CN110374079A - A kind of vertical ship lift docking facilities and method - Google Patents

A kind of vertical ship lift docking facilities and method Download PDF

Info

Publication number
CN110374079A
CN110374079A CN201910669237.1A CN201910669237A CN110374079A CN 110374079 A CN110374079 A CN 110374079A CN 201910669237 A CN201910669237 A CN 201910669237A CN 110374079 A CN110374079 A CN 110374079A
Authority
CN
China
Prior art keywords
work
bay
ship
gate
tail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910669237.1A
Other languages
Chinese (zh)
Other versions
CN110374079B (en
Inventor
金龙
黄金根
温良
王敏
李倩
王曾兰
李宜燃
陆永亚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou State Power Machinery Research and Design Institute Co Ltd
Original Assignee
Hangzhou State Power Machinery Research and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou State Power Machinery Research and Design Institute Co Ltd filed Critical Hangzhou State Power Machinery Research and Design Institute Co Ltd
Priority to CN201910669237.1A priority Critical patent/CN110374079B/en
Publication of CN110374079A publication Critical patent/CN110374079A/en
Application granted granted Critical
Publication of CN110374079B publication Critical patent/CN110374079B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/20Movable barrages; Lock or dry-dock gates
    • E02B7/26Vertical-lift gates
    • E02B7/30Vertical-lift gates with guide wheels or rollers for the gates
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/20Movable barrages; Lock or dry-dock gates
    • E02B7/26Vertical-lift gates
    • E02B7/36Elevating mechanisms for vertical-lift gates
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02CSHIP-LIFTING DEVICES OR MECHANISMS
    • E02C5/00Mechanisms for lifting ships vertically
    • E02C5/02Mechanisms for lifting ships vertically with floating chambers
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/30Flood prevention; Flood or storm water management, e.g. using flood barriers

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Barrages (AREA)

Abstract

The present invention relates to a kind of vertical ship lift docking facilities and method, main hoist system acts on ship reception chamber, head bay and the docking of ship compartment early-stage work door, tail-bay and the docking of ship compartment downstream cleaning door;When upstream is docked, head bay work gate docking guide pin is slowly inserted into ship compartment early-stage work door docking guide groove, and the docking water seal of head bay work gate is pressed on ship compartment early-stage work Men Menye;Subsequent ship reception chamber still uplink, ship compartment early-stage work Men Menye are slowly sunk down into the gate slot of ship reception chamber upstream side;When downstream is docked, downstream cleaning door docking guide pin in ship compartment is slowly inserted into tail-bay work wicket docking guide groove, and downstream cleaning door docking water seal in ship compartment is pressed on tail-bay work wicket;Subsequent ship reception chamber still downlink, tail-bay work wicket are slowly sunk down into the gate slot at tail-bay work gate.Rationally, structure simplifies the design of the application docking facilities, to simplify docking process, improves docking efficiency, reduces accident risk in docking operation.

Description

A kind of vertical ship lift docking facilities and method
Technical field
The present invention relates to hydraulic and hydroelectric engineering navigation structure fields, in particular, being related to a kind of vertical ship lift docking Device and method.
Background technique
Vertical ship lift is the important navigation facilities for overcoming the height of water to realize dam navigation.Vertical ship lift and ship lock phase Than more efficiently realizing that ship gets over dam navigation more energy savingly, improving the ships'passing dam time.But current existing vertical ship lift exists It when upstream and downstream is docked, is all made of ship compartment and is docked with upstream and downstream lock head, using Butt sealing frame and fill drainage system realization to water receiving The linking in road, seriously affects ship navigation efficiency at entire docking operation extremely complex occupancy a big chunk ship navigation time, And docking facilities contain groups oil cylinders and water seal, are easy to appear equipment fault, cause to dock it is not in place, occur ship reception chamber sluice or Rollover etc. serious safety accident, therefore, it is necessary to existing vertical ship lift interconnection method and device improve with it is excellent Change.
Summary of the invention
It is an object of the invention to overcome the above deficiencies in the existing technologies, and provide it is a kind of it is reasonable in design, Docking process can be simplified, improve the vertical ship lift docking facilities of docking efficiency, and give interconnection method.
Technical solution used by the present invention solves the above problems is: a kind of vertical ship lift docking facilities, including master mention The system of liter, ship reception chamber, ship compartment early-stage work door, ship compartment downstream cleaning door, head bay and tail-bay;The main hoist system effect In ship reception chamber, is run above and below for ship reception chamber and power is provided;The ship compartment early-stage work door is mounted on the upstream end of ship reception chamber, institute State the downstream that ship compartment downstream cleaning door is mounted on ship reception chamber;The head bay and the docking of ship compartment early-stage work door, the lower lock The docking of first and ship compartment downstream cleaning door;It is characterized by: the ship compartment early-stage work door includes ship compartment early-stage work Men Menye, institute State ship compartment early-stage work Men Menye along the vertical direction can oscilaltion removably mount in the gate slot of ship reception chamber upstream side, ship compartment Two ship compartment early-stage work door docking guide grooves are at least installed on the top surface of early-stage work Men Menye;The head bay includes brake application The work gate head and head bay work wicket;The land side at head bay work gate is arranged in the head bay work wicket;Institute It states to be provided on the bottom surface at head bay work gate and docks the one-to-one head bay work of guide groove with ship compartment early-stage work door Dock guide pin in gate;When upstream is docked, head bay work gate docking guide pin is inserted into corresponding ship compartment upstream Cleaning door docks in guide groove, when being additionally provided on the bottom surface at head bay work gate for docking with the early-stage work of ship compartment The head bay work gate docking water seal being sealed between door gate flap;The tail-bay includes tail-bay work gate and lower lock The land side at tail-bay work gate is arranged in head work wicket, tail-bay work wicket;Under the tail-bay work wicket is Heavy formula cleaning door at least installs two tail-bays work wickets docking guide grooves on top surface;Ship compartment downstream cleaning door is Hydraulic China's railway industry comprising ship compartment downstream cleaning door headstock gear and ship compartment downstream cleaning door gate flap, ship compartment downstream cleaning door The lower end of gate flap is hinged on ship reception chamber, and the two sides of ship compartment downstream cleaning door gate flap are realized by ship compartment downstream cleaning door headstock gear It drops to the ground opening and closing;It is provided on the bottom surface of the ship reception chamber downstream and docks the one-to-one ship of guide groove with tail-bay work wicket Compartment downstream cleaning door docks guide pin;When downstream is docked, it is corresponding that ship compartment downstream cleaning door docks guide pin insertion Tail-bay works in wicket docking guide groove, when being additionally provided on the bottom surface of the ship reception chamber downstream for docking and tail-bay The ship compartment downstream cleaning door docking water seal being sealed between work wicket top surface.
Preferably, the both sides of the ship compartment early-stage work Men Menye are separately connected a ship compartment early-stage work door hydraulic switch Machine, ship compartment early-stage work door hydraulic headstock gear are mounted in the gate slot of ship reception chamber upstream side, the ship compartment early-stage work door liquid on both sides Press headstock gear driving ship compartment early-stage work Men Menye oscilaltion mobile;It is installed on the top surface of the ship compartment early-stage work Men Menye Two ship compartment early-stage work doors dock guide groove.
Preferably, the head bay further includes head bay headstock gear;The cross section at head bay work gate is in convex, That side that it is protruded is close to ship reception chamber, and the size of the protrusion part is consistent with ship compartment early-stage work Men Menye, and the protrusion Partial structure is hollow structure, and two sides offer gate slot, and the two sides of the head bay work wicket are respectively mounted a column head bay Work wicket guide wheel, and head bay work wicket guide wheel is mounted in the gate slot, and the head bay work wicket side that meets water is also equipped with Head bay work wicket side guide wheel, head bay work wicket land side be equipped be used for head bay work gate between carry out it is close The U-shaped head bay work wicket water seal of envelope;The two sides at head bay work gate are respectively arranged with head bay gate slot, head bay Work gate two sides are respectively mounted column head bay work gate guide wheel, and head bay work gate guide wheel is located at the head bay gate slot Interior, head bay work gate is run under the driving of head bay headstock gear along head bay gate slot energy oscilaltion, to adapt to Variation of water level;The head bay work gate land side is also equipped with head bay work gate side guide wheel, the head bay Work gate meet water side be equipped with for being sealed between head bay gate slot head bay work gate water seal.
Preferably, the tail-bay further includes tail-bay headstock gear and tail-bay work wicket hydraulic headstock gear;Under described The work cross section at gate of lock head is in convex, that side of protrusion is close to ship reception chamber, and during the structure of the protrusion part is Hollow structure, two sides offer gate slot, and it is hydraulic that a tail-bay work wicket is installed in the two sides of the tail-bay work wicket respectively Headstock gear, the tail-bay work wicket hydraulic headstock gear driving tail-bay work wicket along gate slot oscilaltion operation;Under described Lock head, which works, is arranged tail-bay work wicket water seal between wicket and tail-bay work gate;The two of tail-bay work gate Side is respectively arranged with tail-bay gate slot, and tail-bay work gate two sides are respectively mounted column tail-bay work gate guide wheel, tail-bay Work gate guide wheel is located in the tail-bay gate slot, and tail-bay work gate is under the driving lower edge of tail-bay headstock gear Lock head gate slot energy oscilaltion operation, to adapt to variation of water level;The tail-bay work gate land side is also equipped with down Lock head works gate side guide wheel, and the tail-bay work gate side that meets water is equipped with and is used between tail-bay gate slot be sealed Tail-bay work gate water seal.
The present invention also provides another technical solutions: a kind of vertical ship lift interconnection method, using above-mentioned docking facilities into Row is implemented, which is divided into upstream interconnection method and downstream interconnection method.
Upstream interconnection method are as follows: ship reception chamber is by main hoist system uplink, and close to when docking position, the speed of service reduces to low speed Operation, head bay work gate docking guide pin is slowly inserted into ship compartment early-stage work door docking guide groove, until head bay work Make gate docking water seal to be pressed on ship compartment early-stage work Men Menye;The still slow uplink of subsequent ship reception chamber, ship compartment early-stage work door Gate flap is slowly sunk down into the gate slot of ship reception chamber upstream side under the driving of ship compartment early-stage work door hydraulic headstock gear, ship reception chamber uplink When reaching regulation docking location, ship reception chamber stops uplink and locks, and early-stage work Men Menye in ship compartment sinks in place at this time, head bay Work gate is docked in the gate slot of ship reception chamber upstream side;And then head bay headstock gear slings head bay work wicket, at this time Waters and upstream waters connection, ship can drive into or be driven out to ship reception chamber in ship reception chamber;It drives into designated position or is driven out to ship Afterwards, head bay work wicket is closed, and ship reception chamber unlocks and slowly declines, while early-stage work Men Menye in ship compartment is on ship compartment Lower rise of cleaning door hydraulic headstock gear driving is swum to close the door.
Downstream interconnection method are as follows: ship reception chamber is by main hoist system downlink, and close to when docking position, the speed of service reduces to low speed Operation, downstream cleaning door docking guide pin in ship compartment is slowly inserted into tail-bay work wicket docking guide groove, until ship compartment downstream Cleaning door docking water seal is pressed on tail-bay work wicket;The still slow downlink of subsequent ship reception chamber, tail-bay work wicket under It is slowly sunk down into the gate slot at tail-bay work gate under lock head work wicket hydraulic headstock gear driving, ship reception chamber reaches regulation pair When connecing position, ship reception chamber stops uplink and locks, and the wicket of tail-bay work at this time has sunk in place, and ship reception chamber downstream is It is docked in the gate slot at tail-bay work gate;Ship compartment downstream cleaning door gate flap crouches under the driving of ship compartment downstream cleaning door headstock gear It opens, waters and downstream waters connection, ship can drive into or be driven out to ship reception chamber in ship reception chamber at this time;It drives into ship to specified Position or after being driven out to, ship compartment downstream cleaning door gate flap is closed, and ship reception chamber unlocks and slow uplink, while tail-bay work is small Door under tail-bay work wicket hydraulic headstock gear driving slowly close the door by uplink.
Compared with prior art, the present invention having the following advantages that and effect:
1, rationally, structure simplifies the docking facilities design in the application, eliminates the Butt sealing device in traditional docking facilities With fill drainage system, to simplify docking process, improve docking efficiency, reduce accident risk in docking operation;
2, ship compartment early-stage work door and tail-bay work wicket use sunk type cleaning door, and head bay works wicket using winding type Lever gear door shortens ship lift entire length size, and then shortens king-post, reduces the scale of concrete foundation, subtracts significantly Construction investment is lacked.
Detailed description of the invention
Fig. 1 is the general arrangement of the embodiment of the present invention.
Fig. 2 is the schematic view of the front view of ship reception chamber in the embodiment of the present invention.
Fig. 3 is the partial structural diagram in Fig. 2 at ship reception chamber upstream end.
Fig. 4 is the partial structural diagram of ship reception chamber downstream end in Fig. 2.
Fig. 5 is the overlooking structure diagram of ship reception chamber in the embodiment of the present invention.
Fig. 6 is the partial enlarged view in Fig. 5 at ship reception chamber upstream end.
Fig. 7 is the head bay main view of the embodiment of the present invention.
Fig. 8 is the head bay top view of the embodiment of the present invention.
Fig. 9 is the tail-bay main view of the embodiment of the present invention.
Figure 10 is the tail-bay top view of the embodiment of the present invention.
Description of symbols:
Main hoist system 1;Head bay headstock gear 2;Ship reception chamber 3;Tail-bay headstock gear 7;
Head bay 4;Head bay work gate 4-1;Head bay work wicket 4-2;Head bay work wicket guide wheel 4-3;Head bay Work wicket side guide wheel 4-4;Head bay work wicket water seal 4-5;Head bay work gate side guide wheel 4-6;Head bay work is big Door water seal 4-7;Head bay work gate guide wheel 4-8;Dock water seal 4-9 in head bay work gate;Head bay work gate docking Guide pin 4-10;Head bay gate slot 4-11;
Ship compartment early-stage work door 5;Early-stage work door in ship compartment docks guide groove 5-1;Ship compartment early-stage work door hydraulic headstock gear 5-2; Ship compartment early-stage work Men Menye 5-3;
Ship compartment downstream cleaning door 6;Ship compartment downstream cleaning door headstock gear 6-1;Ship compartment downstream cleaning door gate flap 6-2;Ship compartment downstream work Make door docking guide pin 6-3;Ship compartment downstream cleaning door docks water seal 6-4;
Tail-bay 8;Tail-bay work gate guide wheel 8-1;Tail-bay work gate side guide wheel 8-2;Tail-bay work gate water seal 8-3;Tail-bay work gate 8-4;Tail-bay work wicket 8-5;Tail-bay work wicket water seal 8-6;Tail-bay work wicket Dock guide groove 8-7;Tail-bay work wicket hydraulic headstock gear 8-8;Tail-bay gate slot 8-9.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawing and by embodiment, and following embodiment is to this hair Bright explanation and the invention is not limited to following embodiments.
Embodiment.
Referring to Fig. 1 to Figure 10.
A kind of vertical ship lift docking facilities are provided in the present embodiment, which includes main hoist system 1, ship reception chamber 3, ship compartment early-stage work door 5, ship compartment downstream cleaning door 6, head bay 4 and tail-bay 8.Main hoist system 1 acts on ship reception chamber 3, For ship reception chamber 3, operation provides power above and below.Ship compartment early-stage work door 5 is mounted on the upstream end of ship reception chamber 3, the work of ship compartment downstream Door 6 is mounted on the downstream of ship reception chamber 3.Head bay 4 and ship compartment early-stage work door 5 dock, tail-bay 8 and ship compartment downstream cleaning door 6 docking.
In the present embodiment, ship compartment early-stage work door 5 includes ship compartment early-stage work Men Menye 5-3, ship compartment early-stage work door door Leaf 5-3 along the vertical direction can oscilaltion removably mount in the gate slot of 3 upstream side of ship reception chamber, ship compartment early-stage work Men Menye Two ship compartment early-stage work doors are installed on the top surface of 5-3 and dock guide groove 5-1;The both sides of ship compartment early-stage work Men Menye 5-3 point Not Lian Jie a ship compartment early-stage work door hydraulic headstock gear 5-2, ship compartment early-stage work door hydraulic headstock gear 5-2 is mounted on ship reception chamber In the gate slot of 3 upstream sides, on the ship compartment early-stage work door hydraulic headstock gear 5-2 driving ship compartment early-stage work Men Menye 5-3 on both sides Lower lifting moving.
In the present embodiment, head bay 4 includes head bay work gate 4-1, head bay work wicket 4-2 and head bay opening and closing Machine 2;The land side of head bay work gate 4-1 is arranged in head bay work wicket 4-2;The bottom surface of head bay work gate 4-1 On be provided with and dock guide groove 5-1 one-to-one head bay work gate docking guide pin 4-10 with ship compartment early-stage work door; When upstream is docked, head bay work gate docking guide pin 4-10 is inserted into corresponding ship compartment early-stage work door and docks guide groove In 5-1, when being additionally provided on the bottom surface of head bay work gate 4-1 for docking between ship compartment early-stage work Men Menye 5-3 The head bay work gate docking water seal 4-9 being sealed.
In the present embodiment, the work cross section of gate 4-1 of head bay is in convex, that side of protrusion close to ship reception chamber 3, The size of the protrusion part is consistent with ship compartment early-stage work Men Menye 5-3, and the structure of the protrusion part be hollow structure, two Side offers gate slot, and the two sides of head bay work wicket 4-2 are respectively mounted column head bay work wicket guide wheel 4-3, the head bay Work wicket guide wheel 4-3 is mounted in the gate slot.
In the present embodiment, head bay work wicket 4-2 meet water side be also equipped with head bay work wicket side guide wheel 4-4, on Lock head work wicket 4-2 land side is equipped with the U-shaped head bay work for being sealed between head bay work gate 4-1 Wicket water seal 4-5.The two sides of head bay work gate 4-1 are respectively arranged with head bay gate slot 4-11, head bay work gate 4-1 Two sides are respectively mounted column head bay work gate guide wheel 4-8, and head bay work gate guide wheel 4-8 is located at head bay gate slot 4-11 Interior, head bay work gate 4-1 is run under the driving of head bay headstock gear 2 along the 4-11 energy oscilaltion of head bay gate slot, with Adapt to variation of water level.Head bay work gate 4-1 land side is also equipped with head bay work gate side guide wheel 4-6, brake application Head work gate 4-1 meet water side be equipped with for being sealed between head bay gate slot 4-11 head bay work gate water seal 4-7。
In the present embodiment, tail-bay 8 includes tail-bay work gate 8-4, tail-bay headstock gear 7, tail-bay work wicket The back of tail-bay work gate 8-4 is arranged in hydraulic headstock gear 8-8 and tail-bay work wicket 8-5, tail-bay work wicket 8-5 Water side;Tail-bay works wicket 8-5 as sunk type cleaning door, and two tail-bays work wickets of installation dock guide grooves on top surface 8-7。
In the present embodiment, the work cross section of gate 8-4 of tail-bay is in convex, that side of protrusion close to ship reception chamber 3, And the structure of the protrusion part is hollow structure, and two sides offer gate slot, and the two sides of tail-bay work wicket 8-5 are installed respectively One tail-bay work wicket hydraulic headstock gear 8-8, tail-bay work wicket hydraulic headstock gear 8-8 driving tail-bay work are small Door 8-5 is run along gate slot oscilaltion.
In the present embodiment, tail-bay, which works, is arranged tail-bay work wicket between wicket 8-5 and tail-bay work gate 8-4 Water seal 8-6.The two sides of tail-bay work gate 8-4 are respectively arranged with tail-bay gate slot 8-9, the tail-bay work two sides gate 8-4 It is respectively mounted column tail-bay work gate guide wheel 8-1, tail-bay work gate guide wheel 8-1 is located in tail-bay gate slot 8-9, lower lock Head work gate 8-4 is run under the driving of tail-bay headstock gear 7 along the 8-9 energy oscilaltion of tail-bay gate slot, to adapt to upstream SEA LEVEL VARIATION.Tail-bay work gate 8-4 land side is also equipped with tail-bay work gate side guide wheel 8-2, and tail-bay work is big Door 8-4 meet water side be equipped with for being sealed between tail-bay gate slot 8-9 tail-bay work gate water seal 8-3.
In the present embodiment, ship compartment downstream cleaning door 6 is hydraulic China's railway industry comprising ship compartment downstream cleaning door headstock gear 6-1 It is hinged on ship reception chamber 3 with the lower end of ship compartment downstream cleaning door gate flap 6-2, ship compartment downstream cleaning door gate flap 6-2, ship compartment downstream work The two sides for making Men Menye 6-2 opening and closing of droping to the ground is realized by ship compartment downstream cleaning door headstock gear 6-1;The bottom surface of 3 downstream of ship reception chamber On be provided with tail-bay work wicket dock the one-to-one ship compartment guide groove 8-7 downstream cleaning door dock guide pin 6-3;Under When trip docking, ship compartment downstream cleaning door docks the corresponding tail-bay work wicket of guide pin 6-3 insertion and docks guide groove 8-7 It is interior, it is sealed between the tail-bay work top surface wicket 8-5 when being additionally provided on the bottom surface of 3 downstream of ship reception chamber for docking Ship compartment downstream cleaning door dock water seal 6-4.
Vertical ship lift interconnection method is additionally provided in the present embodiment, is implemented using above-mentioned docking facilities, this is right The method of connecing is divided into upstream interconnection method and downstream interconnection method.
Upstream interconnection method are as follows: ship reception chamber 3 is by 1 uplink of main hoist system, and close to when docking position, the speed of service reduces to low Speed operation, head bay work gate docking guide pin 4-10 are slowly inserted into ship compartment early-stage work door docking guide groove 5-1, until Head bay work gate docking water seal 4-9 is pressed on ship compartment early-stage work Men Menye 5-3;The still slow uplink of subsequent ship reception chamber 3, Ship compartment early-stage work Men Menye 5-3 slowly sinks down into 3 upstream of ship reception chamber under ship compartment early-stage work door hydraulic headstock gear 5-2 driving In the gate slot of side, when 3 uplink of ship reception chamber reaches regulation docking location, ship reception chamber 3 stops uplink and locks, at this time ship compartment upstream work Make Men Menye 5-3 to sink in place, head bay work gate 4-1 is docked in the gate slot of 3 upstream side of ship reception chamber;And then head bay Headstock gear 2 slings head bay work wicket 4-2, and waters and upstream waters connection, ship can drive into or be driven out in ship reception chamber 3 at this time Ship reception chamber 3;It is driven into designated position or after being driven out to after ship, head bay work wicket 4-2 is closed, and ship reception chamber 3 unlocks simultaneously Slowly decline, while ship compartment early-stage work Men Menye 5-3 rises under ship compartment early-stage work door hydraulic headstock gear 5-2 driving and closes Door.
Downstream interconnection method are as follows: ship reception chamber 3 is by 1 downlink of main hoist system, and close to when docking position, the speed of service reduces to low Speed operation, ship compartment downstream cleaning door docking guide pin 6-3 are slowly inserted into tail-bay work wicket docking guide groove 8-7, until Ship compartment downstream cleaning door docking water seal 6-4 is pressed on tail-bay work wicket 8-5;The still slow downlink of subsequent ship reception chamber 3, lower lock Head work wicket 8-5 slowly sinks down into tail-bay work gate 8-4's under tail-bay work wicket hydraulic headstock gear 8-8 driving In gate slot, when ship reception chamber 3 reaches regulation docking location, ship reception chamber 3 stops uplink and locks, the wicket 8-5 of tail-bay work at this time Sink in place, 3 downstream of ship reception chamber has been docked in the gate slot of tail-bay work gate 8-4;Ship compartment downstream cleaning door Gate flap 6-2 drops to the ground openings under ship compartment downstream cleaning door headstock gear 6-1 driving, at this time waters and downstream waters connection in ship reception chamber 3 Logical, ship can drive into or be driven out to ship reception chamber 3;It is driven into designated position or after being driven out to after ship, ship compartment downstream cleaning door gate flap 6-2 It closes, ship reception chamber 3 unlocks and slow uplink, while tail-bay work wicket 8-5 is in tail-bay work wicket hydraulic switch Slow uplink is closed the door under machine 8-8 driving.
It is any ripe although the present invention is disclosed as above with embodiment, its protection scope being not intended to limit the invention The technical staff for knowing this technology changes and retouches made without departing from the spirit and scope of the invention, should belong to this The protection scope of invention.

Claims (5)

1. a kind of vertical ship lift docking facilities, including main hoist system (1), ship reception chamber (3), ship compartment early-stage work door (5), ship Compartment downstream cleaning door (6), head bay (4) and tail-bay (8);The main hoist system (1) acts on ship reception chamber (3), to hold ship Operation provides power above and below in compartment (3);The ship compartment early-stage work door (5) is mounted on the upstream end of ship reception chamber (3), the ship compartment Downstream cleaning door (6) is mounted on the downstream of ship reception chamber (3);The head bay (4) and ship compartment early-stage work door (5) docking, institute State tail-bay (8) and ship compartment downstream cleaning door (6) docking;It is characterized by:
The ship compartment early-stage work door (5) includes ship compartment early-stage work Men Menye (5-3), the ship compartment early-stage work Men Menye (5-3) along the vertical direction can oscilaltion removably mount in the gate slot of ship reception chamber (3) upstream side, ship compartment early-stage work door door Two ship compartment early-stage work door docking guide groove (5-1) are at least installed on the top surface of leaf (5-3);
The head bay (4) includes head bay work gate (4-1) and head bay work wicket (4-2);The head bay work Land side of wicket (4-2) setting in head bay work gate (4-1);It is set on the bottom surface of head bay work gate (4-1) It is equipped with and docks one-to-one head bay work gate docking guide pin (4-10) of guide groove (5-1) with ship compartment early-stage work door; When upstream is docked, head bay work gate docking guide pin (4-10) is inserted into corresponding ship compartment early-stage work door docking In guide groove (5-1), when being additionally provided on the bottom surface of head bay work gate (4-1) for docking with the early-stage work of ship compartment Head bay work gate docking water seal (4-9) being sealed between door gate flap (5-3);
The tail-bay (8) includes tail-bay work gate (8-4) and tail-bay work wicket (8-5), tail-bay work wicket Land side of (8-5) setting in tail-bay work gate (8-4);Tail-bay work wicket (8-5) is sunk type cleaning door, Two tail-bay work wicket docking guide groove (8-7) are at least installed on its top surface;
Ship compartment downstream cleaning door (6) is hydraulic China's railway industry comprising under ship compartment downstream cleaning door headstock gear (6-1) and ship compartment It swims cleaning door gate flap (6-2), the lower end of ship compartment downstream cleaning door gate flap (6-2) is hinged on ship reception chamber (3), ship compartment downstream The two sides of cleaning door gate flap (6-2) opening and closing of droping to the ground is realized by ship compartment downstream cleaning door headstock gear (6-1);The ship reception chamber (3) It is provided on the bottom surface of downstream and docks the one-to-one ship compartment downstream cleaning door pair of guide groove (8-7) with tail-bay work wicket Meet guide pin (6-3);When downstream is docked, ship compartment downstream cleaning door docks guide pin (6-3) and is inserted into corresponding lower lock In head work wicket docking guide groove (8-7), when being additionally provided on the bottom surface of ship reception chamber (3) downstream for docking under Ship compartment downstream cleaning door docking water seal (6-4) being sealed between lock head work top surface wicket (8-5).
2. vertical ship lift docking facilities according to claim 1, it is characterised in that: the ship compartment early-stage work Men Menye The both sides of (5-3) are separately connected a ship compartment early-stage work door hydraulic headstock gear (5-2), ship compartment early-stage work door hydraulic headstock gear (5-2) is mounted in the gate slot of ship reception chamber (3) upstream side, and the ship compartment early-stage work door hydraulic headstock gear (5-2) on both sides drives ship Early-stage work Men Menye (5-3) oscilaltion in compartment is mobile;Two are installed on the top surface of the ship compartment early-stage work Men Menye (5-3) Early-stage work door in ship compartment docks guide groove (5-1).
3. vertical ship lift docking facilities according to claim 1, it is characterised in that: on the head bay (4) further includes Lock head headstock gear (2);
The cross section of head bay work gate (4-1) is in convex, that side of protrusion is close to ship reception chamber (3), the protrusion Unanimously, and the structure of the protrusion part is hollow structure by partial size and ship compartment early-stage work Men Menye (5-3), and two sides are opened Equipped with gate slot, the two sides of head bay work wicket (4-2) are respectively mounted column head bay work wicket guide wheel (4-3), on this Lock head work wicket guide wheel (4-3) is mounted in the gate slot, and the side that meets water head bay work wicket (4-2) is also equipped with head bay work Make wicket side guide wheel (4-4), head bay work wicket (4-2) land side be equipped with for and head bay work gate (4-1) it Between be sealed U-shaped head bay work wicket water seal (4-5);
The two sides of head bay work gate (4-1) are respectively arranged with head bay gate slot (4-11), head bay work gate (4- 1) two sides are respectively mounted column head bay work gate guide wheel (4-8), and head bay work gate guide wheel (4-8) is located at the head bay In gate slot (4-11), head bay work gate (4-1) is under the driving of head bay headstock gear (2) along head bay gate slot (4- 11) energy oscilaltion operation, to adapt to variation of water level;Described head bay work gate (4-1) land side is also equipped with Lock head works gate side guide wheel (4-6), head bay work gate (4-1) meet water side be equipped with for and head bay gate slot Head bay work gate water seal (4-7) being sealed between (4-11).
4. vertical ship lift docking facilities according to claim 1, it is characterised in that: under the tail-bay (8) further includes Lock head headstock gear (7) and tail-bay work wicket hydraulic headstock gear (8-8);
The cross section of tail-bay work gate (8-4) is in convex, that side of protrusion is somebody's turn to do close to ship reception chamber (3) The structure for protruding part is hollow structure, and two sides offer gate slot, and the two sides of tail-bay work wicket (8-5) are installed respectively One tail-bay works wicket hydraulic headstock gear (8-8), and tail-bay work wicket hydraulic headstock gear (8-8) drives tail-bay work Make wicket (8-5) to run along gate slot oscilaltion;Tail-bay work wicket (8-5) and tail-bay work gate (8-4) it Between setting tail-bay work wicket water seal (8-6);
The two sides of tail-bay work gate (8-4) are respectively arranged with tail-bay gate slot (8-9), tail-bay work gate (8- 4) two sides are respectively mounted column tail-bay work gate guide wheel (8-1), and tail-bay work gate guide wheel (8-1) is located at the tail-bay In gate slot (8-9), tail-bay work gate (8-4) is under the driving of tail-bay headstock gear (7) along tail-bay gate slot (8-9) Energy oscilaltion operation, to adapt to variation of water level;Described tail-bay work gate (8-4) land side is also equipped with tail-bay Work gate side guide wheel (8-2), tail-bay work gate (8-4) meet water side be equipped with for and tail-bay gate slot (8-9) Between be sealed tail-bay work gate water seal (8-3).
5. a kind of vertical ship lift interconnection method is carried out real using docking facilities described in claim 1-4 any claim It applies, it is characterised in that:
Upstream interconnection method are as follows: ship reception chamber (3) is by main hoist system (1) uplink, and close to when docking position, the speed of service reduces to low Speed operation, head bay work in slow insertion ship compartment early-stage work door docking guide groove (5-1) of gate docking guide pin (4-10), Until head bay work gate docking water seal (4-9) is pressed on ship compartment early-stage work Men Menye (5-3);Subsequent ship reception chamber (3) Still slow uplink, under ship compartment early-stage work Men Menye (5-3) is slow under ship compartment early-stage work door hydraulic headstock gear (5-2) driving It is sink in the gate slot of ship reception chamber (3) upstream side, when ship reception chamber (3) uplink reaches regulation docking location, ship reception chamber (3) stops uplink And lock, ship compartment early-stage work Men Menye (5-3) sinks in place at this time, and head bay work gate (4-1) is docked to ship reception chamber (3) In the gate slot of upstream side;And then head bay headstock gear (2) slings head bay work wicket (4-2), at this time ship reception chamber (3) interior water Domain and upstream waters connection, ship can drive into or be driven out to ship reception chamber (3);It is driven into designated position or after being driven out to after ship, brake application Head work wicket (4-2) is closed, and ship reception chamber (3) unlocks and slowly declines, while ship compartment early-stage work Men Menye (5-3) exists Lower rise of ship compartment early-stage work door hydraulic headstock gear (5-2) driving is closed the door;
Downstream interconnection method are as follows: ship reception chamber (3) is by main hoist system (1) downlink, and close to when docking position, the speed of service reduces to low Speed operation, ship compartment downstream cleaning door dock guide pin (6-3) and are slowly inserted into tail-bay work wicket docking guide groove (8-7), Until ship compartment downstream cleaning door docking water seal (6-4) is pressed in tail-bay work wicket (8-5);Subsequent ship reception chamber (3) is still slow Slow downlink, tail-bay work wicket (8-5) slowly sink down into Xia Zha under tail-bay work wicket hydraulic headstock gear (8-8) driving In the gate slot of head work gate (8-4), when ship reception chamber (3) reaches regulation docking location, ship reception chamber (3) stops uplink and locks, Tail-bay work wicket (8-5) has been sunk in place at this time, and ship reception chamber (3) downstream has been docked to tail-bay work gate In the gate slot of (8-4);Ship compartment downstream cleaning door gate flap (6-2) is droped to the ground under ship compartment downstream cleaning door headstock gear (6-1) driving and is beaten It opens, ship reception chamber (3) interior waters and downstream waters connection, ship can drive into or be driven out to ship reception chamber (3) at this time;It drives into ship to finger After positioning is set or is driven out to, ship compartment downstream cleaning door gate flap (6-2) is closed, and ship reception chamber (3) unlocks and slow uplink, at present Lock head work wicket (8-5) slow uplink under tail-bay work wicket hydraulic headstock gear (8-8) driving is closed the door.
CN201910669237.1A 2019-07-24 2019-07-24 Docking device and method for vertical ship lift Active CN110374079B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910669237.1A CN110374079B (en) 2019-07-24 2019-07-24 Docking device and method for vertical ship lift

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910669237.1A CN110374079B (en) 2019-07-24 2019-07-24 Docking device and method for vertical ship lift

Publications (2)

Publication Number Publication Date
CN110374079A true CN110374079A (en) 2019-10-25
CN110374079B CN110374079B (en) 2024-02-27

Family

ID=68255281

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910669237.1A Active CN110374079B (en) 2019-07-24 2019-07-24 Docking device and method for vertical ship lift

Country Status (1)

Country Link
CN (1) CN110374079B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111424628A (en) * 2020-04-24 2020-07-17 长江三峡通航管理局 Ship chamber butt joint method of ship lift adapting to rapid fluctuation of water level

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2264756Y (en) * 1996-03-05 1997-10-15 电力工业部华东勘测设计研究院 Butt sealing device
CN202380451U (en) * 2011-12-14 2012-08-15 浙江大学 Linearly assembled type full-balance vertical ship lifter
CN108086281A (en) * 2017-12-04 2018-05-29 河海大学 A kind of energy saving ship lift of small-sized lever and its operation method
CN108166458A (en) * 2017-12-28 2018-06-15 中国长江三峡集团公司 The integrated gate of ship lift navigation
CN108914907A (en) * 2018-06-13 2018-11-30 杭州国电机械设计研究院有限公司 A kind of automatic control flow chart of full-balance steel wire rope winch-type vertical ship lift
CN210766697U (en) * 2019-07-24 2020-06-16 杭州国电机械设计研究院有限公司 Butt joint device of vertical ship lift

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2264756Y (en) * 1996-03-05 1997-10-15 电力工业部华东勘测设计研究院 Butt sealing device
CN202380451U (en) * 2011-12-14 2012-08-15 浙江大学 Linearly assembled type full-balance vertical ship lifter
CN108086281A (en) * 2017-12-04 2018-05-29 河海大学 A kind of energy saving ship lift of small-sized lever and its operation method
CN108166458A (en) * 2017-12-28 2018-06-15 中国长江三峡集团公司 The integrated gate of ship lift navigation
CN108914907A (en) * 2018-06-13 2018-11-30 杭州国电机械设计研究院有限公司 A kind of automatic control flow chart of full-balance steel wire rope winch-type vertical ship lift
CN210766697U (en) * 2019-07-24 2020-06-16 杭州国电机械设计研究院有限公司 Butt joint device of vertical ship lift

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111424628A (en) * 2020-04-24 2020-07-17 长江三峡通航管理局 Ship chamber butt joint method of ship lift adapting to rapid fluctuation of water level
CN111424628B (en) * 2020-04-24 2021-09-14 长江三峡通航管理局 Ship chamber butt joint method of ship lift adapting to rapid fluctuation of water level
CN113529679A (en) * 2020-04-24 2021-10-22 长江三峡通航管理局 Ship chamber accurate butt joint method of ship lift under fluctuation of ship chamber water level
CN113529679B (en) * 2020-04-24 2022-05-31 长江三峡通航管理局 Ship chamber accurate butt joint method of ship lift under fluctuation of ship chamber water level

Also Published As

Publication number Publication date
CN110374079B (en) 2024-02-27

Similar Documents

Publication Publication Date Title
CN110318376A (en) A kind of hydraulic engineering valve system
CN110374079A (en) A kind of vertical ship lift docking facilities and method
CN110004889A (en) A kind of hydraulic engineering flashboard
CN106320312A (en) Water-saving ship lock and ship lockage method thereof
CN208857807U (en) It is a kind of to fill sluicing and water charging system for large scale ship
CN201162208Y (en) Floater horizontal opening door
KR101184643B1 (en) Pump mounted gate
CN210766697U (en) Butt joint device of vertical ship lift
KR100960074B1 (en) A hydraulic shutting device for floodgate
CN205188912U (en) Floodgate is overhauld to flotation tank formula
CN201459701U (en) Perpendicular ship elevator
CN211948291U (en) Automatic flood control gate for dam
CN201526034U (en) Dual-linkage pulley guide plate type flap gate
CN209114430U (en) A kind of gear-driven silting blocking postposition flap valve filling valve
CN209384204U (en) A kind of small-sized sluice gate convenient for adjusting flow
CN209144761U (en) With the engineering sluice for intercepting function
JPH0716740Y2 (en) Gate pump equipment
KR200180807Y1 (en) The opening and closing device of wafer interseption plate utilizing the oilpressure
CN106223406B (en) It is a kind of to couple submersible pump certainly with the cable-stayed type for sealing sramana's device
CN206143736U (en) Novel rise horizontal sluice
CN101914908A (en) Water stop rubber protection device for flat steel gate
CN218090741U (en) Water course gate drive arrangement and dam
CN210766696U (en) Vertical ship lift low reaches interfacing apparatus
CN206635728U (en) The small-sized sluice of the semi-automatic keying of energy
CN221320850U (en) Hydraulic engineering flood prevention gate

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant