CN110374132A - A kind of cinder field or the Ecosystem restoration system and construction method of tailings stack antiseepage barrier - Google Patents

A kind of cinder field or the Ecosystem restoration system and construction method of tailings stack antiseepage barrier Download PDF

Info

Publication number
CN110374132A
CN110374132A CN201910442075.8A CN201910442075A CN110374132A CN 110374132 A CN110374132 A CN 110374132A CN 201910442075 A CN201910442075 A CN 201910442075A CN 110374132 A CN110374132 A CN 110374132A
Authority
CN
China
Prior art keywords
wall
antiseepage
pollution sources
layer
barrier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910442075.8A
Other languages
Chinese (zh)
Inventor
冯秀娟
贾水星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA ENERGY COSERVATION DADI ENVIRONMENTAL REMEDIATION Co Ltd
Original Assignee
CHINA ENERGY COSERVATION DADI ENVIRONMENTAL REMEDIATION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA ENERGY COSERVATION DADI ENVIRONMENTAL REMEDIATION Co Ltd filed Critical CHINA ENERGY COSERVATION DADI ENVIRONMENTAL REMEDIATION Co Ltd
Priority to CN201910442075.8A priority Critical patent/CN110374132A/en
Publication of CN110374132A publication Critical patent/CN110374132A/en
Pending legal-status Critical Current

Links

Classifications

    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G9/00Cultivation in receptacles, forcing-frames or greenhouses; Edging for beds, lawn or the like
    • A01G9/02Receptacles, e.g. flower-pots or boxes; Glasses for cultivating flowers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/002Ground foundation measures for protecting the soil or subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/006Sealing of existing landfills, e.g. using mining techniques
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental Sciences (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

The Ecosystem restoration system and construction method obstructed the invention discloses a kind of cinder field or tailings stack antiseepage.The Ecosystem restoration system is provided with antiseepage barrier wall, cured layer and third antiseepage barrier layer, by its side far from the pollution sources in barrier wall, the second antiseepage barrier layer is set, second antiseepage barrier layer can be effectively prevented the problem of liquid such as extraneous rainwater, mountain spring water can enter inside antiseepage barrier wall by cavity wall on the outside of antiseepage barrier wall, aggravate the pollution problem of pollution sources.Especially for Karst geomorphological environment, it is more liquid due to water source, more liquid can flow to pollution sources, can largely liquid barrier be entered in pollution sources from the pollution sources external world by above-mentioned second antiseepage barrier layer, prevent the pollution problem of pollution sources from aggravating.It can effectively obstruct extraneous water body while solidifying slag and/or tailing heap by setting cured layer and third antiseepage barrier layer and enter in slag and/or tailing heap, avoid underground water pollution.

Description

A kind of cinder field or the Ecosystem restoration system and construction method of tailings stack antiseepage barrier
Technical field
The present invention relates to ecological restoration technical fields, and in particular to a kind of cinder field or the ecology of tailings stack antiseepage barrier are repaired Complex system and construction method.
Background technique
China's economy is after high speed development, more and more, the built various bands of all kinds of mines of well hair, newly-built factory There are cinder field, tailings stack and the factory floor of pollution sources ten hundreds of, this also means that various slags, industrial liquid, each Kind chemical raw material, once leakage will generate high risks to environment, entire society face contaminated risk also increasingly Greatly.It is unrepairable on sill once causing particularly with the pollution of underground water, soil.Ensure all kinds of cinder fields, tailing heap Pollution sources are effectively isolated in process of production for field and factory, avoid pollution source since leakage generates pollution, protection to environment Precious groundwater resources become urgent problem.
Antiseepage barrier wall in the prior art to prevent pollutant from leaking is only anti-towards the setting of the side of pollution sources at it Infiltration layer is not leaked out with contaminated liquid and the pollutant etc. that guarantee pollution sources.But in most circumstances, especially In Karst geomorphological environment, more liquid due to water source, the liquid such as rainwater, mountain spring water can pass through antiseepage barrier wall outboard cavity Wall enters inside antiseepage barrier wall, aggravates the pollution problem of pollution sources, and then partial contamination liquid is caused to seep from antiseepage barrier wall Out, serious environmental pollution is caused.Meanwhile also easily there are erosion in slag and/or tailing heap outer surface by extraneous water body, thus into Enter in slag and/or tailing heap, eventually the pollutant in slag and/or tailing heap is taken out of, influences body of groundwater.
Summary of the invention
In view of this, the embodiment of the invention provides a kind of ecologies of the three-dimensional antiseepage barrier of cinder field or the full side of tailings stack to repair Complex system and its construction method, it is poor to the antiseepage barriering effect of slag and/or tailing heap to solve the prior art, it will cause serious The problem of environmental pollution.
The embodiment of the invention provides a kind of Ecosystem restoration system of the three-dimensional antiseepage barrier of cinder field or the full side of tailings stack, packets It includes:
Antiseepage barrier wall, including barrier wall, the first antiseepage barrier layer and the second antiseepage barrier layer, the barrier wall, Upper wall part including being located at earth's surface or more and/or lower layer's wall part in the soil of the earth's surface, with barrier Pollution sources and pollution sources are extraneous;The first antiseepage barrier layer, positioned at the barrier wall its towards the side of the pollution sources, Prevent the solid-liquid pollutant of the pollution sources from exosmosing;The second antiseepage barrier layer, being located at the barrier wall, it is separate described The side of pollution sources prevents the solidliquid mixture in the pollution sources external world from entering the pollution sources;
Cured layer is layed on slag and/or tailing heap outer surface, to solidify the slag and/or tailing heap;
Third antiseepage barrier layer, is layed on the cured layer, enters the slag and/or tailing to obstruct extraneous water body In heap.
Further, cured layer can be macromolecule glue-line, concretely HDPE film layer.
Further, the ratio between thickness of the cured layer and third antiseepage barrier layer is (10-20): (5-40);Preferably, The cured layer with a thickness of 10-20cm;The third antiseepage barrier layer with a thickness of 5-40cm.
Further, further include overburden layer, be covered in the third antiseepage barrier layer and be located in the antiseepage barrier wall Side, the overburden layer with a thickness of 60cm-2m, plant green plant on the overburden layer;
4th antiseepage barrier layer, the surface of bedrock being layed in immediately below cinder field or tailings stack, the basement rock are located at earth's surface Under, in the horizontal direction at the middle part of the slag and/or tailing heap to outer surface, the thickness of the 4th antiseepage barrier layer by It gradually reduces, is drained to the slope on the outside of cinder field or tailings stack suitable for the water body from cinder field or tailings stack to be formed;
4th drainage channel, and is connected at the slope foot on the slope, and water body is guided to far from cinder field or tailings stack Position.
Further, the barrier wall includes the first wall for being positioned close to the pollution sources side, and setting In the second wall being oppositely arranged far from the pollution sources side and first wall, first wall and second wall Hollow cavity is formed between body, and first drawn for that will enter its internal solid-liquid pollutant is provided in the hollow cavity Drainage channel.
Further, the barrier wall its be provided with close to the side of the pollution sources for will be in the pollution sources The second drainage channel and/or described its side far from the pollution sources of barrier wall that solid-liquid pollutant is drawn are arranged useful It guides in by the solidliquid mixture in the pollution sources external world to the third drainage channel far from the pollution source position.
Further, first drainage channel with there is pollutant cavity for handling the solid-liquid pollutant equipment It is connected;
Lower layer's wall part is obliquely installed towards the side close to the pollution sources or lower layer's wall part court It is obliquely installed to the side far from the pollution sources.
Further, the angle of lower layer's wall part and ground level is 20 degree to 70 degree;Preferably, lower layer's wall The angle of body portion and ground level is 30 degree.
Further, the pollution sources are slag heap and/or tailings stack.
Further, the upper wall part is arranged perpendicular to ground level.
In addition, the present invention provides the construction methods of above-mentioned Ecosystem restoration system, comprising the following steps:
Process the barrier wall with the first antiseepage barrier layer and the second antiseepage barrier layer;
Implantation barrier its lower layer's wall part of wall below earth's surface;
Construction obstructs wall layer wall part thereon more than earth's surface;
By the barrier wall, it is logical close to the second drainage of solid-liquid pollutant extraction of the side of the pollution sources for construction The third that the solidliquid mixture of barrier its side far from the pollution sources of wall is drawn is drained and is led to by road, and/or construction Road, and/or the first drainage channel that solid-liquid pollutant intracavitary in the barrier wall wherein sky is drawn in construction;
Cured layer and third antiseepage barrier layer are successively laid on slag and/or tailing heap outer surface;
Surface of bedrock is cleared up, and is laid with the 4th antiseepage barrier layer in surface of bedrock.
Technical solution of the present invention has the advantages that
1. Ecosystem restoration system provided by the invention is provided with antiseepage barrier wall, cured layer and third antiseepage barrier layer, lead to It crosses its side far from the pollution sources in barrier wall and the second antiseepage barrier layer is set, the second antiseepage barrier layer can be effectively It prevents the liquid such as extraneous rainwater, mountain spring water from can enter inside antiseepage barrier wall by cavity wall on the outside of antiseepage barrier wall, makes to pollute The problem of pollution problem in source aggravates.It is more liquid due to water source especially for Karst geomorphological environment, more Liquid can flow to pollution sources, by above-mentioned second antiseepage barrier layer can largely liquid barrier from the pollution sources external world into Enter in pollution sources, prevent the pollution problem of pollution sources from aggravating, and then partial contamination liquid is caused to ooze out from antiseepage barrier wall, causes tight Again the problem of environmental pollution.Simultaneously by setting cured layer and third antiseepage barrier layer, solidifying the same of slag and/or tailing heap When, it can effectively obstruct extraneous water body and enter in slag and/or tailing heap, avoid underground water pollution.
2. Ecosystem restoration system provided by the invention, by optimizing the ratio between the thickness of cured layer and third antiseepage barrier layer, Solidification and barriering effect can be further improved, while reaching preferable solidification and barriering effect, reduces material cost.It is logical Setting overburden layer is crossed, third antiseepage barrier layer and antiseepage barrier wall can be covered, plants green plant on overburden layer in addition, improves slag And/or the appearance environment of tailing heap;
Meanwhile the 4th antiseepage barrier layer is being layed in the surface of bedrock immediately below cinder field or tailings stack, basement rock is located at Under earth's surface, in the horizontal direction at the middle part of the slag and/or tailing heap to outer surface, the thickness of the 4th antiseepage barrier layer by It gradually reduces, is drained to the slope on the outside of cinder field or tailings stack suitable for the water body from cinder field or tailings stack to be formed;Setting The 4th drainage channel being connected to at the slope foot on slope guides water body to the position far from cinder field or tailings stack.
3. Ecosystem restoration system provided by the invention, constituting barrier wall body by the first wall and the second wall can be effective Ground reduces the production installation difficulty of barrier wall, facilitate construction party construct to be formed inside and outside all have the barrier wall of antiseepage function Body.Hollow cavity is formed between first wall and the second wall, it can be by consolidating in the hollow cavity by the first drainage channel Liquid pollutant, which is drawn, carries out subsequent processing, and the solid-liquid pollutant so as to be effectively prevented in hollow cavity passes through the second wall again It is extraneous that body penetrates into pollution sources, or is entered in pollution sources by the first wall, and then the solid-liquid of pollution sources is effectively prevented to pollute The problem of object oozes out, and causes environmental pollution.
4. Ecosystem restoration system provided by the invention, obstructing wall, it is provided with close to the side of the pollution sources for inciting somebody to action The second drainage channel that the solid-liquid pollutant of the pollution sources exudation is drawn, above-mentioned second drainage channel can be effectively by pollutions The solid-liquid pollutant of source exudation draws the pollution sources, to handle above-mentioned solid-liquid pollutant, avoids pollution source and antiseepage A large amount of solid-liquid pollutant is retained between barrier wall, causes the accumulation of solid-liquid pollutant that solid-liquid pollutant is caused to pass through antiseepage barrier wall The problem of oozing out, causing environmental pollution;Described its side far from the pollution sources of barrier wall is provided with for by the dirt The solidliquid mixture in the dye source external world is guided to the third drainage channel (12) far from the pollution source position.Above-mentioned third drainage is logical The solidliquid mixture of external environment effectively can be deflected from antiseepage barrier wall by road, to reduce its second antiseepage of antiseepage barrier wall The pressure of barrier layer prevents rainwater, spring etc. from entering pollution sources by the second antiseepage barrier layer, and the pollution aggravated in pollution sources is asked Topic.
5. Ecosystem restoration system provided by the invention, lower layer's wall part is set towards the inclination close to the side of the pollution sources It sets or side that lower layer's wall part is directed away from the pollution sources is obliquely installed.When antiseepage barrier wall, it is located at soil When lower layer's wall part of lower layer tilts construction, the difficulty of construction of lower layer's wall part can be effectively reduced.Moreover, towards dirt Lower layer's wall part that dye source is obliquely installed can be effectively reduced the soil that lower layer's wall part is subject to and solid-liquid pollutant its The extruding force of the two.
6. the angle of Ecosystem restoration system provided by the invention, lower layer's wall part and ground level is 20 degree to 70 degree.Cause For antiseepage barrier wall, its lower layer's wall part is larger perpendicular to the difficulty of construction of the construction of soil, and antiseepage barrier wall its lower layer's wall Body portion level cannot achieve the package in all directions to pollution sources, solid-liquid pollutant avoided to seep from soil when soil is constructed Out, the problem of environmental pollution is caused.When the angle of lower layer's wall part and ground level is 20 degree to 70 degree, can both guarantee to prevent The construction for seeping barrier wall will not be too high, and the full side's solid antiseepage barrier to form pollution sources can also be effectively matched with basement rock Wall is effectively prevented solid-liquid pollutant and oozes out from topsoil and lower layer, guarantees the anti-seepage effect of antiseepage barrier wall.
7. Ecosystem restoration system provided by the invention, lower layer's wall part extends to soil horizon d below, to make Its lower layer's wall part of antiseepage barrier wall and horizon d surround full side's solid antiseepage barrier wall of package pollution sources, prevent solid-liquid dirty Object is contaminated from the problem of overflowing between lower layer's wall part and horizon d, in turn result in environmental pollution.
8. Ecosystem restoration system provided by the invention, upper wall part is arranged perpendicular to ground level, perpendicular to ground level Its upper layer wall part of the antiseepage barrier wall of setting has the advantages that construction is simple is convenient.
Detailed description of the invention
It, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical solution in the prior art Embodiment or attached drawing needed to be used in the description of the prior art be briefly described, it should be apparent that, it is described below Attached drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not making the creative labor It puts, is also possible to obtain other drawings based on these drawings.
Fig. 1 is lower layer's wall part provided in an embodiment of the present invention towards the inclined Ecosystem restoration system in pollution sources direction Structural schematic diagram;
Fig. 2 is that lower layer's wall part provided in an embodiment of the present invention is directed away from the inclined restoration of the ecosystem system in pollution sources direction The structural schematic diagram of system;
Fig. 3 is the arrangement schematic diagram of its drainage channel of antiseepage barrier wall provided in an embodiment of the present invention.
Description of symbols:
1- obstructs wall;2- upper wall part;3- lower layer wall part;4- pollution sources;5- hollow cavity;6- first is anti- Seep barrier layer;7- the second antiseepage barrier layer;The first wall of 8-;The second wall of 9-;The first drainage channel of 10-;The drainage of 11- second is logical Road;12- third drainage channel;13- pollutant cavity;14- water purification cavity;15- cured layer;16- third antiseepage barrier layer;17- Basement rock;The 4th antiseepage barrier layer of 18-;The 4th drainage channel of 19-.
Specific embodiment
Technical solution of the present invention is clearly and completely described below in conjunction with attached drawing, it is clear that described implementation Example is a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill Personnel's every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that term " center ", "upper", "lower", "left", "right", "vertical", The orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" be based on the orientation or positional relationship shown in the drawings, merely to Convenient for description the present invention and simplify description, rather than the device or element of indication or suggestion meaning must have a particular orientation, It is constructed and operated in a specific orientation, therefore is not considered as limiting the invention.In addition, term " first ", " second ", " third " is used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " installation ", " phase Even ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can To be mechanical connection, it is also possible to be electrically connected;It can be directly connected, can also can be indirectly connected through an intermediary Connection inside two elements.For the ordinary skill in the art, above-mentioned term can be understood at this with concrete condition Concrete meaning in invention.
Embodiment 1
The embodiment of the invention provides a kind of Ecosystem restoration systems of the three-dimensional antiseepage barrier of cinder field or the full side of tailings stack, such as Shown in Fig. 1 and 3, comprising:
Wall 1 is obstructed, the upper wall part 2 including being located at earth's surface or more and the lower layer in the soil of the earth's surface Wall part 3, above-mentioned barrier wall 1 are separately positioned in the soil of ground or more and below ground, can be effectively prevented Solid-liquid pollutant inside cinder field exosmoses under the seepage effect of precipitation and underground water, pollutes environment.The upper wall part 2 It is arranged perpendicular to ground level, lower layer's wall part 3 is obliquely installed towards the side close to the slag heap, above-mentioned lower layer's wall Body portion 3 extends to soil horizon d 15 below, extraneous to obstruct slag heap and pollution sources.When antiseepage barrier wall, it is located at soil When lower layer's wall part 3 of earth lower layer tilts construction, the difficulty of construction of lower layer's wall part 3 can be effectively reduced.Moreover, court The lower layer's wall part 3 being obliquely installed to pollution sources 4 can be effectively reduced the soil that lower layer's wall part 3 is subject to and solid-liquid is dirty Contaminate the extruding force of object the two.The angle of lower layer's wall part 3 and ground level is 30 degree, because of its lower layer of antiseepage barrier wall Wall part 3 is larger perpendicular to the difficulty of construction of the construction of soil, and its lower layer's wall part 3 of antiseepage barrier wall is horizontal in soil When construction, it cannot achieve the package in all directions to pollution sources 4, avoid solid-liquid pollutant from oozing out from soil, cause environmental pollution The problem of.When the angle of lower layer's wall part 3 and ground level is 20 degree to 70 degree, it can both guarantee the construction of antiseepage barrier wall Will not be too high, the full side's solid antiseepage barrier wall to form pollution sources 4 can also be effectively matched with horizon d 15, effectively prevented Only solid-liquid pollutant is oozed out from topsoil and lower layer, guarantees the anti-seepage effect of antiseepage barrier wall.Above-mentioned barrier wall 1 includes setting It sets in the first wall 8 close to the slag heap side, and is arranged far from the slag heap side and first wall 8 The second wall 9 being oppositely arranged;
First antiseepage barrier layer 6, the first antiseepage barrier layer 6 be located at first wall 8 its towards the slag heap Side, prevent the solid-liquid pollutant of the slag heap from exosmosing, positioned at the barrier wall 1 its towards the side of the slag heap With the first antiseepage barrier layer 6, the solid-liquid pollutant extravasation of the slag heap can be effectively prevented;
Second antiseepage barrier layer 7, the second antiseepage barrier layer 7 be located at second wall 9 its far from the slag heap Side, prevent the pollution sources external world solidliquid mixture enter the slag heap.By the way that in barrier wall 1, it is separate described The second antiseepage barrier layer 7 is arranged in the side of slag heap, and the second antiseepage barrier layer 7 can be effectively prevented extraneous rainwater, mountain spring The liquid such as water can be entered inside antiseepage barrier wall by cavity wall on the outside of antiseepage barrier wall, make what the pollution problem of pollution sources aggravated to ask Topic occurs.Especially for Karst geomorphological environment, more liquid due to water source, more liquid can flow to slag heap, It can largely liquid barrier be entered in slag heap from the pollution sources external world by above-mentioned second antiseepage barrier layer 7, prevent dirt The pollution problem in dye source aggravates, and then the problem of cause partial contamination liquid to ooze out from antiseepage barrier wall, cause Heavy environmental pollution.
Cured layer 15 is layed on slag and/or tailing heap outer surface, to solidify the slag and/or tailing heap;Third Antiseepage barrier layer 16 is layed on the cured layer, is entered in the slag and/or tailing heap with obstructing extraneous water body.Simultaneously Extraneous water body can be effectively obstructed while solidifying slag and/or tailing heap by setting cured layer and third antiseepage barrier layer Into in slag and/or tailing heap, underground water pollution is avoided.
Hollow cavity 5 is formed between above-mentioned first wall 8 and the second wall 9, is provided with and is used in the hollow cavity 5 To enter the first drainage channel 10 that its internal solid-liquid pollutant is drawn, the first drainage channel 10 be both ends respectively with pollutant The pipeline that cavity 13 is connected with hollow cavity 5.Constituting barrier wall 1 by the first wall 8 and the second wall 9 can be effectively The production installation difficulty for reducing barrier wall 1, facilitate construction party construct to be formed inside and outside all have the barrier wall of antiseepage function Body 1.As shown in figure 3, forming hollow cavity 5 between the first wall 8 and the second wall 9, can be incited somebody to action by the first drainage channel 10 Solid-liquid pollutant in the hollow cavity 5, which is drawn, carries out subsequent processing, so as to the solid-liquid being effectively prevented in hollow cavity 5 Pollutant passes through the second wall 9 again and penetrates into the pollution sources external world, or is entered in slag heap by the first wall 8, and then effectively The problem of preventing the solid-liquid pollutant of slag heap from oozing out, cause environmental pollution.
Above-mentioned barrier wall 1 its close to the side of the slag heap be provided with the solid-liquid for oozing out the slag heap dirt The second drainage channel 11 that object is drawn is contaminated, the second drainage channel 11 is both ends respectively and in pollutant cavity 13 and barrier wall 1 The pipeline that side is connected;
The solid-liquid pollutant that slag heap oozes out effectively can be drawn the slag heap by above-mentioned second drainage channel 11, thus Above-mentioned solid-liquid pollutant is handled, avoids retaining a large amount of solid-liquid pollutant between slag heap and antiseepage barrier wall, cause The problem of accumulation of solid-liquid pollutant causes solid-liquid pollutant to ooze out by antiseepage barrier wall, cause environmental pollution;The barrier wall Its side far from the slag heap of body 1 is provided with for guiding the solidliquid mixture in the pollution sources external world to far from described The third drainage channel 12 of slag heap position.Third drainage channel 12 is both ends respectively and outside water purification cavity 14 and barrier wall 1 The pipeline that side is connected;
The solidliquid mixture of external environment effectively can be deflected from antiseepage barrier wall by above-mentioned third drainage channel 12, thus The pressure for reducing its second antiseepage barrier layer 7 of antiseepage barrier wall prevents rainwater, spring etc. from entering by the second antiseepage barrier layer 7 Slag heap aggravates the pollution problem in slag heap.
Above-mentioned second drainage channel 11 and the first drainage channel 10 are set for handling the solid-liquid pollutant with having respectively Standby pollutant cavity 13 is connected;The third drainage channel 12 and 14 phase of water purification cavity for accommodating the solidliquid mixture Even.Moreover, lower layer's wall part 3 extends to soil horizon d 15 below, to make its lower layer's wall part 3 of antiseepage barrier wall With horizon d 15 surround package slag heap full side's solid antiseepage barrier wall, prevent solid-liquid pollutant from lower layer's wall part 3 with The problem of overflowing between horizon d 15, in turn result in environmental pollution.
Certainly, the present patent application is not particularly limited antiseepage barrier wall barrier process object, in other embodiments, prevents It seeps barrier wall and surrounds tailings stack, form full side's solid antiseepage to the soil upper and lower level of tailings stack and obstruct.
Certainly, the present patent application is not particularly limited the angle between lower layer's wall part 3 and ground level, in other realities It applies in example, the angle of lower layer's wall part 3 and ground level is 70 degree, though the angle of lower layer's wall part 3 and ground level is larger It so will increase the difficulty of construction of antiseepage barrier wall.But lower layer's wall part 3 can surround the biggish antiseepage sky of area with basement rock Between, to accommodate more pollutants, reduces the pressure of lower layer's wall part 3, reserve drainage time to the first drainage channel 10.
Embodiment 2
On the basis of above-described embodiment 1, the ratio between thickness of cured layer 15 and third antiseepage barrier layer 16 is (10-20): (5-40).Preferably, the cured layer with a thickness of 10-20cm;The third antiseepage barrier layer with a thickness of 5-40cm.
Further, further include overburden layer, be covered in the third antiseepage barrier layer and be located in the antiseepage barrier wall Side, the overburden layer with a thickness of 60cm-2m, plant green plant on the overburden layer;
4th antiseepage barrier layer 18, is layed in 17 surface of basement rock immediately below cinder field or tailings stack, and the basement rock is located at Under earth's surface, in the horizontal direction at the middle part of the slag and/or tailing heap to outer surface, the thickness of the 4th antiseepage barrier layer Degree gradually decreases, and is drained to the slope on the outside of cinder field or tailings stack suitable for the water body from cinder field or tailings stack to be formed;
4th drainage channel 19, and is connected at the slope foot on the slope, and water body is guided to far from cinder field or tailing heap The position of field.
By optimizing the ratio between the thickness of cured layer and third antiseepage barrier layer, solidification and barrier effect can be further improved Fruit reduces material cost while reaching preferable solidification and barriering effect.By the way that overburden layer is arranged, it is anti-that third can be covered Barrier layer and antiseepage barrier wall are seeped, plants green plant on overburden layer in addition, improves the appearance environment of slag and/or tailing heap;
Meanwhile the 4th antiseepage barrier layer is being layed in the surface of bedrock immediately below cinder field or tailings stack, basement rock is located at Under earth's surface, in the horizontal direction at the middle part of the slag and/or tailing heap to outer surface, the thickness of the 4th antiseepage barrier layer by It gradually reduces, is drained to the slope on the outside of cinder field or tailings stack suitable for the water body from cinder field or tailings stack to be formed;Setting The 4th drainage channel being connected to at the slope foot on slope guides water body to the position far from cinder field or tailings stack.
Embodiment 3
The present embodiment the difference from embodiment 1 is that, as shown in Fig. 2, its lower layer of antiseepage barrier wall provided in this embodiment The side that wall part 3 is directed away from the slag heap is obliquely installed.Lower layer's wall part 3 is directed away from the one of the slag heap Side is obliquely installed and extends to soil basement rock below, can also equally play the effect of barrier slag heap and the pollution sources external world.
Embodiment 4
Present embodiments provide the construction method of above-mentioned Ecosystem restoration system, comprising the following steps:
Process the barrier wall 1 with the first antiseepage barrier layer 6 and the second antiseepage barrier layer 7;
Implantation barrier its lower layer's wall part 3 of wall 1 below earth's surface;
Construction barrier its upper layer wall part 2 of wall 1 more than earth's surface;
Construction by it is described barrier wall 1 its close to the side of the pollution sources 4 solid-liquid pollutant draw second drainage Channel 11, and/or the third that the solidliquid mixture of barrier its side far from the pollution sources 4 of wall 1 is drawn in construction Drainage channel 12, and/or the first drainage that the solid-liquid pollutant in described barrier its hollow cavity 5 of wall 1 is drawn in construction are logical Road 10;
Cured layer 15 and third antiseepage barrier layer 16 are successively laid on slag and/or tailing heap outer surface;
Surface of bedrock is cleared up, and is laid with the 4th antiseepage barrier layer 18 in surface of bedrock.
Further, to the restorative procedure of the basement rock of waste residue or tailings stack base impervious weathering, comprising the following steps:
S1 clears up the surface of bedrock by the way of negative inspiratory pressure, to expose the basement rock;
S2 adds macromolecule glue into the crack of the basement rock, and the macromolecule glue is that slag recycles the colloid to be formed, Has the advantages that environmental protection;
S3 is in the 4th antiseepage barrier layer 18 of horizon d surface construction, to prevent contaminated liquid from penetrating into.By adding in base Macromolecule glue in cleft can effectively increase the bearing strength of basement rock, guarantee construction safety.Moreover, passing through above-mentioned high score 4th antiseepage barrier layer 18 of sub- glue and surface of bedrock can be effectively prevented industrial waste, process waste liquor, chemical products, slag Deng above-mentioned pollutant penetrates into the crack of basement rock, causes serious problem of environmental pollution.
In the present embodiment, the step of clearing up surface of bedrock, comprising: remove the coating on the basement rock upper layer and to institute It states basement rock and carries out crack cleaning.Cleaning work is carried out by the crack to basement rock, to make construction personnel in injection macromolecule glue When guarantee macromolecule glue to the filling effect in basement rock crack.
In the present embodiment, the 4th antiseepage barrier layer 18 is the HDPE film being laid on the basement rock, by above-mentioned HDPE film can be effectively avoided contaminated liquid and enter in the crack of basement rock.
The restorative procedure of waste residue or tailings stack base impervious weathered rocks in the present embodiment, further includes following step It is rapid: construction liquid collecting zone, and the construction of the 4th antiseepage barrier layer 18 is formed into the approach channel face being obliquely installed, 18 court of the 4th antiseepage barrier layer It is tilted to the liquid collecting zone and contaminated liquid is introduced into the liquid collecting zone.Above-mentioned liquid collecting zone is the ditch for accommodating the contaminated liquid, is led to Water treatment facilities is crossed to handle the contaminated liquid in the ditch.4th antiseepage barrier layer 18 forms the approach channel face being obliquely installed, Contaminated liquid effectively can be introduced into liquid collecting zone towards the inclined 4th antiseepage barrier layer 18 in liquid collecting zone by above-mentioned, thus convenient The collection of contaminated liquid is handled.It is equipped on the 4th antiseepage barrier layer 18 in the present embodiment for protecting the 4th antiseepage barrier layer 18 Stratum protective layer, the stratum protective layer be non-woven fabrics.
Certainly, the present patent application to cleaning surface of bedrock the step of be not particularly limited, in other embodiments, without pair Basement rock carries out crack cleaning, it is only necessary to remove the coating on the basement rock upper layer.
Certainly, the present patent application is not particularly limited the structure of the 4th antiseepage barrier layer 18, in other embodiments, the Four antiseepage barrier layers 18 are the macromolecule impervious material smeared in surface of bedrock.Alternatively, the 4th antiseepage barrier layer 18 is to be laid on The composite structure of HDPE film and macromolecule impervious material on the basement rock.
Certainly, the present patent application is not particularly limited to whether the 4th antiseepage barrier layer 18 tilts, in other embodiments, 4th antiseepage barrier layer 18 is plane compatible with basement rock shape.
Although being described in conjunction with the accompanying the embodiment of the present invention, those skilled in the art can not depart from the present invention Spirit and scope in the case where various modifications and variations can be made, such modifications and variations are each fallen within by appended claims institute Within the scope of restriction.

Claims (10)

1. a kind of Ecosystem restoration system of the three-dimensional antiseepage barrier of cinder field or the full side of tailings stack characterized by comprising
Antiseepage barrier wall, including barrier wall (1), the first antiseepage barrier layer (6) and the second antiseepage barrier layer (7), the barrier Wall (1), the upper wall part (2) including being located at earth's surface or more and/or lower layer's wall in the soil of the earth's surface Partially (3), it is extraneous to obstruct pollution sources (4) and pollution sources;The first antiseepage barrier layer (6) is located at the barrier wall (1) It prevents the solid-liquid pollutant of the pollution sources (4) from exosmosing towards the side of the pollution sources (4);The second antiseepage barrier Layer (7) is located at described its side far from the pollution sources (4) of barrier wall (1), prevents the solid-liquid in the pollution sources external world mixed It closes object and enters the pollution sources (4);
Cured layer (15) is layed on slag and/or tailing heap outer surface, to solidify the slag and/or tailing heap;
Third antiseepage barrier layer (16), is layed on the cured layer, enters the slag and/or tailing to obstruct extraneous water body In heap.
2. Ecosystem restoration system according to claim 1, which is characterized in that the cured layer (15) and third antiseepage obstruct The ratio between thickness of layer (16) is (10-20): (5-40).
3. Ecosystem restoration system according to claim 2, which is characterized in that further include,
Overburden layer is covered in the third antiseepage barrier layer and is located above the antiseepage barrier wall, the thickness of the overburden layer For 60cm-2m, green plant is planted on the overburden layer;
4th antiseepage barrier layer (18), is layed in basement rock (17) surface immediately below cinder field or tailings stack, and the basement rock is located at Under earth's surface, in the horizontal direction at the middle part of the slag and/or tailing heap to outer surface, the thickness of the 4th antiseepage barrier layer Degree gradually decreases, and is drained to the slope on the outside of cinder field or tailings stack suitable for the water body from cinder field or tailings stack to be formed;
4th drainage channel (19), and is connected at the slope foot on the slope, and water body is guided to far from cinder field or tailings stack Position.
4. Ecosystem restoration system according to claim 1, which is characterized in that the barrier wall (1) includes that setting is being leaned on The first wall (8) of nearly pollution sources (4) side, and it is arranged far from the pollution sources (4) side and first wall The second wall (9) that body (8) is oppositely arranged forms hollow cavity between first wall (8) and second wall (9) (5), the first drainage channel drawn for its internal solid-liquid pollutant will to be entered is provided in the hollow cavity (5) (10)。
5. Ecosystem restoration system according to claim 1 or 2, which is characterized in that the barrier wall (1) its close to described The side of pollution sources (4) is provided with the second drainage channel (11) for drawing the solid-liquid pollutant in the pollution sources (4), And/or described barrier wall (1) its side far from the pollution sources (4) is provided with for by the solid-liquid in the pollution sources external world Mixture is guided to the third drainage channel (12) far from the pollution sources (4) position.
6. Ecosystem restoration system according to claim 4, which is characterized in that first drainage channel (10) with have use It is connected in the pollutant cavity (13) for handling the solid-liquid pollutant equipment;
Lower layer's wall part (3) is obliquely installed towards the side close to the pollution sources (4) or lower layer's wall part (3) side for being directed away from the pollution sources (4) is obliquely installed.
7. Ecosystem restoration system according to claim 5, which is characterized in that lower layer's wall part (3) and ground level Angle be 20 degree to 70 degree.
8. Ecosystem restoration system according to claim 1, which is characterized in that the pollution sources (4) are slag heap and/or tail Mine stockyard.
9. Ecosystem restoration system according to claim 1, which is characterized in that the upper wall part (2) is perpendicular to ground Plane setting.
10. a kind of construction method of Ecosystem restoration system described in any one of claims 1 to 9, which is characterized in that including with Lower step:
Process the barrier wall (1) with the first antiseepage barrier layer (6) and the second antiseepage barrier layer (7);
Implantation barrier wall (1) its lower layer's wall part (3) below earth's surface;
Construction barrier wall (1) its upper layer wall part (2) more than earth's surface;
It constructs second drainage for obstructing wall (1) its solid-liquid pollutant close to the side of the pollution sources (4) and drawing The solidliquid mixture of described barrier wall (1) its side far from the pollution sources (4) is drawn in channel (11), and/or construction Third drainage channel (12), and/or construction by it is described barrier wall (1) its hollow cavity (5) in solid-liquid pollutant draw The first drainage channel (10);
Cured layer and third antiseepage barrier layer are successively laid on slag and/or tailing heap outer surface;
Surface of bedrock is cleared up, and is laid with the 4th antiseepage barrier layer in surface of bedrock.
CN201910442075.8A 2019-05-24 2019-05-24 A kind of cinder field or the Ecosystem restoration system and construction method of tailings stack antiseepage barrier Pending CN110374132A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910442075.8A CN110374132A (en) 2019-05-24 2019-05-24 A kind of cinder field or the Ecosystem restoration system and construction method of tailings stack antiseepage barrier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910442075.8A CN110374132A (en) 2019-05-24 2019-05-24 A kind of cinder field or the Ecosystem restoration system and construction method of tailings stack antiseepage barrier

Publications (1)

Publication Number Publication Date
CN110374132A true CN110374132A (en) 2019-10-25

Family

ID=68248725

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910442075.8A Pending CN110374132A (en) 2019-05-24 2019-05-24 A kind of cinder field or the Ecosystem restoration system and construction method of tailings stack antiseepage barrier

Country Status (1)

Country Link
CN (1) CN110374132A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111456106A (en) * 2020-05-15 2020-07-28 谷亮 In-situ bottom barrier structure, semi-barrier, barrier and liquid discharge system and construction method
CN111622206A (en) * 2020-06-01 2020-09-04 中国地质科学院矿产综合利用研究所 Construction method of ionic rare earth impervious curtain
CN112081091A (en) * 2020-09-08 2020-12-15 中国石油化工股份有限公司 In-service industrial site pollution comprehensive management and control system and method
CN114059598A (en) * 2021-12-07 2022-02-18 湘潭大学 Automatic ecological restoration system suitable for phosphate slag landfill and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001164564A (en) * 1999-12-10 2001-06-19 Shimizu Corp Installation method of drain structure for impervious wall and wall joint section
CN102350437A (en) * 2011-07-15 2012-02-15 沈阳环境科学研究院 Method for carrying out stabilization obstruction on soil with slight heavy metal pollution
CN202390860U (en) * 2011-11-25 2012-08-22 华侨大学 Anti-leakage system capable of guiding and discharging seepage of garbage sanitary landfill
CN104492798A (en) * 2014-12-08 2015-04-08 深圳市如茵生态环境建设有限公司 Composite layer, method for controlling acidization of mining slag heap yard and revegetation method
CN207672630U (en) * 2017-12-26 2018-07-31 四川信耀环境科技有限公司 A kind of garbage loading embeading two-layer barrier structure
CN108951711A (en) * 2018-09-12 2018-12-07 中节能大地环境修复有限公司 A kind of hazardous waste pollution joint vertical divider structure and its construction method for Bed Rock Region
CN210684769U (en) * 2019-05-24 2020-06-05 中节能大地环境修复有限公司 Ecological restoration system for preventing seepage and blocking of slag yard or tailing yard

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001164564A (en) * 1999-12-10 2001-06-19 Shimizu Corp Installation method of drain structure for impervious wall and wall joint section
CN102350437A (en) * 2011-07-15 2012-02-15 沈阳环境科学研究院 Method for carrying out stabilization obstruction on soil with slight heavy metal pollution
CN202390860U (en) * 2011-11-25 2012-08-22 华侨大学 Anti-leakage system capable of guiding and discharging seepage of garbage sanitary landfill
CN104492798A (en) * 2014-12-08 2015-04-08 深圳市如茵生态环境建设有限公司 Composite layer, method for controlling acidization of mining slag heap yard and revegetation method
CN207672630U (en) * 2017-12-26 2018-07-31 四川信耀环境科技有限公司 A kind of garbage loading embeading two-layer barrier structure
CN108951711A (en) * 2018-09-12 2018-12-07 中节能大地环境修复有限公司 A kind of hazardous waste pollution joint vertical divider structure and its construction method for Bed Rock Region
CN210684769U (en) * 2019-05-24 2020-06-05 中节能大地环境修复有限公司 Ecological restoration system for preventing seepage and blocking of slag yard or tailing yard

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111456106A (en) * 2020-05-15 2020-07-28 谷亮 In-situ bottom barrier structure, semi-barrier, barrier and liquid discharge system and construction method
CN111622206A (en) * 2020-06-01 2020-09-04 中国地质科学院矿产综合利用研究所 Construction method of ionic rare earth impervious curtain
CN111622206B (en) * 2020-06-01 2022-02-08 中国地质科学院矿产综合利用研究所 Construction method of ionic rare earth impervious curtain
CN112081091A (en) * 2020-09-08 2020-12-15 中国石油化工股份有限公司 In-service industrial site pollution comprehensive management and control system and method
CN112081091B (en) * 2020-09-08 2022-02-01 中国石油化工股份有限公司 In-service industrial site pollution comprehensive management and control system and method
CN114059598A (en) * 2021-12-07 2022-02-18 湘潭大学 Automatic ecological restoration system suitable for phosphate slag landfill and construction method thereof

Similar Documents

Publication Publication Date Title
CN110374132A (en) A kind of cinder field or the Ecosystem restoration system and construction method of tailings stack antiseepage barrier
CN103321256B (en) Anti-pollution three-dimensional composite anti-penetrating barrier system
CN103736720B (en) A kind of original position of heavy-metal contaminated soil intercepts administering method
CN100551563C (en) A kind of improvement method of heavy-metal contaminated soil
CN104358267A (en) Vacuum tube well precipitation and disposal method for rapidly restoring in-situ water and soil in polluted place
JP2013535597A (en) In-situ leaching method by liquid injection
CN109848195B (en) Foreign soil restoration method for orchard heavy metal contaminated soil
CN106702182B (en) A kind of recovery system of re dip solution
Vaselli et al. Geochemical characterization of the ground waters from the former Hg-mining area of Abbadia San Salvatore (Mt. Amiata, central Italy): Criticalities and perspectives for the reclamation process
CN105921501A (en) In-situ remediation system for heavy metal contaminated soil and construction method thereof
CN111456106A (en) In-situ bottom barrier structure, semi-barrier, barrier and liquid discharge system and construction method
CN109940033B (en) Foreign soil restoration method for farmland heavy metal pollution
CN115180702A (en) Long-acting passive treatment method for acid uranium tailing seepage water
CN113863345A (en) Underground water pollution-removing and shunting treatment structure and method for harmful substance storage field
CN111014226A (en) Ton package and landfill of soluble waste salt
CN113000574A (en) Method for restoring mine mercury polluted acid soil
CN110374143A (en) A kind of antiseepage barrier wall and its construction method
CN207944451U (en) A kind of soil barrier landfill seepage control system
CN110424364B (en) Ecological restoration method and restoration system for ion type rare earth in-situ leaching abandoned mine
CN110206062A (en) The dark construction method of underground river shallow embedding is worn under a kind of Urban Underground pipe gallery
CN207499002U (en) A kind of antiseepage guide structure of refuse landfill
CN113416840B (en) Stope seal seepage-blocking method and application thereof, stope seal seepage-blocking structure and application thereof
CN115125404A (en) System and method for collecting ion type rare earth ore in-situ leaching field leakage liquid
CN210684769U (en) Ecological restoration system for preventing seepage and blocking of slag yard or tailing yard
CN108097713A (en) A kind of restorative procedure in the heavy metal pollution place for valley terrain

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination