CN110409686A - Spliced furred ceiling and installation method - Google Patents
Spliced furred ceiling and installation method Download PDFInfo
- Publication number
- CN110409686A CN110409686A CN201910782130.8A CN201910782130A CN110409686A CN 110409686 A CN110409686 A CN 110409686A CN 201910782130 A CN201910782130 A CN 201910782130A CN 110409686 A CN110409686 A CN 110409686A
- Authority
- CN
- China
- Prior art keywords
- snap
- gauge
- mounting plate
- plate
- centre keel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009434 installation Methods 0.000 title claims abstract description 28
- 238000000034 method Methods 0.000 title claims abstract description 22
- 230000015572 biosynthetic process Effects 0.000 claims description 2
- 238000010276 construction Methods 0.000 description 14
- 238000010586 diagram Methods 0.000 description 6
- 238000005034 decoration Methods 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000004904 shortening Methods 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/06—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/06—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
- E04B9/12—Connections between non-parallel members of the supporting construction
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/22—Connection of slabs, panels, sheets or the like to the supporting construction
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bay Windows, Entrances, And Structural Adjustments Related Thereto (AREA)
Abstract
The invention discloses a kind of spliced furred ceiling and installation methods, the spliced furred ceiling includes at least two lateral hang ceiling panel components and at least one the first centre keels, wherein: lateral hang ceiling panel component includes transverse panel, transom and the first bottom plate positioned at the top of furred ceiling, transom includes the first end, transom is fixedly connected by the first bottom plate with transverse panel, and the first end extends the first bottom plate and transverse panel forms the first gap;First centre keel includes the first mounting plate and the second mounting plate being oppositely arranged, first mounting plate and the second mounting plate are elastic plate, the first snap-gauge is connected on first mounting plate, the second snap-gauge is connected on second mounting plate, first snap-gauge and the second snap-gauge are inserted into the first gap, and at least two lateral hang ceiling panel components is made to be located at the opposite sides of the first centre keel length direction.Implement the present invention, be inserted by the first centre keel in the first gap of two lateral hang ceiling panel components, disperse weight improves resisting deflection.
Description
Technical field
The present invention relates to construction and decoration technical field more particularly to a kind of spliced furred ceilings and installation method.
Background technique
Furred ceiling is the indispensable part of interior decoration to decoration is played the role of at the top of interior architecture.
In the prior art, the side of furred ceiling towards indoor top surface is typically provided with ceiling joist, the face of ceiling joist connection
Plate is usually a monolith, is laid with along indoor width direction, and then ceiling joist is hung on top surface by sunpender.It is existing to hang
It pushes up to improve the resisting deflection of furred ceiling, it will usually increase the height of furred ceiling and indoor top surface, to make between furred ceiling and ground
Height reduces, and generates sense of depression to people, meanwhile, ceiling joist is located on furred ceiling, after furred ceiling hanging is on top surface, works as furred ceiling
It goes wrong when needing to safeguard, need to furred ceiling integral demounting be increased workload, extend construction period, be unfavorable for standardizing
Rapid construction.
Summary of the invention
The purpose of the present invention is to provide a kind of spliced furred ceiling and installation methods, to solve the above technical problems.
Technical solution of the present invention provides a kind of spliced furred ceiling, including at least two lateral hang ceiling panel components and at least
One the first centre keel, in which:
The transverse direction hang ceiling panel component includes transverse panel, transom and the first bottom plate positioned at the top of furred ceiling, institute
Stating transom includes the first end, and the transom is fixedly connected by first bottom plate with the transverse panel, and described
First bottom plate is extended in first end and the transverse panel forms the first gap;
First centre keel includes the first mounting plate and the second mounting plate being oppositely arranged, first mounting plate and institute
Stating the second mounting plate is elastic plate, and the first snap-gauge is connected on first mounting plate, is connected on second mounting plate
Second snap-gauge, first snap-gauge and second snap-gauge are inserted into first gap, make described at least two lateral furred ceilings
Panel assembly is located at the opposite sides of the first centre keel length direction.
Further, the transom includes the third mounting plate and the 4th mounting plate being oppositely arranged, the third installation
Plate and the 4th mounting plate are elastic plate, are connected with third snap-gauge on the third mounting plate, on the 4th mounting plate
It is connected with the 4th snap-gauge;
The front of first bottom plate is equipped with the first buckle and the second buckle, and the back side of first bottom plate is bonded installation
On the transverse panel, first buckle is for being clamped the third snap-gauge, and second buckle is for being clamped described the
Four snap-gauges form the third snap-gauge of first end and the 4th snap-gauge and the transverse panel between described first
Gap.
Further, the quantity of the lateral hang ceiling panel component is multiple, and multiple lateral hang ceiling panel components are equal
The opposite sides of the even length direction for being distributed in first centre keel.
Further, further include abaculus, the quantity of first centre keel be it is multiple, every two adjacent described first is perpendicular
Keel are connected by the abaculus.
Further, first centre keel further includes the 5th mounting plate, far from described first on first mounting plate
Snap-gauge on one side on second mounting plate far from second snap-gauge while pass through the 5th mounting plate and be connected, it is described
First centre keel passes through the 5th mounting plate by bolt from the bottom up and connect with crown wall.
It further, further include fixedly connected part, the fixedly connected part includes the first connecting plate and the second connecting plate, institute
Stating transom includes the second end being oppositely arranged with first end, the third snap-gauge of second end and described
4th snap-gauge and the transverse panel form the second gap;
First connecting plate is fixed on wall, and one end of second connecting plate is perpendicular to first connecting plate
The other end of bottom, second connecting plate is inserted into second gap.
It further, further include the vertical hang ceiling panel component being mutually connected vertically with the lateral hang ceiling panel component,
The vertical hang ceiling panel component includes vertical panel, the second centre keel and the second bottom plate positioned at the top of furred ceiling,
Second centre keel includes the 6th mounting plate and the 7th mounting plate being oppositely arranged, the 6th mounting plate and institute
Stating the 7th mounting plate is elastic plate, and the 5th snap-gauge is connected on the 6th mounting plate, is connected on the 7th mounting plate
6th snap-gauge;
The front of second bottom plate is equipped with third buckle and the 4th buckle, and the back side of second bottom plate is bonded installation
In the vertical panel, third buckle is for being clamped the 5th snap-gauge, and the 4th buckle is for being clamped described the
Six snap-gauges.
It further, further include the limit plate being arranged on wall, the bottom of the limit plate and the vertical panel
The back side abuts.
Technical solution of the present invention also provides a kind of installation method of spliced furred ceiling, and the installation method is for installing such as
The preceding spliced furred ceiling, comprising:
First centre keel is mounted on to the middle position of crown wall, makes the first snap-gauge and the second snap-gauge along the length side of crown wall
To extension;
Transom is connect with the first bottom plate, the first end of the transom is made to extend first bottom plate and transverse direction
Panel forms the first gap, forms at least two lateral hang ceiling panel components;
The lateral hang ceiling panel component is connect with first centre keel, is inserted in one of first snap-gauge
In first gap of the transverse direction hang ceiling panel component, second snap-gauge is inserted into the institute of another lateral hang ceiling panel component
It states in the first gap.
Further, described to connect the lateral hang ceiling panel component with first centre keel, make first card
Plate is inserted in one of in the first gap of the lateral hang ceiling panel component, and second snap-gauge is inserted into another transverse direction and hangs
In first gap of top panel component, later further include:
6th mounting plate of the second centre keel and the 7th mounting plate are blocked with the third of the second bottom plate buckle and the 4th respectively
Buckle connects, and connect second centre keel with the vertical panel, forms vertical hang ceiling panel component;
The vertical hang ceiling panel component is mounted on to the side of the lateral hang ceiling panel component, makes vertical hang ceiling panel
Component forms entire spliced furred ceiling perpendicular to the lateral hang ceiling panel component.
Blocked after adopting the above technical scheme, having the following beneficial effects: by the first snap-gauge of the first centre keel and second
Plate is inserted into the first gap formed between the transverse panel and transom of lateral hang ceiling panel component respectively, makes two lateral furred ceilings
Panel assembly is located at the opposite sides of the first centre keel length direction, and weight is dispersed on the first centre keel, reduces horizontal
Deformation to hang ceiling panel component improves resisting deflection.When one of lateral hang ceiling panel component, which goes wrong, to be needed to safeguard,
One of lateral hang ceiling panel component and the first centre keel need to only be split, without dismantling integrated ceiling, reduce workload, contracting
Short construction period is conducive to transport and standardize rapid construction.
Detailed description of the invention
Referring to attached drawing, the disclosure of the present invention will become more readily understood.It is understood that these attached drawings are merely illustrative
Purpose, and be not intended to limit the scope of protection of the present invention.In figure:
Fig. 1 is a kind of structural schematic diagram for spliced furred ceiling that the embodiment of the present invention one provides;
Fig. 2 is the structural schematic diagram of lateral hang ceiling panel component shown in FIG. 1;
Fig. 3 is the structural schematic diagram of the first centre keel shown in FIG. 1;
Fig. 4 is the sectional view that the first centre keel shown in Fig. 1 is connect with lateral hang ceiling panel component;
Fig. 5 is the sectional view that transom shown in Fig. 2 is connect with the first bottom plate and transverse panel;
Fig. 6 is the structural schematic diagram of the first bottom plate shown in Fig. 2;
Fig. 7 is the sectional view that fixedly connected part shown in FIG. 1 is connect with lateral hang ceiling panel component;
Fig. 8 is the sectional view that limit plate shown in FIG. 1 is connect with vertical hang ceiling panel component;
Fig. 9 is a kind of work flow diagram of the installation method of spliced furred ceiling provided by Embodiment 2 of the present invention;
Figure 10 is a kind of work flow diagram of the installation method for spliced furred ceiling that the embodiment of the present invention three provides.
The appended drawing reference table of comparisons:
10- transverse direction hang ceiling panel component;11- transverse panel;12- transom;121- third mounting plate;1211- third card
Plate;The 4th mounting plate of 122-;The 4th snap-gauge of 1221-;The first bottom plate of 13-;131- first is buckled;132- second is buckled;14- first
Gap;The second gap 15-;The first centre keel of 20-;The first mounting plate of 21-;The first snap-gauge of 211-;The second mounting plate of 22-;221-
Second snap-gauge;The 5th mounting plate of 23-;30- bolt;40- crown wall;50- fixedly connected part;The first connecting plate of 51-;52- second connects
Fishplate bar;60- wall;The vertical hang ceiling panel component of 70-;71- vertical panel;The second centre keel of 72-;The second bottom plate of 73-;80- limit
Position plate.
Specific embodiment
Further illustrate a specific embodiment of the invention with reference to the accompanying drawing.
It is readily appreciated that, according to the technique and scheme of the present invention, in the case where not changing true spirit, the general skill of this field
The various structures mode and implementation that art personnel can be replaced mutually.Therefore, following specific embodiments and attached drawing are only
To the exemplary illustration of technical solution of the present invention, and it is not to be construed as whole of the invention or is considered as to inventive technique scheme
It defines or limits.
It mentions in the present specification or up, down, left, right, before and after, front, the back side, top, the bottom that may mention etc.
Positional terms are defined relative to each construction shown in the drawings, they are opposite concepts, and it is therefore possible to can root
Correspondingly changed according to different location locating for it, different use states.So also should not be by these or others side
Position term is construed to restricted term.
Embodiment one
As Figure 1-Figure 8, the spliced furred ceiling that the embodiment of the present invention one provides, including at least two lateral hang ceiling panels
Component 10 and at least one the first centre keels 20, in which:
Lateral hang ceiling panel component 10 includes transverse panel 11, transom 12 and the first bottom plate positioned at the top of furred ceiling
13, transom 12 includes the first end (not shown), and transom 12 is fixedly connected by the first bottom plate 13 with transverse panel 11,
And first end extend the first bottom plate 13 and form the first gap 14 with transverse panel 11;
First centre keel 20 includes the first mounting plate 21 and the second mounting plate 22 that are oppositely arranged, the first mounting plate 21 and the
Two mounting plates 22 are elastic plate, and the first snap-gauge 211 is connected on the first mounting plate 21, is connected with second on the second mounting plate 22
Snap-gauge 221, the first snap-gauge 211 and the second snap-gauge 221 are inserted into the first gap 14, make at least two lateral hang ceiling panel components 10
It is located at the opposite sides of 20 length direction of the first centre keel.
The quantity of lateral hang ceiling panel component 10 is related with the size of wall top, and wall top is bigger, and 1 quantity of furred ceiling component is more,
The gross area that multiple furred ceiling components 1 are spliced of being subject to can cover wall top.
As shown in Figure 1, the same width that the lateral hang ceiling panel component 10 set is spliced into of arranging is consistent with the length of wall top
Or it is almost the same;The equivalent width or base of length and wall top that the lateral hang ceiling panel component 10 of same row arrangement is spliced into
This is consistent.
It should be noted that the arrangement mode of transverse direction hang ceiling panel component 10 shown in FIG. 1 can be carried out according to user demand
Setting, is not limited by the present embodiment.
The length that the centre of the lateral hang ceiling panel component 10 of two laid out in parallel passes through the first centre keel 20 splicing composition
It is almost the same with the width of wall top.
First mounting plate 21 and the second mounting plate 22 are by elastic steel at the first mounting plate 21 and second peace herein
Loading board 22 is that elastic plate refers to that the first mounting plate 21 and the second mounting plate 22 are relatively close when being squeezed, when being stretched
It is relatively distant from, and restores original state when releasing stress, in order to which the first snap-gauge 211 is inserted into and is connected to the first gap 14
In, the second snap-gauge 221 is inserted into and is connected in the first gap 14.It, can be first by the lateral hang ceiling panel component of two sides when installation
10 one end is fixedly connected with wall, is then squeezed the first mounting plate 21 and the second mounting plate 22, is made the first snap-gauge 211 and second
Snap-gauge 221 is inserted into respectively in the first gap 14 of the lateral hang ceiling panel component 10 of the left and right sides, realizes the first centre keel and a left side
The connection of the lateral hang ceiling panel component 10 of right two sides reduces installation difficulty, improves construction efficiency.Also, compare existing skill
The size of art, lateral hang ceiling panel component 10 can be arbitrarily arranged, and not only simplify production process, also reduce transportation cost.
Spliced furred ceiling provided by the invention is inserted into transverse direction by the first snap-gauge and the second snap-gauge of the first centre keel respectively
The first gap formed between the transverse panel and transom of hang ceiling panel component makes two lateral hang ceiling panel component difference positions
In the opposite sides of the first centre keel length direction, weight is dispersed on the first centre keel, reduces lateral hang ceiling panel component
Deformation, improve resisting deflection.When one of lateral hang ceiling panel component, which goes wrong, to be needed to safeguard, only need one of them
Lateral hang ceiling panel component and the first centre keel are split, and without dismantling integrated ceiling, are reduced workload, are shortened construction period, have
Conducive to transporting and standardize rapid construction.
Optionally, transom 12 includes the third mounting plate 121 and the 4th mounting plate 122 being oppositely arranged, third mounting plate
121 and the 4th mounting plate 122 be elastic plate, third snap-gauge 1211, the 4th mounting plate 122 are connected on third mounting plate 121
On be connected with the 4th snap-gauge 1221;
The front of first bottom plate 13 is equipped with the first buckle 131 and the second buckle 132, and the back side of the first bottom plate 13 is bonded peace
On transverse panel 11, the first buckle 131 is for being clamped third snap-gauge 1211, and the second buckle 132 is for being clamped the 4th snap-gauge
1221, make first gap of third snap-gauge 1211 and the 4th snap-gauge 1221 and the formation of transverse panel 11 of the first end.
The structure of transom 12 can be identical as the structure of the first centre keel 20, but in order to reduce cost, can reduce cross
The structural thickness of keel 12.
When installation, first the first bottom plate 13 is fixed on transverse panel 11, then squeezes third mounting plate 121 and the 4th peace
Loading board 122, third snap-gauge 1211 can be clamped into the first buckle 131, and the 4th snap-gauge 1221 can be clamped into the second buckle 132
In, the stress of third mounting plate 121 and the 4th mounting plate 122 is then released, transom 12 can be firmly connected to first
On bottom plate 13, realize that transom 12 is connected with transverse panel 11.
Preferably, the quantity of transom 12 is two, and two transoms 12 are extended in the same direction along transverse panel 11.Two cross
Keel 12 can increase the support force to transverse panel 11, improve the stability of transverse panel 11.
Optionally, in order to further be advantageously implemented modularized production, transportation cost, lateral hang ceiling panel component 10 are reduced
Quantity be it is multiple, multiple transverse direction hang ceiling panel components 10 are evenly distributed on opposite the two of the length direction of the first centre keel 20
Side.
Optionally, further include abaculus (not shown), the quantity of the first centre keel 20 be it is multiple, every two adjacent first
Centre keel 20 is connected by abaculus.
When the length of the first centre keel 20 is less than the length of wall top, two adjacent the first centre keels are embedded in by abaculus
In the space that 20 the first mounting plate 21 and the second mounting plate 22 limit, to increase the length of the first centre keel 20, further
It is advantageously implemented modularized production, reduces transportation cost.
Optionally, the first centre keel 20 further includes the 5th mounting plate 23, separate first snap-gauge 211 on the first mounting plate 21
On one side on the second mounting plate 22 far from the second snap-gauge 221 while pass through the 5th mounting plate 23 and be connected, the first centre keel 20 leads to
Bolt 30 is crossed to connect across the 5th mounting plate 23 with crown wall 40 from the bottom up.
When installation, the first keel 20 first can be passed through into the 5th mounting plate 23 by bolt 30 from the bottom up and consolidated with crown wall 40
Fixed connection, improves the connective stability of the first centre keel 20.
It optionally, further include fixedly connected part 50, fixedly connected part 50 includes the first connecting plate 51 and the second connecting plate 52,
Transom 12 includes the second end (not shown) being oppositely arranged with the first end, the third snap-gauge 1211 of the second end and
Four snap-gauges 1221 form the second gap 15 with transverse panel 11;
First connecting plate 51 is fixed on wall 60, the bottom of one end of the second connecting plate 52 perpendicular to the first connecting plate 51
The other end in portion, the second connecting plate 52 is inserted into the second gap 15.
Fixedly connected part 50 is for lateral hang ceiling panel component 10 to be fixedly connected with wall 60, thus the company of further increasing
Connect stability.
Optionally, further include the vertical hang ceiling panel component 70 being mutually connected vertically with lateral hang ceiling panel component 10, erect
It include vertical panel 71, the second centre keel 72 and the second bottom plate 73 for being located at the top of furred ceiling to hang ceiling panel component 70,
Second centre keel 72 includes the 6th mounting plate (not shown) and the 7th mounting plate (not shown) being oppositely arranged,
6th mounting plate and the 7th mounting plate are elastic plate, and the 5th snap-gauge (not shown), the 7th peace are connected on the 6th mounting plate
The 6th snap-gauge (not shown) is connected in loading board;
The front of second bottom plate 73 is equipped with third buckle (not shown) and the 4th buckle (not shown), the second bottom plate
73 back side is jointly mounted in vertical panel 71, and third buckle is for being clamped the 5th snap-gauge, and the 4th buckle is for being clamped the 6th
Snap-gauge.
Vertical hang ceiling panel component 70 is similar to the structure of lateral hang ceiling panel component 10, and difference is the second bottom plate 73
Length be two the first bottom plates 13 length, and the arrangement of vertical hang ceiling panel component 70 and lateral hang ceiling panel component 10
Mode is different, and vertical hang ceiling panel component 70 is mutually perpendicular to overlap with lateral hang ceiling panel component 10, vertical hang ceiling panel component
70 are not connected with the first centre keel 20, therefore no longer carry out specifically to the structure of vertical hang ceiling panel component 70 herein
It is bright.It can be under the premise of not influencing the resisting deflection of integrated ceiling, convenient for lateral furred ceiling face by vertical hang ceiling panel component 70
The installation and removal of board group part 10 and the first centre keel 20, further shorten construction period.
It optionally, further include the limit plate 80 being arranged on wall, the bottom of limit plate 80 and the back side of vertical panel 71
It abuts.
Limit plate 80 can be wood-plastic board, is fixedly connected by steel nail with wall 60, the bottom of limit plate 80 and vertical
The back side of panel 71 abuts, and prevents vertical hang ceiling panel component 70 from moving up, and increases connective stability.
Embodiment two
As shown in figure 9, Fig. 9 is a kind of workflow of the installation method of spliced furred ceiling provided by Embodiment 2 of the present invention
Figure, the installation method is for installing foregoing spliced furred ceiling, comprising:
First centre keel: being mounted on the middle position of crown wall by step S101, makes the first snap-gauge and the second snap-gauge along top
The length direction of wall extends;
Step S102: transom is connect with the first bottom plate, and the first end of transom is made to extend the first bottom plate and cross
The first gap is formed to panel, forms at least two lateral hang ceiling panel components;
Step S103: lateral hang ceiling panel component is connect with the first centre keel, the first snap-gauge is made to be inserted in one of cross
Into the first gap of hang ceiling panel component, the second snap-gauge is inserted into the first gap of another lateral hang ceiling panel component.
The installation method of spliced furred ceiling provided by the invention passes through the first snap-gauge of the first centre keel and the second snap-gauge point
The first gap that Cha Ru not be formed between the transverse panel and transom of lateral hang ceiling panel component, makes two lateral hang ceiling panels
Component is located at the opposite sides of the first centre keel length direction, and weight is dispersed on the first centre keel, reduces and laterally hangs
The deformation of top panel component improves resisting deflection.When one of lateral hang ceiling panel component, which goes wrong, to be needed to safeguard, only need
One of lateral hang ceiling panel component and the first centre keel are split, without dismantling integrated ceiling, reduce workload, shortening is applied
The work period is conducive to transport and standardize rapid construction.
Embodiment three
As shown in Figure 10, Figure 10 is a kind of workflow of the installation method for spliced furred ceiling that the embodiment of the present invention three provides
Cheng Tu, the installation method is for installing foregoing spliced furred ceiling, comprising:
First centre keel: being mounted on the middle position of crown wall by step S201, makes the first snap-gauge and the second snap-gauge along top
The length direction of wall extends;
Step S202: transom is connect with the first bottom plate, and the first end of transom is made to extend the first bottom plate and cross
The first gap is formed to panel, forms at least two lateral hang ceiling panel components;
Step S203: lateral hang ceiling panel component is connect with the first centre keel, the first snap-gauge is made to be inserted in one of cross
Into the first gap of hang ceiling panel component, the second snap-gauge is inserted into the first gap of another lateral hang ceiling panel component;
Step S204: the 6th mounting plate of the second centre keel and the 7th mounting plate are buckled with the third of the second bottom plate respectively
With the 4th buckle clamping, it connect the second centre keel with vertical panel, forms vertical hang ceiling panel component;
Step S205: vertical hang ceiling panel component is mounted on to the side of lateral hang ceiling panel component, makes vertical lifting top surface
Board group part forms entire spliced furred ceiling perpendicular to lateral hang ceiling panel component.
The installation method of spliced furred ceiling provided by the invention passes through the first snap-gauge of the first centre keel and the second snap-gauge point
The first gap that Cha Ru not be formed between the transverse panel and transom of lateral hang ceiling panel component, makes two lateral hang ceiling panels
Component is located at the opposite sides of the first centre keel length direction, and weight is dispersed on the first centre keel, reduces and laterally hangs
The deformation of top panel component improves resisting deflection.When one of lateral hang ceiling panel component, which goes wrong, to be needed to safeguard, only need
One of lateral hang ceiling panel component and the first centre keel are split, without dismantling integrated ceiling, reduce workload, shortening is applied
The work period is conducive to transport and standardize rapid construction.
In conclusion spliced furred ceiling provided by the invention and installation method, by the first snap-gauge of the first centre keel and
Second snap-gauge is inserted into the first gap formed between the transverse panel and transom of lateral hang ceiling panel component respectively, makes two cross
It is located at the opposite sides of the first centre keel length direction to hang ceiling panel component, weight is dispersed on the first centre keel,
The deformation for reducing lateral hang ceiling panel component, improves resisting deflection.When one of lateral hang ceiling panel component goes wrong needs
When maintenance, one of lateral hang ceiling panel component and the first centre keel need to only be split, without dismantling integrated ceiling, reduce work
It measures, shortens construction period, be conducive to transport and standardize rapid construction.
Above-described is only the principle of the present invention and preferred embodiment.It should be pointed out that for the common skill of this field
For art personnel, on the basis of the principle of the invention, several other modifications can also be made, also should be regarded as protection model of the invention
It encloses.
Claims (10)
1. a kind of spliced furred ceiling, which is characterized in that perpendicular including at least two lateral hang ceiling panel components and at least one the first
Keel, in which:
The transverse direction hang ceiling panel component includes transverse panel, transom and the first bottom plate positioned at the top of furred ceiling, the cross
Keel include the first end, and the transom is fixedly connected by first bottom plate with the transverse panel, and described first
First bottom plate is extended in end and the transverse panel forms the first gap;
First centre keel includes the first mounting plate and the second mounting plate being oppositely arranged, first mounting plate and described
Two mounting plates are elastic plate, and the first snap-gauge is connected on first mounting plate, is connected with second on second mounting plate
Snap-gauge, first snap-gauge and second snap-gauge are inserted into first gap, make described at least two lateral hang ceiling panels
Component is located at the opposite sides of the first centre keel length direction.
2. spliced furred ceiling as described in claim 1, which is characterized in that the transom includes the third installation being oppositely arranged
Plate and the 4th mounting plate, the third mounting plate and the 4th mounting plate are elastic plate, are connected on the third mounting plate
There is third snap-gauge, is connected with the 4th snap-gauge on the 4th mounting plate;
The front of first bottom plate is equipped with the first buckle and the second buckle, and the back side of first bottom plate is jointly mounted to institute
It states on transverse panel, first buckle is for being clamped the third snap-gauge, and second buckle is for being clamped the 4th card
Plate makes the third snap-gauge of first end and the 4th snap-gauge and the transverse panel form first gap.
3. spliced furred ceiling as described in claim 1, which is characterized in that the quantity of the transverse direction hang ceiling panel component is more
A, multiple lateral hang ceiling panel components are evenly distributed on the opposite sides of the length direction of first centre keel.
4. spliced furred ceiling according to claim 3, which is characterized in that it further include abaculus, the number of first centre keel
It is multiple for measuring, and every two adjacent first centre keel is connected by the abaculus.
5. spliced furred ceiling as claimed in claim 4, which is characterized in that first centre keel further includes the 5th mounting plate,
One side and the one of second snap-gauge separate on second mounting plate on first mounting plate far from first snap-gauge
Side is connected by the 5th mounting plate, and first centre keel passes through the 5th mounting plate and top by bolt from the bottom up
Wall connection.
6. spliced furred ceiling as claimed in claim 2, which is characterized in that it further include fixedly connected part, the fixedly connected part
Including the first connecting plate and the second connecting plate, the transom includes the second end being oppositely arranged with first end, institute
State the second gap of the third snap-gauge and the 4th snap-gauge and transverse panel formation of the second end;
First connecting plate is fixed on wall, the bottom of one end of second connecting plate perpendicular to first connecting plate
The other end in portion, second connecting plate is inserted into second gap.
7. spliced furred ceiling as claimed in any one of claims 1 to 6, which is characterized in that further include and the lateral hang ceiling panel
The vertical hang ceiling panel component that component is mutually connected vertically, the vertical hang ceiling panel component include positioned at the perpendicular of the top of furred ceiling
To panel, the second centre keel and the second bottom plate,
Second centre keel includes the 6th mounting plate and the 7th mounting plate being oppositely arranged, the 6th mounting plate and described
Seven mounting plates are elastic plate, and the 5th snap-gauge is connected on the 6th mounting plate, is connected with the 6th on the 7th mounting plate
Snap-gauge;
The front of second bottom plate is equipped with third buckle and the 4th buckle, and the back side of second bottom plate is jointly mounted to institute
It states in vertical panel, the third buckle is for being clamped the 5th snap-gauge, and the 4th buckle is for being clamped the 6th card
Plate.
8. spliced furred ceiling as claimed in claim 7, which is characterized in that it further include the limit plate being arranged on wall, it is described
The bottom of limit plate is abutted with the back side of the vertical panel.
9. a kind of installation method of spliced furred ceiling, which is characterized in that the installation method is appointed for installing claim 1-8 such as
Spliced furred ceiling described in meaning one, comprising:
First centre keel is mounted on to the middle position of crown wall, prolongs the first snap-gauge and the second snap-gauge along the length direction of crown wall
It stretches;
Transom is connect with the first bottom plate, the first end of the transom is made to extend first bottom plate and transverse panel
The first gap is formed, at least two lateral hang ceiling panel components are formed;
The lateral hang ceiling panel component is connect with first centre keel, is inserted in one of first snap-gauge described
In first gap of lateral hang ceiling panel component, second snap-gauge is inserted into described the of another lateral hang ceiling panel component
In one gap.
10. the installation method of spliced furred ceiling as claimed in claim 9, which is characterized in that described by the lateral furred ceiling face
Board group part is connect with first centre keel, and first snap-gauge is made to be inserted in one of the of the lateral hang ceiling panel component
In one gap, second snap-gauge is inserted into first gap of another lateral hang ceiling panel component, later further include:
6th mounting plate of the second centre keel and the 7th mounting plate are blocked with the third of the second bottom plate buckle and the 4th buckle respectively
It connects, connect second centre keel with the vertical panel, form vertical hang ceiling panel component;
The vertical hang ceiling panel component is mounted on to the side of the lateral hang ceiling panel component, makes vertical hang ceiling panel component
Perpendicular to the lateral hang ceiling panel component, entire spliced furred ceiling is formed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910782130.8A CN110409686A (en) | 2019-08-23 | 2019-08-23 | Spliced furred ceiling and installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910782130.8A CN110409686A (en) | 2019-08-23 | 2019-08-23 | Spliced furred ceiling and installation method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110409686A true CN110409686A (en) | 2019-11-05 |
Family
ID=68368528
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910782130.8A Pending CN110409686A (en) | 2019-08-23 | 2019-08-23 | Spliced furred ceiling and installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110409686A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112554432A (en) * | 2020-12-29 | 2021-03-26 | 浙江亚厦装饰股份有限公司 | Buckle formula fossil fragments connection structure |
CN113374161A (en) * | 2021-06-18 | 2021-09-10 | 浙江亚厦装饰股份有限公司 | Mounting structure and mounting method for assembly type ceiling panel |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20120304575A1 (en) * | 2010-02-16 | 2012-12-06 | Yaakov Vakhnin | Process For Making Cylindrical Bodies |
WO2013042826A1 (en) * | 2011-09-23 | 2013-03-28 | 주식회사 조은이노텍 | Panel assembly structure |
KR20150070984A (en) * | 2013-12-17 | 2015-06-25 | 주식회사 조은데코 | Fit panel assembly |
CN106193413A (en) * | 2016-08-22 | 2016-12-07 | 成都市第四建筑工程公司 | One hides day rail system and a construction method |
CN106677403A (en) * | 2016-12-15 | 2017-05-17 | 浙江亚厦装饰股份有限公司 | Suspended ceiling made of bamboo wood fibre plates and installation method |
CN206941935U (en) * | 2017-07-01 | 2018-01-30 | 大红点商业装饰工程(深圳)有限公司 | A kind of decorative ceiling and its mounting structure |
CN207829262U (en) * | 2018-01-06 | 2018-09-07 | 江苏恒绿建设工程有限公司 | It is a kind of can modular assembly hang ceiling panel structure |
CN207974339U (en) * | 2017-12-30 | 2018-10-16 | 浙江亚厦装饰股份有限公司 | Hang ceiling panel component |
CN208072737U (en) * | 2018-01-29 | 2018-11-09 | 江苏南通三建装饰装潢有限公司 | A kind of assembly type ceiling structure |
CN211114329U (en) * | 2019-08-23 | 2020-07-28 | 浙江亚厦装饰股份有限公司 | Concatenation formula furred ceiling |
-
2019
- 2019-08-23 CN CN201910782130.8A patent/CN110409686A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20120304575A1 (en) * | 2010-02-16 | 2012-12-06 | Yaakov Vakhnin | Process For Making Cylindrical Bodies |
WO2013042826A1 (en) * | 2011-09-23 | 2013-03-28 | 주식회사 조은이노텍 | Panel assembly structure |
KR20150070984A (en) * | 2013-12-17 | 2015-06-25 | 주식회사 조은데코 | Fit panel assembly |
CN106193413A (en) * | 2016-08-22 | 2016-12-07 | 成都市第四建筑工程公司 | One hides day rail system and a construction method |
CN106677403A (en) * | 2016-12-15 | 2017-05-17 | 浙江亚厦装饰股份有限公司 | Suspended ceiling made of bamboo wood fibre plates and installation method |
CN206941935U (en) * | 2017-07-01 | 2018-01-30 | 大红点商业装饰工程(深圳)有限公司 | A kind of decorative ceiling and its mounting structure |
CN207974339U (en) * | 2017-12-30 | 2018-10-16 | 浙江亚厦装饰股份有限公司 | Hang ceiling panel component |
CN207829262U (en) * | 2018-01-06 | 2018-09-07 | 江苏恒绿建设工程有限公司 | It is a kind of can modular assembly hang ceiling panel structure |
CN208072737U (en) * | 2018-01-29 | 2018-11-09 | 江苏南通三建装饰装潢有限公司 | A kind of assembly type ceiling structure |
CN211114329U (en) * | 2019-08-23 | 2020-07-28 | 浙江亚厦装饰股份有限公司 | Concatenation formula furred ceiling |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112554432A (en) * | 2020-12-29 | 2021-03-26 | 浙江亚厦装饰股份有限公司 | Buckle formula fossil fragments connection structure |
CN113374161A (en) * | 2021-06-18 | 2021-09-10 | 浙江亚厦装饰股份有限公司 | Mounting structure and mounting method for assembly type ceiling panel |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110409686A (en) | Spliced furred ceiling and installation method | |
CN106760634B (en) | Movable house | |
CN111622416A (en) | Assembly type suspended ceiling structure of green building | |
CN103938854A (en) | Connection system of steel aluminum frame of steel aluminum frame formwork and keel | |
EP3714115B1 (en) | Device for strengthening and rigging trusses and method in which such device is applied | |
CN207122081U (en) | A kind of dried hanging hang structure and finishing systems | |
CN205224564U (en) | Steel construction vestibule builder's jack fixture formula mounting structure | |
CN218813214U (en) | Lateral limiting device for space special-shaped arch rib construction | |
CN208473060U (en) | A kind of metal curtain wall | |
CN102878162A (en) | Connection device, LED display unit and LED display system | |
CN206428822U (en) | Prefabricated house | |
CN205857505U (en) | A kind of vibration damping ceiling system | |
CN102031869A (en) | Horizontal template steel structure bracket | |
CN211114329U (en) | Concatenation formula furred ceiling | |
CN208907303U (en) | A kind of architectural engineering plank sheathing being easily installed disassembly | |
CN208202294U (en) | Furred ceiling conversion layer structure | |
WO2021103039A1 (en) | Building module, modular building and construction method for modular building | |
CN207176988U (en) | It is easy to the combined partition body of handling | |
CN208918331U (en) | A kind of upright post type high support template scaffold | |
CN213116949U (en) | Can splice skeleton | |
CN217353095U (en) | Connection structure of open honeycomb aluminum curtain wall | |
CN214658075U (en) | Node device of truss curtain wall | |
CN214658753U (en) | Easy dismouting building templates structure of pre-buried nut | |
CN220504245U (en) | Stone plate connecting device of stone curtain wall | |
CN210289241U (en) | Stair mounting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |