CN110396918B - Assembled hollow pier system equivalent to cast-in-situ and construction method thereof - Google Patents

Assembled hollow pier system equivalent to cast-in-situ and construction method thereof Download PDF

Info

Publication number
CN110396918B
CN110396918B CN201910661186.8A CN201910661186A CN110396918B CN 110396918 B CN110396918 B CN 110396918B CN 201910661186 A CN201910661186 A CN 201910661186A CN 110396918 B CN110396918 B CN 110396918B
Authority
CN
China
Prior art keywords
prefabricated
pier
utfc
section
longitudinal connecting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910661186.8A
Other languages
Chinese (zh)
Other versions
CN110396918A (en
Inventor
周敉
曾航
张洋
宋建伟
卢伟
吴江
朱国强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changan University
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN201910661186.8A priority Critical patent/CN110396918B/en
Publication of CN110396918A publication Critical patent/CN110396918A/en
Application granted granted Critical
Publication of CN110396918B publication Critical patent/CN110396918B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

一种等同现浇的装配式空心桥墩体系及其施工方法,该体系包括预埋有金属波纹管的预制承台,端部设有纵向连接钢筋的各预制墩身节段,预制墩身节段包括预制墩底节段、各预制墩中节段以及与墩帽整体预制的预制墩顶节段,用于相邻各预制墩身节段拼装的预制导向块;其施工方法为首先将预制承台吊装就位,然后采用超韧性纤维混凝土(UTFC)灌浆管道连接将预制墩底节段与预制承台连接为整体,此后依次采用超韧性纤维混凝土(UTFC)湿接缝连接完成相邻各预制墩身节段间的连接,最终拼装为桥墩整体,本发明具有施工速度快、对施工现场交通及周围环境影响小,构件质量易于控制的优点和抗震性能好、刚度大、韧性高、耐久性好、抗疲劳性好等特点。

A prefabricated hollow bridge pier system equivalent to cast-in-place and its construction method. The system includes a prefabricated cap platform with metal bellows pre-embedded, and prefabricated pier body segments with longitudinally connected steel bars at the ends. The prefabricated pier body segments It includes prefabricated pier bottom segments, prefabricated pier middle segments, and prefabricated pier top segments that are integrally prefabricated with the pier caps, and prefabricated guide blocks for assembling adjacent prefabricated pier body segments; the construction method is to first place the prefabricated bearings. The platform is hoisted into place, and then ultra-tough fiber concrete (UTFC) grouting pipes are used to connect the prefabricated pier bottom segments and the prefabricated cap as a whole. After that, ultra-tough fiber concrete (UTFC) wet joints are used to connect adjacent prefabricated units. The connection between the pier body segments is finally assembled into the entire bridge pier. The invention has the advantages of fast construction speed, little impact on the traffic at the construction site and the surrounding environment, easy control of component quality, and good seismic resistance, high stiffness, high toughness, and durability. Good, good fatigue resistance and other characteristics.

Description

一种等同现浇的装配式空心桥墩体系及其施工方法An assembled hollow bridge pier system equivalent to cast-in-place and its construction method

技术领域Technical field

本发明涉及装配式桥墩领域,特别涉及一种等同现浇的装配式空心桥墩体系及其施工方法。The invention relates to the field of prefabricated bridge piers, and in particular to a prefabricated hollow bridge pier system equivalent to cast-in-place and a construction method thereof.

背景技术Background technique

预制装配式桥梁建造技术以其施工工期短、对交通影响小、预制构件工厂批量化生产、质量易于控制等优点,在桥梁工程建设中得到了广泛的应用,预制装配式桥梁建造技术已成为桥梁工程建设的主要发展趋势。但装配式桥墩抗震性能尚不完全明确,在中高烈度地震区桥梁工程中应用受到很大的限制。主要原因在于,目前的桥梁延性抗震设计中,桥墩通常作为桥梁结构中的延性构件,通过发展塑性铰耗散地震能量进而保护桥梁其余构件,塑性铰行为也是传统的整体现浇钢筋混凝土延性桥墩在地震荷载作用下的典型特征,而大多数当前的装配式桥墩体系中预制构件的连接可能会对桥墩塑性铰的形成产生影响,进而影响到整个桥梁结构的抗震性能,这些因素导致装配式桥墩技术目前难以在中高烈度地震区广泛推广和应用。Prefabricated bridge construction technology has been widely used in bridge engineering construction due to its short construction period, small impact on traffic, batch production of prefabricated components in factories, and easy quality control. Prefabricated bridge construction technology has become a bridge The main development trends of engineering construction. However, the seismic performance of prefabricated bridge piers is not completely clear, and its application in bridge projects in medium- and high-intensity earthquake areas is greatly restricted. The main reason is that in the current ductile seismic design of bridges, bridge piers are usually used as ductile components in the bridge structure. They dissipate seismic energy through the development of plastic hinges and thereby protect the remaining components of the bridge. The behavior of plastic hinges is also the same as in traditional integral cast-in-situ reinforced concrete ductile bridge piers. Typical characteristics under seismic loads, and the connection of prefabricated components in most current prefabricated pier systems may affect the formation of the pier's plastic hinges, which in turn affects the seismic performance of the entire bridge structure. These factors have led to the development of prefabricated pier technology. At present, it is difficult to widely promote and apply it in medium- and high-intensity earthquake areas.

目前关于装配式桥墩体系的研究与开发,主要是将桥墩沿竖向分为若干预制墩身节段,通过预应力筋施加预应力将各预制墩身节段竖向拼装为桥墩整体,该类预应力装配式桥墩体系在非抗震设防区域和低烈度地震区的桥梁工程中应用较多,但是对于中高烈度地震区的桥梁工程,该类装配式桥墩体系在地震荷载作用下,承台与桥墩接缝处以及各预制墩身节段接缝处易产生应力集中现象,且存在耗能性能差、预应力损失、受力特性与传统整体现浇桥墩差异显著、预应力的使用增加了施工的难度及工程造价等,这些因素导致相关研究成果目前难以在中高烈度地震区桥梁工程中推广使用。此外,当前阶段桥墩类型的选择已经从原有的重力型桥墩逐渐向轻型桥墩过渡,装配式空心桥墩中各预制墩身节段间的连接处理是设计中的关键问题,该连接构造设计得当与否,直接影响到桥墩整体的受力性能以及施工周期和现场施工安全。The current research and development on the prefabricated bridge pier system mainly involves dividing the bridge pier vertically into a number of prefabricated pier body segments, and applying prestressing force through prestressed tendons to vertically assemble each prefabricated pier body segment into a whole bridge pier. Prestressed prefabricated pier systems are widely used in bridge projects in non-seismic fortification areas and low-intensity earthquake areas. However, for bridge projects in medium- and high-intensity earthquake areas, this type of prefabricated pier system will lose its cap and piers under the action of earthquake loads. The joints and the joints of each prefabricated pier segment are prone to stress concentration, and there are poor energy consumption performance, loss of prestress, and stress characteristics that are significantly different from traditional integral cast-in-place piers. The use of prestress increases the construction time. Difficulty and project cost, etc. These factors make it difficult to promote and use relevant research results in bridge projects in medium- and high-intensity earthquake areas. In addition, the selection of pier types at the current stage has gradually transitioned from the original gravity-type piers to light-weight piers. The connection processing between each prefabricated pier body segment in the prefabricated hollow pier is a key issue in the design. The connection structure is properly designed and No, it will directly affect the overall mechanical performance of the bridge pier as well as the construction period and on-site construction safety.

当前适用于地震区域的一类装配式桥墩为等同现浇装配式桥墩体系,即一种具有与传统整体现浇钢筋混凝土桥墩相近受力特性和抗震性能以及可预期的塑性铰行为的装配式桥墩体系。研究证明,灌浆管道连接以及湿接缝连接是应用于装配式桥墩的一种经济有效的连接方式,但两连接类型存在可能由于连接长度较大而影响桥墩的塑性铰行为等问题。因此,开发出具有成本效益、施工快速可行的等同现浇装配式桥墩体系仍是目前装配式桥墩建造技术应用于地震区域桥梁工程所面临的技术难点。One type of prefabricated pier currently suitable for seismic areas is the equivalent cast-in-place prefabricated pier system, that is, a prefabricated pier with similar stress characteristics and seismic performance as traditional monolithic cast-in-place reinforced concrete piers, as well as predictable plastic hinge behavior. system. Research has proven that grouting pipe connections and wet joint connections are a cost-effective connection method for prefabricated bridge piers. However, these two connection types have problems such as the large connection length that may affect the plastic hinge behavior of the bridge pier. Therefore, developing an equivalent cast-in-place prefabricated pier system that is cost-effective, fast and feasible to construct is still a technical difficulty faced by the current application of prefabricated pier construction technology in bridge projects in earthquake areas.

发明内容Contents of the invention

为克服现有技术的不足,本发明提供一种等同现浇的装配式空心桥墩体系及其施工方法,采用超韧性纤维混凝土(UTFC)灌浆管道连接和超韧性纤维混凝土(UTFC)湿接缝连接分别完成预制墩底节段与预制承台以及各相邻预制墩身节段间的连接,能够有效减小灌浆管道连接以及湿接缝连接所需的连接长度、改善接缝处的力学性能,并结合合理的构造设计使该装配式空心桥墩体系在受力特性与抗震性能方面达到等同现浇的性能水平,具有整体性好、抗震性能好、刚度大、韧性高、耐久性好、施工现实可行等优点。In order to overcome the shortcomings of the existing technology, the present invention provides a cast-in-place assembled hollow pier system and its construction method, using ultra-tough fiber concrete (UTFC) grouting pipe connections and ultra-tough fiber concrete (UTFC) wet joint connections. Complete the connection between the precast pier bottom segments and the precast caps and adjacent precast pier body segments respectively, which can effectively reduce the connection length required for grouting pipe connections and wet joint connections, and improve the mechanical properties of the joints. Combined with reasonable structural design, the prefabricated hollow pier system reaches the same performance level as cast-in-place in terms of stress characteristics and seismic performance. It has good integrity, good seismic performance, high stiffness, high toughness, good durability, and practical construction. Feasibility and other advantages.

为实现上述目的,本发明的技术方案是这样实现的:In order to achieve the above objects, the technical solution of the present invention is implemented as follows:

一种等同现浇的装配式空心桥墩体系,包括设置在地基土层的预制承台1,预制承台1上方设置有桥墩,桥墩由各预制墩身节段5拼装而成,各预制墩身节段5包括预制墩底节段16、预制墩中节段14以及与墩帽6整体预制的预制墩顶节段7。A prefabricated hollow bridge pier system that is equivalent to cast-in-place, including a prefabricated cap platform 1 set on the foundation soil layer. A pier is provided above the prefabricated cap platform 1. The bridge pier is assembled from prefabricated pier body segments 5. Each prefabricated pier body is The section 5 includes a prefabricated pier bottom section 16 , a prefabricated pier middle section 14 and a prefabricated pier top section 7 that is integrally prefabricated with the pier cap 6 .

所述预制承台1和各预制墩身节段5为普通钢筋混凝土材料预制而成,内部均配置有纵向钢筋12和横向箍筋13;所述预制承台1内部预埋有金属波纹管2、顶面设有凹槽3;所述各预制墩身节段5为空心矩形截面,且两端或一端设有纵向连接钢筋18和支承齿块15。The prefabricated cap 1 and each prefabricated pier segment 5 are prefabricated with ordinary reinforced concrete materials, and are equipped with longitudinal steel bars 12 and transverse stirrups 13 inside; the prefabricated cap 1 has metal bellows 2 embedded inside. , the top surface is provided with a groove 3; each of the prefabricated pier segments 5 has a hollow rectangular cross-section, and is provided with longitudinal connecting steel bars 18 and supporting tooth blocks 15 at both ends or one end.

所述预制墩中节段14和预制墩顶节段7底端的支承齿块15预埋有粗直径内螺纹及螺栓8,预制墩底节段16和预制墩中节段14顶端的支承齿块15设置有剪力钉11和钢板9。The supporting tooth blocks 15 at the bottom of the precast pier middle section 14 and the precast pier top section 7 are pre-embedded with thick-diameter internal threads and bolts 8, and the supporting tooth blocks at the top of the precast pier bottom section 16 and the precast pier middle section 14 are pre-embedded. 15 is provided with shear nails 11 and steel plates 9 .

所述预制承台1与预制墩底节段16之间采用UTFC灌浆管道连接完成拼接,相邻各预制墩身节段5之间采用超韧性纤维混凝土UTFC湿接缝连接完成拼接;所述UTFC湿接缝连接处的桥墩内腔设置有用于各预制墩身节段拼装的预制导向块19以及用于支承预制导向块19的横向支承钢筋20,所述预制导向块19由石膏材料预制,截面形式可为空心或实心截面。The precast cap 1 and the precast pier bottom segment 16 are connected by UTFC grouting pipes to complete the splicing, and the adjacent precast pier body segments 5 are connected by super tough fiber concrete UTFC wet joints to complete the splicing; the UTFC The inner cavity of the pier at the wet joint connection is provided with prefabricated guide blocks 19 for assembling each prefabricated pier segment and transverse supporting steel bars 20 for supporting the prefabricated guide blocks 19. The prefabricated guide blocks 19 are prefabricated from gypsum material, and the cross-section The form can be hollow or solid section.

所述UTFC湿接缝连接中相邻各预制墩身节段5之间的纵向连接钢筋18做搭接、焊接、机械连接、或记忆合金连接处理,UTFC湿接缝连接设置长度L按下式计算确定:In the UTFC wet joint connection, the longitudinal connecting steel bars 18 between adjacent prefabricated pier segments 5 are overlapped, welded, mechanically connected, or memory alloy connected, and the UTFC wet joint connection setting length L is as follows: Calculate to determine:

式中:In the formula:

d为纵向连接钢筋18直径;d is the diameter of longitudinal connecting steel bar 18;

fs为纵向连接钢筋18强度,取fs=max(1.5fy,fu),其中fy为纵向连接钢筋18屈服强度,fu为纵向连接钢筋18极限强度;f s is the longitudinal connecting steel bar 18 strength, take f s =max (1.5f y , fu ), where f y is the longitudinal connecting steel bar 18 yield strength, f u is the longitudinal connecting steel bar 18 ultimate strength;

fUTFC为超韧性纤维混凝土UTFC材料28d实测抗压强度;f UTFC is the measured compressive strength of super tough fiber concrete UTFC material for 28 days;

α为纵向连接钢筋18直径大小影响系数,d=12mm时,α=1.0,d=32mm时,α=1.2,d为12~32mm之间时,由线性内插确定α取值;α is the influence coefficient of the diameter of the longitudinal connecting steel bar 18. When d=12mm, α=1.0; when d=32mm, α=1.2; when d is between 12 and 32mm, the value of α is determined by linear interpolation;

c为纵向连接钢筋18连接处理影响系数,当纵向连接钢筋做搭接、焊接、机械连接、记忆合金连接处理时,c分别取1.0、0.5、0.65、0.87;c is the influence coefficient of the longitudinal connecting steel bar 18 connection processing. When the longitudinal connecting steel bars are overlapped, welded, mechanically connected, and memory alloy connected, c is taken to be 1.0, 0.5, 0.65, and 0.87 respectively;

所述UTFC灌浆管道连接中的纵向连接钢筋18设置有4d长度的纵筋剥离段17。The longitudinal connecting steel bars 18 in the UTFC grouting pipe connection are provided with longitudinal bar stripping sections 17 of 4d length.

基于上述等同现浇的装配式空心桥墩体系的施工方法:The construction method of the prefabricated hollow pier system based on the above equivalent to cast-in-place:

步骤一:吊装预制承台1就位,吊装预制墩底节段16与预制承台1进行预拼装,然后向预埋的金属波纹管2与凹槽3内灌注UTFC4,再将预制墩底节段16吊装至预定位置并通过支架固定,预制墩底节段16与预制承台1完成拼装;Step 1: Lift the prefabricated cap 1 into place, hoist the prefabricated pier bottom section 16 and the prefabricated cap 1 for pre-assembly, then pour UTFC4 into the pre-embedded metal bellows 2 and groove 3, and then install the prefabricated pier bottom section. Section 16 is hoisted to the predetermined position and fixed with brackets, and the prefabricated pier bottom section 16 and the prefabricated cap 1 are assembled;

步骤二:吊装预制导向块19至预制墩底节段16的横向支承钢筋20,然后吊装相邻预制墩中节段14至预制墩底节段16上方,通过预制导向块19与支承齿块15以及粗直径内螺纹及螺栓8完成预制墩中节段14拼装位置及垂直度的调整,并通过对螺栓和钢板9进行点焊以对该预制墩中节段进行初步固定,再对预制导向块19与相接的预制墩身节段5内壁之间的缝隙进行环氧树脂胶24填充密封,使预制导向块19作为UTFC湿接缝连接处的内模;Step 2: Lift the prefabricated guide blocks 19 to the lateral supporting steel bars 20 of the prefabricated pier bottom section 16, and then hoist the adjacent prefabricated pier middle section 14 to above the prefabricated pier bottom section 16. Through the prefabricated guide blocks 19 and the supporting tooth blocks 15 And the thick-diameter internal threads and bolts 8 complete the adjustment of the assembly position and verticality of the precast pier middle section 14, and the bolts and steel plates 9 are spot welded to initially fix the precast pier middle section, and then the precast guide blocks The gap between 19 and the inner wall of the connected prefabricated pier segment 5 is filled and sealed with epoxy resin glue 24, so that the prefabricated guide block 19 serves as the internal mold of the UTFC wet joint connection;

步骤三:对预制墩底节段16和相邻预制墩中节段14的纵向连接钢筋18进行搭接、或焊接、或机械连接、或记忆合金连接处理,然后绑扎横向箍筋13并支护外模板21,再通过注浆口22灌注UTFC4,直至UTFC4从出浆口23冒出,进行振捣和养护,UTFC湿接缝连接浇筑完成,至此预制墩底节段16与相邻预制墩中节段14完成拼装;Step 3: Overlap, weld, mechanically connect, or memory alloy connect the longitudinal connecting steel bars 18 of the precast pier bottom section 16 and the adjacent precast pier middle section 14, and then tie and support the transverse stirrups 13 The outer formwork 21 is then poured with UTFC4 through the grouting port 22 until the UTFC4 emerges from the grouting port 23. It is vibrated and cured. The UTFC wet joint connection pouring is completed. At this point, the precast pier bottom segment 16 is connected with the adjacent precast pier. Section 14 is assembled;

步骤四:依次重复上述步骤二和步骤三,完成其余相邻各预制墩身节段之间的拼装,最终整个桥墩施工完成。Step 4: Repeat the above steps 2 and 3 in sequence to complete the assembly of the remaining adjacent prefabricated pier segments, and finally the entire bridge pier construction is completed.

本发明利用UTFC材料强度远高于普通混凝土和常规灌浆料的特点,通过减小纵向连接钢筋所需的锚固长度,有效减小了UTFC灌浆管道连接和UTFC湿接缝连接所需的连接长度;通过在UTFC灌浆管道连接中的纵向连接钢筋设置4d长度的纵筋剥离段,能够有效避免该纵筋连接钢筋在预制承台与预制墩底节段间拼接面处产生应力集中,防止其在往复荷载作用下发生疲劳破坏,并将该纵向连接钢筋的变形扩展到更大的长度范围,进而扩展墩底的塑性铰区域,减缓塑性铰集中破坏程度,提高该装配式桥墩体系的延性;通过在预制承台顶部表面设计浅凹槽以增强预制墩底节段与预制承台间拼接面处的剪力传递;各预制墩身节段一端或两端的支承齿块,避免了后浇UTFC湿接缝连接与预制墩身节段的接触面完全处于同一平面,能够协同UTFC湿接缝连接处的剪力传递,且通过转动预制墩身节段底端的支承齿块中预埋的粗直径螺栓能够在预制墩身节段拼装时对其垂直度进行微调,以确保垂直度符合设计要求;石膏材料的预制导向块的设置,既充当预制墩身节段拼装时的导向块,又充当了浇筑UTFC湿接缝浇筑时的内模,且石膏材料的较低强度避免了该预制导向块对桥墩整体受力性能产生影响;墩底的UTFC灌浆管道连接是一种延性连接,该连接被设计成在高水平地震力作用下以延性方式屈服,墩底附近仍是潜在的塑性铰区;预制墩身节段间的UTFC湿接缝连接是一个很强的连接,当墩底在高水平地震力作用下屈服时,该连接受到保护而保持弹性;上述各细部构造设计将确保本发明所提出的装配式空心桥墩体系各项力学特性和抗震性能与传统整体现浇钢筋混凝土桥墩相近,即达到等同现浇的性能水平,且UTFC灌浆管道连接和UTFC湿接缝连接均采用灌浆工艺完成UTFC的浇筑,施工方便可行,UTFC优越的力学性能将确保连接性能的稳定;利用预制拼装的施工方法,极大的提高了施工效率,缩短了施工周期,经济效益好,在很大程度上节省了人力物力。该发明具有重大的实用价值和良好的经济效益,尤其是在桥墩施工技术领域具有广阔的应用前景。The present invention takes advantage of the fact that the strength of UTFC material is much higher than that of ordinary concrete and conventional grouting materials. By reducing the anchoring length required for longitudinally connecting steel bars, the invention effectively reduces the connection length required for UTFC grouting pipe connection and UTFC wet joint connection; By setting a longitudinal bar stripping section of 4d length in the longitudinal connecting steel bar in the UTFC grouting pipe connection, it can effectively avoid the stress concentration of the longitudinal connecting steel bar at the splicing surface between the precast cap and the precast pier bottom segment, and prevent it from reciprocating Fatigue failure occurs under load, and the deformation of the longitudinal connecting steel bars is extended to a larger length range, thereby expanding the plastic hinge area at the bottom of the pier, slowing down the degree of concentrated damage of the plastic hinges, and improving the ductility of the prefabricated pier system; by The top surface of the precast cap is designed with shallow grooves to enhance the shear force transfer at the splicing surface between the precast pier bottom segment and the precast cap; the support teeth at one or both ends of each precast pier segment avoid post-cast UTFC wet joints The contact surface between the joint connection and the precast pier segment is completely on the same plane, which can cooperate with the shear force transmission at the UTFC wet joint connection, and by rotating the thick-diameter bolt embedded in the support tooth block at the bottom of the precast pier segment. When assembling the precast pier segments, fine-tune the verticality to ensure that the verticality meets the design requirements; the setting of precast guide blocks made of gypsum material not only serves as guide blocks when assembling the precast pier segments, but also serves as a guide for pouring UTFC The internal mold during wet joint pouring, and the lower strength of the gypsum material prevents the prefabricated guide block from affecting the overall stress performance of the pier; the UTFC grouting pipe connection at the bottom of the pier is a ductile connection, which is designed to It yields in a ductile manner under the action of high-level seismic forces, and there is still a potential plastic hinge area near the pier bottom; the UTFC wet joint connection between the precast pier segments is a strong connection. When the bottom of the pier is under the action of high-level seismic forces, When yielding, the connection is protected and remains elastic; the above detailed structural design will ensure that the mechanical properties and seismic performance of the assembled hollow pier system proposed by the present invention are similar to those of traditional monolithic cast-in-situ reinforced concrete bridge piers, that is, they achieve the same level of performance. The performance level of pouring, and both the UTFC grouting pipe connection and the UTFC wet joint connection use grouting technology to complete the pouring of UTFC. The construction is convenient and feasible. The superior mechanical properties of UTFC will ensure the stability of the connection performance; the use of prefabricated assembly construction method greatly greatly It improves the construction efficiency, shortens the construction cycle, has good economic benefits, and saves manpower and material resources to a large extent. The invention has great practical value and good economic benefits, especially in the field of bridge pier construction technology, and has broad application prospects.

附图说明Description of the drawings

图1为本发明等同现浇的装配式空心桥墩构造示意图。Figure 1 is a schematic diagram of the structure of a cast-in-place assembled hollow bridge pier equivalent to the present invention.

图2为本发明预制墩中节段和预制墩顶节段底端支承齿块的布置图。Figure 2 is a layout diagram of the supporting tooth blocks at the bottom of the precast pier middle section and the precast pier top section of the present invention.

图3为本发明各预制墩身节段5配筋示意图。Figure 3 is a schematic diagram of the reinforcement of each prefabricated pier segment 5 of the present invention.

图4为本发明预制墩底节段16结构示意图。Figure 4 is a schematic structural diagram of the prefabricated pier bottom segment 16 of the present invention.

图5为本发明预制墩中节段14结构示意图。Figure 5 is a schematic structural diagram of the middle section 14 of the prefabricated pier of the present invention.

图6为本发明UTFC湿接缝连接预制导向块19及外模板21设置示意图。Figure 6 is a schematic diagram showing the arrangement of the UTFC wet joint connection prefabricated guide block 19 and the outer formwork 21 of the present invention.

图7为本发明UTFC湿接缝连接预制导向块19及外模板21设置俯视图。Figure 7 is a top view of the installation of the UTFC wet joint connection prefabricated guide block 19 and the outer formwork 21 of the present invention.

图8为本发明UTFC湿接缝连接纵向连接钢筋18采用搭接的构造示意图。Figure 8 is a schematic structural diagram of the UTFC wet joint connection longitudinal connecting steel bar 18 using overlap according to the present invention.

图9为本发明UTFC湿接缝连接纵向连接钢筋18采用焊接的构造示意图。Figure 9 is a schematic structural diagram of the UTFC wet joint connection longitudinal connecting steel bar 18 using welding according to the present invention.

图10为本发明UTFC湿接缝连接纵向连接钢筋18采用机械连接的构造示意图。Figure 10 is a schematic structural diagram of the mechanical connection of the longitudinal connecting steel bars 18 of the UTFC wet joint connection according to the present invention.

图11为本发明UTFC湿接缝连接纵向连接钢筋18采用记忆合金连接的构造示意图。Figure 11 is a schematic structural diagram of the UTFC wet joint connection longitudinal connection steel bar 18 of the present invention using memory alloy connection.

其中:1、预制承台;2、金属波纹管;3、凹槽;4、UTFC;5、各预制墩身节段;6、墩帽;7、预制墩顶节段;8、粗直径内螺纹及螺栓;9、钢板;10、纵向连接钢筋机械连接;11、剪力钉;12、纵向钢筋;13、横向箍筋;14、预制墩中节段;15、支承齿块;16、预制墩底节段;17、纵筋剥离段;18、纵向连接钢筋;19、预制导向块;20、横向支承钢筋;21、外模板;22、注浆口;23、出浆口;24、环氧树脂胶;25、纵向连接钢筋搭接;26、纵向连接钢筋焊接;27、纵向连接钢筋记忆合金连接。Among them: 1. Prefabricated cap; 2. Metal corrugated pipe; 3. Groove; 4. UTFC; 5. Each prefabricated pier body segment; 6. Pier cap; 7. Prefabricated pier top segment; 8. Large diameter inner Threads and bolts; 9. Steel plate; 10. Mechanical connection of longitudinal connecting steel bars; 11. Shear nails; 12. Longitudinal steel bars; 13. Transverse stirrups; 14. Prefabricated pier middle section; 15. Supporting tooth blocks; 16. Precast Pier bottom segment; 17. Stripped section of longitudinal bars; 18. Longitudinal connecting steel bars; 19. Prefabricated guide blocks; 20. Transverse supporting steel bars; 21. External formwork; 22. Grouting port; 23. Grouting outlet; 24. Ring Oxygen resin glue; 25. Overlap of longitudinal connecting steel bars; 26. Welding of longitudinal connecting steel bars; 27. Memory alloy connection of longitudinal connecting steel bars.

具体实施方式Detailed ways

实施例一Embodiment 1

如图1所示,一种等同现浇的装配式空心桥墩体系,包括预制承台1,预制承台1内部预埋有金属波纹管2、顶面设置有凹槽3,预制承台1上方设置有各预制墩身节段5,各预制墩身节段5包括预制墩底节段16、预制墩中节段14、以及与墩帽6整体预制的预制墩顶节段7;As shown in Figure 1, a prefabricated hollow pier system that is equivalent to cast-in-place includes a prefabricated cap 1. A metal bellows 2 is embedded inside the prefabricated cap 1, and a groove 3 is provided on the top surface. Above the prefabricated cap 1 Each prefabricated pier body segment 5 is provided, and each prefabricated pier body segment 5 includes a prefabricated pier bottom segment 16, a prefabricated pier middle segment 14, and a prefabricated pier top segment 7 that is integrally prefabricated with the pier cap 6;

如图2、图3所示,预制承台1和各预制墩身节段5均为普通钢筋混凝土材料预制而成,内部均配置有纵向钢筋12和横向箍筋13,各预制墩身节段5为空心矩形截面;As shown in Figures 2 and 3, the precast cap 1 and each precast pier segment 5 are prefabricated with ordinary reinforced concrete materials, and are equipped with longitudinal steel bars 12 and transverse stirrups 13 inside. Each precast pier segment 5 is a hollow rectangular section;

如图4、图5所示,各预制墩身节段5两端或一端设有纵向连接钢筋18和支承齿块15,预制墩中节段14和预制墩顶节段7底端的支承齿块15预埋有粗直径内螺纹及螺栓8,预制墩底节段16和预制墩中节段14顶端的支承齿块15设置有剪力钉11和钢板9;As shown in Figures 4 and 5, each prefabricated pier body segment 5 is provided with longitudinal connecting steel bars 18 and supporting tooth blocks 15 at both ends or one end of the precast pier middle section 14 and the supporting tooth blocks at the bottom end of the precast pier top section 7 15 is pre-embedded with thick-diameter internal threads and bolts 8, and the supporting tooth blocks 15 at the top of the prefabricated pier bottom section 16 and the prefabricated pier middle section 14 are provided with shear nails 11 and steel plates 9;

如图6、图7所示,UTFC湿接缝连接处的桥墩内腔设置有用于各预制墩身节段拼装的预制导向块19以及用于支承预制导向块19的横向支承钢筋20,预制导向块19由石膏材料预制,截面形式可为空心或实心截面,本实施例选为实心截面;As shown in Figures 6 and 7, the inner cavity of the pier at the UTFC wet joint connection is provided with prefabricated guide blocks 19 for assembling each prefabricated pier segment and transverse supporting steel bars 20 for supporting the prefabricated guide blocks 19. The prefabricated guide blocks Block 19 is prefabricated from gypsum material, and the cross-section form can be hollow or solid cross-section. In this embodiment, solid cross-section is selected;

UTFC湿接缝连接处纵向连接钢筋为机械连接处理时,UTFC湿接缝设置长度L按下式计算确定:When the longitudinal connecting steel bars at the UTFC wet joint connection are mechanically connected, the set length L of the UTFC wet joint is calculated and determined according to the following formula:

式中:In the formula:

d为纵向连接钢筋直径;d is the diameter of longitudinal connecting steel bars;

fs为纵向连接钢筋强度,取fs=max(1.5fy,fu),其中fy为纵向连接钢筋屈服强度,fu为纵向连接钢筋极限强度;f s is the strength of longitudinal connecting steel bars, take f s =max(1.5f y , fu ), where f y is the yield strength of longitudinal connecting steel bars, and f u is the ultimate strength of longitudinal connecting steel bars;

fUTFC为超韧性纤维混凝土(UTFC)材料28d实测抗压强度;f UTFC is the measured compressive strength of ultra-tough fiber concrete (UTFC) material for 28 days;

α为纵向连接钢筋直径大小影响系数,d=12mm时,α=1.0,d=32mm时,α=1.2,d为12~32mm之间时,由线性内插确定α取值;α is the influence coefficient of the diameter of the longitudinal connecting steel bars. When d=12mm, α=1.0. When d=32mm, α=1.2. When d is between 12 and 32mm, the value of α is determined by linear interpolation;

c为纵向连接钢筋连接处理影响系数,当纵向连接钢筋做机械连接处理时,参照图10,取0.65;c is the influence coefficient of the connection processing of the longitudinal connecting steel bars. When the longitudinal connecting steel bars are mechanically connected, refer to Figure 10 and take 0.65;

上述本实施例的等同现浇的装配式空心桥墩体系的施工步骤为:The construction steps of the above-mentioned cast-in-place assembled hollow pier system of this embodiment are as follows:

步骤一:吊装预制承台1就位,吊装预制墩底节段16与预制承台进行预拼装,然后向预埋的金属波纹管3与凹槽3内灌注UTFC 4,再将预制墩底节段16吊装至预定位置并通过支架固定,预制墩底节段16与预制承台1完成拼装;Step 1: Lift the prefabricated cap 1 into place, hoist the prefabricated pier bottom section 16 and preassemble the prefabricated cap, then pour UTFC 4 into the pre-embedded metal bellows 3 and groove 3, and then install the prefabricated pier bottom section Section 16 is hoisted to the predetermined position and fixed with brackets, and the prefabricated pier bottom section 16 and the prefabricated cap 1 are assembled;

步骤二:吊装预制导向块19至预制墩底节段16的横向支撑钢筋20,然后吊装相邻预制墩中节段14至预制墩底节段16上方,通过预制导向块19与支承齿块15以及转动8中的螺栓完成该预制墩中节段14拼装位置及垂直度的调整,并通过对粗直径内螺纹及螺栓8中的螺栓和钢板9进行点焊以对该预制墩中节段14进行初步固定,再对预制导向块19与相接的预制墩身节段5内壁之间的缝隙进行环氧树脂胶24填充密封,使预制导向块19作为UTFC湿接缝连接处的内模;Step 2: Lift the prefabricated guide blocks 19 to the lateral support steel bars 20 of the prefabricated pier bottom section 16, and then hoist the adjacent prefabricated pier middle section 14 to above the prefabricated pier bottom section 16. Through the prefabricated guide blocks 19 and the supporting tooth blocks 15 And rotate the bolts in 8 to complete the adjustment of the assembly position and verticality of the precast pier middle section 14, and spot weld the thick diameter internal threads and the bolts and steel plates 9 in bolt 8 to adjust the precast pier middle section 14 After preliminary fixing, the gap between the prefabricated guide block 19 and the inner wall of the adjacent prefabricated pier segment 5 is filled and sealed with epoxy resin glue 24, so that the prefabricated guide block 19 serves as the internal mold for the UTFC wet joint connection;

步骤三:对预制墩底节段16和相邻预制墩中节段14的纵向连接钢筋18做纵向连接钢筋机械连接10处理,参照图10,然后绑扎横向箍筋13并支护外模板21,再通过注浆口22灌注UTFC 4,直至UTFC 4从出浆口23冒出,进行振捣和养护,UTFC湿接缝连接浇筑完成,至此预制墩底节段16与相邻预制墩中节段14完成拼装;Step 3: Perform longitudinal connecting steel mechanical connection 10 on the longitudinal connecting steel bars 18 of the precast pier bottom section 16 and the adjacent precast pier middle section 14. Refer to Figure 10, then tie the transverse stirrups 13 and support the outer formwork 21. Then pour UTFC 4 through the grouting port 22 until UTFC 4 emerges from the grouting port 23. Vibration and curing are performed. The UTFC wet joint connection pouring is completed. At this point, the precast pier bottom section 16 is connected to the adjacent precast pier middle section. 14Complete assembly;

步骤四:依次重复上述步骤二和步骤三,完成其余相邻各预制墩身节段5之间的拼装,最终整个桥墩施工完成。Step 4: Repeat the above-mentioned steps 2 and 3 in sequence to complete the assembly between the remaining adjacent prefabricated pier segments 5, and finally the entire bridge pier construction is completed.

实施例二Embodiment 2

如图1、图8所示,一种等同现浇的装配式空心桥墩体系,包括预制承台1,预制承台1内部预埋有金属波纹管2、顶面设置有凹槽3,预制承台1上方设置有各预制墩身节段5,各预制墩身节段5包括预制墩底节段16、预制墩中节段14、以及与墩帽6整体预制的预制墩顶节段7;As shown in Figures 1 and 8, a prefabricated hollow bridge pier system that is equivalent to cast-in-place includes a prefabricated bearing platform 1, with a metal bellows 2 embedded inside the prefabricated bearing platform 1, and a groove 3 provided on the top surface. Each prefabricated pier body segment 5 is provided above the platform 1. Each prefabricated pier body segment 5 includes a prefabricated pier bottom segment 16, a prefabricated pier middle segment 14, and a prefabricated pier top segment 7 that is integrally prefabricated with the pier cap 6;

如图2、图3所示,预制承台1和各预制墩身节段5均为普通钢筋混凝土材料预制而成,内部均配置有纵向钢筋12和横向箍筋13,各预制墩身节段5为空心矩形截面;As shown in Figures 2 and 3, the precast cap 1 and each precast pier segment 5 are prefabricated with ordinary reinforced concrete materials, and are equipped with longitudinal steel bars 12 and transverse stirrups 13 inside. Each precast pier segment 5 is a hollow rectangular section;

如图4、图5所示,各预制墩身节段5两端或一端设有纵向连接钢筋18和支承齿块15,预制墩中节段14和预制墩顶节段7底端的支承齿块15预埋有粗直径内螺纹及螺栓8,预制墩底节段16和预制墩中节段14顶端的支承齿块15设置有剪力钉11和钢板9;As shown in Figures 4 and 5, each prefabricated pier body segment 5 is provided with longitudinal connecting steel bars 18 and supporting tooth blocks 15 at both ends or one end of the precast pier middle section 14 and the supporting tooth blocks at the bottom end of the precast pier top section 7 15 is pre-embedded with thick-diameter internal threads and bolts 8, and the supporting tooth blocks 15 at the top of the prefabricated pier bottom section 16 and the prefabricated pier middle section 14 are provided with shear nails 11 and steel plates 9;

如图6、图7所示,UTFC湿接缝连接处的桥墩内腔设置有用于各预制墩身节段拼装的预制导向块19以及用于支承预制导向块19的横向支承钢筋20,预制导向块19由石膏材料预制,截面形式可为空心或实心截面,本实施例选为实心截面;As shown in Figures 6 and 7, the inner cavity of the pier at the UTFC wet joint connection is provided with prefabricated guide blocks 19 for assembling each prefabricated pier segment and transverse supporting steel bars 20 for supporting the prefabricated guide blocks 19. The prefabricated guide blocks Block 19 is prefabricated from gypsum material, and the cross-section form can be hollow or solid cross-section. In this embodiment, solid cross-section is selected;

UTFC湿接缝连接处纵向连接钢筋为搭接处理时,UTFC湿接缝设置长度L按下式计算确定:When the longitudinal connecting steel bars at the UTFC wet joint connection are overlapped, the length L of the UTFC wet joint is calculated and determined according to the following formula:

式中:In the formula:

d为纵向连接钢筋直径;d is the diameter of longitudinal connecting steel bars;

fs为纵向连接钢筋强度,取fs=max(1.5fy,fu),其中fy为纵向连接钢筋屈服强度,f s is the strength of longitudinal connecting steel bars, take f s =max(1.5f y , fu ), where f y is the yield strength of longitudinal connecting steel bars,

fu为纵向连接钢筋极限强度;f u is the ultimate strength of longitudinal connecting steel bars;

fUTFC为超韧性纤维混凝土(UTFC)材料28d实测抗压强度;f UTFC is the measured compressive strength of ultra-tough fiber concrete (UTFC) material for 28 days;

α为纵向连接钢筋直径大小影响系数,d=12mm时,α=1.0,d=32mm时,α=1.2,d为12~32mm之间时,由线性内插确定α取值;α is the influence coefficient of the diameter of the longitudinal connecting steel bars. When d=12mm, α=1.0. When d=32mm, α=1.2. When d is between 12 and 32mm, the value of α is determined by linear interpolation;

c为纵向连接钢筋连接处理影响系数,当纵向连接钢筋做搭接处理时,参照图8,取1.0;c is the influence coefficient of the longitudinal connecting steel bar connection treatment. When the longitudinal connecting steel bar is overlapped, refer to Figure 8 and take 1.0;

上述本实施例的等同现浇的装配式空心桥墩体系的施工步骤为:The construction steps of the above-mentioned cast-in-place assembled hollow pier system of this embodiment are as follows:

步骤一:吊装预制承台1就位,吊装预制墩底节段16与预制承台进行预拼装,然后向预埋的金属波纹管2与凹槽3内灌注UTFC 4,再将预制墩底节段16吊装至预定位置并通过支架固定,预制墩底节段16与预制承台1完成拼装;Step 1: Lift the prefabricated cap 1 into place, hoist the prefabricated pier bottom section 16 and preassemble the prefabricated cap, then pour UTFC 4 into the pre-embedded metal bellows 2 and groove 3, and then install the prefabricated pier bottom section Section 16 is hoisted to the predetermined position and fixed with brackets, and the prefabricated pier bottom section 16 and the prefabricated cap 1 are assembled;

步骤二:吊装预制导向块19至预制墩底节段16的横向支撑钢筋20,然后吊装相邻预制墩中节段14至预制墩底节段16上方,通过预制导向块19与支承齿块15以及转动粗直径内螺纹及螺栓8中的螺栓完成该预制墩中节段14拼装位置及垂直度的调整,并通过对粗直径内螺纹及螺栓8中的螺栓和钢板9进行点焊以对该预制墩中节段14进行初步固定,再对预制导向块19与相接的预制墩身节段5内壁之间的缝隙进行环氧树脂胶24填充密封,使预制导向块19作为UTFC湿接缝连接处的内模;Step 2: Lift the prefabricated guide blocks 19 to the lateral support steel bars 20 of the prefabricated pier bottom section 16, and then hoist the adjacent prefabricated pier middle section 14 to above the prefabricated pier bottom section 16. Through the prefabricated guide blocks 19 and the supporting tooth blocks 15 And rotate the bolts in the thick-diameter internal threads and bolts 8 to complete the adjustment of the assembly position and verticality of the prefabricated pier middle section 14, and spot-weld the thick-diameter internal threads and the bolts and steel plates 9 in the bolts 8 to adjust the assembly position and verticality of the prefabricated pier segment 14 The prefabricated pier middle section 14 is initially fixed, and then the gap between the prefabricated guide block 19 and the inner wall of the adjacent prefabricated pier body section 5 is filled and sealed with epoxy resin glue 24, so that the prefabricated guide block 19 serves as a UTFC wet joint. Internal mold at the joint;

步骤三:对预制墩底节段16和相邻预制墩中节段14的纵向连接钢筋18做纵向连接钢筋搭接25处理,参照图8,然后绑扎横向箍筋13并支护外模板21,再通过注浆口22灌注UTFC 4,直至UTFC 4从出浆口23冒出,进行振捣和养护,UTFC湿接缝连接浇筑完成,至此预制墩底节段16与相邻预制墩中节段14完成拼装;Step 3: Perform longitudinal connecting steel bar overlap 25 processing on the longitudinal connecting steel bars 18 of the precast pier bottom section 16 and the adjacent precast pier middle section 14. Refer to Figure 8, then tie the transverse stirrups 13 and support the outer formwork 21. Then pour UTFC 4 through the grouting port 22 until UTFC 4 emerges from the grouting port 23. Vibration and curing are performed. The UTFC wet joint connection pouring is completed. At this point, the precast pier bottom section 16 is connected to the adjacent precast pier middle section. 14Complete assembly;

步骤四:依次重复上述步骤二和步骤三,完成其余相邻各预制墩身节段5之间的拼装,最终整个桥墩施工完成。Step 4: Repeat the above-mentioned steps 2 and 3 in sequence to complete the assembly between the remaining adjacent prefabricated pier segments 5, and finally the entire bridge pier construction is completed.

参照图8、图9、图10、图11,对预制墩底节段16和相邻预制墩中节段14的纵向连接钢筋18除了做实施例一的机械连接处理、实施例二的纵向连接钢筋搭接25处理外,还可以做纵向连接钢筋焊接26处理或纵向连接钢筋记忆合金连接27处理,参照图9为本发明UTFC湿接缝连接纵向连接钢筋18采用焊接的构造示意图;图11为本发明UTFC湿接缝连接纵向连接钢筋18采用记忆合金连接的构造示意图。Referring to Figures 8, 9, 10, and 11, in addition to the mechanical connection processing of Embodiment 1 and the longitudinal connection of Embodiment 2, the longitudinal connecting steel bars 18 of the precast pier bottom section 16 and the adjacent precast pier middle section 14 are In addition to the steel bar overlap 25 process, the longitudinal connecting steel bar welding 26 process or the longitudinal connecting steel bar memory alloy connection 27 process can also be performed. Refer to Figure 9 for a schematic structural diagram of the UTFC wet joint connection longitudinal connecting steel bar 18 using welding according to the present invention; Figure 11 is Schematic diagram of the structure of the UTFC wet joint connection longitudinal connection steel bar 18 using memory alloy connection according to the present invention.

本发明的原理和优势:Principles and advantages of the invention:

本发明提出的等同现浇的装配式空心桥墩体系及其施工方法是利用超韧性纤维混凝土(UTFC)材料的抗压强度高,各项力学性能优越,与钢筋的粘结性能好的优点,有效缩短了拼接缝所需长度,消除了在装配式桥墩技术中各预制节段间拼接处钢筋连接构造复杂、混凝土强度不足和接缝力学性能差等缺点,通过构造设计使装配式空心桥墩的连接构造更为简单,施工方便可行,提高了桥墩施工的效率,并确保了本发明所提出的装配式空心桥墩体系各项力学特性和抗震性能及塑性铰行为与传统整体现浇钢筋混凝土桥墩相近,最终达到等同现浇的性能水平。The prefabricated hollow bridge pier system and its construction method proposed by the present invention are equivalent to cast-in-situ and utilize the advantages of ultra-tough fiber concrete (UTFC) materials such as high compressive strength, superior mechanical properties, and good bonding performance with steel bars, and are effective The required length of the splicing joints is shortened, and the disadvantages of the prefabricated pier technology such as the complicated steel connection structure, insufficient concrete strength, and poor joint mechanical properties in the prefabricated segments are eliminated. Through structural design, the prefabricated hollow piers are made more durable. The connection structure is simpler, the construction is convenient and feasible, the efficiency of bridge pier construction is improved, and the mechanical properties, seismic performance and plastic hinge behavior of the assembled hollow pier system proposed by the invention are similar to those of traditional integral cast-in-situ reinforced concrete bridge piers. , ultimately reaching a performance level equivalent to cast-in-place.

本领域内的超韧性纤维混凝土(UTFC)为一专有名称,在本发明中一般是指采用毫米级颗粒(骨料)并添加钢纤维的水泥基混凝土,其是相对普通混凝土、高性能混凝土而言的另一类力学综合性能更加优异的混凝土材料,例如活性粉末混凝土、超高性能纤维增强混凝土、注浆纤维混凝土、密实配筋复合材料等,但优选为超高性能钢纤维增强混凝土或注浆纤维混凝土。Ultra-tough fiber concrete (UTFC) in this field is a proprietary name. In the present invention, it generally refers to cement-based concrete using millimeter-sized particles (aggregate) and adding steel fibers. It is relatively ordinary concrete and high-performance concrete. Another type of concrete material with better comprehensive mechanical properties, such as reactive powder concrete, ultra-high performance fiber reinforced concrete, grouting fiber concrete, dense reinforced composite materials, etc., but ultra-high performance steel fiber reinforced concrete or ultra-high performance steel fiber reinforced concrete is preferred. Grouted fiber concrete.

与现有技术相比,本发明在空心桥墩连接处设置超韧性纤维混凝土UTFC,在超韧性纤维混凝土UTFC中的钢筋采用搭接、焊接或机械连接,这显著改变了预制拼装空心桥墩的结构形式和工作状态,也使得本发明的技术方案具备以下明显的优势:Compared with the existing technology, the present invention sets super-tough fiber concrete UTFC at the connection point of the hollow bridge piers. The steel bars in the super-tough fiber concrete UTFC are overlapped, welded or mechanically connected, which significantly changes the structural form of the prefabricated assembled hollow bridge piers. and working status, which also makes the technical solution of the present invention have the following obvious advantages:

首先,本发明的超韧性纤维混凝土连接空心桥墩结构共同受力,超韧性纤维混凝土UTFC自身的应力、变形等指标均能满足于现浇空心桥墩结构工作的要求;First of all, the super-tough fiber concrete connected hollow pier structure of the present invention is stressed together, and the stress, deformation and other indicators of the super-tough fiber concrete UTFC itself can meet the requirements of the cast-in-place hollow pier structure;

其次,本发明的超韧性纤维混凝土UTFC增大了桥墩的刚度,保证连接段与墩身节段的粘结性能,提高了连接段的抗裂性能和耐久性能。Secondly, the super tough fiber concrete UTFC of the present invention increases the stiffness of the bridge pier, ensures the bonding performance between the connecting section and the pier body section, and improves the crack resistance and durability of the connecting section.

此外,本发明技术方案中的超韧性纤维混凝土UTFC所选用的是适用于空心桥墩连接的配比,其组成材料不同粒径颗粒以最佳比例形成最紧密堆积,不仅易于施工操作,且能够保证密实性,提高了桥墩的抗震性能和在恶劣环境条件下的耐侵蚀能力和耐久性。In addition, the ultra-tough fiber concrete UTFC in the technical solution of the present invention is selected with a ratio suitable for the connection of hollow bridge piers. The particles of different particle sizes of its constituent materials are in the best proportion to form the most densely packed, which is not only easy to construct and operate, but also ensures The compactness improves the seismic performance of the bridge pier and its erosion resistance and durability under harsh environmental conditions.

连接段可以通过对超韧性纤维混凝土层不同壁厚和高度的取值,使连接后的空心桥墩骨架曲线峰值及延性达到或优于现浇墩柱的性能。综上所述,本发明提出的超韧性纤维混凝土作为预制拼装空心桥墩湿接缝,具有结构刚度大、层间粘结性好、耐久性好、抗疲劳性能好等优点,具有重大的实用价值和良好的经济效益,尤其是在空心桥墩预制拼装领域具有广阔的应用前景。并具有抗震性能好,耐久性能优越,在预制空心桥墩下节段上放置石膏导向块,并将空心桥墩上下节段通过支撑齿块进行对接,对墩身上下节段的受力纵筋进行搭接、焊接或机械连接;安装模板,浇筑超韧性纤维混凝土,完成后采用振动平台加以振实;对浇筑后的超韧性纤维混凝土进行养护,待混凝土的力学指标达到设计要求后拆模,完成整个施工。The connecting section can adjust the values of different wall thicknesses and heights of the super-tough fiber concrete layer to make the curve peak value and ductility of the connected hollow pier skeleton reach or exceed the performance of cast-in-place pier columns. In summary, the super-tough fiber concrete proposed in the present invention, as a prefabricated assembled hollow bridge pier wet joint, has the advantages of large structural rigidity, good inter-layer bonding, good durability, and good fatigue resistance, and has great practical value. And good economic benefits, especially in the field of precast assembly of hollow bridge piers, it has broad application prospects. It has good seismic resistance and excellent durability. Plaster guide blocks are placed on the lower sections of the prefabricated hollow piers, and the upper and lower sections of the hollow piers are connected through supporting tooth blocks, and the longitudinal reinforcements of the upper and lower sections of the pier are laid. connection, welding or mechanical connection; install the formwork, pour the super tough fiber concrete, and use a vibration platform to vibrate it after completion; maintain the poured super tough fiber concrete, remove the formwork after the mechanical index of the concrete reaches the design requirements, and complete the entire construction.

Claims (3)

1.一种等同现浇的装配式空心桥墩体系,其特征在于:包括预制承台(1),所述预制承台(1)上方连接有桥墩,桥墩由各预制墩身节段(5)拼装而成,各预制墩身节段(5)包括预制墩底节段(16)、预制墩中节段(14)以及与墩帽(6)整体预制的预制墩顶节段(7);1. A prefabricated hollow bridge pier system equivalent to cast-in-place, characterized by: including a prefabricated cap platform (1), a pier is connected above the prefabricated cap platform (1), and the bridge pier is composed of each prefabricated pier body segment (5) Assembled, each prefabricated pier body segment (5) includes a prefabricated pier bottom segment (16), a prefabricated pier middle segment (14), and a prefabricated pier top segment (7) integrally prefabricated with the pier cap (6); 所述预制承台(1)和各预制墩身节段(5)为普通钢筋混凝土材料预制而成,内部均配置有纵向钢筋(12)和横向箍筋(13),所述预制承台(1)内部预埋有金属波纹管(2)、顶面设有凹槽(3),所述各预制墩身节段(5)为空心矩形截面,所述各预制墩身节段(5)两端或一端设有纵向连接钢筋(18)和支承齿块(15);The prefabricated capping platform (1) and each prefabricated pier segment (5) are prefabricated with ordinary reinforced concrete materials, and are equipped with longitudinal steel bars (12) and transverse stirrups (13) inside. The prefabricated capping platform (1) 1) There is a metal bellows (2) embedded inside, and a groove (3) is provided on the top surface. Each of the prefabricated pier body segments (5) has a hollow rectangular cross-section. The prefabricated pier body segments (5) Both ends or one end are provided with longitudinal connecting steel bars (18) and supporting tooth blocks (15); 所述预制墩中节段(14)和预制墩顶节段(7)底端的支承齿块(15)预埋有粗直径内螺纹及螺栓(8),所述预制墩底节段(16)和预制墩中节段(14)顶端的支承齿块(15)设置有剪力钉(11)和钢板(9);The supporting tooth blocks (15) at the bottom of the prefabricated pier middle section (14) and the prefabricated pier top section (7) are pre-embedded with thick-diameter internal threads and bolts (8), and the prefabricated pier bottom section (16) And the supporting tooth block (15) at the top of the prefabricated pier middle section (14) is provided with shear nails (11) and steel plates (9); 所述预制承台(1)与预制墩底节段(16)之间采用超韧性纤维混凝土(UTFC)灌浆管道连接完成拼接,所述相邻各预制墩身节段(5)之间采用超韧性纤维混凝土(UTFC)湿接缝连接完成拼接,所述UTFC湿接缝连接处的桥墩内腔设置有用于各预制墩身节段拼装的预制导向块(19)以及用于支承预制导向块(19)的横向支承钢筋(20),所述预制导向块(19)由石膏材料预制,截面形式可为空心或实心截面;The prefabricated cap (1) and the prefabricated pier bottom segments (16) are connected by ultra-tough fiber concrete (UTFC) grouting pipes to complete the splicing, and the adjacent prefabricated pier body segments (5) are connected by ultra-tough fiber concrete (UTFC) grouting pipes. The ductile fiber concrete (UTFC) wet joint connection completes the splicing. The inner cavity of the pier at the UTFC wet joint connection is provided with prefabricated guide blocks (19) for assembling each prefabricated pier segment and for supporting the prefabricated guide blocks (19). 19) transverse supporting steel bars (20), the prefabricated guide block (19) is prefabricated from gypsum material, and the cross-sectional form can be hollow or solid cross-section; 所述的UTFC湿接缝连接中相邻各预制墩身节段(5)之间的纵向连接钢筋(18)做搭接、焊接、机械连接、或记忆合金连接处理,UTFC湿接缝连接设置长度L按下式计算确定:In the described UTFC wet joint connection, the longitudinal connecting steel bars (18) between adjacent prefabricated pier segments (5) are overlapped, welded, mechanically connected, or memory alloy connected, and the UTFC wet joint connection is configured The length L is calculated and determined according to the following formula: 式中:In the formula: d为纵向连接钢筋(18)直径;d is the diameter of the longitudinal connecting steel bar (18); fs为纵向连接钢筋(18)强度,取fs=max(1.5fy,fu),其中fy为纵向连接钢筋18f s is the strength of the longitudinal connecting steel bar (18), take f s =max (1.5f y , fu ), where f y is the longitudinal connecting steel bar 18 屈服强度,fu为纵向连接钢筋(18)极限强度;Yield strength, f u is the ultimate strength of longitudinal connecting steel bars (18); fUTFC为超韧性纤维混凝土UTFC材料28d实测抗压强度;f UTFC is the measured compressive strength of super tough fiber concrete UTFC material for 28 days; α为纵向连接钢筋(18)直径大小影响系数,d=12mm时,α=1.0,d=32mm时,α=1.2,d为12~32mm之间时,由线性内插确定α取值;α is the influence coefficient of the diameter of the longitudinal connecting steel bar (18). When d=12mm, α=1.0. When d=32mm, α=1.2. When d is between 12 and 32mm, the value of α is determined by linear interpolation; c为纵向连接钢筋(18)连接处理影响系数,当纵向连接钢筋做搭接、焊接、机械连接、记忆合金连接处理时,c分别取1.0、0.5、0.65、0.87。c is the influence coefficient of the connection processing of the longitudinal connecting steel bars (18). When the longitudinal connecting steel bars are overlapped, welded, mechanically connected, and memory alloy connected, c is taken to be 1.0, 0.5, 0.65, and 0.87 respectively. 2.根据权利要求1所述的一种等同现浇的装配式空心桥墩体系,其特征在于:所述的UTFC灌浆管道连接中的纵向连接钢筋(18)设置有4d长度的纵筋剥离段(17)。2. A cast-in-place assembled hollow bridge pier system according to claim 1, characterized in that: the longitudinal connecting steel bars (18) in the UTFC grouting pipe connection are provided with a 4d length longitudinal bar stripping section ( 17). 3.基于权利要求1所述的一种等同现浇的装配式空心桥墩体系的施工方法,其特征在于,包括以下步骤:3. A construction method based on a cast-in-place assembled hollow bridge pier system according to claim 1, characterized in that it includes the following steps: 步骤一:吊装预制承台(1)就位,吊装预制墩底节段(16)与预制承台(1)进行预拼装,然后向预埋金属波纹管(2)与凹槽(3)灌注UTFC(4),再将预制墩底节段(16)吊装至预定位置并通过支架固定,预制墩底节段(16)与预制承台(1)完成拼装;Step 1: Lift the prefabricated cap (1) into place, hoist the prefabricated pier bottom segment (16) and the prefabricated cap (1) for pre-assembly, and then pour the embedded metal bellows (2) and the groove (3) UTFC (4), then hoist the prefabricated pier bottom section (16) to the predetermined position and fix it through the bracket, and the prefabricated pier bottom section (16) and the prefabricated cap platform (1) are assembled; 步骤二:吊装预制导向块(19)至预制墩底节段(16)的横向支承钢筋(20),然后吊装相邻预制墩中节段(14)至预制墩底节段(16)上方,通过预制导向块(19)与支承齿块(15)以及粗直径内螺纹及螺栓(8)完成预制墩中节段(14)拼装位置及垂直度的调整,并通过对螺栓和钢板进行点焊以对该预制墩中节段进行初步固定,再对预制导向块(19)与相接的预制墩身节段(5)内壁之间的缝隙进行环氧树脂胶(24)填充密封,使预制导向块(19)作为UTFC湿接缝连接处的内模;Step 2: Lift the prefabricated guide blocks (19) to the lateral supporting steel bars (20) of the prefabricated pier bottom section (16), and then hoist the adjacent prefabricated pier middle section (14) to the top of the prefabricated pier bottom section (16). The assembly position and verticality of the prefabricated pier middle section (14) are adjusted through the prefabricated guide block (19) and the supporting tooth block (15) as well as the thick-diameter internal thread and bolt (8), and the bolts and steel plates are spot welded. The middle section of the prefabricated pier is initially fixed, and then the gap between the prefabricated guide block (19) and the inner wall of the connected prefabricated pier body section (5) is filled and sealed with epoxy resin glue (24), so that the prefabricated pier can be The guide block (19) serves as the inner mold for the UTFC wet joint connection; 步骤三:对预制墩底节段(16)和预制墩中节段(14)的纵向连接钢筋(18)进行搭接、或焊接、或机械连接、或记忆合金连接处理,然后绑扎横向箍筋(13)并支护外模板(21),再通过注浆口(22)灌注UTFC(4),直至UTFC(4)从出浆口(23)冒出,进行振捣和养护,UTFC湿接缝连接浇筑完成,至此预制墩底节段(16)与相邻预制墩中节段(14)完成拼装;Step 3: Overlap, weld, mechanically connect, or memory alloy the longitudinal connecting steel bars (18) of the precast pier bottom section (16) and the precast pier middle section (14), and then tie the transverse stirrups (13) and support the outer formwork (21), then pour UTFC (4) through the grouting port (22) until UTFC (4) emerges from the grouting port (23), vibrate and maintain, and UTFC is wet-joined The joint pouring is completed, and the precast pier bottom section (16) and the adjacent precast pier middle section (14) are assembled; 步骤四:依次重复上述步骤二和步骤三,完成其余相邻各预制墩身节段(5)之间的拼装,最终整个桥墩施工完成。Step 4: Repeat the above-mentioned steps 2 and 3 in sequence to complete the assembly of the remaining adjacent prefabricated pier segments (5), and finally the entire bridge pier construction is completed.
CN201910661186.8A 2019-07-22 2019-07-22 Assembled hollow pier system equivalent to cast-in-situ and construction method thereof Active CN110396918B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910661186.8A CN110396918B (en) 2019-07-22 2019-07-22 Assembled hollow pier system equivalent to cast-in-situ and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910661186.8A CN110396918B (en) 2019-07-22 2019-07-22 Assembled hollow pier system equivalent to cast-in-situ and construction method thereof

Publications (2)

Publication Number Publication Date
CN110396918A CN110396918A (en) 2019-11-01
CN110396918B true CN110396918B (en) 2024-03-12

Family

ID=68325760

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910661186.8A Active CN110396918B (en) 2019-07-22 2019-07-22 Assembled hollow pier system equivalent to cast-in-situ and construction method thereof

Country Status (1)

Country Link
CN (1) CN110396918B (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113123221A (en) * 2020-01-10 2021-07-16 中国国家铁路集团有限公司 Prefabricated assembled hollow pier based on UHPC joint and construction method
CN111350125A (en) * 2020-02-28 2020-06-30 重庆交通大学 Prefabricated pier and construction method thereof
CN111501525A (en) * 2020-03-26 2020-08-07 上海市政工程设计研究总院(集团)有限公司 Prefabricated bridge pier column and bearing platform connecting structure with pier base and construction method thereof
EP4179155A4 (en) * 2020-05-21 2024-09-25 Blaine Miller BRIDGE SUPPORT SYSTEM
CN111893868A (en) * 2020-08-24 2020-11-06 上海市城市建设设计研究总院(集团)有限公司 The connection structure of the prefabricated pier column with the positioning structure and the connected structure
CN112282215A (en) * 2020-09-21 2021-01-29 华南理工大学 Prefabricated FRP pipe-concrete-steel pipe double-wall hollow column and construction method
CN112853983B (en) * 2021-01-11 2023-03-21 山东高速建设管理集团有限公司 Manufacturing and on-site assembling process of light segment prefabricated bridge pier
CN113389135B (en) * 2021-06-17 2022-10-28 北京工业大学 Assembled multidirectional energy consumption pier with three-dimensional serrated racking and fiber concrete grouting
CN113668369B (en) * 2021-09-13 2022-05-24 江南大学 A kind of prefabricated segment reinforced concrete bridge pier socket connection structure and manufacturing method
CN114263093A (en) * 2022-01-22 2022-04-01 郑州大学 Fully-prefabricated assembled bridge and construction method
CN115852818B (en) * 2022-12-30 2025-06-17 长安大学 A prefabricated double-column pier system equivalent to cast-in-place and its construction method
CN116516832A (en) * 2023-06-02 2023-08-01 洛阳市政建设集团有限公司 Construction equipment and construction method for special-shaped bridge pier
CN116676857A (en) * 2023-07-18 2023-09-01 防灾科技学院 Prefabricated assembled viaduct pier stud

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200241339Y1 (en) * 2001-04-12 2001-10-11 (주)종합건축사사무소범건축 Delay joint construction of reforced concrete structure
JP2009209514A (en) * 2008-02-29 2009-09-17 East Japan Railway Co Joint structure of concrete member
CN205046464U (en) * 2015-10-21 2016-02-24 大连理工大学 Prefabricated assembled concrete bridge mound
CN205576723U (en) * 2016-02-15 2016-09-14 上海应用技术学院 Adoption is excelled in prefabrication of fibre mortar and bellows joint and is assembled pier
CN106592440A (en) * 2016-12-30 2017-04-26 河南省交通规划设计研究院股份有限公司 Construction method of prefabricated segment type pier
CN208235312U (en) * 2018-05-04 2018-12-14 中南大学 Precast segment assembly bridge pier
CN109162199A (en) * 2018-10-24 2019-01-08 湖南大学 Assembling-type precast pier connection structure and its construction method
CN109440627A (en) * 2018-11-07 2019-03-08 中铁第四勘察设计院集团有限公司 A kind of precast segment assembly seam system and method based on early strong UHPC
CN211113140U (en) * 2019-07-22 2020-07-28 长安大学 Equal cast-in-place assembly type hollow pier system

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200241339Y1 (en) * 2001-04-12 2001-10-11 (주)종합건축사사무소범건축 Delay joint construction of reforced concrete structure
JP2009209514A (en) * 2008-02-29 2009-09-17 East Japan Railway Co Joint structure of concrete member
CN205046464U (en) * 2015-10-21 2016-02-24 大连理工大学 Prefabricated assembled concrete bridge mound
CN205576723U (en) * 2016-02-15 2016-09-14 上海应用技术学院 Adoption is excelled in prefabrication of fibre mortar and bellows joint and is assembled pier
CN106592440A (en) * 2016-12-30 2017-04-26 河南省交通规划设计研究院股份有限公司 Construction method of prefabricated segment type pier
CN208235312U (en) * 2018-05-04 2018-12-14 中南大学 Precast segment assembly bridge pier
CN109162199A (en) * 2018-10-24 2019-01-08 湖南大学 Assembling-type precast pier connection structure and its construction method
CN109440627A (en) * 2018-11-07 2019-03-08 中铁第四勘察设计院集团有限公司 A kind of precast segment assembly seam system and method based on early strong UHPC
CN211113140U (en) * 2019-07-22 2020-07-28 长安大学 Equal cast-in-place assembly type hollow pier system

Also Published As

Publication number Publication date
CN110396918A (en) 2019-11-01

Similar Documents

Publication Publication Date Title
CN110396918B (en) Assembled hollow pier system equivalent to cast-in-situ and construction method thereof
CN206109970U (en) Prefabricated assembled pier suitable for well meizoseismal area
CN113322792B (en) Prefabricated double-column pier system of assembling of area recycled concrete festival section
CN212200035U (en) A prefabricated composite bridge pier
CN107165272A (en) Prestressed assembled concrete frame joint connection structure and its construction method
CN107794837A (en) Suitable for the prefabricated assembled bridge pier and its construction method of middle meizoseismal area
CN114382005B (en) Segment-assembled pier with stair performance and construction method thereof
CN103758031A (en) Method for manufacturing assembled type bridge pier by utilizing steel fiber reinforced self-compacting concrete
CN216740039U (en) Self-resetting fabricated composite structure beam column side node with floor
CN211113140U (en) Equal cast-in-place assembly type hollow pier system
CN205329526U (en) Pier is assembled to precast concrete
CN112267616B (en) Prefabricated steel-encased concrete spliced column and construction process
CN103774755A (en) Prestressed prefabricated ECC-RC combination beam column joint component
CN106013432A (en) Joint connecting structure in high-ductility assembled integrated frame and construction method
CN112081242B (en) Assembled integral beam-column joint provided with shape memory alloy reinforcement and construction method
CN111733692A (en) A segmental pre-pressed prefabricated concrete bridge pier structure and its construction method
CN115182235A (en) A kind of prefabricated cover beam pier-column composite structure and its construction method
CN114622685A (en) A prefabricated UHPC-steel-UHPC tubular concrete composite column and construction method thereof
CN105970803B (en) Shear energy-dissipating device and construction method of prefabricated bridge piers
CN107905091A (en) A kind of section assembling FRP using SMA presstressed reinforcing steel systems strengthens concrete pier of steel tube
CN109898540B (en) Wet joint structure among bridge pier, bearing platform and pile foundation and construction process thereof
CN111305052A (en) A connection structure of prefabricated bridge pier segments
CN102587576B (en) Combined precast column with nodes
CN205369295U (en) Basis precast prestressed beam slab formula wind power generation column foot plinth
CN110878513A (en) A kind of prefabricated prestressed concrete beam and steel-concrete composite beam splicing bridge and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant