A (en) 2019-07-31 2019-07-31 A kind of hydraulic mobile jumbo of Varied section and operating method

Publications (1)

Publication Number Publication Date
CN110424344A true CN110424344A (en) 2019-11-08

Family

ID=68411821

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910701691.0A Pending CN110424344A (en) 2019-07-31 2019-07-31 A kind of hydraulic mobile jumbo of Varied section and operating method

Country Status (1)

Country Link
CN (1) CN110424344A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110924987A (en) * 2019-12-19 2020-03-27 广东欣龙隧道装备股份有限公司 Tunnel secondary lining construction trolley
CN115262961A (en) * 2022-08-12 2022-11-01 甘肃盛宏建筑工程有限责任公司 Cantilever structure pouring formwork supporting device and construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204152523U (en) * 2014-09-23 2015-02-11 中铁二十一局集团轨道交通工程有限公司 Subway tunnel change section two serves as a contrast construction convenient regulating type chassis
CN204984438U (en) * 2015-07-27 2016-01-20 湖南五新隧道智能装备股份有限公司 Tunnel lining platform truck with adjustable
CN205936646U (en) * 2016-08-19 2017-02-08 中国水利水电第八工程局有限公司 A trolley -bus formworking jumbo for tunnel side wall concrete construction
CN207436062U (en) * 2017-11-16 2018-06-01 中国水利水电第五工程局有限公司 A kind of high flow rate big cross section flood discharging tunnel low slump concrete puts in storage system
CN109630160A (en) * 2019-02-13 2019-04-16 山东博远重工有限公司 Novel Varied section lining trolley

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204152523U (en) * 2014-09-23 2015-02-11 中铁二十一局集团轨道交通工程有限公司 Subway tunnel change section two serves as a contrast construction convenient regulating type chassis
CN204984438U (en) * 2015-07-27 2016-01-20 湖南五新隧道智能装备股份有限公司 Tunnel lining platform truck with adjustable
CN205936646U (en) * 2016-08-19 2017-02-08 中国水利水电第八工程局有限公司 A trolley -bus formworking jumbo for tunnel side wall concrete construction
CN207436062U (en) * 2017-11-16 2018-06-01 中国水利水电第五工程局有限公司 A kind of high flow rate big cross section flood discharging tunnel low slump concrete puts in storage system
CN109630160A (en) * 2019-02-13 2019-04-16 山东博远重工有限公司 Novel Varied section lining trolley

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨党荣,伟建,邱天文: "特大纵坡巨型龙落尾液压钢模台车设计与施工", 《水利水电施工》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110924987A (en) * 2019-12-19 2020-03-27 广东欣龙隧道装备股份有限公司 Tunnel secondary lining construction trolley
CN115262961A (en) * 2022-08-12 2022-11-01 甘肃盛宏建筑工程有限责任公司 Cantilever structure pouring formwork supporting device and construction method
CN115262961B (en) * 2022-08-12 2024-01-05 甘肃盛宏建筑工程有限责任公司 Cantilever structure pouring formwork supporting device and construction method

Similar Documents

Publication Publication Date Title
CN204627625U (en) Automatic walking lining trolley
CN106812120A (en) Hydraulic self-lifting truss-like cantilever heavy type arch dam template system
CN108442255B (en) Movable formwork bridge fabrication machine and construction method for cast-in-situ bridge fabrication
CN102022123B (en) Integral lining method for tunnel with altered diameter by model board trolley
CN206680962U (en) Hydraulic self-lifting truss-like cantilever heavy type arch dam template system
CN110453613B (en) Full-section one-step suspension casting construction method for large-span beam bridge box girder
CN108118620B (en) Integral self-climbing integrated platform for bridge tower construction and construction method thereof
CN106593469A (en) Trolley for construction of inverted arch
CN110424344A (en) A kind of hydraulic mobile jumbo of Varied section and operating method
CN108589773A (en) A kind of construction system and form of construction work of piping lane engineering
CN107829370B (en) High pier self-climbing hydraulic rollover construction process
CN106948593A (en) A kind of wheeled robot climbing frame
CN110714611A (en) Light climbing formwork steel frame system
CN209411723U (en) A kind of elevator with flexible workbench
CN214993219U (en) Concrete placement platform truck is contained to apron
CN204938875U (en) City integrated piping lane preformed part hoists and erecting equipment
CN109778713A (en) A kind of steel truss girder bridge scene suspension and slipping assembly device and method
CN109457619A (en) A kind of mobile bracket of composite multi-functional for concrete girder cast-in-place construction
CN107815971B (en) High mound is from climbing hydraulic pressure mould system that turns over
CN210422637U (en) A concreting system for full section concrete of circular tunnel
CN112482317A (en) Door slot second-stage concrete self-climbing slip form pouring system and construction method
CN209722761U (en) A kind of steel truss girder bridge scene suspension and slipping assembly device
CN108425348B (en) Hydraulic overhaul platform for flood discharge flow channel of hydropower station and operation method
CN107724235B (en) A kind of bridge-collision-avoidance wall Safety operation platform
CN214573768U (en) Self-climbing sliding formwork pouring system for second-stage concrete pouring of gate slot

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191108

RJ01 Rejection of invention patent application after publication