CN110359492A - A kind of construction method of large scale prefabricated piping lane - Google Patents

A kind of construction method of large scale prefabricated piping lane Download PDF

Info

Publication number
CN110359492A
CN110359492A CN201910596060.7A CN201910596060A CN110359492A CN 110359492 A CN110359492 A CN 110359492A CN 201910596060 A CN201910596060 A CN 201910596060A CN 110359492 A CN110359492 A CN 110359492A
Authority
CN
China
Prior art keywords
piping lane
large scale
pushing tow
prefabricated piping
scale prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910596060.7A
Other languages
Chinese (zh)
Other versions
CN110359492B (en
Inventor
王宝莹
关宏生
张荣福
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ANSHAN SANYE CONSTRUCTION ENGINEERING Co Ltd
Original Assignee
ANSHAN SANYE CONSTRUCTION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANSHAN SANYE CONSTRUCTION ENGINEERING Co Ltd filed Critical ANSHAN SANYE CONSTRUCTION ENGINEERING Co Ltd
Priority to CN201910596060.7A priority Critical patent/CN110359492B/en
Publication of CN110359492A publication Critical patent/CN110359492A/en
Application granted granted Critical
Publication of CN110359492B publication Critical patent/CN110359492B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

A kind of construction method of large scale prefabricated piping lane, this method is that track is laid in foundation pit, and large scale prefabricated piping lane is transported to installation site by translating, realizes the installation of large scale prefabricated piping lane.The present invention in foundation pit using track is laid with, and the mode for translate in foundation pit to large-scale piping lane is installed, and piping lane absolute altitude is easy to adjust, and installation accuracy is high, saves foundation pit space, and translation mode is simple and fast.Pushing tow trolley of the invention jacks up the Hoisting Position of large scale prefabricated piping lane with strut from below, and the installed height mark of piping lane is adjusted by the thread, and precision is very high, and convenient for construction.For piping lane when prestressing force connects, the stability of erecting structure is very high, and installation error is small.The form that pushing tow driving device of the invention is combined using flexible pushing tow hydraulic jack with hydraulic rail meter pushes pushing tow trolley to carry out by push-and-pull repeatedly, realize the translation of large scale prefabricated piping lane, whole device occupies little space, convenient and quick construction, high-efficient.

Description

A kind of construction method of large scale prefabricated piping lane
Technical field
The present invention relates to the realm of building construction more particularly to a kind of construction methods of large scale prefabricated piping lane.
Background technique
The prefabricated piping lane of open cut is the advanced technology of rising in recent years, can greatly speed up construction speed, reduces construction investment.Certain City's pipe gallery project is certain province's major project, this engineering cloth is the first batch of piping lane demonstration work in the Northeast all over entire urban district Journey.To accelerate piping lane construction speed, which uses prefabricated piping lane, by certain group's building product Engineering company carries out Deepen Design, production, installation.
The prefabricated piping lane job location across a urban district main road, can only half range closing half range construction, and below road Various municipal pipelines have been covered with it, for the complex situations of the engineering, installation for large-scale piping lane can not be using directly hanging The form of dress brings very big difficulty to construction.
Summary of the invention
It is right using being laid with track in foundation pit the object of the present invention is to provide a kind of construction method of large scale prefabricated piping lane The mode that large-scale piping lane translate in foundation pit is installed, and piping lane absolute altitude is easy to adjust, and installation accuracy is high, and it is empty to save foundation pit Between, translation mode is simple and fast, easy for construction high-efficient, thus solve can not lifting construction the technology of large scale prefabricated piping lane is installed Problem.
In order to achieve the above object, the present invention is implemented with the following technical solutions:
A kind of construction method of large scale prefabricated piping lane, this method is that track is laid in foundation pit, will be large-scale pre- by translation Tubulation corridor is transported to installation site, realizes the installation of large scale prefabricated piping lane, the specific method is as follows:
1) make pushing tow trolley: pushing tow trolley includes girder steel vehicle frame, supporting steel pipe, adjusting screw rod, and adjusting screw rod is hinged on The upper end of girder steel vehicle frame, supporting steel pipe are connected through a screw thread adjusting screw rod, are equipped with bracket in the upper end of supporting steel pipe, bracket and big Lifting steel pipe on the prefabricated piping lane of type matches;
2) tile track in the installation foundation pit of prefabricated piping lane, and a pushing tow trolley is respectively set on two tracks;
3) make two pushing tow driving devices: pushing tow driving device is made of hydraulic rail meter and pushing tow jack, hydraulic In orbit, one end of pushing tow jack connects hydraulic rail meter for rail meter setting, and the other end connects pushing tow trolley;
4) large scale prefabricated piping lane is maneuvered into the top of two pushing tow trolleies by crane, makes to be plugged on large scale prefabricated piping lane The top steel loading stick of lower end two sides is placed on two pushing tow trolleies, then respectively places a jacking in the side of two girder steel vehicle frames Jack will push up steel loading stick by jack and jack up, large scale prefabricated piping lane is jacked up to mounting height, supporting steel pipe is adjusted Height and the lifting rod iron for being plugged on large scale prefabricated piping lane upper end two sides is held by the bracket of supporting steel pipe upper end, then pushing up Pad upper billet in steel loading stick bottom;
5) by hydraulic rail meter clamping track, it is small to stretch out pushing tow of the pushing tow jack pushing frame equipped with large scale prefabricated piping lane Vehicle is advanced forward, and hydraulic rail meter is then unclamped, and retracts pushing tow jack, and band hydrodynamic pressure rail meter is advanced forward, repeated above-mentioned The translation to large scale prefabricated piping lane is realized in operation;
6) after large scale prefabricated piping lane being moved to installation site, directly large scale prefabricated piping lane is carried out under the mounting height Installed under prestressing.
The hydraulic rail meter includes hydraulic cylinder, locating piece, positioning plate, link arm, clamping jaw, the locating piece and hydraulic cylinder Connection, the piston of hydraulic cylinder pass through locating piece, end articulated linkage arm, and the positioning plate is fixed on the positioning block, the clamping jaw Fulcrum and positioning plate it is hinged, the other end and clamping jaw of the link arm are hinged.
Compared with prior art, the beneficial effects of the present invention are:
A kind of construction method of large scale prefabricated piping lane carries out in foundation pit large-scale piping lane using track is laid in foundation pit The mode of translation is installed, and piping lane absolute altitude is easy to adjust, and installation accuracy is high, saves foundation pit space, and translation mode is simple and fast, It is easy for construction high-efficient.
Pushing tow trolley of the invention jacks up the Hoisting Position of large scale prefabricated piping lane with strut from below, the installation mark of piping lane High pass screw thread is adjusted, and precision is very high, and convenient for construction.For piping lane when prestressing force connects, the stability of erecting structure is non- Chang Gao, installation error are small.
The form that pushing tow driving device of the invention is combined using flexible pushing tow hydraulic jack with hydraulic rail meter, leads to Push-and-pull repeatedly is crossed, pushes pushing tow trolley to carry out, realizes the translation of large scale prefabricated piping lane, whole device occupies little space, construction It is convenient and efficient, it is high-efficient.
Detailed description of the invention
Fig. 1 is the foundation pit handling figure of the medium-and-large-sized prefabricated piping lane of the present invention;
Fig. 2 is that large scale prefabricated piping lane sets up the pushing tow schematic diagram to adjustment absolute altitude on pushing tow trolley;
Fig. 3 is erection schematic diagram (side view) of the large scale prefabricated piping lane on pushing tow trolley after adjusting absolute altitude;
Fig. 4 is the main view of Fig. 3;
Fig. 5 is the schematic diagram of internal structure of hydraulic rail meter;
Fig. 6 is the side view of the internal structure of hydraulic rail meter.
In figure: 1- hydraulic rail clamp, 1-1 hydraulic cylinder, 1-2 locating piece, 1-3 piston, 1-4 link arm, 1-5 clamping jaw, 1-6 are sliding Rail, 1-7 shell, 1-8 positioning plate, 2- track, 3- pushing tow jack, the large scale prefabricated piping lane of 4-, 5- lift rod iron, 6- supporting steel Pipe, 7- adjusting screw rod, 8- girder steel vehicle frame, 9- steel bearing beam, 10- billet, 11- pea gravel concreten waterproof protective layer, 12- pushing tow thousand Jin top, 13- hydraulic oil pipe, 14- idler wheel, 15- reserve hole for hoist, 16- pushing tow rod iron.
Specific embodiment
Specific embodiments of the present invention will be further explained with reference to the accompanying drawing:
See Fig. 1-Fig. 6, a kind of construction method of large scale prefabricated piping lane, this method is the laying track 2 in foundation pit, by flat It moves and large scale prefabricated piping lane 4 is transported to installation site, realize the installation of large scale prefabricated piping lane 4, the specific method is as follows:
1) make pushing tow trolley: pushing tow trolley includes girder steel vehicle frame 8, supporting steel pipe 6, adjusting screw rod 7, and adjusting screw rod 7 is cut with scissors It connecing in the upper end of girder steel vehicle frame 8, supporting steel pipe 6 is connected through a screw thread adjusting screw rod 7, it is equipped with bracket in the upper end of supporting steel pipe 6, Bracket matches with the lifting steel pipe 5 on large scale prefabricated piping lane 4.
The length of girder steel vehicle frame 8 is 3-4 times of large scale prefabricated 4 width of piping lane, and the supporting steel pipe 6 and adjusting screw rod 7 are equal It is two, two adjusting screw rods 7 are symmetricly set on the both ends of girder steel vehicle frame 8, and the distance between two 7 hinge joints of adjusting screw rod are 2-3 times of large scale prefabricated 4 width of piping lane.Supporting steel pipe 6 and adjusting screw rod 7 are socketed, and high-strength spiral shell is bolted on adjusting screw rod 7 Mother, supporting steel pipe 6 are withstood on high-strength nut, opposite with adjusting screw rod 7 by screwing the adjustable supporting steel pipe 6 of high-strength nut Highly.
2) tile track 2 in the installation foundation pit of prefabricated piping lane, and it is small that a pushing tow is respectively set on two tracks 2 Vehicle.
Track 2 is heavy rail, and 8 traveling of girder steel vehicle frame is on track 2.The bottom of girder steel vehicle frame 8 is equipped with and 2 phase of track The sliding rail groove matched, fills lubricating oil between girder steel vehicle frame 8 and track 2, girder steel vehicle frame 8 can slide on track 2.In girder steel The upper end of vehicle frame 8 is further fixed on steel bearing beam 9.Rail wheel can also be set in 8 bottom of girder steel vehicle frame, by rail wheel in track 2 Upper walking.
3) make two pushing tow driving devices: pushing tow driving device is made of hydraulic rail meter 1 and pushing tow jack 3, liquid Rail meter 1 is pressed to be arranged on track 2, one end of pushing tow jack 3 connects hydraulic rail meter 1, and the other end connects pushing tow trolley;
4) large scale prefabricated piping lane 4 is maneuvered into the top of two pushing tow trolleies by crane, makes to be plugged on large scale prefabricated pipe The top steel loading stick 16 of 4 lower end two sides of corridor is placed on two pushing tow trolleies, then respectively places one in the side of two girder steel vehicle frames 8 A jack 12 is jacked up steel loading stick 16 is pushed up by jack 12, large scale prefabricated piping lane 4 is jacked up high to installation Degree adjusts the height of supporting steel pipe 6 and is held by the bracket of 6 upper end of supporting steel pipe and be plugged on large scale prefabricated 4 upper end two of piping lane The lifting rod iron 5 of side, then upper billet 10 is padded in top 16 bottom of steel loading stick;Billet 10 can be for one or multiple, Depending on the height of top steel loading stick 16.
It is equipped with reserved hole for hoist 15 in the two sides of large scale prefabricated piping lane 4, is plugged with and hangs in the reserved hole for hoist 15 of upper end Steel loading stick 5 is plugged with top steel loading stick 16 in the reserved hole for hoist 15 of lower end.
Reserved hole for hoist 15 is 4, and in the setting two each up and down of large scale prefabricated piping lane 4, two in sustained height are pre- Hole for hoist 15 is stayed to be symmetrical arranged.
5) by hydraulic 1 clamping track 2 of rail meter, the top that 3 pushing frame of pushing tow jack is equipped with large scale prefabricated piping lane 4 is stretched out It pushes away trolley to advance forward, then unclamps hydraulic rail meter 1, retract pushing tow jack 3, band hydrodynamic pressure rail meter 1 is advanced forward, weight Multiple aforesaid operations, realize the translation to large scale prefabricated piping lane 4;
6) after large scale prefabricated piping lane 4 being moved to installation site, under the mounting height directly to large scale prefabricated piping lane 4 into Row installed under prestressing.
The hydraulic rail meter 1 includes hydraulic cylinder 1-1, locating piece 1-2, positioning plate 1-8, link arm 1-4, clamping jaw 1-5, institute Locating piece 1-2 is stated to connect with hydraulic cylinder 1-1, the piston 1-3 of hydraulic cylinder 1-1 passes through locating piece 1-2, end articulated linkage arm 1-4, The positioning plate 1-8 is fixed on locating piece 1-2, the clamping jaw 1-5 be crank-type lever construction, the fulcrum of clamping jaw 1-5 with Positioning plate 1-8 is hinged, and the other end and clamping jaw 1-5 of the link arm 1-4 is hinged.The inner shape of clamping jaw 1-5 and track phase Match.
It clamped, unclamped by the flexible drive clamping jaw 1-5 of piston 1-3, be additionally provided with sliding rail 1-6 in the two sides of clamping jaw 1-5, it is sliding Rail 1-6 is equipped with the sliding rail groove to match with track 2, and hydraulic rail meter 1 is slided on track 2.When clamping jaw 1-5 is pressed from both sides When tight track, pushing tow jack 3 is stretched out, girder steel vehicle frame 8 is pushed to advance on track 2;When unclamping clamping jaw 1-5, pushing tow thousand is retracted Jin top 3, then hydraulic rail meter 1 is advanced in orbit.Above-mentioned movement is repeated, pushing tow driving device will constantly promote pushing tow small Vehicle and the translation of large scale prefabricated piping lane 4 are advanced, and large scale prefabricated piping lane 4 is finally transported to installation site and carries out prestressing force connection installation.
The present invention sets up large scale prefabricated piping lane 4, and adjustable large size by two girder steel vehicle frames 8 walked in orbit The erection absolute altitude of prefabricated piping lane 4 guarantees that large scale prefabricated piping lane 4 smoothly moves to installation site in foundation pit, and guarantees big Stability and installation accuracy when prefabricated 4 installed under prestressing of piping lane of type;When reducing foundation pit upper end has barrier, large scale prefabricated piping lane 4 installation difficulty improves construction efficiency, guarantees construction quality.

Claims (2)

1. a kind of construction method of large scale prefabricated piping lane, which is characterized in that this method is to lay track in foundation pit, passes through translation Large scale prefabricated piping lane is transported to installation site, realizes the installation of large scale prefabricated piping lane, the specific method is as follows:
1) make pushing tow trolley: pushing tow trolley includes girder steel vehicle frame, supporting steel pipe, adjusting screw rod, and adjusting screw rod is hinged on girder steel The upper end of vehicle frame, supporting steel pipe are connected through a screw thread adjusting screw rod, are equipped with bracket in the upper end of supporting steel pipe, bracket is pre- with large size Lifting steel pipe on tubulation corridor matches;
2) tile track in the installation foundation pit of prefabricated piping lane, and a pushing tow trolley is respectively set on two tracks;
3) make two pushing tow driving devices: pushing tow driving device is made of hydraulic rail meter and pushing tow jack, hydraulic clamp rail In orbit, one end of pushing tow jack connects hydraulic rail meter for device setting, and the other end connects pushing tow trolley;
4) large scale prefabricated piping lane is maneuvered into the top of two pushing tow trolleies by crane, makes to be plugged on large scale prefabricated piping lane lower end The top steel loading stick of two sides is placed on two pushing tow trolleies, and it is very heavy then respectively to place a jacking in the side of two girder steel vehicle frames Top will push up steel loading stick by jack and jack up, large scale prefabricated piping lane is jacked up to mounting height, the height of supporting steel pipe is adjusted It spends and the bracket for passing through supporting steel pipe upper end holds the lifting rod iron for being plugged on large scale prefabricated piping lane upper end two sides, then in top steel loading Pad upper billet in stick bottom;
5) by hydraulic rail meter clamping track, stretch out pushing tow jack pushing frame be equipped with the pushing tow trolley of large scale prefabricated piping lane to Move ahead into, then unclamp hydraulic rail meter, retract pushing tow jack, band hydrodynamic pressure rail meter is advanced forward, repeat aforesaid operations, Realize the translation to large scale prefabricated piping lane;
6) after large scale prefabricated piping lane being moved to installation site, directly large scale prefabricated piping lane is answered in advance under the mounting height Power installation.
2. a kind of construction method of large scale prefabricated piping lane according to claim 1, which is characterized in that the hydraulic rail meter Including hydraulic cylinder, locating piece, positioning plate, link arm, clamping jaw, the locating piece is connect with hydraulic cylinder, and the piston of hydraulic cylinder passes through Locating piece, end articulated linkage arm, the positioning plate are fixed on the positioning block, and the fulcrum and positioning plate of the clamping jaw are hinged, institute The other end and the clamping jaw for stating link arm are hinged.
CN201910596060.7A 2019-07-03 2019-07-03 Construction method of large prefabricated pipe gallery Active CN110359492B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910596060.7A CN110359492B (en) 2019-07-03 2019-07-03 Construction method of large prefabricated pipe gallery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910596060.7A CN110359492B (en) 2019-07-03 2019-07-03 Construction method of large prefabricated pipe gallery

Publications (2)

Publication Number Publication Date
CN110359492A true CN110359492A (en) 2019-10-22
CN110359492B CN110359492B (en) 2021-07-13

Family

ID=68218049

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910596060.7A Active CN110359492B (en) 2019-07-03 2019-07-03 Construction method of large prefabricated pipe gallery

Country Status (1)

Country Link
CN (1) CN110359492B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112523257A (en) * 2020-11-20 2021-03-19 中冶天工集团有限公司 Multi-angle prefabricated pipe gallery sliding device with adjustable lifting points and using method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201580385U (en) * 2010-02-07 2010-09-15 太原市银利达机械配件厂 Hydraulic pulling rail clamping vehicle
CN105442399A (en) * 2015-12-28 2016-03-30 上海市安装工程集团有限公司 Rail assembly supporting trolley and rail assembly method
CN206267152U (en) * 2016-12-05 2017-06-20 上海公路桥梁(集团)有限公司 Prefabricated pipe gallery installs alignment system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201580385U (en) * 2010-02-07 2010-09-15 太原市银利达机械配件厂 Hydraulic pulling rail clamping vehicle
CN105442399A (en) * 2015-12-28 2016-03-30 上海市安装工程集团有限公司 Rail assembly supporting trolley and rail assembly method
CN206267152U (en) * 2016-12-05 2017-06-20 上海公路桥梁(集团)有限公司 Prefabricated pipe gallery installs alignment system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112523257A (en) * 2020-11-20 2021-03-19 中冶天工集团有限公司 Multi-angle prefabricated pipe gallery sliding device with adjustable lifting points and using method thereof

Also Published As

Publication number Publication date
CN110359492B (en) 2021-07-13

Similar Documents

Publication Publication Date Title
US20210354735A1 (en) Telescopic multifunctional working vehicle capable of operating in both directions and evacuating transversely and application method thereof
CN104908149A (en) Template system of magnetic-levitation linear track beam and application method
CN204457802U (en) Formed by integrally casting formula formwork jumbo
CN100424322C (en) Full circle once lining segregation type nose girder module bench and its construction method
CN103938880A (en) Overall sliding construction method for large-span special-shaped space grid pipe truss
CN203213623U (en) Slide guiding and rectifying device
CN106593469A (en) Trolley for construction of inverted arch
CN110359492A (en) A kind of construction method of large scale prefabricated piping lane
CN102305035B (en) Device for adjusting centration of complete vehicle-mounted service machine to wellhead
CN210421166U (en) Large-scale prefabricated piping lane pushes away construction structures
CN106988689A (en) A kind of drilling tool automatic migration device of land science probing rig
CN110359489A (en) A kind of large scale prefabricated piping lane incremental launching construction structure
CN210421167U (en) Installation translation device of large-scale prefabricated piping lane
CN107476334B (en) Prefabricated pipe joint assembling equipment and construction method thereof
CN208632979U (en) The three-dimensional adjustment tooling positioned in erection process for precast segment spliced girder
CN207824160U (en) A kind of quick pressurize pushes away convex DC railway rail flash butt welding machine
CN204002842U (en) In full section, slide rail moves steel form carrier
CN215806769U (en) Drainage pipe of municipal works supports connection structure
CN114232483A (en) Method and device for transversely moving prestressed T beam
CN110359490A (en) A kind of translational installation method of large scale prefabricated piping lane
CN210262748U (en) Cantilever supporting structure for steel box girder pushing construction
CN110359491A (en) A kind of installation translating device of large scale prefabricated piping lane
CN211113199U (en) Pre-assembly equipment for segmental beam
CN207485449U (en) A kind of formwork jumbo for construction
CN213571580U (en) Novel concrete box girder bridging via hole is equipped

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant