CN110412454A - A kind of one or two complete switch closed loop test methods - Google Patents

A kind of one or two complete switch closed loop test methods Download PDF

Info

Publication number
CN110412454A
CN110412454A CN201910615823.8A CN201910615823A CN110412454A CN 110412454 A CN110412454 A CN 110412454A CN 201910615823 A CN201910615823 A CN 201910615823A CN 110412454 A CN110412454 A CN 110412454A
Authority
CN
China
Prior art keywords
signal
test
voltage
current
primary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910615823.8A
Other languages
Chinese (zh)
Other versions
CN110412454B (en
Inventor
李志�
杨瀚鹏
胡景博
郑志曜
高一波
余绍峰
苏毅方
吴钢
林建钦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Huadian Equipment Inspection Institute
State Grid Zhejiang Electric Power Co Ltd
Haiyan Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Zhejiang Huadian Equipment Inspection Institute
State Grid Zhejiang Electric Power Co Ltd
Haiyan Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Huadian Equipment Inspection Institute, State Grid Zhejiang Electric Power Co Ltd, Haiyan Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical Zhejiang Huadian Equipment Inspection Institute
Priority to CN201910615823.8A priority Critical patent/CN110412454B/en
Publication of CN110412454A publication Critical patent/CN110412454A/en
Priority to US16/897,130 priority patent/US11402457B2/en
Application granted granted Critical
Publication of CN110412454B publication Critical patent/CN110412454B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/327Testing of circuit interrupters, switches or circuit-breakers
    • G01R31/3271Testing of circuit interrupters, switches or circuit-breakers of high voltage or medium voltage devices
    • G01R31/3272Apparatus, systems or circuits therefor
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/327Testing of circuit interrupters, switches or circuit-breakers
    • G01R31/3277Testing of circuit interrupters, switches or circuit-breakers of low voltage devices, e.g. domestic or industrial devices, such as motor protections, relays, rotation switches
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R35/00Testing or calibrating of apparatus covered by the other groups of this subclass
    • G01R35/02Testing or calibrating of apparatus covered by the other groups of this subclass of auxiliary devices, e.g. of instrument transformers according to prescribed transformation ratio, phase angle, or wattage rating
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R35/00Testing or calibrating of apparatus covered by the other groups of this subclass
    • G01R35/04Testing or calibrating of apparatus covered by the other groups of this subclass of instruments for measuring time integral of power or current

Abstract

The present invention relates to a kind of one or two complete switch closed loop test methods, including test macro, the test macro includes: switching route device, test method is the following steps are included: establish electrical connection, establish communication connection, accuracy test, primary side, secondary side and integration precision, protection test and generation test report, advantages of the present invention: since primary side standard mutual inductor tester can acquire 16 channels simultaneously, secondary side standard mutual inductor tester energy while 8 channels, therefore the accuracy test in all channels can disposably be completed, both the time is saved, also ensure the similarity of measurement condition and real working condition;Additionally by the test of switching route device switching primary side, secondary side test and integration test, realizes primary connection primary side, secondary side and integrative closed ring test, high degree of automation can be completed and improve detection efficiency.

Description

A kind of one or two complete switch closed loop test methods
Technical field
The present invention relates to a kind of one or two complete switch closed loop test methods.
Background technique
In electric system 10kV power distribution network, the design seperated with distribution terminal of conventional electrical distribution on-pole switch, installation, equipment With low, poor reliability is spent, with the extensive networking of one or two complete switch, on the one hand there is missing in existing detectability, difficult To guarantee primary side, secondary side and integrated stable state and transient characterisitics, on the other hand, there are bottlenecks for existing detection efficiency, need For primary side, secondary side and integration tested respectively, a secondary complete switch under low efficiency, for one or two times at The closed loop test method of set switch quality control, it is difficult to guarantee the penetration power and coverage rate of the control of one or two complete switch quality.
Summary of the invention
The present invention wants purpose to be achieved to be just to provide a kind of one or two complete on-pole switch integrated testing methods, has The blind area of the complete on-pole switch quality control of elimination one or two times of effect improves the penetration power and detection effect of one or two complete switch Rate.
In order to solve the above-mentioned technical problem, the present invention is achieved by the following technical solutions: a kind of one or two times complete to open Ring test method is closed, including test macro, the test macro include:
Industrial personal computer, the industrial personal computer is for being arranged preset parameter, status switch, and acquisition standard mutual inductor tester, mark Data in the distribution terminal of quasi- powermeter verification instrumeter and one or two complete switch, produce examining report after analysis;
Low pressure and low power source: for preset parameter output electromagnetic type terminal voltage signal and terminal current signal to be arranged;Or electricity Minor terminal voltage signal and terminal current signal;
High-voltage power source: secondary voltage signal and secondary current signal to be amplified are exported for preset parameter to be arranged;
Booster: for amplifying the secondary voltage signal of high-voltage power source output to primary voltage signal;
Current lifting device: for amplifying the secondary current signal of high-voltage power source output to primary current signal;
Standard potential transformer: for primary voltage signal to be switched to the voltage signal convenient for measurement;
Standard current transformer: for secondary current signal to be switched to the current signal convenient for measurement;
Primary side standard mutual inductor tester: for acquire output to one or two complete switch primary sides voltage signal and Current signal;
Secondary side standard mutual inductor tester: for acquire output to one or two complete switch secondary sides voltage signal and Current signal;
Switch route device: for loop switch in the detection process;When test macro carries out primary side test, switching Route device will switch secondary side output and be transferred by terminal into primary side standard mutual inductor tester;When test macro carries out two When secondary side is tested, switching route device transfers the program-controlled source output of low pressure into the distribution end of one or two complete switch by terminal End;When test macro, which carries out integration, to be tested, switched router will switch secondary side by terminal and export direct-connected such as one or two times The input of the distribution terminal of complete switch;
Standard electric energy meter tester: for acquiring standard electric power signal, and according to the distribution according to one or two complete switch The collected electric power signal of terminal calculates electric flux error;
The test method the following steps are included:
Step 1: test macro High voltage output electric interfaces are established and are connected with the electrical of the primary side of one or two complete switch It connects, establishes the electrical connection of the switching route device of the secondary side output access test macro of one or two complete switch, establish and survey The electrical connection of the distribution terminal of the switching route device and one or two complete switch of test system;
Step 2: the communication connection of test macro Yu one or two complete switch is established;
Step 3: test macro applies stable voltage signal to one or two complete switch by the electrical connection of step 1 And current signal, when carrying out primary side test, switching route device will switch secondary side output and be transferred by terminal into primary Side standard mutual inductor tester;When carrying out secondary side test, switching route device turns the program-controlled source output of low pressure by terminal Access the distribution terminal of one or two complete switch;When carrying out integration test, switched router will be switched secondary by terminal Side exports the input of the direct-connected such as distribution terminal of one or two complete switch.And the communication connection through step 2 will tested one or two times at Set switchs collected voltage, electric current back production to test macro, carries out primary side, secondary side and integration precision, protection test;
Step 4: the test result of step 3 is input to industrial personal computer, generates test report.
Preferably, the communication connection of the test macro in step 2 and one or two complete switch is established by serial ports/network interface.
Preferably, the switching route device is connected with industrial personal computer.
Preferably, step 3 successively the following steps are included:
Step 30: industrial personal computer establishes one or two complete switch primary sides and primary side standard is mutual by switching route device The electrical connection of sensor tester;
Step 31: industrial personal computer controls high-voltage power source and exports secondary voltage signal and two simultaneously by preset load point Primary current signal;
Step 32: high-voltage power source output secondary voltage signal is enlarged by primary voltage signal by booster, and Low pressure and low power source output secondary current signal is enlarged into primary current signal by current lifting device;
Step 33: primary side standard mutual inductor tester acquires the primary electricity that booster exports by standard potential transformer Signal is pressed, the primary current signal of booster output is acquired by standard current transformer;
Step 34: the acquisition of primary side standard mutual inductor tester switchs secondary current, the voltage signal of secondary output;
Step 35: primary side standard mutual inductor tester according to collected signal calculate error, and will be sent in result to Industrial personal computer completes primary side accuracy test;
Step 36: industrial personal computer by switching route device, establish the program-controlled source of low pressure and secondary side standard mutual inductor tester, The electrical connection of the distribution terminal of one or two complete switch;
Step 37: industrial personal computer controls low pressure and low power source and exports secondary voltage signal and two simultaneously by preset load point Primary current signal;
Step 38: secondary side standard mutual inductor tester acquires secondary current, the voltage signal of the program-controlled source output of low pressure, and It will send on acquisition signal to industrial personal computer;
Step 39: secondary current, the voltage signal of standard electric energy meter tester mesolow program-controlled source output, and by electric flux It is sent on signal to industrial personal computer;
Step 310: industrial personal computer acquires distribution terminal by the communication interface of the distribution terminal with one or two complete switch and adopts Electric current, voltage, the electric flux signal collected, and with give on secondary side standard mutual inductor tester and standard electric energy meter tester Signal compares, and calculates error, completes secondary side accuracy test;
Step 311: for industrial personal computer by preset waveform, control low pressure and low power source exports secondary voltage signal and secondary simultaneously Current signal;
Step 312: industrial personal computer is defeated by the communication interface acquisition distribution terminal of the distribution terminal with one or two complete switch Remote signals out complete secondary side transmission test;
Step 313: industrial personal computer establishes matching for one or two complete switch and one or two complete switch by switching route device The electrical connection of electric terminals;
Step 314: industrial personal computer controls high-voltage power source and exports secondary voltage signal and two simultaneously by preset load point Primary current signal;
Step 315: high-voltage power source output secondary voltage signal is enlarged by primary voltage signal by booster, and Low pressure and low power source output secondary current signal is enlarged into primary current signal by current lifting device;
Step 316: primary side standard mutual inductor tester acquires the primary of booster output by standard potential transformer Voltage signal, the primary current signal of booster output is acquired by standard current transformer, and will be sent on signal to industrial personal computer;
Step 317: industrial personal computer acquires distribution terminal by the communication interface of the distribution terminal with one or two complete switch and adopts Electric current, the voltage signal collected, and error is calculated, complete integration precision test;
Step 318: for industrial personal computer by preset waveform, control high-voltage power source exports secondary voltage signal and secondary simultaneously Current signal;
Step 319: high-voltage power source output secondary voltage signal is enlarged by primary voltage signal by booster, and Low pressure and low power source output secondary current signal is enlarged into primary current signal by current lifting device;
Step 320: industrial personal computer is defeated by the communication interface acquisition distribution terminal of the distribution terminal with one or two complete switch Remote signals out complete integration transmission test;
Step 321: industrial personal computer exports test report according to test result, completes closed loop detection.
In conclusion advantages of the present invention: establishing electrical connection by step 1, step 2 establishes communication connection, step Three test macros carry out primary side, secondary side and integration precision, protection test and the test of step 4 generation test report Method, since primary side standard mutual inductor tester can acquire 16 channels simultaneously, secondary side standard mutual inductor tester can be same When 8 channels, therefore can disposably complete the accuracy test in all channels, both save the time, also ensure measurement condition with The similarity of real working condition;It is real additionally by the test of switching route device switching primary side, secondary side test and integration test Having showed primary connection can be completed primary side, secondary side and integrative closed ring test, high degree of automation, improve detection effect Rate.
Specific embodiment
A kind of one or two complete switch closed loop test methods, including test macro, the test macro include:
Industrial personal computer, the industrial personal computer is for being arranged preset parameter, status switch, and acquisition standard mutual inductor tester, mark Data in the distribution terminal of quasi- powermeter verification instrumeter and one or two complete switch, produce examining report after analysis;
Low pressure and low power source: for preset parameter output electromagnetic type terminal voltage signal and terminal current signal to be arranged;Or electricity Minor terminal voltage signal and terminal current signal;
High-voltage power source: secondary voltage signal and secondary current signal to be amplified are exported for preset parameter to be arranged;
Booster: for amplifying the secondary voltage signal of high-voltage power source output to primary voltage signal;
Current lifting device: for amplifying the secondary current signal of high-voltage power source output to primary current signal;
Standard potential transformer: for primary voltage signal to be switched to the voltage signal convenient for measurement;
Standard current transformer: for secondary current signal to be switched to the current signal convenient for measurement;
Primary side standard mutual inductor tester: for acquire output to one or two complete switch primary sides voltage signal and Current signal, primary side standard mutual inductor tester support input three-phase current, back production three-phase current, return at input zero-sequence current It adopts 16 zero-sequence current, input three-phase voltage, input residual voltage, back production three-phase voltage, back production residual voltage channels while adopting Collection;
Secondary side standard mutual inductor tester: for acquire output to one or two complete switch secondary sides voltage signal and Current signal, secondary side standard mutual inductor tester support input three-phase current, input zero-sequence current, input three-phase voltage, is defeated Enter 8 channels of residual voltage while acquiring;
Switch route device: for loop switch in the detection process;When test macro carries out primary side test, switching Route device will switch secondary side output and be transferred by terminal into primary side standard mutual inductor tester;When test macro carries out two When secondary side is tested, switching route device transfers the program-controlled source output of low pressure into the distribution end of one or two complete switch by terminal End;When test macro, which carries out integration, to be tested, switched router will switch secondary side by terminal and export direct-connected such as one or two times The input of the distribution terminal of complete switch;
Standard electric energy meter tester: for acquiring standard electric power signal, and according to the distribution according to one or two complete switch The collected electric power signal of terminal calculates electric flux error;
The test method the following steps are included:
Step 1: test macro High voltage output electric interfaces are established and are connected with the electrical of the primary side of one or two complete switch It connects, establishes the electrical connection of the switching route device of the secondary side output access test macro of one or two complete switch, establish and survey The electrical connection of the distribution terminal of the switching route device and one or two complete switch of test system;
Step 2: the communication connection of test macro Yu one or two complete switch is established;
Step 3: test macro applies stable voltage signal to one or two complete switch by the electrical connection of step 1 And current signal, when carrying out primary side test, switching route device will switch secondary side output and be transferred by terminal into primary Side standard mutual inductor tester;When carrying out secondary side test, switching route device turns the program-controlled source output of low pressure by terminal Access the distribution terminal of one or two complete switch;When carrying out integration test, switched router will be switched secondary by terminal Side exports the input of the direct-connected such as distribution terminal of one or two complete switch.And the communication connection through step 2 will tested one or two times at Set switchs collected voltage, electric current back production to test macro, carries out primary side, secondary side and integration precision, protection test;
Step 4: the test result of step 3 is input to industrial personal computer, generates test report.
Electrical connection is established by step 1, step 2 establishes communication connection, step 3 test macro carries out primary side, two Secondary side and integration precision, protection test and step 4 generate the test method of test report, due to primary side standard mutual inductor Device tester can acquire 16 channels, secondary side standard mutual inductor tester energy while 8 channels simultaneously, therefore can be disposable complete At the accuracy test in all channels, the time is both saved, also ensures the similarity of measurement condition and real working condition;Additionally by Switch the test of route device switching primary side, secondary side test and integration test, realizing primary connection can be completed once Side, secondary side and integrative closed ring test, high degree of automation improve detection efficiency.
The communication connection of test macro and one or two complete switch in step 2 is established by serial ports/network interface, is adapted to Different working environments and installation requirements, practical performance is good, and the switching route device is connected with industrial personal computer, is able to achieve switching road By the accurate control of device, operated convenient for operator.
Step 3 successively the following steps are included:
Step 30: industrial personal computer establishes one or two complete switch primary sides and primary side standard is mutual by switching route device The electrical connection of sensor tester;
Step 31: industrial personal computer controls high-voltage power source and exports secondary voltage signal and two simultaneously by preset load point Primary current signal;
Step 32: high-voltage power source output secondary voltage signal is enlarged by primary voltage signal by booster, and Low pressure and low power source output secondary current signal is enlarged into primary current signal by current lifting device;
Step 33: primary side standard mutual inductor tester acquires the primary electricity that booster exports by standard potential transformer Signal is pressed, the primary current signal of booster output is acquired by standard current transformer;
Step 34: the acquisition of primary side standard mutual inductor tester switchs secondary current, the voltage signal of secondary output;
Step 35: primary side standard mutual inductor tester according to collected signal calculate error, and will be sent in result to Industrial personal computer completes primary side accuracy test;
Step 36: industrial personal computer by switching route device, establish the program-controlled source of low pressure and secondary side standard mutual inductor tester, The electrical connection of the distribution terminal of one or two complete switch;
Step 37: industrial personal computer controls low pressure and low power source and exports secondary voltage signal and two simultaneously by preset load point Primary current signal;
Step 38: secondary side standard mutual inductor tester acquires secondary current, the voltage signal of the program-controlled source output of low pressure, and It will send on acquisition signal to industrial personal computer;
Step 39: secondary current, the voltage signal of standard electric energy meter tester mesolow program-controlled source output, and by electric flux It is sent on signal to industrial personal computer;
Step 310: industrial personal computer acquires distribution terminal by the communication interface of the distribution terminal with one or two complete switch and adopts Electric current, voltage, the electric flux signal collected, and with give on secondary side standard mutual inductor tester and standard electric energy meter tester Signal compares, and calculates error, completes secondary side accuracy test;
Step 311: for industrial personal computer by preset waveform, control low pressure and low power source exports secondary voltage signal and secondary simultaneously Current signal;
Step 312: industrial personal computer is defeated by the communication interface acquisition distribution terminal of the distribution terminal with one or two complete switch Remote signals out complete secondary side transmission test;
Step 313: industrial personal computer establishes matching for one or two complete switch and one or two complete switch by switching route device The electrical connection of electric terminals;
Step 314: industrial personal computer controls high-voltage power source and exports secondary voltage signal and two simultaneously by preset load point Primary current signal;
Step 315: high-voltage power source output secondary voltage signal is enlarged by primary voltage signal by booster, and Low pressure and low power source output secondary current signal is enlarged into primary current signal by current lifting device;
Step 316: primary side standard mutual inductor tester acquires the primary of booster output by standard potential transformer Voltage signal, the primary current signal of booster output is acquired by standard current transformer, and will be sent on signal to industrial personal computer;
Step 317: industrial personal computer acquires distribution terminal by the communication interface of the distribution terminal with one or two complete switch and adopts Electric current, the voltage signal collected, and error is calculated, complete integration precision test;
Step 318: for industrial personal computer by preset waveform, control high-voltage power source exports secondary voltage signal and secondary simultaneously Current signal;
Step 319: high-voltage power source output secondary voltage signal is enlarged by primary voltage signal by booster, and Low pressure and low power source output secondary current signal is enlarged into primary current signal by current lifting device;
Step 320: industrial personal computer is defeated by the communication interface acquisition distribution terminal of the distribution terminal with one or two complete switch Remote signals out complete integration transmission test;
Step 321: industrial personal computer exports test report according to test result, completes closed loop detection.
In addition to above preferred embodiment, there are other embodiments of the invention, and those skilled in the art can be according to this Invention makes various changes and modifications, and as long as it does not depart from the spirit of the invention, should belong to appended claims of the present invention and determines The range of justice.

Claims (4)

1. a kind of one or two complete switch closed loop test methods, it is characterised in that: including test macro, the test macro packet It includes:
Industrial personal computer, the industrial personal computer is for being arranged preset parameter, status switch and acquisition standard mutual inductor tester, standard electric Data in the distribution terminal of energy table tester and one or two complete switch, produce examining report after analysis;
Low pressure and low power source: for preset parameter output electromagnetic type terminal voltage signal and terminal current signal to be arranged;Or electronic type Terminal voltage signal and terminal current signal;
High-voltage power source: secondary voltage signal and secondary current signal to be amplified are exported for preset parameter to be arranged;
Booster: for amplifying the secondary voltage signal of high-voltage power source output to primary voltage signal;
Current lifting device: for amplifying the secondary current signal of high-voltage power source output to primary current signal;
Standard potential transformer: for primary voltage signal to be switched to the voltage signal convenient for measurement;
Standard current transformer: for secondary current signal to be switched to the current signal convenient for measurement;
Primary side standard mutual inductor tester: for acquiring the voltage signal and electric current of output to one or two complete switch primary sides Signal, primary side standard mutual inductor tester support input three-phase current, input zero-sequence current, back production three-phase current, back production zero 16 sequence electric current, input three-phase voltage, input residual voltage, back production three-phase voltage, back production residual voltage channels acquire simultaneously;
Secondary side standard mutual inductor tester: for acquiring the voltage signal and electric current of output to one or two complete switch secondary sides Signal, secondary side standard mutual inductor tester support input three-phase current, input zero-sequence current, input three-phase voltage, input zero 8 channels of sequence voltage acquire simultaneously;
Switch route device: for loop switch in the detection process;When test macro carries out primary side test, switching routing Device will switch secondary side output and be transferred by terminal into primary side standard mutual inductor tester;When test macro carries out secondary side When test, switching route device transfers the program-controlled source output of low pressure into the distribution terminal of one or two complete switch by terminal;When When test macro carries out integration test, switched router by terminal will switch secondary side export it is direct-connected as one or two times complete are opened The input of the distribution terminal of pass;
Standard electric energy meter tester: for acquiring standard electric power signal, and according to the distribution terminal according to one or two complete switch Collected electric power signal calculates electric flux error;
The test method the following steps are included:
Step 1: the electrical connection of the primary side of test macro High voltage output electric interfaces and one or two complete switch is established, is built The electrical connection of the switching route device of the secondary side output access test macro of vertical one or two complete switch, establishes test macro Switching route device and one or two complete switch distribution terminal electrical connection;
Step 2: the communication connection of test macro Yu one or two complete switch is established;
Step 3: test macro applies stable voltage signal and electricity to one or two complete switch by the electrical connection of step 1 Signal is flowed, when carrying out primary side test, switching route device will switch secondary side output and transfer by terminal into primary side mark Quasi- mutual-inductor tester;When carrying out secondary side test, switching route device by the output of low pressure program-controlled source by terminal transfer into The distribution terminal of one or two complete switch;When carrying out integration test, will to switch secondary side defeated by terminal for switched router The input of the direct-connected distribution terminal such as one or two complete switch out, and the communication connection through step 2 complete will open for tested one or two times Collected voltage, electric current back production to test macro are closed, primary side, secondary side and integration precision, protection test are carried out;
Step 4: the test result of step 3 is input to industrial personal computer, generates test report.
2. a kind of one or two complete switch closed loop test methods according to claim 1, it is characterised in that: in step 2 The communication connection of test macro and one or two complete switch is established by serial ports/network interface.
3. a kind of one or two complete switch closed loop test methods according to claim 1, it is characterised in that: the switching road It is connected by device with industrial personal computer.
4. a kind of one or two complete switch closed loop test methods according to claim 1, it is characterised in that: step 3 is successively The following steps are included:
Step 30: industrial personal computer establishes one or two complete switch primary sides and primary side standard mutual inductor by switching route device The electrical connection of tester;
Step 31: industrial personal computer controls high-voltage power source and exports secondary voltage signal and secondary electricity simultaneously by preset load point Flow signal;
Step 32: high-voltage power source output secondary voltage signal is enlarged by primary voltage signal, and up-flow by booster Low pressure and low power source output secondary current signal is enlarged into primary current signal by device;
Step 33: primary side standard mutual inductor tester, which acquires the primary voltage that booster exports by standard potential transformer, to be believed Number, the primary current signal of booster output is acquired by standard current transformer;
Step 34: the acquisition of primary side standard mutual inductor tester switchs secondary current, the voltage signal of secondary output;
Step 35: primary side standard mutual inductor tester calculates error according to collected signal, and will be sent in result to industry control Machine completes primary side accuracy test;
Step 36: industrial personal computer establishes the program-controlled source of low pressure and secondary side standard mutual inductor tester, one or two by switching route device The electrical connection of the distribution terminal of secondary complete switch;
Step 37: industrial personal computer controls low pressure and low power source and exports secondary voltage signal and secondary electricity simultaneously by preset load point Flow signal;
Step 38: secondary side standard mutual inductor tester acquires secondary current, the voltage signal of the program-controlled source output of low pressure, and will adopt It send on collection signal to industrial personal computer;
Step 39: secondary current, the voltage signal of standard electric energy meter tester mesolow program-controlled source output, and by electric flux signal On send to industrial personal computer;
Step 310: industrial personal computer acquires distribution terminal by the communication interface of the distribution terminal with one or two complete switch and collects Electric current, voltage, electric flux signal, and with the signal that is sent on secondary side standard mutual inductor tester and standard electric energy meter tester It compares, calculates error, complete secondary side accuracy test;
Step 311: industrial personal computer exports secondary voltage signal and secondary current by preset waveform, control low pressure and low power source simultaneously Signal;
Step 312: industrial personal computer acquires what distribution terminal exported by the communication interface of the distribution terminal with one or two complete switch Remote signals complete secondary side transmission test;
Step 313: for industrial personal computer by switching route device, the distribution for establishing one or two complete switch and one or two complete switch is whole The electrical connection at end;
Step 314: industrial personal computer controls high-voltage power source and exports secondary voltage signal and secondary electricity simultaneously by preset load point Flow signal;
Step 315: high-voltage power source output secondary voltage signal is enlarged by primary voltage signal, and up-flow by booster Low pressure and low power source output secondary current signal is enlarged into primary current signal by device;
Step 316: primary side standard mutual inductor tester acquires the primary voltage that booster exports by standard potential transformer Signal, the primary current signal of booster output is acquired by standard current transformer, and will be sent on signal to industrial personal computer;
Step 317: industrial personal computer acquires distribution terminal by the communication interface of the distribution terminal with one or two complete switch and collects Electric current, voltage signal, and calculate error, complete integration precision test;
Step 318: industrial personal computer exports secondary voltage signal and secondary current by preset waveform, control high-voltage power source simultaneously Signal;
Step 319: high-voltage power source output secondary voltage signal is enlarged by primary voltage signal, and up-flow by booster Low pressure and low power source output secondary current signal is enlarged into primary current signal by device;
Step 320: industrial personal computer acquires what distribution terminal exported by the communication interface of the distribution terminal with one or two complete switch Remote signals complete integration transmission test;
Step 321: industrial personal computer exports test report according to test result, completes closed loop detection.
CN201910615823.8A 2019-06-10 2019-07-09 Primary and secondary complete switch closed-loop test method Active CN110412454B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201910615823.8A CN110412454B (en) 2019-07-09 2019-07-09 Primary and secondary complete switch closed-loop test method
US16/897,130 US11402457B2 (en) 2019-06-10 2020-06-09 System and method for integrated test on primary-secondary pole-mounted breaker

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910615823.8A CN110412454B (en) 2019-07-09 2019-07-09 Primary and secondary complete switch closed-loop test method

Publications (2)

Publication Number Publication Date
CN110412454A true CN110412454A (en) 2019-11-05
CN110412454B CN110412454B (en) 2021-09-24

Family

ID=68360775

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910615823.8A Active CN110412454B (en) 2019-06-10 2019-07-09 Primary and secondary complete switch closed-loop test method

Country Status (1)

Country Link
CN (1) CN110412454B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110780256A (en) * 2019-11-19 2020-02-11 国网湖北省电力有限公司电力科学研究院 System and method for detecting accuracy of circuit breaker on primary and secondary fusion complete set of columns
CN111929483A (en) * 2020-08-07 2020-11-13 贵州电网有限责任公司 Primary and secondary fusion equipment test system and test method thereof
CN113589044A (en) * 2021-07-27 2021-11-02 国网江苏省电力有限公司电力科学研究院 Automatic signal switching device for primary and secondary fusion detection equipment
US11402457B2 (en) * 2019-06-10 2022-08-02 Zhejiang Huadian Equipment Testing Institute Co., Ltd. System and method for integrated test on primary-secondary pole-mounted breaker

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108414960A (en) * 2018-04-13 2018-08-17 南京丹迪克电力仪表有限公司 A kind of multichannel directly measures formula mutual-inductor tester and method of calibration
CN109406897A (en) * 2018-11-01 2019-03-01 珠海许继电气有限公司 Detection device and detection method
CN109507459A (en) * 2018-11-27 2019-03-22 国网江苏省电力有限公司电力科学研究院 Standard electric signal creating method, device and accuracy checking method of one or two fusion switchgears and system
CN109521235A (en) * 2018-11-27 2019-03-26 国网江苏省电力有限公司电力科学研究院 The complete accuracy checking method of one or two fusion switchgears of one kind and system
CN109613424A (en) * 2018-12-29 2019-04-12 国网河南省电力公司电力科学研究院 One or two fusion switchgear assembly actuation time detection method and device
CN109828202A (en) * 2019-03-19 2019-05-31 国网陕西省电力公司电力科学研究院 One or two fusion panel switches high-frequency conduction interference experiment platforms and test method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108414960A (en) * 2018-04-13 2018-08-17 南京丹迪克电力仪表有限公司 A kind of multichannel directly measures formula mutual-inductor tester and method of calibration
CN109406897A (en) * 2018-11-01 2019-03-01 珠海许继电气有限公司 Detection device and detection method
CN109507459A (en) * 2018-11-27 2019-03-22 国网江苏省电力有限公司电力科学研究院 Standard electric signal creating method, device and accuracy checking method of one or two fusion switchgears and system
CN109521235A (en) * 2018-11-27 2019-03-26 国网江苏省电力有限公司电力科学研究院 The complete accuracy checking method of one or two fusion switchgears of one kind and system
CN109613424A (en) * 2018-12-29 2019-04-12 国网河南省电力公司电力科学研究院 One or two fusion switchgear assembly actuation time detection method and device
CN109828202A (en) * 2019-03-19 2019-05-31 国网陕西省电力公司电力科学研究院 One or two fusion panel switches high-frequency conduction interference experiment platforms and test method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李红青等: ""配电网新型一二次融合成套设备测试方法研究"", 《湖南电力》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11402457B2 (en) * 2019-06-10 2022-08-02 Zhejiang Huadian Equipment Testing Institute Co., Ltd. System and method for integrated test on primary-secondary pole-mounted breaker
CN110780256A (en) * 2019-11-19 2020-02-11 国网湖北省电力有限公司电力科学研究院 System and method for detecting accuracy of circuit breaker on primary and secondary fusion complete set of columns
CN111929483A (en) * 2020-08-07 2020-11-13 贵州电网有限责任公司 Primary and secondary fusion equipment test system and test method thereof
CN111929483B (en) * 2020-08-07 2023-12-12 贵州电网有限责任公司 Secondary fusion equipment testing system and testing method thereof
CN113589044A (en) * 2021-07-27 2021-11-02 国网江苏省电力有限公司电力科学研究院 Automatic signal switching device for primary and secondary fusion detection equipment

Also Published As

Publication number Publication date
CN110412454B (en) 2021-09-24

Similar Documents

Publication Publication Date Title
CN110412454A (en) A kind of one or two complete switch closed loop test methods
CN110286319B (en) One-time and two-time complete column switch integrated test method
CN203324463U (en) Performance test and evaluation platform for small-current grounding line selection device
CN110161331B (en) Detection platform for primary and secondary fusion complete equipment and control method
CN112564740B (en) Device for detecting advanced application function of HPLC
CN106018991A (en) Power distribution network ferroresonance and single phase earth fault calculating analysis method and device
CN103336262B (en) The online live calibration device of a kind of mutual inductor
CN101769968B (en) Mutual inductor no-load voltage ratio tester
CN103076560B (en) Electrical test equipment non-contact measurement combination unit and application thereof
CN106707028A (en) Transformer short-circuit impedance on-line monitoring method and device
CN111562544B (en) Parameter consistency diagnosis method and system for digital electric energy metering system
CN110261764B (en) Integrated debugging method for primary and secondary complete column switch
CN202177693U (en) Industrial frequency withstand voltage and insulation resistance testing apparatus for current transformer
CN103995207A (en) Three-remote automatic test device for power distribution terminal
CN207937587U (en) A kind of detection device and detecting system of electric mutual inductor
CN204556744U (en) The detection platform of a kind of APF of 380V electric pressure
CN109521390A (en) A kind of SV sampling circuit test macro and method for intelligent substation
CN106501752A (en) A kind of electrical energy meter electricity presses access way automatic identifying method
CN203365667U (en) On-line live calibration device for mutual inductor
CN209311613U (en) A kind of transformer temperature rise test automatic control device
CN207946512U (en) Electronic current mutual inductor check system
CN105933079A (en) Detection system and detection method for communication performance of carrier signals with different frequencies
CN112838572A (en) 220kVA transformer substation relay protection system and installation and debugging method
CN104833875A (en) Transformer secondary side load matching device and automatic matching method
CN215728422U (en) Online collection and processing system for electric parameters of power transmission line

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant