CN110424213A - A kind of EPDM color grains plastic floor construction method - Google Patents
A kind of EPDM color grains plastic floor construction method Download PDFInfo
- Publication number
- CN110424213A CN110424213A CN201910630166.4A CN201910630166A CN110424213A CN 110424213 A CN110424213 A CN 110424213A CN 201910630166 A CN201910630166 A CN 201910630166A CN 110424213 A CN110424213 A CN 110424213A
- Authority
- CN
- China
- Prior art keywords
- construction
- epdm
- stage
- area
- black
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C13/00—Pavings or foundations specially adapted for playgrounds or sports grounds; Drainage, irrigation or heating of sports grounds
- E01C13/06—Pavings made in situ, e.g. for sand grounds, clay courts E01C13/003
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C13/00—Pavings or foundations specially adapted for playgrounds or sports grounds; Drainage, irrigation or heating of sports grounds
- E01C13/06—Pavings made in situ, e.g. for sand grounds, clay courts E01C13/003
- E01C13/065—Pavings made in situ, e.g. for sand grounds, clay courts E01C13/003 at least one in situ layer consisting of or including bitumen, rubber or plastics
Abstract
The present invention relates to a kind of EPDM color grains plastic floor construction methods, comprising: crosses stage, construction stage subregion;The construction stage includes: pretreatment stage, paving black basecoat stage, spreads colored surface layer stage, finishing phase, acceptance phase;The subregion scribing line stage is the following steps are included: Step1: dividing region;Step3: construction area is surrounded.Compared with prior art, implementation result of the invention is as follows by the present invention: by the efficiency of sectional streak and the method lifting construction of parallel construction, reducing the error rate of construction;The success rate that colour EPDM particle is laid with is promoted by first spreading the method that black basecoat repaves colored surface layer, reduces thickness dosage needed for being laid with colour EPDM particle;By efficiency and order that pretreatment stage lifting construction is arranged.The present invention is intended to provide a kind of efficient colour EPDM granule plastic rubber ground construction scheme.
Description
Technical field
The present invention relates to plastic cement technical field, specifically a kind of EPDM color grains plastic floor construction method.
Background technique
EPDM, the entitled ethylene propylene diene rubber of Chinese, full name in English are Ethylene-Propylene-Diene Monomer,
Abbreviation EPDM.This material has good resistance to ag(e)ing, corrosion resistance, heat resistance and good elasticity, caking property, very suitable
Share in the plastic cement race track as sports ground and be laid on the ground of many pleasure grounds.This is a kind of novel terrace, by
In the characteristic of EPDM and material engaged therewith, the construction requirement for having comparison stringent when being laid with plastic floor.Now provide
A kind of plastic floor construction method for EPDM color grains.
Summary of the invention
The present invention is exactly in view of the deficienciess of the prior art, provide a kind of EPDM color grains plastic floor construction party
Method.
To solve the above problems, the technical solution used in the present invention is as follows:
A kind of EPDM color grains plastic floor construction method characterized by comprising cross stage, construction subregion
Stage;The construction stage includes: pretreatment stage, paving black basecoat stage, spreads colored surface layer stage, finishing phase, examination
Stage;The subregion scribing line stage is the following steps are included: Step1: dividing region;The ground that will be constructed is divided into multiple apply
Work area;Step2: selection construction access road;A construction access road is selected, construction direction delimited;It is more on same construction access road
It successively constructs according to construction access road a construction area;It constructs simultaneously multiple construction areas on the vertical line of same construction access road;
Step3: construction area is surrounded;The construction area that will be constructed and construction area to be onstructed are separated.
As an improvement of the above technical solution, the pretreatment stage is the following steps are included: Step1: cleaning ground;Use fourth
Ester clears up ground to be onstructed, it is ensured that does not have booty, dust, water stain, grease stain etc. on ground;Step2: sample;Take each construction area
A tile position as sample area;EPDM black particle is prepared in proportion, viscose is coated on the ground of sample area, it will
The EPDM black particle prepared is laid on the viscose of sample area;It waits for 24 hours, solidifies to EPDM black particle, detect sample area
EPDM black particle adhesive force and intensity, it is ensured that not easy to fall off, intensity reaches requirement, can start formally to construct;
Step3: viscose is smeared;Viscose is smeared on the construction area ground that will be constructed;Step4: bottom ingredient;It will be black needed for bottom
Color EPDM particle mixes in proportion, the EPDM black particle dosage coordinative construction area area that ingredient is selected.
As an improvement of the above technical solution, the paving black basecoat stage is the following steps are included: Step1: stirring bottom
Ingredient;The bottom black EPDM granule formulations that pretreatment stage mixes are stirred well even;Step2: upper bottom;The bottom that mixing is stirred
Layer ingredient is routed on the viscose of construction area, is flattened the bottom ingredient laid using press machine, after bottom ingredient flattens
With a thickness of 10cm;Step3: solidifying and processes next construction area;The bottom ingredient being laid with is placed for 24 hours, waits it solid
Change.
As an improvement of the above technical solution, the paving colored surface layer stage is the following steps are included: Step1: scribing line;To institute
After having the first-class black basecoat in construction area, the pattern on surface layer to be enameled is finished with white line on black basecoat;After having crossed, inspection
It looks into whether scribing line malfunctions, does not malfunction, carry out in next step;Step2: partition domain;According to the construction area originally divided, by what is finished
Region to be painted is assigned in each construction area, is successively constructed according to the construction access road for the construction area set, adjacent sequence of construction
Construction section separated with plank;Step3: surface layer ingredient and stirring;By colored EPDM particle ingredient in proportion, it is stirred for mixing
It is even;Ingredient dosage is component needed for the construction area that will be constructed;Ingredient again and stirring are all needed before the construction of every a batch construction area;
Step4: it is laid with colored surface layer;The colored EPDM particle of mixing is laid with to the layout line, then presses colour EPDM particle with pressure
Surface, with a thickness of 4cm;Step5: it checks;After all construction areas are laid with, check for being laid with mistake in order to whole in time
Change;The colored EPDM particle drag flight descaling of outlet is fallen, paving is mended in the place not being laid in place in time;Step6: solidification;It waits
48h, allows the particles cured molding of colored EPDM;While the complete construction area of this construction waits solidification, to next construction area
Colored surface layer is laid with.
As an improvement of the above technical solution, the finishing phase is packed up the various tools in construction, in plastic cement
The outermost in face sets up the enclosure wall that plank is built into, and the plastic floor after construction is 21 days or more idle.
As an improvement of the above technical solution, the proportion of diluent and water is 3.5:1 in the viscose.
As an improvement of the above technical solution, in the Step3 in the paving black basecoat stage, this construction area is being waited
While bottom black EPDM is particles cured, the Step1 and Step2 that spread the black basecoat stage are repeated, is spread in next construction area black
Color EPDM particle is as bottom.
As an improvement of the above technical solution, before spreading the colored surface layer stage, one layer of viscose is smeared on black basecoat.
Compared with prior art, implementation result of the invention is as follows by the present invention: passing through sectional streak and parallel construction
The efficiency of method lifting construction reduces the error rate of construction;Coloured silk is promoted by first spreading the method that black basecoat repaves colored surface layer
The success rate that color EPDM particle is laid with reduces thickness dosage needed for being laid with colour EPDM particle;By the way that pretreatment stage is arranged
The efficiency and order of lifting construction.The present invention is intended to provide a kind of efficient colour EPDM granule plastic rubber ground construction scheme.
Detailed description of the invention
Fig. 1 is the construction direction figure of construction area;
Fig. 2 is construction procedure figure.
Specific embodiment
Illustrate the contents of the present invention below in conjunction with specific embodiments.
Arrangement and method for construction of the present invention includes: the subregion scribing line stage, construction stage.Fig. 2 is working procedure table, such as Fig. 2
It is shown.
The construction stage includes: pretreatment stage, paving black basecoat stage, spreads the colored surface layer stage, finishing phase, tests
The receipts stage.
The subregion scribing line stage the following steps are included:
Step1: region is divided.The ground that will be constructed is divided into multiple construction areas.
Step2: selection construction access road.A construction access road is selected, construction direction delimited.Fig. 1 is construction access road schematic diagram,
As shown in Figure 1.It successively constructs according to construction access road multiple construction areas on same construction access road.Positioned at same construction access road
Vertical line on multiple construction areas construct simultaneously.
Step3: construction area is surrounded.The construction area that will be constructed and construction area to be onstructed are separated.
In arrangement and method for construction, construction laying is carried out to a biggish region using subregion scribing line, efficiently solves and accounts for
When ground area is excessive, laying does not catch up with the problem of ingredient solidifies, and reduces the loss of ingredient.And in this way, to construct
More orderly, it can control effectively to each process in construction.While with the above advantages, add because setting
Work route, in the case that multiple construction areas are processed there are simultaneous processing and successively, the solidification of a upper construction area and next construction area
Two processes of laying carry out simultaneously, reduce error in the case where, improve speed of application and efficiency.
Be divided into pretreatment stage in construction stage, it is desirable to provide a good laying environment, construction area ground, match
Material etc. is ready to carry out the laying of bottom again, rather than only prepares the position that will be laid with, and can be effectively reduced error rate
With promotion working efficiency.
The paving black basecoat stage is that subsequent laying color grains are prepared, and first stamps one layer of bottom, is conducive to color grains paving
If scribing line, also can visually protrude color grains.This programme is also added into finishing phase and acceptance phase, is respectively used to
Extra object and inspection qualification degree reduce do over again workload and promotion and are laid with after tidying up scribing line and solidifying to rectify and improve in time
Accuracy.
The pretreatment stage the following steps are included:
Step1: cleaning ground;Ground to be onstructed is cleared up with butyl ester, it is ensured that there is no booty, dust, water stain, oily on ground
Stain etc..It avoids because the object on ground influences the effect of viscose smearing.
Step2: sample;Take a tile position of each construction area as sample area.EPDM black particle is prepared in proportion
It is good, viscose is coated on the ground of sample area, and the EPDM black particle prepared is laid on the viscose of sample area.It waits for 24 hours,
Solidify to EPDM black particle, detects the EPDM black particle adhesive force and intensity of sample area, it is ensured that not easy to fall off, intensity reaches
To requirement, can start formally to construct.There is no problem for the combination of bottom ingredient and viscose that specimen is used to ensure, avoids just
Because cementitiousness is inadequate when formula is constructed, the construction speed of construction area is influenced, engineering is caused to trail.
Step3: viscose is smeared;Viscose is smeared on the construction area ground that will be constructed.Viscose is for promoting black EPDM
The cementitiousness of particle and ground reduces a possibility that damaging, promotes the service life of plastic floor.
Step4: bottom ingredient;Black EPDM particle needed for bottom is mixed in proportion, the EPDM black that ingredient is selected
Amount of particles coordinative construction area area.
The paving black basecoat stage the following steps are included:
Step1: stirring bottom ingredient;The bottom black EPDM granule formulations that pretreatment stage mixes are stirred well even.It avoids
The Density inhomogeneity that bottom ingredient is laid with.
Step2: upper bottom;The bottom ingredient being stirred will be mixed to be routed on the viscose of construction area, will be spread using press machine
If good bottom ingredient flattens, bottom ingredient flatten after with a thickness of 10cm.It flattens while ensuring earth's surface plastic cement flatness,
Convenient for it is subsequent enamel surface layer when scribing line,
Step3: solidifying and processes next construction area.The bottom ingredient being laid with places for 24 hours, waits its solidification.In
While waiting the bottom black EPDM of this construction area particles cured, above step is repeated, spreads black in next construction area
EPDM particle is as bottom.
Before spreading the colored surface layer stage, one layer of viscose is smeared on black basecoat.The paving colored surface layer stage include with
Lower step:
Step1: scribing line;After the first-class black basecoat in all construction areas, coloured silk to be gone up is finished with white line on black basecoat
The pattern of color table layer.It after having crossed, checks whether scribing line malfunctions, does not malfunction, carry out in next step.
Step2: partition domain;According to the construction area originally divided, the region to be painted finished is assigned to each construction area
In, it successively constructs according to the construction access road for the construction area set, the construction section of adjacent sequence of construction is separated with plank.To next
When the construction area of sequence is constructed, the plank of separation is taken away.It can be realized efficient colouring in this way, avoid this construction
The colored EPDM particle in area goes to next construction area, reduces colour EPDM particle and spreads out the probability outside line.
Step3: surface layer ingredient and stirring;By colored EPDM particle ingredient in proportion, it is stirred for mixing.Ingredient dosage is i.e.
Component needed for construction area by construction.It is every a batch construction area construction before all need ingredient again and stirring, to avoid be laid with when
Colored EPDM particle through ingredient is cured and precipitates, and influences colored EPDM mobility of particle when being laid with, and reduce colour
The waste of EPDM particle.
Step4: it is laid with colored surface layer;The colored EPDM particle of mixing is laid with to the layout line, then presses colour with pressure
The surface of EPDM particle, with a thickness of 4cm.
Step5: it checks;After all construction areas are laid with, check for being laid with mistake in order to rectify and improve in time.By outlet
Colored EPDM particle fallen with drag flight descaling, be not laid in place place in time mend paving.Setting checks that link can be avoided effectively
Useless working hour reduces error, and makes up in time after error.
Step6: solidification.48h is waited, allows the particles cured molding of colored EPDM.It is waited in the complete construction area of this construction solid
While change, the colored surface layer of next construction area is laid with, the mode of such parallel construction is effectively saved the construction time,
Improve construction efficiency.
This programme uses black basecoat bottoming, and surface layer is laid with the construction method of colour EPDM particle, convenient for EPDM colored
Grain scribing line and laying, not only contribute to construct, and also improve the whole cementitiousness with ground of EPDM particle, with ensure that plastic cement
The service life in face.This paving mode reduces the dosage of colour EPDM particle, section in the case where the standard thickness of plastic floor requires
About cost and construction time.
Also, the mode of subregion scribing line and parallel construction greatly improves construction also on the arrangement and method for construction of script
Efficiency reduces error rate.
Various tools in construction are packed up, set up plank in the outermost of plastic floor and build by the finishing phase
At enclosure wall, plastic floor after construction is 21 days or more idle, to ensure use intensity.
The acceptance phase removes enclosure wall after finishing phase, is checked and accepted by Party A.
For construction, there are also claimed below:
Before construction: bituminous concrete can be used in the requirement of construction ground or cement concrete carries out basis and mats formation, and requires
With certain strength and stability (coagulating cement earth foundation needs to cut expansion joint, can not do waterproof layer).Construction ground is tight
Cut-off gives birth to crack and due to differential frost heave caused by freezing;Construction ground must have preferably flatness and the regulation gradient.It applies
It building site face must flat, guarantee draining.Construction ground will keep cleaning drying.
In construction: best 15 DEG C~35 DEG C of construction temperature, it is too high or too low for temperature, it influences to construct.Mixing stirring is had to
It is full and uniform.Each batch of material will be connected, and otherwise be connected bad meeting seam.One when finally to the plastic floor deburring of laying
Surely it to modify neat.
Ingredient is carried out in strict accordance with ratio and is matched depending on particle situation.Good granular mass glue is few, poor
It is more with glue;Bulky grain to pour water consumption few, it is short grained that pour water consumption more.Bottom rubber grain viscose=6:1~8:1;
Catalyst does not need generally to add, and when being lower than 10 DEG C such as environment temperature, can be suitably added the catalyst that mass ratio is 5~10%.
In the viscose, diluent and water are prepared according to 3.5:1.
Although the numberical range of each technological parameter involved in the present invention can not all embody in the above-described embodiments,
As long as but those skilled in the art's envisioned any numerical value fallen into the above-mentioned numberical range completely can be implemented this
Invention also includes any combination of occurrence in several numberical ranges certainly.Herein, due to space considerations, be omitted to
Out in certain one or more numberical range occurrence embodiment, be not to be construed as herein to technical solution of the present invention require protect
The formula and processing range of shield lack the understanding that sufficient embodiment is supported.
The Applicant declares that the present invention is explained by the above embodiments detailed process equipment and process flow of the invention,
But the present invention is not limited to the above detailed process equipment and process flow, that is, it is above-mentioned detailed not mean that the present invention must rely on
Process equipment and process flow could be implemented.It should be clear to those skilled in the art, any improvement in the present invention,
Addition, selection of concrete mode of equivalence replacement and auxiliary element to each raw material of product of the present invention etc., all fall within of the invention
Within protection scope and the open scope.
Claims (8)
1. a kind of EPDM color grains plastic floor construction method characterized by comprising cross stage, construction rank subregion
Section;
The construction stage includes: pretreatment stage, paving black basecoat stage, spreads the colored surface layer stage, finishing phase, checks and accepts rank
Section;
The subregion scribing line stage the following steps are included:
Step1: region is divided;The ground that will be constructed is divided into multiple construction areas;
Step2: selection construction access road;A construction access road is selected, construction direction delimited;It is multiple on same construction access road
It successively constructs according to construction access road construction area;It constructs simultaneously multiple construction areas on the vertical line of same construction access road;
Step3: construction area is surrounded;The construction area that will be constructed and construction area to be onstructed are separated.
2. a kind of EPDM color grains plastic floor construction method according to claim 1, which is characterized in that the pre- place
The reason stage the following steps are included:
Step1: cleaning ground;Ground to be onstructed is cleared up with butyl ester, it is ensured that there is no booty, dust, water stain, grease stain on ground
Deng;
Step2: sample;Take a tile position of each construction area as sample area;EPDM black particle is prepared in proportion, In
Viscose is coated on the ground of sample area, the EPDM black particle prepared is laid on the viscose of sample area;Wait for 24 hours, to
The solidification of EPDM black particle, detects the EPDM black particle adhesive force and intensity of sample area, it is ensured that not easy to fall off, intensity reaches
It is required that can start formally to construct;
Step3: viscose is smeared;Viscose is smeared on the construction area ground that will be constructed;
Step4: bottom ingredient;Black EPDM particle needed for bottom is mixed in proportion, the EPDM black particle that ingredient is selected
Dosage coordinative construction area area.
3. a kind of EPDM color grains plastic floor construction method according to claim 2, which is characterized in that the paving is black
The color bottom stage the following steps are included:
Step1: stirring bottom ingredient;The bottom black EPDM granule formulations that pretreatment stage mixes are stirred well even;
Step2: upper bottom;The bottom ingredient being stirred will be mixed to be routed on the viscose of construction area, will be laid using press machine
Bottom ingredient flatten, bottom ingredient flatten after with a thickness of 10cm;
Step3: solidifying and processes next construction area;The bottom ingredient being laid with places for 24 hours, waits its solidification.
4. a kind of EPDM color grains plastic floor construction method according to claim 3, which is characterized in that the paving is color
The color table layer stage the following steps are included:
Step1: scribing line;After the first-class black basecoat in all construction areas, table to be enameled is finished with white line on black basecoat
The pattern of layer;It after having crossed, checks whether scribing line malfunctions, does not malfunction, carry out in next step;
Step2: partition domain;According to the construction area originally divided, the region to be painted finished is assigned in each construction area, is pressed
It successively constructs according to the construction access road for the construction area set, the construction section of adjacent sequence of construction is separated with plank;
Step3: surface layer ingredient and stirring;By colored EPDM particle ingredient in proportion, it is stirred for mixing;Ingredient dosage is that will apply
Component needed for the construction area of work;Ingredient again and stirring are all needed before the construction of every a batch construction area;
Step4: it is laid with colored surface layer;The colored EPDM particle of mixing is laid with to the layout line, then EPDM colored with pressure pressure
The surface of grain, with a thickness of 4cm;
Step5: it checks;After all construction areas are laid with, check for being laid with mistake in order to rectify and improve in time;By the coloured silk of outlet
Color EPDM particle is fallen with drag flight descaling, and paving is mended in the place not being laid in place in time;
Step6: solidification;48h is waited, allows the particles cured molding of colored EPDM;It is waited in the complete construction area of this construction cured
Meanwhile the colored surface layer of next construction area is laid with.
5. a kind of EPDM color grains plastic floor construction method according to claim 1, which is characterized in that the ending
Stage packs up the various tools in construction, the enclosure wall that plank is built into is set up in the outermost of plastic floor, after construction
Plastic floor is 21 days or more idle.
6. a kind of EPDM color grains plastic floor construction method according to claim 3, which is characterized in that the viscose
The proportion of middle diluent and water is 3.5:1.
7. a kind of EPDM color grains plastic floor construction method according to claim 3, which is characterized in that the paving is black
In the Step3 in color bottom stage, while the bottom black EPDM for waiting this construction area is particles cured, repeat to spread black bottom
The Step1 and Step2 in layer stage, in next construction area, paving black EPDM particle is as bottom.
8. a kind of EPDM color grains plastic floor construction method according to claim 4, which is characterized in that colored in paving
Before the stage of surface layer, one layer of viscose is smeared on black basecoat.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910630166.4A CN110424213A (en) | 2019-07-12 | 2019-07-12 | A kind of EPDM color grains plastic floor construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910630166.4A CN110424213A (en) | 2019-07-12 | 2019-07-12 | A kind of EPDM color grains plastic floor construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110424213A true CN110424213A (en) | 2019-11-08 |
Family
ID=68410612
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910630166.4A Pending CN110424213A (en) | 2019-07-12 | 2019-07-12 | A kind of EPDM color grains plastic floor construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110424213A (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101792997A (en) * | 2010-03-31 | 2010-08-04 | 成都建筑工程集团总公司 | Mixed type plastic track construction method |
CN106007557A (en) * | 2016-05-16 | 2016-10-12 | 天津纽威特橡胶制品股份有限公司 | Environment-friendly water-based plastic track |
CN107090761A (en) * | 2017-05-26 | 2017-08-25 | 青岛科兴教育装备有限公司 | A kind of construction method of mixed type runway |
CN206956497U (en) * | 2017-03-16 | 2018-02-02 | 苏州大乘环保新材有限公司 | A kind of novel aqueous environmental protection weeping plastic track |
CN208933781U (en) * | 2018-07-11 | 2019-06-04 | 南京飞能橡塑制品有限公司 | A kind of colour EPDM plastic cement race track not easy to fade |
CN109989315A (en) * | 2019-04-11 | 2019-07-09 | 河北绿城园林绿化工程有限公司 | A kind of method for paving on plastics road surface |
-
2019
- 2019-07-12 CN CN201910630166.4A patent/CN110424213A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101792997A (en) * | 2010-03-31 | 2010-08-04 | 成都建筑工程集团总公司 | Mixed type plastic track construction method |
CN106007557A (en) * | 2016-05-16 | 2016-10-12 | 天津纽威特橡胶制品股份有限公司 | Environment-friendly water-based plastic track |
CN206956497U (en) * | 2017-03-16 | 2018-02-02 | 苏州大乘环保新材有限公司 | A kind of novel aqueous environmental protection weeping plastic track |
CN107090761A (en) * | 2017-05-26 | 2017-08-25 | 青岛科兴教育装备有限公司 | A kind of construction method of mixed type runway |
CN208933781U (en) * | 2018-07-11 | 2019-06-04 | 南京飞能橡塑制品有限公司 | A kind of colour EPDM plastic cement race track not easy to fade |
CN109989315A (en) * | 2019-04-11 | 2019-07-09 | 河北绿城园林绿化工程有限公司 | A kind of method for paving on plastics road surface |
Non-Patent Citations (1)
Title |
---|
卢江山: "浅析EPDM彩色颗粒塑胶地面施工操作要点", 《建材与装饰》 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20130330469A1 (en) | Eco-friendly road surface coating material for thawing ice and snow and methods of preparing and using the same | |
CN201933388U (en) | Distribution structure for epoxy asphalt distribution truck | |
CN104975553B (en) | A kind of cold-mix asphalt mixing material manufacturing technique and its mixing plant | |
CN109021505A (en) | Sealing material and its preparation method and application at polymer emulsified asphalt ultrathin table | |
CN103966935B (en) | ECC (engineered cementitious composite) durable type colored road pavement structure and paving method thereof | |
CN110424213A (en) | A kind of EPDM color grains plastic floor construction method | |
CN106351256A (en) | Pipe rack bottom waterproof construction method | |
CN104070719B (en) | A kind of manufacture method of the polymer membranes of energy-conserving and environment-protective without Colophonium | |
CN206553884U (en) | A kind of multi-stage hybrid bituminous epoxy distribution vehicle | |
CN202688825U (en) | Bituminous mixture blending device | |
CN102619153A (en) | Construction method of green building, environmental protection, permeable and venting artificial playground and structure of artificial playground | |
CN108046683A (en) | A kind of anti-rut splits regenerated road surface haveing excellent performance and preparation method thereof | |
CN110284402A (en) | A kind of ultra micro spray coating constructing technique of Colorful Asphalt Pavement | |
CN109826325A (en) | A kind of anti-seepage construction method of architectural engineering | |
CN114059741A (en) | Anti-cracking ceramic floor material and assembled floor paving structure | |
CN109958024B (en) | Anti-skid pavement construction equipment and construction method thereof | |
CN104164091B (en) | Highway affixing kerfs belt | |
CN105419642B (en) | A kind of roof seamless anticorrosion Waterproof Construction Technique | |
CN103382724A (en) | Corrosion-prevention construction method for water pool by adopting vinyl ester | |
CN205044712U (en) | Modular clean system of radar response vehicle | |
CN103740057B (en) | Reaction resin sizing material and synchronous breakstone spreading machine | |
CN103334372A (en) | Bi-component internal mixing line-marking device | |
CN107938460A (en) | A kind of automobile test low attached bituminous paving and its laying method | |
CN107090761A (en) | A kind of construction method of mixed type runway | |
CN100419165C (en) | Waterproof structure for deck and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191108 |