CN110306404A - A kind of colored street floor file construction method - Google Patents

A kind of colored street floor file construction method Download PDF

Info

Publication number
CN110306404A
CN110306404A CN201910618181.7A CN201910618181A CN110306404A CN 110306404 A CN110306404 A CN 110306404A CN 201910618181 A CN201910618181 A CN 201910618181A CN 110306404 A CN110306404 A CN 110306404A
Authority
CN
China
Prior art keywords
parts
floor tile
floor
cement
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910618181.7A
Other languages
Chinese (zh)
Inventor
刘焕新
郭伟民
刘超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Was Established As Polytron Technologies Inc
Original Assignee
Shanghai Was Established As Polytron Technologies Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Was Established As Polytron Technologies Inc filed Critical Shanghai Was Established As Polytron Technologies Inc
Priority to CN201910618181.7A priority Critical patent/CN110306404A/en
Publication of CN110306404A publication Critical patent/CN110306404A/en
Pending legal-status Critical Current

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C15/00Pavings specially adapted for footpaths, sidewalks or cycle tracks
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C5/00Pavings made of prefabricated single units
    • E01C5/003Pavings made of prefabricated single units characterised by material or composition used for beds or joints; characterised by the way of laying
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C5/00Pavings made of prefabricated single units
    • E01C5/04Pavings made of prefabricated single units made of bricks

Abstract

The present invention relates to Construction Technology of Street fields, and disclose a kind of colored street floor file construction method, including following construction procedure: 1) base treatment: the laitance being stained in base, landing ash etc. is fallen with temporary son or brushing, surface dust is cleaned up with broom again, 2) absolute altitude is looked for: according to horizontal standard line and design thickness, in surrounding wall, the upper flat absolute altitude control line of surface layer is popped up on column, 3) it arranges floor tile: staying seam size according to the size of floor tile, the placement location of floor tile is discharged, and ten word control lines and frame bar are popped up in basic ground, row's floor tile should meet design requirement.The flower street floor file construction method, by the way that building waste aggregate will be used in constituent used by floor tile, secondary use can be carried out to discarded construction waste, and then cost can be reduced, and save resource, and by using pigment in the constituent used by floor tile, aesthetics can be increased using the coating of different colours.

Description

A kind of colored street floor file construction method
Technical field
The present invention relates to Construction Technology of Street field, specially a kind of colored street floor file construction method.
Background technique
Landscape floor tile is common engineering material in a kind of landscape design and construction, is mainly used for square, pavement etc. Large area is mated formation in engineering, and brick body is generally regular planar, and thickness directly uses cement bonded sand at 20-30 centimetres or so, use Slurry is layed on sand-gravel cushion, and laying floor is highly important, then good floor, if laying is incorrect, still can be gone out The problems such as now bending, breakage.
But the floor tile that ground is laid with use now is all directly bought, thus there are problems that higher cost.
Summary of the invention
(1) the technical issues of solving
In view of the deficiencies of the prior art, the present invention provides a kind of colored street floor file construction methods, have low in cost etc. excellent Point, solves the problems, such as higher cost.
(2) technical solution
For the purpose for realizing above-mentioned colored street floor file construction method, the invention provides the following technical scheme: a kind of colored street floor file Construction method, including following construction procedure:
1) base treatment: laitance, landing ash being stained in base etc. is fallen with temporary son or brushing, then will with broom Surface dust cleans up.
2) it looks for absolute altitude: according to horizontal standard line and design thickness, the upper flat absolute altitude control of surface layer is popped up on surrounding wall, column Line.
3) it arranges floor tile: staying seam size according to the size of floor tile, the placement location of floor tile is discharged, and pop up ten in basic ground Word control line and frame bar, row's floor tile should meet design requirement, when designing no requirement (NR), preferably avoid the occurrence of plate less than 1/4 side Long leftover pieces.
4) it is laid with binder course mortar: should be by bed moist before laying, and one of plain-water slurry or interface knot are brushed in substrate Mixture, the dry cement mortar stirred evenly with brush with laying.
5) floor tile: floor tile is placed on spice, levelling with rubber hammer, later picks up floor tile, on dry mixing material Appropriate plain-water slurry is poured, while applying the plain cement cream of thickness about l nm at the floor tile back side, then floor tile is placed on and looked for flat do On spice, with rubber hammer by absolute altitude control line and upright control line sit it is flat sit just, floor tile Shi Yingxian in a room between according to ten Wordline is laid with cross and controls floor tile, is laid with around according to cross control floor tile later, and examined at any time with 2m guiding ruler and horizontal ruler Look into flatness, when large area paving should be segmented, Divisional paving, and when having pattern requirement, accurate point should be popped up according to layout Ruling, and mark, prevent mistake, the floor tile component, comprising: 18-22 parts of building waste aggregate, 15-18 parts of cement, stone 6-8 parts, 0.5-1 parts 10-12 parts sub-, 5-7 parts of well as clay fines, 3-5 parts of flyash, 3-5 parts of pigment, water water-reducing agents.
6) maintenance and jointing: when tile paved surface paving it is complete for 24 hours in should start water seasoning, curing time cannot be less than 7d, When the intensity of tile paved surface, which reaches, to go up people, jointing is carried out, use is of the same race, same to strength grade, homochromy cement cream or 1: 1 Cement mortar, jointing is clear, straight, smooth, smooth, the depth is consistent, and seam should be lower than floor tile face 0.5-1mm
Preferably, the floor tile includes the raw material of following parts by weight proportion: 19-22 parts of building waste aggregate, cement 16- 18 parts, 11-12 parts of stone, 6-7 parts of well as clay fines, 4.5-5 parts of flyash, 7-8 parts, 0.5-1 parts 4-5 parts of pigment, water water-reducing agents.
Preferably, the floor tile includes the raw material of following parts by weight proportion: 19-22 parts of building waste aggregate, cement 16- 18 parts, 11-12 parts of stone, 6-7 parts of well as clay fines, 4-5 parts of flyash, 6-7 parts, 0.5-0.9 parts 3-4 parts of pigment, water water-reducing agents.
Preferably, the floor tile includes the raw material of following parts by weight proportion: 20-22 parts of building waste aggregate, cement 17- 18 parts, 11-12 parts of stone, 5-6 parts of well as clay fines, 4-5 parts of flyash, 7-8 parts, 0.6-1 parts 3-5 parts of pigment, water water-reducing agents.
Preferably, the floor tile includes the raw material of following parts by weight proportion: 18.2-22 parts of building waste aggregate, cement 16-18 parts, 11-12 parts of stone, 5.5-7 parts of well as clay fines, 3-4 parts of flyash, 4-5 parts of pigment, 7-8 parts of water, 0.5-0.8 parts subtract Aqua.
Preferably, the floor tile includes the raw material of following parts by weight proportion: 19-22 parts of building waste aggregate, cement 16- 18 parts, 11.5-12 parts of stone, 6-7 parts of well as clay fines, 4-4.5 parts of flyash, 3-4.5 parts of pigment, 6-7 parts of water, 0.6-1 parts subtract Aqua.
Preferably, the floor tile includes the raw material of following parts by weight proportion: 17-21 parts of building waste aggregate, cement 14- 16 parts, 11-12 parts of stone, 6-7 parts of well as clay fines, 4-5 parts of flyash, 7-8 parts, 0.7-1 parts 4-5 parts of pigment, water water-reducing agents.
Preferably, the floor tile includes the raw material of following parts by weight proportion: 16-22 parts of building waste aggregate, cement 16- 18 parts, 11-12 parts of stone, 5-6 parts of well as clay fines, 4-5 parts of flyash, 6-7.5 parts, 0.5-1 parts 4-5 parts of pigment, water water-reducing agents.
(3) beneficial effect
Compared with prior art, the present invention provides a kind of colored street floor file construction method, have it is following the utility model has the advantages that
1, flower street floor file construction method, by the way that building waste aggregate, energy will be used in constituent used by floor tile It is enough that secondary use is carried out to discarded construction waste, and then cost can be reduced, and save resource, and by being adopted in floor tile Pigment is used in constituent, and aesthetics can be increased using the coating of different colours.
2, the flower street floor file construction method, is enabled to further by avoiding the occurrence of plate less than the corner of 1/4 side length Reduce construction cost, and can be more beautiful, avoid because during being laid with to floor tile because many places are using less than 1/4 side Long corner leads to the waste of muti-piece floor tile.
Specific embodiment
Below in conjunction with the embodiment of the present invention, technical solution in the embodiment of the present invention is clearly and completely retouched It states, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Based on the present invention In embodiment, every other implementation obtained by those of ordinary skill in the art without making creative efforts Example, shall fall within the protection scope of the present invention.
Embodiment one:
A kind of colored street floor file construction method, including following construction procedure:
1) base treatment: laitance, landing ash being stained in base etc. is fallen with temporary son or brushing, then will with broom Surface dust cleans up.
2) it looks for absolute altitude: according to horizontal standard line and design thickness, the upper flat absolute altitude control of surface layer is popped up on surrounding wall, column Line.
3) it arranges floor tile: staying seam size according to the size of floor tile, the placement location of floor tile is discharged, and pop up ten in basic ground Word control line and frame bar, row's floor tile should meet design requirement, when designing no requirement (NR), preferably avoid the occurrence of plate less than 1/4 side Long leftover pieces.
4) it is laid with binder course mortar: should be by bed moist before laying, and one of plain-water slurry or interface knot are brushed in substrate Mixture, the dry cement mortar stirred evenly with brush with laying.
5) floor tile: floor tile is placed on spice, levelling with rubber hammer, later picks up floor tile, on dry mixing material Appropriate plain-water slurry is poured, while applying the plain cement cream of thickness about l nm at the floor tile back side, then floor tile is placed on and looked for flat do On spice, with rubber hammer by absolute altitude control line and upright control line sit it is flat sit just, floor tile Shi Yingxian in a room between according to ten Wordline is laid with cross and controls floor tile, is laid with around according to cross control floor tile later, and examined at any time with 2m guiding ruler and horizontal ruler Look into flatness, when large area paving should be segmented, Divisional paving, and when having pattern requirement, accurate point should be popped up according to layout Ruling, and mark, prevent mistake, the floor tile component, comprising: 19 parts of building waste aggregate, 16 parts of cement, stone 11 7 parts, 0.6 part part, 6 parts of well as clay fines, 4 parts of flyash, 4 parts of pigment, water water-reducing agent.
6) maintenance and jointing: when tile paved surface paving it is complete for 24 hours in should start water seasoning, curing time cannot be less than 7d, When the intensity of tile paved surface, which reaches, to go up people, jointing is carried out, use is of the same race, same to strength grade, homochromy cement cream or 1: 1 Cement mortar, jointing is clear, straight, smooth, smooth, the depth is consistent, and seam should be lower than floor tile face 0.5-1mm.
Embodiment two:
A kind of colored street floor file construction method, including following construction procedure:
1) base treatment: laitance, landing ash being stained in base etc. is fallen with temporary son or brushing, then will with broom Surface dust cleans up.
2) it looks for absolute altitude: according to horizontal standard line and design thickness, the upper flat absolute altitude control of surface layer is popped up on surrounding wall, column Line.
3) it arranges floor tile: staying seam size according to the size of floor tile, the placement location of floor tile is discharged, and pop up ten in basic ground Word control line and frame bar, row's floor tile should meet design requirement, when designing no requirement (NR), preferably avoid the occurrence of plate less than 1/4 side Long leftover pieces.
4) it is laid with binder course mortar: should be by bed moist before laying, and one of plain-water slurry or interface knot are brushed in substrate Mixture, the dry cement mortar stirred evenly with brush with laying.
5) floor tile: floor tile is placed on spice, levelling with rubber hammer, later picks up floor tile, on dry mixing material Appropriate plain-water slurry is poured, while applying the plain cement cream of thickness about l nm at the floor tile back side, then floor tile is placed on and looked for flat do On spice, with rubber hammer by absolute altitude control line and upright control line sit it is flat sit just, floor tile Shi Yingxian in a room between according to ten Wordline is laid with cross and controls floor tile, is laid with around according to cross control floor tile later, and examined at any time with 2m guiding ruler and horizontal ruler Look into flatness, when large area paving should be segmented, Divisional paving, and when having pattern requirement, accurate point should be popped up according to layout Ruling, and mark, prevent mistake, the floor tile component, comprising: 18 parts of building waste aggregate, 15 parts of cement, stone 10 6 parts, 0.5 part part, 5 parts of well as clay fines, 3 parts of flyash, 3 parts of pigment, water water-reducing agent.
6) maintenance and jointing: when tile paved surface paving it is complete for 24 hours in should start water seasoning, curing time cannot be less than 7d, When the intensity of tile paved surface, which reaches, to go up people, jointing is carried out, use is of the same race, same to strength grade, homochromy cement cream or 1: 1 Cement mortar, jointing is clear, straight, smooth, smooth, the depth is consistent, and seam should be lower than floor tile face 0.5-1mm.
Embodiment three:
A kind of colored street floor file construction method, including following construction procedure:
1) base treatment: laitance, landing ash being stained in base etc. is fallen with temporary son or brushing, then will with broom Surface dust cleans up.
2) it looks for absolute altitude: according to horizontal standard line and design thickness, the upper flat absolute altitude control of surface layer is popped up on surrounding wall, column Line.
3) it arranges floor tile: staying seam size according to the size of floor tile, the placement location of floor tile is discharged, and pop up ten in basic ground Word control line and frame bar, row's floor tile should meet design requirement, when designing no requirement (NR), preferably avoid the occurrence of plate less than 1/4 side Long leftover pieces.
4) it is laid with binder course mortar: should be by bed moist before laying, and one of plain-water slurry or interface knot are brushed in substrate Mixture, the dry cement mortar stirred evenly with brush with laying.
5) floor tile: floor tile is placed on spice, levelling with rubber hammer, later picks up floor tile, on dry mixing material Appropriate plain-water slurry is poured, while applying the plain cement cream of thickness about l nm at the floor tile back side, then floor tile is placed on and looked for flat do On spice, with rubber hammer by absolute altitude control line and upright control line sit it is flat sit just, floor tile Shi Yingxian in a room between according to ten Wordline is laid with cross and controls floor tile, is laid with around according to cross control floor tile later, and examined at any time with 2m guiding ruler and horizontal ruler Look into flatness, when large area paving should be segmented, Divisional paving, and when having pattern requirement, accurate point should be popped up according to layout Ruling, and mark, prevent mistake, the floor tile component, comprising: 22 parts of building waste aggregate, 18 parts of cement, stone 12 8 parts, 1 part part, 7 parts of well as clay fines, 5 parts of flyash, 5 parts of pigment, water water-reducing agent.
6) maintenance and jointing: when tile paved surface paving it is complete for 24 hours in should start water seasoning, curing time cannot be less than 7d, When the intensity of tile paved surface, which reaches, to go up people, jointing is carried out, use is of the same race, same to strength grade, homochromy cement cream or 1: 1 Cement mortar, jointing is clear, straight, smooth, smooth, the depth is consistent, and seam should be lower than floor tile face 0.5-1mm.
Example IV:
A kind of colored street floor file construction method, including following construction procedure:
1) base treatment: laitance, landing ash being stained in base etc. is fallen with temporary son or brushing, then will with broom Surface dust cleans up.
2) it looks for absolute altitude: according to horizontal standard line and design thickness, the upper flat absolute altitude control of surface layer is popped up on surrounding wall, column Line.
3) it arranges floor tile: staying seam size according to the size of floor tile, the placement location of floor tile is discharged, and pop up ten in basic ground Word control line and frame bar, row's floor tile should meet design requirement, when designing no requirement (NR), preferably avoid the occurrence of plate less than 1/4 side Long leftover pieces.
4) it is laid with binder course mortar: should be by bed moist before laying, and one of plain-water slurry or interface knot are brushed in substrate Mixture, the dry cement mortar stirred evenly with brush with laying.
5) floor tile: floor tile is placed on spice, levelling with rubber hammer, later picks up floor tile, on dry mixing material Appropriate plain-water slurry is poured, while applying the plain cement cream of thickness about l nm at the floor tile back side, then floor tile is placed on and looked for flat do On spice, with rubber hammer by absolute altitude control line and upright control line sit it is flat sit just, floor tile Shi Yingxian in a room between according to ten Wordline is laid with cross and controls floor tile, is laid with around according to cross control floor tile later, and examined at any time with 2m guiding ruler and horizontal ruler Look into flatness, when large area paving should be segmented, Divisional paving, and when having pattern requirement, accurate point should be popped up according to layout Ruling, and mark, prevent mistake, the floor tile component, comprising: 18.5 parts of building waste aggregate, 15.5 parts of cement, stone 11 parts, 6 parts of well as clay fines, 3.5 parts of flyash, 7.5 parts, 0.7 part 4 parts of pigment, water water-reducing agent.
6) maintenance and jointing: when tile paved surface paving it is complete for 24 hours in should start water seasoning, curing time cannot be less than 7d, When the intensity of tile paved surface, which reaches, to go up people, jointing is carried out, use is of the same race, same to strength grade, homochromy cement cream or 1: 1 Cement mortar, jointing is clear, straight, smooth, smooth, the depth is consistent, and seam should be lower than floor tile face 0.5-1mm.
Embodiment five:
A kind of colored street floor file construction method, including following construction procedure:
1) base treatment: laitance, landing ash being stained in base etc. is fallen with temporary son or brushing, then will with broom Surface dust cleans up.
2) it looks for absolute altitude: according to horizontal standard line and design thickness, the upper flat absolute altitude control of surface layer is popped up on surrounding wall, column Line.
3) it arranges floor tile: staying seam size according to the size of floor tile, the placement location of floor tile is discharged, and pop up ten in basic ground Word control line and frame bar, row's floor tile should meet design requirement, when designing no requirement (NR), preferably avoid the occurrence of plate less than 1/4 side Long leftover pieces.
4) it is laid with binder course mortar: should be by bed moist before laying, and one of plain-water slurry or interface knot are brushed in substrate Mixture, the dry cement mortar stirred evenly with brush with laying.
5) floor tile: floor tile is placed on spice, levelling with rubber hammer, later picks up floor tile, on dry mixing material Appropriate plain-water slurry is poured, while applying the plain cement cream of thickness about l nm at the floor tile back side, then floor tile is placed on and looked for flat do On spice, with rubber hammer by absolute altitude control line and upright control line sit it is flat sit just, floor tile Shi Yingxian in a room between according to ten Wordline is laid with cross and controls floor tile, is laid with around according to cross control floor tile later, and examined at any time with 2m guiding ruler and horizontal ruler Look into flatness, when large area paving should be segmented, Divisional paving, and when having pattern requirement, accurate point should be popped up according to layout Ruling, and mark, prevent mistake, the floor tile component, comprising: 19.5 parts of building waste aggregate, 16.5 parts of cement, stone 11 parts, 6.5 parts of well as clay fines, 4.3 parts of flyash, 7 parts, 0.8 part 3.6 parts of pigment, water water-reducing agent.
6) maintenance and jointing: when tile paved surface paving it is complete for 24 hours in should start water seasoning, curing time cannot be less than 7d, When the intensity of tile paved surface, which reaches, to go up people, jointing is carried out, use is of the same race, same to strength grade, homochromy cement cream or 1: 1 Cement mortar, jointing is clear, straight, smooth, smooth, the depth is consistent, and seam should be lower than floor tile face 0.5-1mm.
Embodiment six:
A kind of colored street floor file construction method, including following construction procedure:
1) base treatment: laitance, landing ash being stained in base etc. is fallen with temporary son or brushing, then will with broom Surface dust cleans up.
2) it looks for absolute altitude: according to horizontal standard line and design thickness, the upper flat absolute altitude control of surface layer is popped up on surrounding wall, column Line.
3) it arranges floor tile: staying seam size according to the size of floor tile, the placement location of floor tile is discharged, and pop up ten in basic ground Word control line and frame bar, row's floor tile should meet design requirement, when designing no requirement (NR), preferably avoid the occurrence of plate less than 1/4 side Long leftover pieces.
4) it is laid with binder course mortar: should be by bed moist before laying, and one of plain-water slurry or interface knot are brushed in substrate Mixture, the dry cement mortar stirred evenly with brush with laying.
5) floor tile: floor tile is placed on spice, levelling with rubber hammer, later picks up floor tile, on dry mixing material Appropriate plain-water slurry is poured, while applying the plain cement cream of thickness about l nm at the floor tile back side, then floor tile is placed on and looked for flat do On spice, with rubber hammer by absolute altitude control line and upright control line sit it is flat sit just, floor tile Shi Yingxian in a room between according to ten Wordline is laid with cross and controls floor tile, is laid with around according to cross control floor tile later, and examined at any time with 2m guiding ruler and horizontal ruler Look into flatness, when large area paving should be segmented, Divisional paving, and when having pattern requirement, accurate point should be popped up according to layout Ruling, and mark, prevent mistake, the floor tile component, comprising: 19 parts of building waste aggregate, 16 parts of cement, stone 11 7 parts, 0.7 part part, 6.8 parts of well as clay fines, 3.5 parts of flyash, 4.5 parts of pigment, water water-reducing agent.
6) maintenance and jointing: when tile paved surface paving it is complete for 24 hours in should start water seasoning, curing time cannot be less than 7d, When the intensity of tile paved surface, which reaches, to go up people, jointing is carried out, use is of the same race, same to strength grade, homochromy cement cream or 1: 1 Cement mortar, jointing is clear, straight, smooth, smooth, the depth is consistent, and seam should be lower than floor tile face 0.5-1mm.
In conclusion the flower street floor file construction method, by the way that building waste will be used in constituent used by floor tile Aggregate can carry out secondary use to discarded construction waste, and then can reduce cost, and save resource, and by Pigment is used in constituent used by floor tile, aesthetics can be increased using the coating of different colours, by avoiding the occurrence of Plate enables to be further reduced construction cost less than the corner of 1/4 side length, and can be more beautiful, avoids because to floor tile Because many places are using the waste for leading to muti-piece floor tile less than the corner of 1/4 side length during being laid with.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (8)

1. a kind of colored street floor file construction method, which is characterized in that including following construction procedure:
1) base treatment: falling the laitance that is stained in base, the temporarily sub or brushing of landing ash etc., then with broom by surface dust It cleans up.
2) it looks for absolute altitude: according to horizontal standard line and design thickness, the upper flat absolute altitude control line of surface layer is popped up on surrounding wall, column.
3) it arranges floor tile: staying seam size according to the size of floor tile, the placement location of floor tile is discharged, and pop up cross control in basic ground Line and frame bar processed, row's floor tile should meet design requirement, when designing no requirement (NR), preferably avoid the occurrence of plate less than 1/4 side length Leftover pieces.
4) it is laid with binder course mortar: should be by bed moist before laying, and one of plain-water slurry or interface cohesion agent are brushed in substrate, The dry cement mortar stirred evenly with brush with laying.
5) floor tile: floor tile is placed on spice, levelling with rubber hammer, later picks up floor tile, is poured on dry mixing material suitable Plain-water slurry is measured, while applying the plain cement cream of thickness about lnm at the floor tile back side, then floor tile is placed on and looked for flat dry mixing material On, with rubber hammer by absolute altitude control line and upright control line sit it is flat sit just, floor tile Shi Yingxian in a room between according to cross hairs It is laid with cross and controls floor tile, be laid with around according to cross control floor tile later, and is flat with 2m guiding ruler and horizontal ruler inspection at any time Whole degree, when large area paving should be segmented, Divisional paving, when having pattern requirement, should pop up accurate frame bar according to layout, And mark, prevent mistake, the floor tile component, comprising: 18-22 parts of building waste aggregate, 15-18 parts of cement, stone 10- 12 parts, 5-7 parts of well as clay fines, 3-5 parts of flyash, 6-8 parts, 0.5-1 parts 3-5 parts of pigment, water water-reducing agents.
6) maintenance and jointing: when tile paved surface paving it is complete for 24 hours in should start water seasoning, curing time cannot be less than 7d, local The intensity of brick surface layer reaches when can go up people, carries out jointing, and use is of the same race, same to strength grade, homochromy cement cream or 1: 1 cement Mortar, jointing is clear, straight, smooth, smooth, the depth is consistent, and seam should be lower than floor tile face 0.5-1mm.
2. a kind of colored street floor file construction method according to claim 1, which is characterized in that the floor tile includes following weight The raw material of number proportion: 19-22 parts of building waste aggregate, 16-18 parts of cement, 11-12 parts of stone, 6-7 parts of well as clay fines, fine coal 7-8 parts, 0.5-1 parts 4.5-5 parts grey, 4-5 parts of pigment, water water-reducing agents.
3. a kind of colored street floor file construction method according to claim 1, which is characterized in that the floor tile includes following weight The raw material of number proportion: 19-22 parts of building waste aggregate, 16-18 parts of cement, 11-12 parts of stone, 6-7 parts of well as clay fines, fine coal 6-7 parts, 0.5-0.9 parts 4-5 parts grey, 3-4 parts of pigment, water water-reducing agents.
4. a kind of colored street floor file construction method according to claim 1, which is characterized in that the floor tile includes following weight The raw material of number proportion: 20-22 parts of building waste aggregate, 17-18 parts of cement, 11-12 parts of stone, 5-6 parts of well as clay fines, fine coal 7-8 parts, 0.6-1 parts 4-5 parts grey, 3-5 parts of pigment, water water-reducing agents.
5. a kind of colored street floor file construction method according to claim 1, which is characterized in that the floor tile includes following weight Number proportion raw material: 18.2-22 parts of building waste aggregate, 16-18 parts of cement, 11-12 parts of stone, 5.5-7 parts of well as clay fines, 7-8 parts, 0.5-0.8 parts 3-4 parts of flyash, 4-5 parts of pigment, water water-reducing agents.
6. a kind of colored street floor file construction method according to claim 1, which is characterized in that the floor tile includes following weight The raw material of number proportion: 19-22 parts of building waste aggregate, 16-18 parts of cement, 11.5-12 parts of stone, 6-7 parts of well as clay fines, powder 6-7 parts, 0.6-1 parts 4-4.5 parts of coal ash, 3-4.5 parts of pigment, water water-reducing agents.
7. a kind of colored street floor file construction method according to claim 1, which is characterized in that the floor tile includes following weight The raw material of number proportion: 17-21 parts of building waste aggregate, 14-16 parts of cement, 11-12 parts of stone, 6-7 parts of well as clay fines, fine coal 7-8 parts, 0.7-1 parts 4-5 parts grey, 4-5 parts of pigment, water water-reducing agents.
8. a kind of colored street floor file construction method according to claim 1, which is characterized in that the floor tile includes following weight The raw material of number proportion: 16-22 parts of building waste aggregate, 16-18 parts of cement, 11-12 parts of stone, 5-6 parts of well as clay fines, fine coal 6-7.5 parts, 0.5-1 parts 4-5 parts grey, 4-5 parts of pigment, water water-reducing agents.
CN201910618181.7A 2019-07-10 2019-07-10 A kind of colored street floor file construction method Pending CN110306404A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910618181.7A CN110306404A (en) 2019-07-10 2019-07-10 A kind of colored street floor file construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910618181.7A CN110306404A (en) 2019-07-10 2019-07-10 A kind of colored street floor file construction method

Publications (1)

Publication Number Publication Date
CN110306404A true CN110306404A (en) 2019-10-08

Family

ID=68079795

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910618181.7A Pending CN110306404A (en) 2019-07-10 2019-07-10 A kind of colored street floor file construction method

Country Status (1)

Country Link
CN (1) CN110306404A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111172835A (en) * 2020-02-18 2020-05-19 深圳市科建建设集团有限公司 Manufacturing and mounting method of building energy-saving floor tile

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101565997A (en) * 2009-05-25 2009-10-28 青岛恒生源集团建设有限公司 Construction method for large-area irregular floor tile
CN106400639A (en) * 2016-08-29 2017-02-15 唐健发 Permeable brick pavement and construction technology thereof
DE202016101363U1 (en) * 2016-03-11 2017-06-13 Arno Kwade Cast stone composite system
CN108677652A (en) * 2018-06-26 2018-10-19 苏州望意阳环保科技有限公司 A kind of permeable people's row sidewalk for visually impaired people and its construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101565997A (en) * 2009-05-25 2009-10-28 青岛恒生源集团建设有限公司 Construction method for large-area irregular floor tile
DE202016101363U1 (en) * 2016-03-11 2017-06-13 Arno Kwade Cast stone composite system
CN106400639A (en) * 2016-08-29 2017-02-15 唐健发 Permeable brick pavement and construction technology thereof
CN108677652A (en) * 2018-06-26 2018-10-19 苏州望意阳环保科技有限公司 A kind of permeable people's row sidewalk for visually impaired people and its construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111172835A (en) * 2020-02-18 2020-05-19 深圳市科建建设集团有限公司 Manufacturing and mounting method of building energy-saving floor tile

Similar Documents

Publication Publication Date Title
US6610224B2 (en) Processes for producing monolithic architectural cementitious structures having decorative aggregate-containing cementitious surfaces
CN102358693B (en) Levelling mortar and ground construction process based on the same
CN107254954A (en) Ground paving ceramic tile construction technology
CN101565997A (en) Construction method for large-area irregular floor tile
US20140000214A1 (en) Decorative aggregate concrete surface preparation process
CN105271980A (en) Two-component interface agent and use method thereof
CN108640612A (en) A kind of polishing concrete decoration terrace
CN108625252A (en) Urban road laying construction method
CN106121188A (en) Large area is seamless overall ground and construction method thereof
CN109369133A (en) A kind of high-impermeable waterproof inorganic coating and preparation method thereof
CN113027055A (en) White clear water-imitating concrete facing process
CN105272113A (en) Dry plastering technology
KR101224040B1 (en) Paving method using gravel
CN110306404A (en) A kind of colored street floor file construction method
CN106477993A (en) Water-proof concrete and its construction method containing FS102 waterproof compacting agent
CN109293319A (en) A kind of water mill stone walling and preparation method thereof
KR101032767B1 (en) Functional road-pavement added loess eco pavement and method thereof
CN208776593U (en) A kind of polishing concrete decoration terrace
CN108947464B (en) Ground surface layer based on phosphorus-magnesium material and construction process thereof
CN107299731A (en) A kind of anti-hollowing of mountain sand cement mortar plastering and cracking construction method
CN201809928U (en) Texture planning module unit for sealing ice flaws
CN115286337A (en) Construction method of pouring type phosphogypsum-based sand-free self-leveling mortar and construction surface structure thereof
CN114876155A (en) Construction process for polishing ground by using non-ignition fine stone concrete
CN110130615B (en) Indoor composite floor based on phosphorus-magnesium material and self-leveling gypsum and construction method thereof
CN112575977A (en) Sound insulation mortar, sound insulation floor slab, building and construction method of sound insulation floor slab

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191008