CN110396918A - A kind of equivalent cast-in-place assembled hollow pier system and its construction method - Google Patents

A kind of equivalent cast-in-place assembled hollow pier system and its construction method Download PDF

Info

Publication number
CN110396918A
CN110396918A CN201910661186.8A CN201910661186A CN110396918A CN 110396918 A CN110396918 A CN 110396918A CN 201910661186 A CN201910661186 A CN 201910661186A CN 110396918 A CN110396918 A CN 110396918A
Authority
CN
China
Prior art keywords
prefabricated
pier
segment
utfc
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910661186.8A
Other languages
Chinese (zh)
Other versions
CN110396918B (en
Inventor
周敉
曾航
张洋
宋建伟
卢伟
吴江
朱国强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changan University
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN201910661186.8A priority Critical patent/CN110396918B/en
Publication of CN110396918A publication Critical patent/CN110396918A/en
Application granted granted Critical
Publication of CN110396918B publication Critical patent/CN110396918B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

A kind of equivalent cast-in-place assembled hollow pier system and its construction method, the system includes the prefabricated cushion cap for being embedded with metal bellows, end is equipped with each prefabricated pier shaft segment of longitudinally connected reinforcing bar, prefabricated pier shaft segment includes prefabricated pier bottom segment, segment and the prefabricated pier top segment integral prefabricated with pier cap in each prefabricated pier, the prefabricated guide pad for adjacent each prefabricated pier shaft section assembling;Its construction method is first to lift prefabricated cushion cap in place, then prefabricated pier bottom segment and prefabricated cushion cap are connected as by entirety using the connection of ultra-tough fiber concrete (UTFC) grout lines, hereafter adjacent each prefabricated intersegmental connection of pier shaft is successively completed using ultra-tough fiber concrete (UTFC) wet seam connection, finally it is assemblied into bridge pier entirety, the present invention has speed of application fast, it is small to construction site traffic and surrounding environment influence, the easily controllable advantage of component quality and anti-seismic performance are good, rigidity is big, toughness is high, durability is good, the features such as fatigue resistance is good.

Description

A kind of equivalent cast-in-place assembled hollow pier system and its construction method
Technical field
The present invention relates to assembled bridge pier field, in particular to a kind of equivalent cast-in-place assembled hollow pier system and its Construction method.
Background technique
Prefabricated assembled bridge construction technology is short with its construction period, prefabricated components factory mass small to traffic impact The advantages that life quality is easily controllable, is widely used, prefabricated assembled bridge construction skill in bridge engineering construction Art has become the Main Trends of The Development of bridge engineering construction.But assembled bridge pier anti-seismic performance is not completely clear, in middle Gao Lie It applies and is very restricted in degree earthquake territory science of bridge building.Main reason is that in current bridge Ductility Design, bridge Pier protects remaining structure of bridge usually as the ductile reinforced member in bridge structure, by developing plastic hinge dissipation seismic energy Part, plastic hinge behavior are also characteristic feature of traditional integral cast-in-situ armored concrete ductility bridge pier under seismic loading, And the connection of prefabricated components may have an impact the formation of bridge pier plastic hinge in most of current assembled bridge pier systems, And then the anti-seismic performance of entire bridge structure is influenced, these factors cause assembled bridge pier technology to be difficult at present in middle highlight lines Earthquake territory is widely popularized and applies.
Bridge pier is mainly vertically divided into several prefabricated pier shafts by the research and development about assembled bridge pier system at present Segment applies prestressing force by presstressed reinforcing steel and each prefabricated pier shaft segment is vertically assemblied into bridge pier entirety, the assembly of such prestressing force Formula bridge pier system in the science of bridge building of non-antidetonation security area and low intensity in quake zone using more, but for middle highlight lines The science of bridge building of earthquake territory, such assembled bridge pier system is under seismic loading, cushion cap and bridge pier seam crossing and each pre- It is also easy to produce stress concentration phenomenon at pier shaft segmental joints processed, and there are energy-dissipating properties poor, loss of prestress, mechanical characteristic and tradition Integral cast-in-situ bridge pier significant difference, prestressed use increase difficulty and project cost of construction etc., these factors lead to phase Research achievement is closed to be difficult to promote the use of in middle high intensity Zone science of bridge building at present.In addition, current generation bridge pier type Selection is from original gravity-type bridge pier gradually to lighter pier transition, in assembled hollow pier between each prefabricated pier shaft segment Connection processing be design in critical issue, the connecting structure be designed ought whether, directly influence the stress of bridge pier entirety Performance and construction period and site operation safety.
A kind of assembled bridge pier for being currently adapted for seismic region is equivalent cast-in-place assembled bridge pier system, i.e. one kind has Mechanical characteristic close with traditional integral cast-in-situ reinforced concrete bridge pier and anti-seismic performance and the dress of expected plastic hinge behavior With formula bridge pier system.Research has shown that grout lines connection and the connection of wet seam are to be applied to a kind of economy of assembled bridge pier Effective connection type, but there is the plastic hinge behavior etc. that may influence bridge pier since connection length is larger and ask in two connection types Topic.Therefore, developing with cost-effectiveness, the quick feasible equivalent cast-in-place assembled bridge pier system of construction is still current assembled Bridge pier building technology is applied to the technological difficulties that seismic region science of bridge building is faced.
Summary of the invention
In order to overcome the deficiencies of the prior art, the present invention provides a kind of equivalent cast-in-place assembled hollow pier system and its applies Work method is connected using the connection of ultra-tough fiber concrete (UTFC) grout lines and ultra-tough fiber concrete (UTFC) wet seam It connects and is respectively completed prefabricated pier bottom segment and prefabricated cushion cap and each intersegmental connection of contiguous prefabricated pier shaft, filling can be effectively reduced Connection length needed for starching pipeline connection and the connection of wet seam improves the mechanical property of seam crossing, and combines reasonable construction Designing, which reaches the assembled hollow pier system in terms of mechanical characteristic and anti-seismic performance, is equal to cast-in-place performance level, has The advantages that good integrity, anti-seismic performance are good, rigidity is big, toughness is high, durability is good, construction practicable.
To achieve the above object, the technical scheme of the present invention is realized as follows:
A kind of equivalent cast-in-place assembled hollow pier system, the prefabricated cushion cap 1 including foundation soil is arranged in are prefabricated to hold Bridge pier is provided with above platform 1, bridge pier is assembled by each prefabricated pier shaft segment 5, and each prefabricated pier shaft segment 5 includes prefabricated pier bottom section Segment 14 and the prefabricated pier top segment 7 integral prefabricated with pier cap 6 in section 16, prefabricated pier.
The prefabricated cushion cap 1 and each prefabricated pier shaft segment 5, which are that ordinary reinforced concrete is prefabricated, to be formed, and inside configures There are longitudinal reinforcement 12 and lateral tie 13;Metal bellows 2 is embedded with inside the prefabricated cushion cap 1, top surface is equipped with groove 3;Institute Stating each prefabricated pier shaft segment 5 is hollow rectangular section, and both ends or one end are equipped with longitudinally connected reinforcing bar 18 and support teeth block 15.
In the prefabricated pier support teeth block 15 of segment 14 and prefabricated 7 bottom end of pier top segment be embedded with thick diameter internal screw thread and Bolt 8, the support teeth block 15 on 14 top of segment is provided with WELDING STUDS 11 and steel plate 9 in prefabricated pier bottom segment 16 and prefabricated pier.
Splicing is completed using the connection of UTFC grout lines between the prefabricated cushion cap 1 and prefabricated pier bottom segment 16, it is adjacent each Splicing is completed using the wet seam connection of ultra-tough fiber concrete UTFC between prefabricated pier shaft segment 5;The wet seam of UTFC connects The bridge pier inner cavity at the place of connecing is provided with for the prefabricated guide pad 19 of each prefabricated pier shaft section assembling and for supporting prefabricated guiding The lateral support reinforcing bar 20 of block 19, the prefabricated guide pad 19 is prefabricated by gypsum material, and section form can be hollow or solid section Face.
Longitudinally connected reinforcing bar 18 in the wet seam connection of UTFC between adjacent each prefabricated pier shaft segment 5 is overlapped, is welded It connects, mechanical connection or memorial alloy connection processing, determination is calculated as follows in the wet seam connection setting length L of UTFC:
In formula:
D is longitudinally connected 18 diameter of reinforcing bar;
fsFor longitudinally connected 18 intensity of reinforcing bar, f is takens=max (1.5fy,fu), wherein fyIt is surrendered by force for longitudinally connected reinforcing bar 18 Degree, fuFor longitudinally connected 18 ultimate strength of reinforcing bar;
fUTFCCompression strength is surveyed for ultra-tough fiber concrete UTFC material 28d;
α is that longitudinally connected 18 diameter of reinforcing bar influences coefficient, when d=12mm, when α=1.0, d=32mm, and α=1.2, d When between 12~32mm, α value is determined by linear interpolation;
C is that the connection processing of longitudinally connected reinforcing bar 18 influences coefficient, when longitudinally connected reinforcing bar overlaps, welds, is mechanically connected, When memorial alloy connection processing, c takes 1.0,0.5,0.65,0.87 respectively;
Longitudinally connected reinforcing bar 18 in the UTFC grout lines connection is provided with the vertical muscle removing section 17 of 4d length.
Construction method based on above-mentioned equivalent cast-in-place assembled hollow pier system:
Step 1: hoisting prefabricated cushion cap 1 is in place, and hoisting prefabricated pier bottom segment 16 carries out preassembling with prefabricated cushion cap 1, then UTFC4 is perfused into pre-buried metal bellows 2 and groove 3, then prefabricated pier bottom segment 16 is lifted to predetermined position and passed through Bracket is fixed, and assembly is completed with prefabricated cushion cap 1 in prefabricated pier bottom segment 16;
Step 2: then hoisting prefabricated guide pad 19 lifts adjacent to the lateral support reinforcing bar 20 of prefabricated pier bottom segment 16 Segment 14 to prefabricated 16 top of pier bottom segment, passes through prefabricated guide pad 19 and spiral shell in support teeth block 15 and thick diameter in prefabricated pier Line and bolt 8 complete the adjustment of the assembled position in segment 14 in prefabricated pier and verticality, and by carrying out spot welding to bolt and steel plate 9 It is tentatively fixed to be carried out to segment in the prefabricated pier, then between prefabricated guide pad 19 and prefabricated 5 inner wall of pier shaft segment to connect Gap carry out epoxide-resin glue 24 filling sealing, make internal model of the prefabricated guide pad 19 as the wet commissural junctions of UTFC;
Step 3: the longitudinally connected reinforcing bar 18 of segment 14 in prefabricated pier bottom segment 16 and contiguous prefabricated pier is overlapped, Or welding or mechanical connection or memorial alloy connection processing, lateral tie 13 and supporting exterior sheathing 21 are then bound, then pass through UTFC4 is perfused in grouting port 22, until UTFC4 is emerged from grout outlet 23, is vibrated and is conserved, and the wet seam connection of UTFC has poured At so far assembly is completed with segment 14 in contiguous prefabricated pier in prefabricated pier bottom segment 16;
Step 4: being repeated in above-mentioned steps two and step 3, completes the spelling between remaining adjacent each prefabricated pier shaft segment Dress, final entire Bridge Pier Construction are completed.
It is the characteristics of present invention is much higher than normal concrete and conventional grout material using the UTFC strength of materials, longitudinal by reducing Anchorage length needed for connecting reinforcing bar, the connection effectively reduced needed for the connection of UTFC grout lines is connected with the wet seam of UTFC are long Degree;Section is removed by the vertical muscle of the longitudinally connected steel-bar arrangement 4d length in the connection of UTFC grout lines, can effectively be avoided The vertical muscle connection reinforcing bar generates stress between prefabricated cushion cap and prefabricated pier bottom segment and concentrates at Mosaic face, prevent it in Cyclic Loading Effect is lower to occur fatigue rupture, and the deformation of the longitudinally connected reinforcing bar is expanded to bigger length range, and then extend pier bottom Areas of plasticity hinge, slow down plastic hinge concentrate extent of the destruction, improve the ductility of the assembled bridge pier system;By in prefabricated cushion cap Top surface designs shallow grooves to enhance the Shear transfer between prefabricated pier bottom segment and prefabricated cushion cap at Mosaic face;Each prefabricated pier shaft The support teeth block of segment one or both ends, pours the wet seam connection of UTFC after avoiding and the contact surface of prefabricated pier shaft segment is located completely In same plane, the Shear transfer of the wet commissural junctions of UTFC can be cooperateed with, and passes through the branch of rotation prefabricated pier shaft segment bottom end Its verticality can be finely adjusted in prefabricated pier shaft section assembling by holding thick diameter screw pre-buried in tooth block, vertical to ensure Degree meets design requirement;Guide pad when prefabricated pier shaft section assembling had not only been served as in the setting of the prefabricated guide pad of gypsum material, but also Act as the internal model poured when the wet seam of UTFC pours, and gypsum material avoids the prefabricated guide pad to bridge pier compared with low-intensity Holistic resistant behavior has an impact;The UTFC grout lines connection of pier bottom is a kind of ductility connection, which is designed in height It is surrendered in a manner of ductility under action of horizontal seismic, pier bottom is still nearby potential plastic hinge region;Prefabricated pier shaft is intersegmental The wet seam connection of UTFC is a very strong connection, and when pier bottom is surrendered under high-level seismic force effects, which is protected It protects and keeps elasticity;Above-mentioned each detail structure design will ensure that assembled hollow pier system items mechanics proposed by the invention Characteristic and anti-seismic performance are close with traditional integral cast-in-situ reinforced concrete bridge pier, that is, reach equally cast-in-place performance level, and The connection of UTFC grout lines is connected with the wet seam of UTFC is all made of pouring for grouting process completion UTFC, easy for construction feasible, The superior mechanical property of UTFC will ensure that the stabilization of switching performance;Using the construction method of precast assembly, greatly improves and apply Work efficiency rate shortens construction period, good in economic efficiency, largely saves manpower and material resources.The invention has great Practical value and good economic benefit especially have broad application prospects in Bridge Pier Construction technical field.
Detailed description of the invention
Fig. 1 is the equivalent cast-in-place assembled hollow pier organigram of the present invention.
Fig. 2 is the layout drawing of segment and prefabricated pier top segment bottom end support teeth block in the prefabricated pier of the present invention.
Fig. 3 is each prefabricated 5 arrangement of reinforcement schematic diagram of pier shaft segment of the present invention.
Fig. 4 is prefabricated 16 structural schematic diagram of pier bottom segment of the present invention.
Fig. 5 is 14 structural schematic diagram of segment in the prefabricated pier of the present invention.
Fig. 6 is that the wet seam of UTFC of the present invention connects prefabricated guide pad 19 and schematic diagram is arranged in exterior sheathing 21.
Fig. 7 is that the wet seam of UTFC of the present invention connects prefabricated guide pad 19 and top view is arranged in exterior sheathing 21.
Fig. 8 is that the wet seam of UTFC of the present invention connects the longitudinally connected use of reinforcing bar 18 overlapped organigram.
Fig. 9 is that the wet seam of UTFC of the present invention connects longitudinally connected reinforcing bar 18 using the organigram of welding.
Figure 10 is that the wet seam of UTFC of the present invention connects longitudinally connected reinforcing bar 18 using the organigram of mechanical connection.
Figure 11 is that the wet seam of UTFC of the present invention connects longitudinally connected reinforcing bar 18 using the organigram of memorial alloy connection.
Wherein: 1, prefabricated cushion cap;2, metal bellows;3, groove;4,UTFC;5, each prefabricated pier shaft segment;6, pier cap;7, Prefabricated pier top segment;8, thick diameter internal screw thread and bolt;9, steel plate;10, longitudinally connected steel concrete supporting;11, WELDING STUDS; 12, longitudinal reinforcement;13, lateral tie;14, segment in prefabricated pier;15, support teeth block;16, prefabricated pier bottom segment;17, muscle stripping is indulged From section;18, longitudinally connected reinforcing bar;19, prefabricated guide pad;20, lateral support reinforcing bar;21, exterior sheathing;22, grouting port;23, go out Starch mouth;24, epoxide-resin glue;25, longitudinally connected bar splicing;26, longitudinally connected reinforcement welding;27, longitudinally connected reinforcing bar note Recall alloy connection.
Specific embodiment
Embodiment one
As shown in Figure 1, a kind of equivalent cast-in-place assembled hollow pier system, including prefabricated cushion cap 1, in prefabricated cushion cap 1 Portion is embedded with metal bellows 2, top surface setting fluted 3, is provided with each prefabricated pier shaft segment 5 above prefabricated cushion cap 1, each prefabricated Pier shaft segment 5 includes segment 14 and the prefabricated pier top segment integral prefabricated with pier cap 6 in prefabricated pier bottom segment 16, prefabricated pier 7;
As shown in Figure 2 and Figure 3, prefabricated cushion cap 1 and each prefabricated pier shaft segment 5 be ordinary reinforced concrete it is prefabricated and At inside is each equipped with longitudinal reinforcement 12 and lateral tie 13, and each prefabricated pier shaft segment 5 is hollow rectangular section;
As shown in Figure 4, Figure 5, each prefabricated 5 both ends or one end of pier shaft segment are equipped with longitudinally connected reinforcing bar 18 and support teeth block 15, the support teeth block 15 of segment 14 and prefabricated 7 bottom end of pier top segment is embedded with thick diameter internal screw thread and bolt 8 in prefabricated pier, in advance The support teeth block 15 on 14 top of segment is provided with WELDING STUDS 11 and steel plate 9 in pier bottom segment 16 processed and prefabricated pier;
As shown in Figure 6, Figure 7, the bridge pier inner cavity of the wet commissural junctions of UTFC is provided with for each prefabricated pier shaft section assembling Prefabricated guide pad 19 and lateral support reinforcing bar 20 for supporting prefabricated guide pad 19, prefabricated guide pad 19 is by gypsum material Prefabricated, section form can be hollow or solid section, and the present embodiment is selected as solid section;
When the longitudinally connected reinforcing bar of the wet commissural junctions of UTFC is mechanical connection processing, the wet seam setting length L of UTFC is pressed Formula, which calculates, to be determined:
In formula:
D is longitudinally connected bar diameter;
fsFor longitudinally connected reinforced steel bar strength, f is takens=max (1.5fy,fu), wherein fyFor longitudinally connected reinforcement yielding intensity, fuFor longitudinally connected reinforcing bar ultimate strength;
fUTFCCompression strength is surveyed for ultra-tough fiber concrete (UTFC) material 28d;
α is that longitudinally connected bar diameter size influences coefficient, and when d=12mm, when α=1.0, d=32mm, α=1.2, d are When between 12~32mm, α value is determined by linear interpolation;
C is that longitudinally connected rebar junction reason influences coefficient, when longitudinally connected reinforcing bar does mechanical connection processing, referring to figure 10, take 0.65;
The construction procedure of the equivalent cast-in-place assembled hollow pier system of above-mentioned the present embodiment are as follows:
Step 1: hoisting prefabricated cushion cap 1 is in place, and hoisting prefabricated pier bottom segment 16 carries out preassembling with prefabricated cushion cap, then UTFC 4 is perfused into pre-buried metal bellows 3 and groove 3, then prefabricated pier bottom segment 16 is lifted to predetermined position and passed through Bracket is fixed, and assembly is completed with prefabricated cushion cap 1 in prefabricated pier bottom segment 16;
Step 2: then hoisting prefabricated guide pad 19 lifts adjacent to the cross-brace reinforcing bar 20 of prefabricated pier bottom segment 16 Segment 14 is to prefabricated 16 top of pier bottom segment in prefabricated pier, by prefabricated guide pad 19 and support teeth block 15 and rotation 8 Bolt completes the adjustment of the assembled position in segment 14 in the prefabricated pier and verticality, and by thick diameter internal screw thread and bolt 8 Bolt and steel plate 9 carry out spot welding tentatively to be fixed to segment 14 in the prefabricated pier, then to prefabricated guide pad 19 with connect Prefabricated 5 inner wall of pier shaft segment between gap carry out the filling sealing of epoxide-resin glue 24, make prefabricated guide pad 19 as UTFC The internal model of wet commissural junctions;
Step 3: the longitudinally connected reinforcing bar 18 of segment 14 in prefabricated pier bottom segment 16 and contiguous prefabricated pier is done longitudinally connected The processing of steel concrete supporting 10, referring to Fig.1 0, lateral tie 13 and supporting exterior sheathing 21 are then bound, then fill by grouting port 22 UTFC 4 is infused, until UTFC 4 is emerged from grout outlet 23, is vibrated and is conserved, the wet seam connection of UTFC pours completion, so far Assembly is completed with segment 14 in contiguous prefabricated pier in prefabricated pier bottom segment 16;
Step 4: being repeated in above-mentioned steps two and step 3, completes the spelling between remaining adjacent each prefabricated pier shaft segment 5 Dress, final entire Bridge Pier Construction are completed.
Embodiment two
As shown in Fig. 1, Fig. 8, a kind of equivalent cast-in-place assembled hollow pier system, including prefabricated cushion cap 1, prefabricated cushion cap It is embedded with metal bellows 2, top surface setting fluted 3 inside 1, is provided with each prefabricated pier shaft segment 5 above prefabricated cushion cap 1, respectively Prefabricated pier shaft segment 5 includes segment 14 and the prefabricated pier top integral prefabricated with pier cap 6 in prefabricated pier bottom segment 16, prefabricated pier Segment 7;
As shown in Figure 2 and Figure 3, prefabricated cushion cap 1 and each prefabricated pier shaft segment 5 be ordinary reinforced concrete it is prefabricated and At inside is each equipped with longitudinal reinforcement 12 and lateral tie 13, and each prefabricated pier shaft segment 5 is hollow rectangular section;
As shown in Figure 4, Figure 5, each prefabricated 5 both ends or one end of pier shaft segment are equipped with longitudinally connected reinforcing bar 18 and support teeth block 15, the support teeth block 15 of segment 14 and prefabricated 7 bottom end of pier top segment is embedded with thick diameter internal screw thread and bolt 8 in prefabricated pier, in advance The support teeth block 15 on 14 top of segment is provided with WELDING STUDS 11 and steel plate 9 in pier bottom segment 16 processed and prefabricated pier;
As shown in Figure 6, Figure 7, the bridge pier inner cavity of the wet commissural junctions of UTFC is provided with for each prefabricated pier shaft section assembling Prefabricated guide pad 19 and lateral support reinforcing bar 20 for supporting prefabricated guide pad 19, prefabricated guide pad 19 is by gypsum material Prefabricated, section form can be hollow or solid section, and the present embodiment is selected as solid section;
When the longitudinally connected reinforcing bar of the wet commissural junctions of UTFC is overlap joint processing, the wet seam setting length L of UTFC is counted as the following formula It calculates and determines:
In formula:
D is longitudinally connected bar diameter;
fsFor longitudinally connected reinforced steel bar strength, f is takens=max (1.5fy,fu), wherein fyFor longitudinally connected reinforcement yielding intensity,
fuFor longitudinally connected reinforcing bar ultimate strength;
fUTFCCompression strength is surveyed for ultra-tough fiber concrete (UTFC) material 28d;
α is that longitudinally connected bar diameter size influences coefficient, and when d=12mm, when α=1.0, d=32mm, α=1.2, d are When between 12~32mm, α value is determined by linear interpolation;
C is that longitudinally connected rebar junction reason influences coefficient, when longitudinally connected reinforcing bar does overlap joint processing, referring to Fig. 8, is taken 1.0;
The construction procedure of the equivalent cast-in-place assembled hollow pier system of above-mentioned the present embodiment are as follows:
Step 1: hoisting prefabricated cushion cap 1 is in place, and hoisting prefabricated pier bottom segment 16 carries out preassembling with prefabricated cushion cap, then UTFC 4 is perfused into pre-buried metal bellows 2 and groove 3, then prefabricated pier bottom segment 16 is lifted to predetermined position and passed through Bracket is fixed, and assembly is completed with prefabricated cushion cap 1 in prefabricated pier bottom segment 16;
Step 2: then hoisting prefabricated guide pad 19 lifts adjacent to the cross-brace reinforcing bar 20 of prefabricated pier bottom segment 16 Segment 14 passes through prefabricated guide pad 19 and support teeth block 15 and the thick diameter of rotation to prefabricated 16 top of pier bottom segment in prefabricated pier Bolt in internal screw thread and bolt 8 completes the adjustment of the assembled position in segment 14 in the prefabricated pier and verticality, and by thick straight Caliber inner screw thread and bolt in bolt 8 and steel plate 9 carry out spot welding tentatively to be fixed to segment 14 in the prefabricated pier, then to pre- Gap between guide pad 19 processed and prefabricated 5 inner wall of pier shaft segment to connect carries out the filling sealing of epoxide-resin glue 24, makes prefabricated Internal model of the guide pad 19 as the wet commissural junctions of UTFC;
Step 3: the longitudinally connected reinforcing bar 18 of segment 14 in prefabricated pier bottom segment 16 and contiguous prefabricated pier is done longitudinally connected Bar splicing 25 is handled, and referring to Fig. 8, then binds lateral tie 13 and supporting exterior sheathing 21, then be perfused by grouting port 22 UTFC 4 is vibrated and is conserved until UTFC 4 is emerged from grout outlet 23, and the wet seam connection of UTFC pours completion, so far in advance Assembly is completed with segment 14 in contiguous prefabricated pier in pier bottom segment 16 processed;
Step 4: being repeated in above-mentioned steps two and step 3, completes the spelling between remaining adjacent each prefabricated pier shaft segment 5 Dress, final entire Bridge Pier Construction are completed.
Referring to Fig. 8, Fig. 9, Figure 10, Figure 11, in prefabricated pier bottom segment 16 and contiguous prefabricated pier segment 14 it is longitudinally connected Reinforcing bar 18, can be in addition to doing other than the mechanical connection of embodiment one is handled, the longitudinally connected bar splicing 25 of embodiment two is handled 27 processing of the longitudinally connected processing of reinforcement welding 26 or the connection of longitudinally connected reinforcing bar memorial alloy is done, is UTFC of the present invention referring to Fig. 9 Wet seam connects longitudinally connected reinforcing bar 18 using the organigram of welding;Figure 11, which is that the wet seam connection of UTFC of the present invention is longitudinal, to be connected Reinforcing bar 18 is connect using the organigram of memorial alloy connection.
The principle of the present invention and advantage:
Equivalent cast-in-place assembled hollow pier system and its construction method proposed by the present invention are to utilize ultra-tough fiber The compression strength of concrete (UTFC) material is high, every excellent in mechanical performance, the good advantage with the adhesive property of reinforcing bar, effectively contracts Length needed for short splicing seams, eliminates in assembled bridge pier technology that stitching portion reinforcing bar connecting structure is multiple between each prefabricated subsection The disadvantages of miscellaneous, Concrete intensity insufficient and seam poor mechanical property, makes the connection structure of assembled hollow pier by tectonic sieving Make it is more simple, it is easy for construction feasible, improve the efficiency of Bridge Pier Construction, and ensure that assembled proposed by the invention is hollow Bridge pier system items mechanical characteristic and anti-seismic performance and plastic hinge behavior are close with traditional integral cast-in-situ reinforced concrete bridge pier, most Reach equally cast-in-place performance level eventually.
Ultra-tough fiber concrete (UTFC) in the art is a proprietary name, is generally referred in the present invention using milli Scale particles (aggregate) and the cement-base concrete for adding steel fibre are with respect to for normal concrete, high performance concrete The more excellent concrete material of another kind of mechanical property, such as Reactive Powder Concrete, very-high performance fiber reinforcement It is concrete, slip casting fiber concrete, closely knit with rib reinforced composite material etc., but preferably very-high performance steel fiber reinforced concrete or note Pulp fibres concrete.
Compared with prior art, ultra-tough fiber concrete UTFC is arranged in hollow pier junction in the present invention, in ultra-toughness Property fiber concrete UTFC in reinforcing bar using overlap joint, welding or mechanical connection, this changed dramatically precast assembly hollow pier Structure type and working condition, but also technical solution of the present invention has following apparent advantage:
Firstly, ultra-tough fiber concrete of the invention connects the common stress of hollow pier structure, ultra-tough fiber coagulation The indexs such as stress, the deformation of native UTFC itself are able to satisfy in the requirement of cast-in-place hollow bridge pier structure work;
Secondly, ultra-tough fiber concrete UTFC of the invention increases the rigidity of bridge pier, guarantee linkage section and pier shaft section The adhesive property of section, improves the cracking resistance and endurance quality of linkage section.
In addition, being to be suitable for hollow pier to connect selected by ultra-tough fiber concrete UTFC in technical solution of the present invention The proportion connect, composition material different-grain diameter particle form closestpacking with optimal proportion, are not only easy to constructing operation, and energy Enough guarantee density, improves the anti-seismic performance and erosion resistance and durability in harsh environments of bridge pier.
Linkage section can be hollow after making connection by the value to ultra-tough fiber concrete layer different wall thickness and height Bridge pier skeleton curve peak value and ductility reach or better than cast-in-place pier stud performance.In conclusion ultra-tough proposed by the present invention is fine Concrete is tieed up as the wet seam of precast assembly hollow pier, with the rigidity of structure is big, interlayer adhesion is good, durability is good, it is tired to resist The advantages that labor performance is good has great practical value and good economic benefit, especially leads in hollow pier precast assembly Domain has broad application prospects.And having anti-seismic performance good, endurance quality is superior, places on segment under precast hollow bridge pier Gypsum guide pad, and hollow pier upper-lower segment is docked by branch supporting tooth block, muscle is indulged to the stress of pier shaft upper-lower segment It overlapped, welded or is mechanically connected;Installation template is poured ultra-tough fiber concrete, is subject to after the completion using shaking platform Jolt ramming;Ultra-tough fiber concrete after pouring is conserved, the demoulding after the mechanical index of concrete reaches design requirement, Complete entire construction.

Claims (7)

1. a kind of equivalent cast-in-place assembled hollow pier system, it is characterised in that: described prefabricated to hold including prefabricated cushion cap (1) It is connected with bridge pier above platform (1), bridge pier is assembled by each prefabricated pier shaft segment (5), and each prefabricated pier shaft segment (5) includes prefabricated Segment (14) and the prefabricated pier top segment (7) integral prefabricated with pier cap (6) in pier bottom segment (16), prefabricated pier.
2. a kind of equivalent cast-in-place assembled hollow pier system according to claim 1, it is characterised in that: described prefabricated Cushion cap (1) and each prefabricated pier shaft segment (5), which are that ordinary reinforced concrete is prefabricated, to be formed, and inside is each equipped with longitudinal reinforcement (12) and lateral tie (13), prefabricated cushion cap (1) inside are embedded with metal bellows (2), top surface equipped with groove (3), institute Stating each prefabricated pier shaft segment (5) is hollow rectangular section, and each prefabricated pier shaft segment (5) both ends or one end are equipped with longitudinally connected Reinforcing bar (18) and support teeth block (15).
3. a kind of equivalent cast-in-place assembled hollow pier system according to claim 1 or 2, it is characterised in that: described The support teeth block (15) of segment (14) and prefabricated pier top segment (7) bottom end is embedded with thick diameter internal screw thread and bolt in prefabricated pier (8), the support teeth block (15) on segment (14) top is provided with WELDING STUDS (11) in the prefabricated pier bottom segment (16) and prefabricated pier With steel plate (9).
4. a kind of equivalent cast-in-place assembled hollow pier system according to claim 1 or 2, it is characterised in that: described Completion is connect using ultra-tough fiber concrete (UTFC) grout lines between prefabricated cushion cap (1) and prefabricated pier bottom segment (16) to spell It connects, splicing is completed using ultra-tough fiber concrete (UTFC) wet seam connection between adjacent each prefabricated pier shaft segment (5), The bridge pier inner cavity of the wet commissural junctions of UTFC be provided with the prefabricated guide pad (19) for each prefabricated pier shaft section assembling with And the lateral support reinforcing bar (20) for supporting prefabricated guide pad (19), the prefabricated guide pad (19) is prefabricated by gypsum material, Section form can be hollow or solid section.
5. a kind of equivalent cast-in-place assembled hollow pier system according to claim 4, it is characterised in that: described Longitudinally connected reinforcing bar (18) in the wet seam connection of UTFC between adjacent each prefabricated pier shaft segment (5) is overlapped, is welded, machinery connects It connects or determination is calculated as follows in memorial alloy connection processing, the wet seam connection setting length L of UTFC:
In formula:
D is longitudinally connected reinforcing bar (18) diameter;
fsFor longitudinally connected reinforcing bar (18) intensity, f is takens=max (1.5fy,fu), wherein fyIt is surrendered by force for longitudinally connected reinforcing bar 18 Degree, fuFor longitudinally connected reinforcing bar (18) ultimate strength;
fUTFCCompression strength is surveyed for ultra-tough fiber concrete UTFC material 28d;
α is that longitudinally connected reinforcing bar (18) diameter influences coefficient, and when d=12mm, when α=1.0, d=32mm, α=1.2, d are When between 12~32mm, α value is determined by linear interpolation;
C is that longitudinally connected reinforcing bar (18) connection processing influences coefficient, when longitudinally connected reinforcing bar overlaps, welds, is mechanically connected, remembers When recalling alloy connection processing, c takes 1.0,0.5,0.65,0.87 respectively.
6. a kind of equivalent cast-in-place assembled hollow pier system according to claim 4, it is characterised in that: described Longitudinally connected reinforcing bar (18) in the connection of UTFC grout lines is provided with vertical muscle removing section (17) of 4d length.
7. based on a kind of construction method of equivalent cast-in-place assembled hollow pier system described in claim 1, feature exists In, comprising the following steps:
Step 1: in place, hoisting prefabricated pier bottom segment (16) and prefabricated cushion cap (1) carry out preassembling to hoisting prefabricated cushion cap (1), so Backward built-in metal bellows (2) and groove (3) perfusion UTFC (4), then prefabricated pier bottom segment (16) is lifted to predetermined position And be fixed by the bracket, assembly is completed in prefabricated pier bottom segment (16) and prefabricated cushion cap (1);
Step 2: the lateral support reinforcing bar (20) of hoisting prefabricated guide pad (19) to prefabricated pier bottom segment (16) then lifts phase In adjacent prefabricated pier above segment (14) to prefabricated pier bottom segment (16), by prefabricated guide pad (19) and support teeth block (15) and Thick diameter internal screw thread and bolt (8) complete the adjustment of the assembled position in segment (14) in prefabricated pier and verticality, and by bolt It is tentatively fixed to carry out to segment in the prefabricated pier that spot welding is carried out with steel plate, then to prefabricated guide pad (19) and the prefabricated pier that connects Gap between body segment (5) inner wall carries out epoxide-resin glue (24) filling sealing, keeps prefabricated guide pad (19) wet as UTFC The internal model of commissural junctions;
Step 3: overlapping the longitudinally connected reinforcing bar (18) of segment (14) in prefabricated pier bottom segment (16) and prefabricated pier or Welding or mechanical connection or memorial alloy connection processing, then bind lateral tie (13) and supporting exterior sheathing (21), then lead to It crosses grouting port (22) perfusion UTFC (4) to be vibrated and conserved until UTFC (4) emerge from grout outlet (23), the wet seam of UTFC Connection pours completion, and so far prefabricated pier bottom segment (16) is completed assembled with segment (14) in contiguous prefabricated pier;
Step 4: being repeated in above-mentioned steps two and step 3, completes the spelling between remaining adjacent each prefabricated pier shaft segment (5) Dress, final entire Bridge Pier Construction are completed.
CN201910661186.8A 2019-07-22 2019-07-22 Assembled hollow pier system equivalent to cast-in-situ and construction method thereof Active CN110396918B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910661186.8A CN110396918B (en) 2019-07-22 2019-07-22 Assembled hollow pier system equivalent to cast-in-situ and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910661186.8A CN110396918B (en) 2019-07-22 2019-07-22 Assembled hollow pier system equivalent to cast-in-situ and construction method thereof

Publications (2)

Publication Number Publication Date
CN110396918A true CN110396918A (en) 2019-11-01
CN110396918B CN110396918B (en) 2024-03-12

Family

ID=68325760

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910661186.8A Active CN110396918B (en) 2019-07-22 2019-07-22 Assembled hollow pier system equivalent to cast-in-situ and construction method thereof

Country Status (1)

Country Link
CN (1) CN110396918B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111350125A (en) * 2020-02-28 2020-06-30 重庆交通大学 Prefabricated pier and construction method thereof
CN111501525A (en) * 2020-03-26 2020-08-07 上海市政工程设计研究总院(集团)有限公司 Prefabricated bridge pier column and bearing platform connecting structure with pier base and construction method thereof
CN112853983A (en) * 2021-01-11 2021-05-28 山东高速建设管理集团有限公司 Manufacturing and on-site assembling process of light segment prefabricated bridge pier
CN113123221A (en) * 2020-01-10 2021-07-16 中国国家铁路集团有限公司 Prefabricated assembled hollow pier based on UHPC joint and construction method
CN113389135A (en) * 2021-06-17 2021-09-14 北京工业大学 Assembled multidirectional energy dissipation pier with three-dimensional serrated racking and fiber concrete grouting
CN113668369A (en) * 2021-09-13 2021-11-19 江南大学 Socket type connection structure of prefabricated segment reinforced concrete pier and manufacturing method
WO2021237102A1 (en) * 2020-05-21 2021-11-25 Blaine Miller Bridge support system
CN114263093A (en) * 2022-01-22 2022-04-01 郑州大学 Fully-prefabricated assembled bridge and construction method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200241339Y1 (en) * 2001-04-12 2001-10-11 (주)종합건축사사무소범건축 Delay joint construction of reforced concrete structure
JP2009209514A (en) * 2008-02-29 2009-09-17 East Japan Railway Co Joint structure of concrete member
CN205046464U (en) * 2015-10-21 2016-02-24 大连理工大学 Prefabricated assembled concrete bridge mound
CN205576723U (en) * 2016-02-15 2016-09-14 上海应用技术学院 Adoption is excelled in prefabrication of fibre mortar and bellows joint and is assembled pier
CN106592440A (en) * 2016-12-30 2017-04-26 河南省交通规划设计研究院股份有限公司 Construction method of prefabricated segment type pier
CN208235312U (en) * 2018-05-04 2018-12-14 中南大学 Precast segment assembly bridge pier
CN109162199A (en) * 2018-10-24 2019-01-08 湖南大学 Assembling-type precast pier connection structure and its construction method
CN109440627A (en) * 2018-11-07 2019-03-08 中铁第四勘察设计院集团有限公司 A kind of precast segment assembly seam system and method based on early strong UHPC
CN211113140U (en) * 2019-07-22 2020-07-28 长安大学 Equal cast-in-place assembly type hollow pier system

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200241339Y1 (en) * 2001-04-12 2001-10-11 (주)종합건축사사무소범건축 Delay joint construction of reforced concrete structure
JP2009209514A (en) * 2008-02-29 2009-09-17 East Japan Railway Co Joint structure of concrete member
CN205046464U (en) * 2015-10-21 2016-02-24 大连理工大学 Prefabricated assembled concrete bridge mound
CN205576723U (en) * 2016-02-15 2016-09-14 上海应用技术学院 Adoption is excelled in prefabrication of fibre mortar and bellows joint and is assembled pier
CN106592440A (en) * 2016-12-30 2017-04-26 河南省交通规划设计研究院股份有限公司 Construction method of prefabricated segment type pier
CN208235312U (en) * 2018-05-04 2018-12-14 中南大学 Precast segment assembly bridge pier
CN109162199A (en) * 2018-10-24 2019-01-08 湖南大学 Assembling-type precast pier connection structure and its construction method
CN109440627A (en) * 2018-11-07 2019-03-08 中铁第四勘察设计院集团有限公司 A kind of precast segment assembly seam system and method based on early strong UHPC
CN211113140U (en) * 2019-07-22 2020-07-28 长安大学 Equal cast-in-place assembly type hollow pier system

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113123221A (en) * 2020-01-10 2021-07-16 中国国家铁路集团有限公司 Prefabricated assembled hollow pier based on UHPC joint and construction method
CN111350125A (en) * 2020-02-28 2020-06-30 重庆交通大学 Prefabricated pier and construction method thereof
CN111501525A (en) * 2020-03-26 2020-08-07 上海市政工程设计研究总院(集团)有限公司 Prefabricated bridge pier column and bearing platform connecting structure with pier base and construction method thereof
WO2021237102A1 (en) * 2020-05-21 2021-11-25 Blaine Miller Bridge support system
CN112853983A (en) * 2021-01-11 2021-05-28 山东高速建设管理集团有限公司 Manufacturing and on-site assembling process of light segment prefabricated bridge pier
CN113389135A (en) * 2021-06-17 2021-09-14 北京工业大学 Assembled multidirectional energy dissipation pier with three-dimensional serrated racking and fiber concrete grouting
CN113668369A (en) * 2021-09-13 2021-11-19 江南大学 Socket type connection structure of prefabricated segment reinforced concrete pier and manufacturing method
CN114263093A (en) * 2022-01-22 2022-04-01 郑州大学 Fully-prefabricated assembled bridge and construction method

Also Published As

Publication number Publication date
CN110396918B (en) 2024-03-12

Similar Documents

Publication Publication Date Title
CN110396918A (en) A kind of equivalent cast-in-place assembled hollow pier system and its construction method
CN104120647B (en) It is suitable for section assembling concrete frame bridge pier system and the construction method of rapid construction
CN106869017B (en) A kind of the precast assembly bridge pier-cushion cap node connection type and its practice of pier bottom setting flexible layer
CN106087629B (en) Without the prefabricated baffle foam concrete light road bank structure of conical slope and construction method
CN104153287B (en) There is the section assembling concrete frame bridge pier system and method for self-resetting capability
CN211113140U (en) Equal cast-in-place assembly type hollow pier system
CN108049498A (en) The prefabricated post and Prefabricated beam connection structure and method of assembled architecture frame structure
CN104988844B (en) Two times tensioning prestressing force assembled Wavelike steel webplate combination beam
CN205313967U (en) Connection construction between precast pier and bearing platform
CN106013432B (en) A kind of high ductility prefabricated integral frame interior joint connection structure and construction method
CN104947603B (en) A kind of rc beam bridge girder reinforcing construction and reinforcement means
CN107675812B (en) Ultra-high performance concrete plate seam connection structure and its construction method
CN107355010A (en) Precast concrete shear wall shaped steel node connection structure
CN108374332A (en) A kind of bridge substructure and its construction method using ultra-tough fiber concrete
CN107165271A (en) A kind of assembled Special-Shaped Column concrete frame structure
CN112081242A (en) Assembled integral beam-column joint provided with shape memory alloy reinforcement and construction method
CN208717720U (en) A kind of bridge substructure using ultra-tough fiber concrete
CN106337512B (en) Bottom reinforced steel pipe concrete frame high-strength concrete compound shear wall and production method
CN109457608A (en) A kind of construction method of prefabricated steel reinforced concrete combined bridge deck
CN109208463A (en) Bottom segment uses the Precast Concrete Segmental Bridges bridge pier of Component composition form
CN105951984B (en) A kind of high ductility prefabricated integral frame mid-side node connection structure and construction method
CN108412079A (en) A kind of fabricated shear wall horizontal connection structure and construction method
CN209523119U (en) A kind of prefabricated steel reinforced concrete combined bridge deck
CN218061703U (en) Concrete strip foundation reinforced by additional concrete sleeve
CN110424600A (en) It is a kind of it is distributed after pour assembled integral prefabricated concrete hollow slab rib-beam floor frame and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant