CN110300021A - A kind of method and computing device calculating substation recording bulletin data processing time - Google Patents

A kind of method and computing device calculating substation recording bulletin data processing time Download PDF

Info

Publication number
CN110300021A
CN110300021A CN201910536632.2A CN201910536632A CN110300021A CN 110300021 A CN110300021 A CN 110300021A CN 201910536632 A CN201910536632 A CN 201910536632A CN 110300021 A CN110300021 A CN 110300021A
Authority
CN
China
Prior art keywords
substation
time
main website
delay time
recorder data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910536632.2A
Other languages
Chinese (zh)
Other versions
CN110300021B (en
Inventor
巫聪云
刘斌
蒙亮
李海勇
杨彥
田君杨
黄超
杜杨华
陈志�
韩冰
覃丙川
秦蓓
何洪
孙翔
曾剑锋
卢德宏
于彬
汤小兵
张坎
俞小俊
石磊
毛春岳
孙泽
冯林江
顾霞玲
徐海涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Sp Nice Technology Development Ltd By Share Ltd
Guangxi Power Grid Co Ltd
Original Assignee
Nanjing Sp Nice Technology Development Ltd By Share Ltd
Guangxi Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Sp Nice Technology Development Ltd By Share Ltd, Guangxi Power Grid Co Ltd filed Critical Nanjing Sp Nice Technology Development Ltd By Share Ltd
Priority to CN201910536632.2A priority Critical patent/CN110300021B/en
Publication of CN110300021A publication Critical patent/CN110300021A/en
Application granted granted Critical
Publication of CN110300021B publication Critical patent/CN110300021B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L41/00Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
    • H04L41/06Management of faults, events, alarms or notifications
    • H04L41/0631Management of faults, events, alarms or notifications using root cause analysis; using analysis of correlation between notifications, alarms or events based on decision criteria, e.g. hierarchy, tree or time analysis
    • H04L41/064Management of faults, events, alarms or notifications using root cause analysis; using analysis of correlation between notifications, alarms or events based on decision criteria, e.g. hierarchy, tree or time analysis involving time analysis
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L67/00Network arrangements or protocols for supporting network services or applications
    • H04L67/01Protocols
    • H04L67/10Protocols in which an application is distributed across nodes in the network
    • H04L67/1095Replication or mirroring of data, e.g. scheduling or transport for data synchronisation between network nodes
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L67/00Network arrangements or protocols for supporting network services or applications
    • H04L67/14Session management

Landscapes

  • Engineering & Computer Science (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Signal Processing (AREA)
  • Telephonic Communication Services (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The embodiment of the invention discloses a kind of methods and computing device, readable storage medium storing program for executing for calculating substation recording bulletin data processing time to reduce delay, save system resource for improving the treatment effeciency for calculating substation recording bulletin data processing time.The method comprise the steps that obtaining the link transmission delay time between the main website and the substation when main website and substation are established and communicated to connect;According to the link transmission delay time, the time adjusted value between protective device and the main website is obtained;According to the link transmission delay time and the time adjusted value, the delay time that the substation handles the time of current recorder data and reports the current recorder data to the main website is calculated, the current recorder data is the recorder data that the substation reports;Disconnect the communication connection of the main website Yu the substation.

Description

A kind of method and computing device calculating substation recording bulletin data processing time
Technical field
The present invention relates to computer field more particularly to it is a kind of calculate substation recording bulletin data processing time method and Computing device, readable storage medium storing program for executing.
Background technique
Relay protection and fault information system (system referred to as information-preserving) passes through the smart machines such as acquisition protective device, oscillograph Information, monitoring and protection devices type operation and is analyzed electric network fault by the fault message that protective device reports, for operation Personnel's judgement and disposition electric network fault provide necessary foundation, to improve relay protection and fault information system management and failure The automatization level of information processing.
System information-preserving is made of main website and substation, handles and analyze failure, is an important process of system main website information-preserving. The various protections of access and wave recording device are then responsible in substation, and information is summarized and uploads to main website, the timely upload of substation data, especially It is protective device recorder data, is the most important data of this failure cause of detailed analysis and nature of trouble, by recording Conclusion obtained from the analysis of data is the important evidence that auxiliary dispatching operations staff carries out operation decision.Therefore, fault moment The timeliness that protection recorder data reports is to judge an important indicator of system implementation result information-preserving, and play system information-preserving System effect, an essential condition for enabling main station side quickly to analyze failure, guarantee power grid operation.
The producer of domestic production prudential sub-station product is more, and the product of a producer also has different model and version, and stands Interior protective device model be also it is varied, communication protocol may be also different, prudential sub-station access protective device effect It is influenced by several factors, the performance to main website active reporting data is different.Based on protection recorder data to information-preserving The importance of system, in the evaluation to prudential sub-station product quality, prudential sub-station processing protection recorder data simultaneously reports information It is a very important index to the speed of main website speed.
In order to evaluate the performance of substation active reporting information, the timeliness especially reported to protection recorder data needs The data such as the delay time of corresponding information reported are collected as analysis, the foundation judged.
Data are exchanged using 103 communication protocols between system boss station information-preserving, data are not transmitted in 103 communication protocols Performance metric provide response support, and to 103 communication protocols carry out expand nor one be easy implement scheme, largely The prudential sub-station of storage is implemented according to original 103 Communications Protocol Specification, and 103 communication protocols of modification need huge work Work amount and capital investment are related to the links such as Consistency test, qualified detection, product up-gradation, field adjustable service.
Summary of the invention
The embodiment of the invention provides it is a kind of calculate substation recording bulletin data processing time method and computing device, can Storage medium is read, for improving the treatment effeciency for calculating substation recording bulletin data processing time, delay is reduced, saves system money Source.
In view of this, first aspect present invention provides a kind of method for calculating substation recording bulletin data processing time, it can To include:
When main website and substation, which are established, to be communicated to connect, when obtaining the link transmission delay between the main website and the substation Between;
According to the link transmission delay time, the time adjusted value between protective device and the main website is obtained;
According to the link transmission delay time and the time adjusted value, calculates the substation and handle current recorder data Time and delay time of the current recorder data is reported to the main website, the current recorder data is on the substation The recorder data of report;
Disconnect the communication connection of the main website Yu the substation.
Optionally, in some embodiments of the invention, the link obtained between the main website and the substation passes Defeated delay time, comprising:
Record the time t that the main website sends request for test frame to the substation0, and the substation is received to the master The time t of the confirmation test frame for feedback of standing1
According to the time t of the request for test frame0With the time t of the exact p-value frame1, be calculated the main website and Link transmission delay time T between the substationl
Optionally, in some embodiments of the invention, described according to the link transmission delay time, obtain protection dress Set the time adjusted value between the main website, comprising:
Obtain the markers t in the warning information and event information that the substation reports about the protective devicef, Yi Jisuo State the receiving time t that main website receives the warning information and event informationm
According to the link transmission delay time Tl, the markers tfAnd the receiving time tm, protection dress is calculated Set the time adjusted value Δ T between the main website.
Optionally, in some embodiments of the invention, described according to the link transmission delay time and the time Adjusted value calculates the substation and handles the time of current recorder data and report prolonging for the current recorder data to the main website The slow time, comprising:
According to the markers tfWith the time adjusted value Δ T, protective device markers t adjusted is calculatedd
According to the link transmission delay time Tl, the receiving time tmWith the protective device markers t adjustedd, The time T that the substation handles current recorder data is calculated;
According to the receiving time tmWith the protective device markers t adjustedd, it is calculated to the main website and reports The delay time T of the current recorder datadly
Optionally, in some embodiments of the invention, the main website and substation, which are established, communicates to connect, comprising:
First, which is sent, to the substation by the main website establishes request;
Receiving establishing to described first for the substation transmission by the main website requests send first to be successfully established sound It answers;
Alternatively,
Second, which is sent, to the main website by the substation establishes request;
Receiving establishing to described second for the main website transmission by the substation requests send second to be successfully established sound It answers.
Second aspect of the present invention provides a kind of computing device, may include:
Transceiver module, for obtaining between the main website and the substation when main website and substation foundation communication connection The link transmission delay time;
Processing module, for according to the link transmission delay time, obtain between protective device and the main website when Between adjusted value;According to the link transmission delay time and the time adjusted value, calculates the substation and handle current recording number According to time and report to the main website delay time of the current recorder data, the current recorder data is the substation The recorder data reported;Disconnect the communication connection of the main website Yu the substation.
Optionally, in some embodiments of the invention,
The transceiver module, specifically for recording time t of the main website to substation transmission request for test frame0, with And receive the time t of the confirmation test frame fed back to the main website substation1;According to the time t of the request for test frame0With The time t of the exact p-value frame1, the link transmission delay time T between the main website and the substation is calculatedl
Optionally, in some embodiments of the invention,
The processing module, specifically for obtaining in the warning information and event information that the substation reports about the guarantor The markers t of protection unitfAnd the main website receives the receiving time t of the warning information and event informationm;According to the link Propagation delay time Tl, the markers tfAnd the receiving time tm, be calculated between protective device and the main website when Between adjusted value Δ T.
Optionally, in some embodiments of the invention,
The processing module is specifically used for according to the markers tfWith the time adjusted value Δ T, calculate adjusted Protective device markers td;According to the link transmission delay time Tl, the receiving time tmWith the protective device adjusted Markers td, the time T that the substation handles current recorder data is calculated;According to the receiving time tmAfter the adjustment Protective device markers td, the delay time T that the current recorder data is reported to the main website is calculateddly
Optionally, in some embodiments of the invention,
The transceiver module is also used to send first to the substation by the main website and establishes request;Pass through the master Establishing to described first for reception of the standing substation transmission requests send first to be successfully established response;
Alternatively,
The transceiver module is also used to send second to the main website by the substation and establishes request;Pass through the son Establishing to described second for reception of the standing main website transmission requests send second to be successfully established response.
Third aspect present invention provides a kind of computing device, may include:
Transceiver, processor, memory, wherein the transceiver, the processor and the memory are connected by bus It connects;
The memory, for storing operational order;
The transceiver, for obtaining between the main website and the substation when main website and substation foundation communication connection The link transmission delay time;
The processor, for calling the operational order, execute such as first aspect present invention and first aspect is any can The step of selecting the method that recording bulletin data processing time in substation is calculated described in mode.
Fourth aspect present invention provides a kind of readable storage medium storing program for executing, is stored thereon with computer program, the computer The calculating substation as described in first aspect present invention and first aspect any optional way is realized when program is executed by processor The step of method of recording bulletin data processing time.
As can be seen from the above technical solutions, the embodiment of the present invention has the advantage that
In embodiments of the present invention, when main website and substation, which are established, to be communicated to connect, obtain the main website and the substation it Between the link transmission delay time;According to the link transmission delay time, obtain between protective device and the main website when Between adjusted value;According to the link transmission delay time and the time adjusted value, calculates the substation and handle current recording number According to time and report to the main website delay time of the current recorder data, the current recorder data is the substation The recorder data reported;Disconnect the communication connection of the main website Yu the substation.Substation recording bulletin data are calculated for improving The treatment effeciency of time is handled, and the delay time for reporting the current recorder data to the main website is calculated, is reduced System resource is saved in delay.
Detailed description of the invention
Technical solution in order to illustrate the embodiments of the present invention more clearly, below will be to institute in embodiment and description of the prior art Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention Example, can also be obtained according to these attached drawings other attached drawings.
Fig. 1 is the timing diagram of alarm/event communication in the embodiment of the present invention;
Fig. 2 is the timing diagram of recording bulletin communication in the embodiment of the present invention;
Fig. 3 be the embodiment of the present invention fall into a trap operator station recording bulletin data processing time method embodiment schematic diagram;
Fig. 4 is the schematic diagram that the link transmission delay time between main website and substation is calculated in the embodiment of the present invention;
Fig. 5 is the schematic diagram that the time adjusted value between protective device and main website is calculated in the embodiment of the present invention;
Fig. 6 be the embodiment of the present invention fall into a trap operator station recorder data handle the time schematic diagram;
Fig. 7 is one embodiment schematic diagram of computing device in the embodiment of the present invention;
Fig. 8 is another embodiment schematic diagram of computing device in the embodiment of the present invention.
Specific embodiment
The embodiment of the invention provides it is a kind of calculate substation recording bulletin data processing time method and computing device, can Storage medium is read, for improving the treatment effeciency for calculating substation recording bulletin data processing time, delay is reduced, saves system money Source.
In order to enable those skilled in the art to better understand the solution of the present invention, below in conjunction in the embodiment of the present invention Attached drawing, technical solution in the embodiment of the present invention are described, it is clear that described embodiment is only present invention a part Embodiment, instead of all the embodiments.Based on the embodiments of the present invention, it should fall within the scope of the present invention.
On the basis of existing communication agreement, the present invention proposes a kind of feasible method of low cost, is not changing original son Under the premise of soft and hardware and the overall system structure of standing, by designing new software algorithm in main station side, substation is handled to realize Recorder data and the evaluation for reporting recording bulletin information performance.
Below for the embodiment of the present invention fall into a trap operator station recording bulletin data processing time principle explanation:
When grid collapses or device operation occur abnormal, prudential sub-station can be by the action message of device or abnormal letter Breath is converted to 103 message formats, and active upload quickly handled after receiving information so as to main website to main website, to tune Degree person and protection staff carry out the alarm prompts such as failure, exception, and provide necessary data for accident analysis and support.
Prudential sub-station can also be referred to as substation, sub-station device, and the information of active upload mainly includes warning information, event Information and recording bulletin information are respectively that 1,2 and 12 application layer data units are reported and (can be used in the present embodiment with number ASDU1/ASDU2/ASDU12 is indicated).Alarm, event information transfer mechanism and recording bulletin transfer mechanism it is different: The warning information and event information that protective device generates, generally by station communication network, active reporting is to sub-station device, substation Device should actively be transmitted to main website in the first time for receiving protective device information;The recording bulletin information that protective device generates, Equally by station communication network, active reporting is answered after receiving the recording bulletin information of protection to sub-station device, sub-station device Corresponding recorder data is called to protective device in time and is stored in the local memory device of substation, is then pushed to main station system Recording bulletin information.
As shown in Figure 1, for the timing diagram of alarm/event communication in the embodiment of the present invention.As shown in Fig. 2, real for the present invention Apply the timing diagram that recording bulletin communicates in example.
In timing diagram shown in Fig. 2, the delay that protective device wave-record chart reports is that failure record is generated from protective device Wave information time tdStart, the time t of recording bulletin ASDU12 message is received to main websitemUntil, delay time TdlyAre as follows:
Tdly=tm-td
If the recording bulletin ASDU12 message time that substation receives protective device generation is ts1, recording letter is sent to main website Reporting ASDU12 message time is ts2, the T of data network transmission delayl, then the time T of substation handling failure recorder data are as follows:
T=ts2-ts1=tm-ts1-Tl
Therefore, if main website can obtain protective device generate recorder data time and main website receive ASDU12 message when Between, it can acquire the delay time that recording bulletin data report;If it is known that substation receive protective device information time and Data network link delay, it can acquire the time used in substation processing data.Through due to the information that protective device generates and change Power station local networks are transferred to substation, and the time for handling recorder data relative to substation and data network chain road delay time numerical value are very Small (protective device reports information time to have special test), therefore for ease of calculation, it is believed that substation receives protective device The time of fault message is approximately equal to the time that protective device generates fault data, the also approximately equal to time of failure generation, it may be assumed that
ts1≈td
In 103 communication protocol specifications, without special data network link delay test method, find after study, it can To use link layer test frame to reach measurement TlPurpose.The time t for the request for test frame that record main website is sent respectively0With receive The time t for the confirmation test frame that substation is answered1, then link transmission times can be calculated by following mode:
Tl=(t1-t0)/2
Protective device generates Fault Recorder Information time tdIt can be replaced with the time that failure occurs.Protective device is detecting When to electric network fault, markers can be stamped to fault recorder data, which is generated by the clock that protective device is kept, and in recording Sub-station device is transmitted in bulletin data, " fault time " domain section of the sub-station device in ASDU12 is filled in the markers and be reported to Main website, the value are the markers t in protective device time systemf
Since the time source of main website and substation and protective device is different, such as main website uses NTP in main station side net Acquisition time in network, stand in protective device when generally using GPS or pulse synchronous signal, and in standing protective device exist by The markers abnormal phenomenon caused by time source failure.Therefore, main website and protective device time are in different time system, lead Cause main website that can not be computed correctly substation truthful data and report delay time, at the same also can not each substation of lateral comparison performance.
Therefore, main station side needs to be unified in markers in system at the same time, i.e., by tfIt is transformed into main station time td, with Just it is calculated and is analyzed.According to code requirement, substation should pass the alarm/event information that protective device reports to main website immediately It is defeated, therefore can use this characteristic, estimate the discrepancy delta T of the time system of protective device time system and main station system:
Δ T=tm-[tf+(ts2-ts1)+Tl]
Since the information is transmitted in substation immediately after receiving protective device information, can will receive protective device information to The time that main website is sent between information ignores, it may be assumed that
ts2-ts1≈0
Then: Δ T=tm-(tf+Tl)
Δ T is brought into the time t for adjusting each recording bulletin and generating in protective devicef, have:
td=tf+ΔT
Thus, it is possible to calculate this recording bulletin data approximate processing time of substation T and approximate transmission delay Tdly
Below by way of examples, technical solution of the present invention is described further, as shown in figure 3, for the present invention Embodiment fall into a trap operator station recording bulletin data processing time method embodiment schematic diagram.In order to calculate substation recording bulletin Data processing time, main station side are divided into 3 sub-function modules, are respectively as follows: link delay calculating, protective device markers adjusted value meter It calculates and recording bulletin data processing time calculates.May include:
301, when main website and substation, which are established, to be communicated to connect, the link transmission obtained between the main website and the substation is prolonged The slow time.
Wherein, the link transmission delay time obtained between the main website and the substation may include: record institute State the time t that main website sends request for test frame to the substation0, and receive the confirmation fed back to the main website substation and survey Try the time t of frame1;According to the time t of the request for test frame0With the time t of the exact p-value frame1, the master is calculated The link transmission delay time T to stand between the substationl
Illustratively, as shown in figure 4, when to calculate the link transmission delay between main website and substation in the embodiment of the present invention Between schematic diagram.After main website and substation establish communication connection, that is, enter link delay time calculation stages, and through entire logical Believe all processes of connection.Link delay is multiplexed the necessary test frame question answering process in the communication process of boss station, without additional Increase communication overhead, mainly comprises the steps that
(a) question and answer counter is removed, question and answer frequency threshold value k, sliding window value w (w≤k), error threshold σ are set;
(b) main website timing sends request for test frame to substation, and records sending time t0
(c) main website receives substation exact p-value frame, and records receiving time t1
(d) cache-time is to (t0, t1), question and answer counter increases by 1;
(e) check whether question and answer counter reaches defined number k and such as not up to go to (b)
(f) (t is calculated1-t0)/2, and mean square error is used to calculate the error of each sample, remove greater than error threshold σ's Sample;
(g) remaining sample is calculated into ∑ (t1-t0)/2 are simultaneously averaged, the length of delay T as current ink transmissionl
(h) w sample before deleting, counter are set as k-w, go to (b).
302, according to the link transmission delay time, the time adjusted value between protective device and the main website is obtained.
Wherein, described according to the link transmission delay time, obtain the time tune between protective device and the main website Whole value may include: the markers t obtained in the warning information and event information that the substation reports about the protective devicef, And the main website receives the receiving time t of the warning information and event informationm;According to the link transmission delay time Tl、 The markers tfAnd the receiving time tm, the time adjusted value Δ T between protective device and the main website is calculated.
Illustratively, as shown in figure 5, to calculate the time adjusted value between protective device and main website in the embodiment of the present invention Schematic diagram.On the basis of the link transmission delay time is calculated, main website can by ASDU1 that substation reports and Protective device markers in ASDU2 message calculates the adjusted value Δ T with main station time.The calculating process runs through entire communication link The all processes connect.Due to calculating the message information in the communication process of multiplexing boss station, opened without additional increase communication Pin, calculating process mainly comprise the steps that
(a) count pick up device is removed, receive number threshold value k, sliding window value w (w≤k), error threshold σ are set;
(b) substation active reporting information is monitored;
Protective device markers t if (c) substation reports ASDU1 or ASDU2, in recorded messagefAnd when main website reception Between tm
(d) cache-time is to (tf, tm), it receives number device and increases by 1;
(e) check whether count pick up device reaches defined number k and such as not up to go to (b);
(f) the length of delay T of link transmission is checkedlWhether effectively, such as turn (i) in vain;
(g) t is calculatedm-(tf+Tl), the error of each sample is calculated using mean square error, removes the sample greater than error threshold σ This;
(h) remaining sample is calculated into ∑ [tm-(tf+Tl)] and be averaged, as current protective device markers adjusted value Δ T;
(i) w sample before deleting, counter are set as k-w, go to (b).
303, it according to the link transmission delay time and the time adjusted value, calculates the substation and handles current recording The time of data and the delay time that the current recorder data is reported to the main website, the current recorder data are the son The recorder data that station reports.
Wherein, described according to the link transmission delay time and the time adjusted value, it calculates the substation processing and works as The time of preceding recorder data and the delay time that the current recorder data is reported to the main website, may include: according to Markers tfWith the time adjusted value Δ T, protective device markers t adjusted is calculatedd;When according to the link transmission delay Between Tl, the receiving time tmWith the protective device markers t adjustedd, the substation is calculated and handles current recording number According to time T;According to the receiving time tmWith the protective device markers t adjustedd, it is calculated in the main website Report the delay time T of the current recorder datadly
Illustratively, as shown in fig. 6, for the embodiment of the present invention fall into a trap operator station recorder data handle the time schematic diagram. On the basis of link delay time and protective device markers adjusted value is calculated, main website is estimated that receives substation every time When reporting ASDU12, substation handles the time of this recorder data and reports the delay time of process, and calculating process mainly includes Following steps:
(a) substation active reporting information is monitored;
Protective device markers t if (b) substation reports ASDU12, in recorded messagefAnd main website receiving time tm
(c) the length of delay T of link transmission is checkedl, protective device markers adjusted value Δ T it is whether effective, if any of them One invalid, then recording this recorder data of substation processing time and reporting delay time is null value, turns (a);
(d) device markers t adjusted is calculatedd=tf+ΔT;
(e) substation outlet recorder data time T=t is calculatedm-(td+Tl) and report delay time Tdly=tm-td
(f) record this recorder data of substation handles the time and reports delay time, turns (a).
304, the communication connection of the main website and the substation is disconnected.
In embodiments of the present invention, when main website and substation, which are established, to be communicated to connect, obtain the main website and the substation it Between the link transmission delay time;According to the link transmission delay time, obtain between protective device and the main website when Between adjusted value;According to the link transmission delay time and the time adjusted value, calculates the substation and handle current recording number According to time and report to the main website delay time of the current recorder data, the current recorder data is the substation The recorder data reported;Disconnect the communication connection of the main website Yu the substation.Substation recording bulletin data are calculated for improving The treatment effeciency of time is handled, and the delay time for reporting the current recorder data to the main website is calculated, is reduced System resource is saved in delay.
As shown in fig. 7, may include: for one embodiment schematic diagram of computing device in the embodiment of the present invention
Transceiver module 701, for obtaining between the main website and the substation when main website and substation foundation communication connection The link transmission delay time;
Processing module 702, for obtaining between protective device and the main website according to the link transmission delay time Time adjusted value;According to the link transmission delay time and the time adjusted value, calculates the substation and handle current recording The time of data and the delay time that the current recorder data is reported to the main website, the current recorder data are the son The recorder data that station reports;Disconnect the communication connection of the main website Yu the substation.
Optionally, in some embodiments of the invention,
Transceiver module 701, specifically for recording time t of the main website to substation transmission request for test frame0, and Receive the time t of the confirmation test frame fed back to the main website substation1;According to the time t of the request for test frame0And institute State the time t of exact p-value frame1, the link transmission delay time T between the main website and the substation is calculatedl
Optionally, in some embodiments of the invention,
Processing module 702, specifically for obtaining in the warning information and event information that the substation reports about the guarantor The markers t of protection unitfAnd the main website receives the receiving time t of the warning information and event informationm;According to the link Propagation delay time Tl, the markers tfAnd the receiving time tm, be calculated between protective device and the main website when Between adjusted value Δ T.
Optionally, in some embodiments of the invention,
Processing module 702 is specifically used for according to the markers tfWith the time adjusted value Δ T, calculate adjusted Protective device markers td;According to the link transmission delay time Tl, the receiving time tmWith the protective device adjusted Markers td, the time T that the substation handles current recorder data is calculated;According to the receiving time tmAfter the adjustment Protective device markers td, the delay time T that the current recorder data is reported to the main website is calculateddly
Optionally, in some embodiments of the invention,
Transceiver module 701 is also used to send first to the substation by the main website and establishes request;Pass through the main website Receiving establishing to described first for the substation transmission requests send first to be successfully established response;
Alternatively,
Transceiver module 701 is also used to send second to the main website by the substation and establishes request;Pass through the substation Receiving establishing to described second for the main website transmission requests send second to be successfully established response.
As shown in figure 8, may include: for another embodiment schematic diagram of computing device in the embodiment of the present invention
Transceiver 801, processor 802, memory 803, wherein transceiver 801, processor 802 and memory 803 pass through Bus connection;
Memory 803, for storing operational order;
Transceiver 801, for obtaining between the main website and the substation when main website and substation foundation communication connection The link transmission delay time;
Processor 802, according to the link transmission delay time, obtains protective device for calling the operational order Time adjusted value between the main website;According to the link transmission delay time and the time adjusted value, described in calculating Substation handles the time of current recorder data and reports the delay time of the current recorder data to the main website, described current Recorder data is the recorder data that the substation reports;Disconnect the communication connection of the main website Yu the substation.
Optionally, in some embodiments of the invention,
Transceiver 801, specifically for recording time t of the main website to substation transmission request for test frame0, Yi Jishou The time t of the confirmation test frame fed back to the substation to the main website1;According to the time t of the request for test frame0With it is described The time t of exact p-value frame1, the link transmission delay time T between the main website and the substation is calculatedl
Optionally, in some embodiments of the invention,
Processor 802, specifically for obtaining in the warning information and event information that the substation reports about the protection The markers t of devicefAnd the main website receives the receiving time t of the warning information and event informationm;It is passed according to the link Defeated delay time Tl, the markers tfAnd the receiving time tm, the time between protective device and the main website is calculated Adjusted value Δ T.
Optionally, in some embodiments of the invention,
Processor 802 is specifically used for according to the markers tfWith the time adjusted value Δ T, guarantor adjusted is calculated Protection unit markers td;According to the link transmission delay time Tl, the receiving time tmWhen with the protective device adjusted Mark td, the time T that the substation handles current recorder data is calculated;According to the receiving time tmWith it is described adjusted Protective device markers td, the delay time T that the current recorder data is reported to the main website is calculateddly
Optionally, in some embodiments of the invention,
Transceiver 801 is also used to send first to the substation by the main website and establishes request;It is connect by the main website Receiving establishing to described first for the substation transmission requests send first to be successfully established response;
Alternatively,
Transceiver 801 is also used to send second to the main website by the substation and establishes request;It is connect by the substation Receiving establishing to described second for the main website transmission requests send second to be successfully established response.
In the above-described embodiments, can come wholly or partly by software, hardware, firmware or any combination thereof real It is existing.When implemented in software, it can entirely or partly realize in the form of a computer program product.
The computer program product includes one or more computer instructions.Load and execute on computers the meter When calculation machine program instruction, entirely or partly generate according to process or function described in the embodiment of the present invention.The computer can To be general purpose computer, special purpose computer, computer network or other programmable devices.The computer instruction can be deposited Storage in a computer-readable storage medium, or from a computer readable storage medium to another computer readable storage medium Transmission, for example, the computer instruction can pass through wired (example from a web-site, computer, server or data center Such as coaxial cable, optical fiber, Digital Subscriber Line (DSL)) or wireless (such as infrared, wireless, microwave) mode to another website Website, computer, server or data center are transmitted.The computer readable storage medium can be computer and can deposit Any usable medium of storage either includes that the data storages such as one or more usable mediums integrated server, data center are set It is standby.The usable medium can be magnetic medium, (for example, floppy disk, hard disk, tape), optical medium (for example, DVD) or partly lead Body medium (such as solid state hard disk Solid State Disk (SSD)) etc..
It is apparent to those skilled in the art that for convenience and simplicity of description, the system of foregoing description, The specific work process of device and unit, can refer to corresponding processes in the foregoing method embodiment, and details are not described herein.
In several embodiments provided by the present invention, it should be understood that disclosed system, device and method can be with It realizes by another way.For example, the apparatus embodiments described above are merely exemplary, for example, the unit It divides, only a kind of logical function partition, there may be another division manner in actual implementation, such as multiple units or components It can be combined or can be integrated into another system, or some features can be ignored or not executed.Another point, it is shown or The mutual coupling, direct-coupling or communication connection discussed can be through some interfaces, the indirect coupling of device or unit It closes or communicates to connect, can be electrical property, mechanical or other forms.
The unit as illustrated by the separation member may or may not be physically separated, aobvious as unit The component shown may or may not be physical unit, it can and it is in one place, or may be distributed over multiple In network unit.It can select some or all of unit therein according to the actual needs to realize the mesh of this embodiment scheme 's.
It, can also be in addition, the functional units in various embodiments of the present invention may be integrated into one processing unit It is that each unit physically exists alone, can also be integrated in one unit with two or more units.Above-mentioned integrated list Member both can take the form of hardware realization, can also realize in the form of software functional units.
If the integrated unit is realized in the form of SFU software functional unit and sells or use as independent product When, it can store in a computer readable storage medium.Based on this understanding, technical solution of the present invention is substantially The all or part of the part that contributes to existing technology or the technical solution can be in the form of software products in other words It embodies, which is stored in a storage medium, including some instructions are used so that a computer Equipment (can be personal computer, server or the network equipment etc.) executes the complete of each embodiment the method for the present invention Portion or part steps.And storage medium above-mentioned includes: USB flash disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), magnetic or disk etc. are various can store journey The medium of sequence code.
The above, the above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although referring to before Stating embodiment, invention is explained in detail, those skilled in the art should understand that: it still can be to preceding Technical solution documented by each embodiment is stated to modify or equivalent replacement of some of the technical features;And these It modifies or replaces, the spirit and scope for technical solution of various embodiments of the present invention that it does not separate the essence of the corresponding technical solution.

Claims (10)

1. a kind of method for calculating substation recording bulletin data processing time characterized by comprising
When main website and substation, which are established, to be communicated to connect, the link transmission delay time between the main website and the substation is obtained;
According to the link transmission delay time, the time adjusted value between protective device and the main website is obtained;
According to the link transmission delay time and the time adjusted value, calculate the substation handle current recorder data when Between and report to the main website delay time of the current recorder data, the current recorder data substation reports Recorder data;
Disconnect the communication connection of the main website Yu the substation.
2. the method according to claim 1, wherein the link obtained between the main website and the substation Propagation delay time, comprising:
Record the time t that the main website sends request for test frame to the substation0, and to receive the substation anti-to the main website The time t of the confirmation test frame of feedback1
According to the time t of the request for test frame0With the time t of the exact p-value frame1, the main website and described is calculated Link transmission delay time T between substationl
3. according to the method described in claim 2, acquisition is protected it is characterized in that, described according to the link transmission delay time Time adjusted value between protection unit and the main website, comprising:
Obtain the markers t in the warning information and event information that the substation reports about the protective devicefAnd the master It stands and receives the receiving time t of the warning information and event informationm
According to the link transmission delay time Tl, the markers tfAnd the receiving time tm, be calculated protective device with Time adjusted value Δ T between the main website.
4. according to the method described in claim 3, it is characterized in that, it is described according to the link transmission delay time and it is described when Between adjusted value, calculate the substation and handle the time of current recorder data and report the current recorder data to the main website Delay time, comprising:
According to the markers tfWith the time adjusted value Δ T, protective device markers t adjusted is calculatedd
According to the link transmission delay time Tl, the receiving time tmWith the protective device markers t adjustedd, calculate Obtain the time T that the substation handles current recorder data;
According to the receiving time tmWith the protective device markers t adjustedd, be calculated reported to the main website it is described The delay time T of current recorder datadly
5. method according to any of claims 1-4, which is characterized in that communication link is established in the main website and substation It connects, comprising:
First, which is sent, to the substation by the main website establishes request;
Receiving establishing to described first for the substation transmission by the main website requests send first to be successfully established response;
Alternatively,
Second, which is sent, to the main website by the substation establishes request;
Receiving establishing to described second for the main website transmission by the substation requests send second to be successfully established response.
6. a kind of computing device characterized by comprising
Transceiver module, for obtaining the link between the main website and the substation when main website and substation foundation communication connection Propagation delay time;
Processing module, for obtaining the time tune between protective device and the main website according to the link transmission delay time Whole value;According to the link transmission delay time and the time adjusted value, calculates the substation and handle current recorder data Time and the delay time that the current recorder data is reported to the main website, the current recorder data are that the substation reports Recorder data;Disconnect the communication connection of the main website Yu the substation.
7. computing device according to claim 6, which is characterized in that
The transceiver module, specifically for recording time t of the main website to substation transmission request for test frame0, and receive The time t for the confirmation test frame that the substation is fed back to the main website1;According to the time t of the request for test frame0With it is described really Recognize the time t of test frame1, the link transmission delay time T between the main website and the substation is calculatedl
The processing module is filled specifically for obtaining in the warning information and event information that the substation reports about the protection The markers t setfAnd the main website receives the receiving time t of the warning information and event informationm;According to the link transmission Delay time Tl, the markers tfAnd the receiving time tm, the time tune between protective device and the main website is calculated Whole value Δ T;
The processing module is specifically used for according to the markers tfWith the time adjusted value Δ T, protection adjusted is calculated Device markers td;According to the link transmission delay time Tl, the receiving time tmWith the protective device markers adjusted td, the time T that the substation handles current recorder data is calculated;According to the receiving time tmWith the guarantor adjusted Protection unit markers td, the delay time T that the current recorder data is reported to the main website is calculateddly
8. computing device according to claim 6 or 7, which is characterized in that
The transceiver module is also used to send first to the substation by the main website and establishes request;It is connect by the main website Receiving establishing to described first for the substation transmission requests send first to be successfully established response;
Alternatively,
The transceiver module is also used to send second to the main website by the substation and establishes request;It is connect by the substation Receiving establishing to described second for the main website transmission requests send second to be successfully established response.
9. a kind of computing device characterized by comprising
Transceiver, processor, memory, wherein the transceiver, the processor and the memory are connected by bus;
The memory, for storing operational order;
The transceiver, for obtaining the chain between the main website and the substation when main website and substation foundation communication connection The road propagation delay time;
The processor executes calculating substation record according to any one of claims 1 to 5 for calling the operational order The step of method of wave bulletin data processing time.
10. a kind of readable storage medium storing program for executing, is stored thereon with computer program, which is characterized in that the computer program is processed Device realizes the step of the method according to any one of claims 1 to 5 for calculating substation recording bulletin data processing time when executing Suddenly.
CN201910536632.2A 2019-06-20 2019-06-20 Method and computing device for computing data processing time of recording bulletin of substation Active CN110300021B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910536632.2A CN110300021B (en) 2019-06-20 2019-06-20 Method and computing device for computing data processing time of recording bulletin of substation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910536632.2A CN110300021B (en) 2019-06-20 2019-06-20 Method and computing device for computing data processing time of recording bulletin of substation

Publications (2)

Publication Number Publication Date
CN110300021A true CN110300021A (en) 2019-10-01
CN110300021B CN110300021B (en) 2022-09-16

Family

ID=68028333

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910536632.2A Active CN110300021B (en) 2019-06-20 2019-06-20 Method and computing device for computing data processing time of recording bulletin of substation

Country Status (1)

Country Link
CN (1) CN110300021B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110838760A (en) * 2019-11-27 2020-02-25 中国南方电网有限责任公司 Power grid fault data collection method and device
CN114422408A (en) * 2021-12-16 2022-04-29 深圳供电局有限公司 Transformer substation monitoring method and device, computer equipment and storage medium

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103501047A (en) * 2013-10-09 2014-01-08 云南电力调度控制中心 Intelligent fault wave recording main station information management system
CN107566072A (en) * 2017-10-24 2018-01-09 广东电网有限责任公司电力调度控制中心 A kind of secondary device clock synchronizing method based on dual time correction
CN108205096A (en) * 2017-11-24 2018-06-26 国网浙江省电力公司温州供电公司 A kind of multi-source failure data analyzing method based on active time adjustment

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103501047A (en) * 2013-10-09 2014-01-08 云南电力调度控制中心 Intelligent fault wave recording main station information management system
CN107566072A (en) * 2017-10-24 2018-01-09 广东电网有限责任公司电力调度控制中心 A kind of secondary device clock synchronizing method based on dual time correction
CN108205096A (en) * 2017-11-24 2018-06-26 国网浙江省电力公司温州供电公司 A kind of multi-source failure data analyzing method based on active time adjustment

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110838760A (en) * 2019-11-27 2020-02-25 中国南方电网有限责任公司 Power grid fault data collection method and device
CN110838760B (en) * 2019-11-27 2021-02-26 中国南方电网有限责任公司 Power grid fault data collection method and device
CN114422408A (en) * 2021-12-16 2022-04-29 深圳供电局有限公司 Transformer substation monitoring method and device, computer equipment and storage medium
CN114422408B (en) * 2021-12-16 2023-12-22 深圳供电局有限公司 Substation monitoring method, device, computer equipment and storage medium

Also Published As

Publication number Publication date
CN110300021B (en) 2022-09-16

Similar Documents

Publication Publication Date Title
CN110365529B (en) Edge computing intelligent gateway service processing method and edge computing intelligent gateway
CN107819645B (en) Internet of things testing method based on software simulation
CN104038371B (en) A kind of electric power communication transmission network adaptive performance acquisition method
US20110185235A1 (en) Apparatus and method for abnormality detection
CN101189895A (en) Abnormality detecting method and system, and upkeep method and system
CN104468200B (en) The Adaptive critic method of data center network apparatus health degree
EP3851973A1 (en) Data collection and processing method, apparatus and system
CN106301837B (en) Passive optical network alarm detection method and device
CN110728818A (en) Electrical fire monitoring system based on cloud platform and early warning analysis method thereof
CN110300021A (en) A kind of method and computing device calculating substation recording bulletin data processing time
CN106787169A (en) A kind of method of multi-data source comparison techniques diagnosis transformer station remote measurement failure
CN106533791A (en) End-to-end business quality optimization apparatus and method based on big data platform
CN112637006A (en) Power communication gateway key node and influence domain analysis method
CN110730234A (en) Electrical fire monitoring system and intelligent early warning analysis method thereof
CN105187554A (en) Method and system for monitoring server performance
CN101364892A (en) Time conversion method based on network element of different time zones
CN102082677B (en) Alarm information processing method, device and system
CN111901134B (en) Method and device for predicting network quality based on recurrent neural network model (RNN)
CN110275815A (en) A kind of system exception alert processing method and device
WO2021249546A1 (en) Network monitoring method, electronic device and storage medium
CN110675598A (en) Data exchange method and platform for railway earthquake early warning
CN109963292B (en) Complaint prediction method, complaint prediction device, electronic apparatus, and storage medium
CN103645417B (en) A kind of pure internet access-prepositioneddata data acquisition method
CN108768995A (en) Substation adaptive access main website method
CN111585350A (en) Power control station communication and analysis system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant