CN110318387A - 一种强风化岩钢板桩施工方法 - Google Patents
一种强风化岩钢板桩施工方法 Download PDFInfo
- Publication number
- CN110318387A CN110318387A CN201910565464.XA CN201910565464A CN110318387A CN 110318387 A CN110318387 A CN 110318387A CN 201910565464 A CN201910565464 A CN 201910565464A CN 110318387 A CN110318387 A CN 110318387A
- Authority
- CN
- China
- Prior art keywords
- drilling
- region
- steel sheet
- sheet pile
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/02—Placing by driving
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Composite Materials (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910565464.XA CN110318387A (zh) | 2019-06-27 | 2019-06-27 | 一种强风化岩钢板桩施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910565464.XA CN110318387A (zh) | 2019-06-27 | 2019-06-27 | 一种强风化岩钢板桩施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110318387A true CN110318387A (zh) | 2019-10-11 |
Family
ID=68121203
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910565464.XA Pending CN110318387A (zh) | 2019-06-27 | 2019-06-27 | 一种强风化岩钢板桩施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110318387A (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112962617A (zh) * | 2021-02-06 | 2021-06-15 | 中冶成都勘察研究总院有限公司 | 一种用于风化岩层地区的综合管廊基坑支护方法 |
CN115094872A (zh) * | 2022-07-14 | 2022-09-23 | 中铁九桥工程有限公司 | 一种锁扣钢管桩入岩施工方法及其应用 |
CN115110518A (zh) * | 2022-06-15 | 2022-09-27 | 中交二航局广西建设工程有限公司 | 一种利用旋挖钻机进行水下强风化岩层钢板桩施工方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101649210B1 (ko) * | 2016-01-26 | 2016-08-22 | 원남토건 주식회사 | 원형 강관 벽체 강가시설 |
CN108457283A (zh) * | 2017-04-24 | 2018-08-28 | 中交公局厦门工程有限公司 | 深水硬岩钢板桩围堰引孔开槽注浆施工方法 |
CN109487807A (zh) * | 2018-11-14 | 2019-03-19 | 安徽省公路桥梁工程有限公司 | 一种钢管桩围堰引孔换填施工方法 |
-
2019
- 2019-06-27 CN CN201910565464.XA patent/CN110318387A/zh active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101649210B1 (ko) * | 2016-01-26 | 2016-08-22 | 원남토건 주식회사 | 원형 강관 벽체 강가시설 |
CN108457283A (zh) * | 2017-04-24 | 2018-08-28 | 中交公局厦门工程有限公司 | 深水硬岩钢板桩围堰引孔开槽注浆施工方法 |
CN109487807A (zh) * | 2018-11-14 | 2019-03-19 | 安徽省公路桥梁工程有限公司 | 一种钢管桩围堰引孔换填施工方法 |
Non-Patent Citations (1)
Title |
---|
谭正清等: "《地基与基础工程施工》", 31 May 2016, 电子科技大学出版社 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112962617A (zh) * | 2021-02-06 | 2021-06-15 | 中冶成都勘察研究总院有限公司 | 一种用于风化岩层地区的综合管廊基坑支护方法 |
CN115110518A (zh) * | 2022-06-15 | 2022-09-27 | 中交二航局广西建设工程有限公司 | 一种利用旋挖钻机进行水下强风化岩层钢板桩施工方法 |
CN115110518B (zh) * | 2022-06-15 | 2024-06-25 | 中交二航局广西建设工程有限公司 | 一种利用旋挖钻机进行水下强风化岩层钢板桩施工方法 |
CN115094872A (zh) * | 2022-07-14 | 2022-09-23 | 中铁九桥工程有限公司 | 一种锁扣钢管桩入岩施工方法及其应用 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110318387A (zh) | 一种强风化岩钢板桩施工方法 | |
CN106930766A (zh) | 大埋深tbm施工隧洞岩爆处理结构 | |
CN102031775A (zh) | 硬斜岩中孔爆破钻孔桩施工技术 | |
US20200190907A1 (en) | Method of Surface Borehole Mining Using Horizontal Drilling Techniques | |
CN111593734B (zh) | 一种上软下硬地层中浅埋隧道基坑围护施工方法 | |
CN112647955A (zh) | 一种开挖盲区预处理方法及隧道掘进施工方法 | |
JP4550792B2 (ja) | 地中壁の施工法 | |
CN104612132A (zh) | 挡板搅拌桩墙机 | |
CN207878472U (zh) | 密排阶梯型旋挖桩支护体系 | |
CN213014284U (zh) | 引孔法插打锁扣钢管桩结构 | |
KR100529726B1 (ko) | 강관형 널말뚝 및 그의 시공방법 | |
JP4341029B2 (ja) | 杭基礎工法 | |
CN107462118A (zh) | 大断面隧道循环爆破掘进方法 | |
JP5584373B1 (ja) | 矢板打設工法 | |
KR20180127703A (ko) | 두 개의 롯드를 동시에 장착할 수 있는 2축 일체형 헤드기어박스 천공기계장치 | |
CN208328900U (zh) | 适用于深孔大直径孔桩钢筋笼施工的操作平台 | |
CN113266360A (zh) | 掘进巷道贯通防治冲击地压方法 | |
KR20020068981A (ko) | 강관마이크로파일 및 그라우팅 시공방법 | |
KR20140132640A (ko) | 암 파쇄수단이 구비된 오거드릴 | |
CN218862611U (zh) | Tbm侧向平交山区高速公路隧道掘进平行导洞施工结构 | |
CN113737790B (zh) | 一种桥梁桩与钢板桩同步施工方法 | |
SU1719639A1 (ru) | Способ разработки прочных пород | |
JP7357524B2 (ja) | 山留遮水工法 | |
JPS5848693B2 (ja) | 高圧支柱連続壁工法 | |
Pereira | Cutoffs in dams: overview and recent developments |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20200309 Address after: 545007 No. 138 Heping Road, the Guangxi Zhuang Autonomous Region, Liuzhou Applicant after: THE 4TH ENGINEERING CO., LTD.OF CHINA RAILWAY 25TH BUREAU GROUP Applicant after: China Railway twenty-five Bureau Group Sixth Engineering Co., Ltd. Applicant after: China Railway 25 Bureau Group Co., Ltd. Applicant after: LIUZHOU RAILWAY PROJECT QUALITY AND INSPECTION CENTER CO., LTD. Address before: 545007 No. 75, two district, Hongyan Road, Liuzhou, the Guangxi Zhuang Autonomous Region. Applicant before: China Railway twenty-five Bureau Group Sixth Engineering Co., Ltd. Applicant before: China Railway 25 Bureau Group Co., Ltd. |
|
TA01 | Transfer of patent application right | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191011 |
|
RJ01 | Rejection of invention patent application after publication |