CN110295543A - A kind of science of bridge building prefabricated assembled anticollision barrier and its construction method - Google Patents

A kind of science of bridge building prefabricated assembled anticollision barrier and its construction method Download PDF

Info

Publication number
CN110295543A
CN110295543A CN201910587621.7A CN201910587621A CN110295543A CN 110295543 A CN110295543 A CN 110295543A CN 201910587621 A CN201910587621 A CN 201910587621A CN 110295543 A CN110295543 A CN 110295543A
Authority
CN
China
Prior art keywords
guardrail
science
anticollision barrier
bridge
prefabricated assembled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910587621.7A
Other languages
Chinese (zh)
Inventor
刘波
王世昌
赵庆贺
刘福才
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yantai University
Original Assignee
Yantai University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yantai University filed Critical Yantai University
Priority to CN201910587621.7A priority Critical patent/CN110295543A/en
Publication of CN110295543A publication Critical patent/CN110295543A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • E01D19/103Parapets, railings ; Guard barriers or road-bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F15/00Safety arrangements for slowing, redirecting or stopping errant vehicles, e.g. guard posts or bollards; Arrangements for reducing damage to roadside structures due to vehicular impact
    • E01F15/14Safety arrangements for slowing, redirecting or stopping errant vehicles, e.g. guard posts or bollards; Arrangements for reducing damage to roadside structures due to vehicular impact specially adapted for local protection, e.g. for bridge piers, for traffic islands

Abstract

The invention belongs to science of bridge building technologies, and in particular to the prefabricated assembled anticollision barrier of a kind of science of bridge building based on prestress wire connection is preset with the duct worn for prestress wire including the guardrail being prefabricated into the guardrail.Radial pressure caused by prestressed stretch-draw to produce powerful vertical pressure between concrete guardrail and bridge floor, and horizontal component caused by the frictional resistance collaboration prestressed stretch-draw which provides can be effective against the outside Transverse Impact power of Vehicular impact generation.Prefabricated construction eliminates the processes such as live assembling reinforcement, shuttering, cast-in-place concrete, maintenance, also mitigates environmental protection pressure.

Description

A kind of science of bridge building prefabricated assembled anticollision barrier and its construction method
Technical field
The invention belongs to science of bridge building technologies, and in particular to a kind of science of bridge building based on prestress wire connection is in advance The construction method of assembled anticollision barrier processed and the anticollision barrier.
Background technique
Bridge concrete anticollision barrier is current most widely used guardrail form, for support vehicles traveling safety extremely It closes important.However current concrete anti-collision guard bar, especially outside concrete guardrail use cast-in-situ steel reinforced concrete substantially, are applying Need to complete the processes such as assembling reinforcement, shuttering, concreting, concrete curing, form removal during work, required time compared with Long, work efficiency is lower.
Summary of the invention
To solve the above-mentioned problems, the present invention provides a kind of prefabricated assembled anticollision barrier of science of bridge building and the anticollisions The construction construction method of guardrail saves duration, easy for construction, mitigation environmental protection pressure.The technical solution adopted by the invention is as follows:
A kind of prefabricated assembled anticollision barrier of science of bridge building is preset in the guardrail including the guardrail being prefabricated into for pre- The duct that prestress steel strand is worn.
The prefabricated assembled anticollision barrier of above-mentioned science of bridge building, the arched curve in duct, in the lower end at guardrail both ends Face is respectively kept with port.
The prefabricated assembled anticollision barrier of above-mentioned science of bridge building, through there is bellows to be formed in the duct, the wave Port is stretched out at the both ends of line pipe respectively, and the prestress wire may pass through bellows.
The prefabricated assembled anticollision barrier of above-mentioned science of bridge building further includes two anchorages, and the anchorage is used for respectively will be pre- The both ends of prestress steel strand are fixed in the cantilever of bridge.
The prefabricated assembled anticollision barrier of above-mentioned science of bridge building, the anchorage is fixed on cantilever by anchoring tooth block, described Anchoring tooth block side is type, the section at its both ends is triangular in shape.
The prefabricated assembled anticollision barrier of above-mentioned science of bridge building, also embedded in the cantilever there are two spiral reinforcements, described Spiral reinforcement is respectively used to be arranged the both ends of bellows, the connected anchorage in the lower end of the spiral reinforcement.
The end face of the prefabricated assembled anticollision barrier of above-mentioned science of bridge building, the cantilever and guardrail cooperation is equipped with several anti- Shear-steel muscle, the height that the shear reinforcement exposes are 100 ~ 120mm, between longitudinally adjacent two shear reinforcements of bridge between Away from for 180 ~ 260mm.
A kind of construction method of the prefabricated assembled anticollision barrier of science of bridge building as described above, comprising the following steps:
S1) precast concrete guardrail;
S2) the cantilever installation guard rail position of bridge carries out installation spiral reinforcement and shear reinforcement construction;
S3) production anchoring tooth block;
S4) the brushing adhesive layer on the contact surface of guardrail and cantilever;
S5 guardrail) is lifted into installation site, after adhesive layer knot is hard, prestress wire is worn in bellows, tensioning is pre- Prestress steel strand and its both ends is fastened on cantilever with anchorage;
S6) the mud jacking into bellows completes installation after to be solidified.
Above-mentioned construction method, the stretch-draw prestressing force size of the prestress wire is 1339.2MPa ~ 1395MPa, bent Line radius is 3000mm.
Above-mentioned construction method, the adhesive layer be epoxy resin mortar layer and its with a thickness of 4.5 ~ 6.5mm, it is strong with concrete binding Degree is greater than 4MPa;Polypropylene fibre or steel fibre are added in the guardrail and the volume is 0.6 ~ 1.8kg/m3
The invention has the benefit that
(1) radial pressure caused by prestressed stretch-draw to produce powerful vertical pressure between concrete guardrail and bridge floor Power, the frictional resistance which provides cooperate with horizontal component caused by prestressed stretch-draw that can be effective against Vehicular impact production Raw outside Transverse Impact power.Prefabricated construction eliminates the works such as live assembling reinforcement, shuttering, cast-in-place concrete, maintenance Sequence also mitigates environmental protection pressure.
(2) shearing resistance that the cohesive force and shearing resistance bar dowel that epoxy resin mortar adhesive layer provides provide can effectively enhance guardrail Resist the ability of lateral impact.Since the epoxy resin mortar adhesive layer knot hard time is very short, prestressed stretch-draw finishes shield on the outside of bridge Column can be put into, and the duration can be obviously shortened, and bridge can be open to traffic in advance, can bring apparent economic benefit and society's effect Benefit.
(3) application of polypropylene fibre or steel fiber reinforced concrete is so that the wearability and crack resistance of concrete are improved, Concrete guardrail is hardly damaged in vehicle collision.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is cross-sectional view of the invention.
In figure: 1 being guardrail, 2 be prestress wire, 3 be anchorage, 4 be spiral reinforcement, 5 be shear reinforcement, 6 be bonding Layer, 7 be anchor tooth block, 8 be bellows, 9 be cantilever, 10 be bridge floor.
Specific embodiment
The present invention is further explained with reference to the accompanying drawing.
The prefabricated assembled anticollision barrier of a kind of science of bridge building, including the guardrail 1 being prefabricated into, it is characterised in that: the shield The duct worn for prestress wire 3 is preset in column 1.
The prefabricated assembled anticollision barrier of above-mentioned science of bridge building, the arched curve in duct, in the lower end at 1 both ends of guardrail Face is respectively kept with port.
The prefabricated assembled anticollision barrier of above-mentioned science of bridge building, through having bellows 8 to be formed in the duct, the wave Port is stretched out at the both ends of line pipe 8 respectively, and the prestress wire 3 may pass through bellows 8.
The prefabricated assembled anticollision barrier of above-mentioned science of bridge building, further includes two anchorages 3, and the anchorage 3 is used to respectively to The both ends of prestress wire 3 are fixed in the cantilever 9 of bridge.
The prefabricated assembled anticollision barrier of above-mentioned science of bridge building, the anchorage 3 are fixed on cantilever 9 by anchoring tooth block 7, institute It is triangular in shape for type, the section at its both ends to state anchoring 7 side of tooth block.
The prefabricated assembled anticollision barrier of above-mentioned science of bridge building, also embedded in the cantilever 9 there are two spiral reinforcement 4, institutes Spiral reinforcement 4 is stated to be respectively used to be arranged the both ends of bellows 8, the connected anchorage 3 in the lower end of the spiral reinforcement 4.
The prefabricated assembled anticollision barrier of above-mentioned science of bridge building, the cantilever 9 are equipped with several with the end face that guardrail 1 cooperates Shear reinforcement 5, the height that the shear reinforcement 5 exposes are 100 ~ 120mm, longitudinally adjacent two shear reinforcements 5 of bridge it Between spacing be 180 ~ 260mm.
Construction method one
A kind of construction method of the prefabricated assembled anticollision barrier of science of bridge building as described above, comprising the following steps:
S1) precast concrete guardrail 1, addition polypropylene fibre or steel fibre and the volume are 0.6 ~ 1.0kg/m when production3;? Bellows 8 is made in guardrail 1 and remains for the hole for cooperating shear reinforcement 5 in advance;
S2) cantilever 9 of bridge, which is installed, carries out installation spiral reinforcement 4 and the construction of shear reinforcement 5 at guardrail 1, what shear reinforcement 5 exposed Height is 100mm, and the spacing between longitudinally adjacent two shear reinforcements 5 of bridge is 200mm.
S3) production anchoring tooth block 7;
S4) the brushing adhesive layer 6 on the contact surface of guardrail 1 and cantilever 4;The adhesive layer 6 be epoxy resin mortar layer and its with a thickness of 5mm, it is greater than 4MPa with Concrete Bond Strength;
S5 guardrail 1) is lifted into installation site, after 6 knot of adhesive layer is hard, prestress wire 8 is worn in bellows 8, in advance 8 stretch-draw prestressing force of prestress steel strand to 1339.2 MPa, sweep 3000mm, specification is 5 Φs15.2* long 5800mm
And its both ends anchorage 3 is fastened on cantilever 9;
S6) the mud jacking into bellows 8 completes installation after to be solidified.
Construction method two
The main distinction of this construction method and above-mentioned construction method one is to have adjusted prestressing force size, the specific steps are as follows:
S1) precast concrete guardrail 1, addition polypropylene fibre or steel fibre and the volume are 1.6 ~ 1.8kg/m when production3;? Bellows 8 is made in guardrail 1 and remains for the hole for cooperating shear reinforcement 5 in advance;
S2) cantilever 9 of bridge, which is installed, carries out installation spiral reinforcement 4 and the construction of shear reinforcement 5 at guardrail 1, what shear reinforcement 5 exposed Height is 200mm, and the spacing between longitudinally adjacent two shear reinforcements 5 of bridge is 260mm.
S3) production anchoring tooth block 7;
S4) the brushing adhesive layer 6 on the contact surface of guardrail 1 and cantilever 4;The adhesive layer 6 be epoxy resin mortar layer and its with a thickness of 6.5mm, it is greater than 4MPa with Concrete Bond Strength;
S5 guardrail 1) is lifted into installation site, after 6 knot of adhesive layer is hard, prestress wire 8 is worn in bellows 8, in advance 8 stretch-draw prestressing force of prestress steel strand to 1395MPa, sweep 3000mm, specification is 5 Φs15.2* long 5800mm, and Its both ends anchorage 3 is fastened on cantilever 9;
S6) the mud jacking into bellows 8 completes installation after to be solidified.
Comparative example
The guardrail with above-mentioned specification of the same race is made with the mode of existing live formwork, welding, installation connection reinforcing bar.
Above-mentioned construction method one and two and comparative example are respectively equipped with two groups of finished products, carry out vertical direction maximal impact Test, the result is as follows:
Project Construction method one Construction method two Comparative example
Maximal impact (kN/m) 274 285 284
Site operation duration (h/m) 0.10 0.10 1.0
Site operation personnel amount (person-time) 8 8 20
It can be seen that this construction method of the application, can save great amount of cost from time and manpower, guardrail 1 is prefabricated Formula can assembled in situ, the equipment for simplifying construction site.Prestress wire 8 increases pressure to improve 1 transverse direction of guardrail Frictional force realizes high-intensitive connection, traffic safety is effectively ensured.

Claims (10)

1. the prefabricated assembled anticollision barrier of a kind of science of bridge building, including the guardrail (1) being prefabricated into, it is characterised in that: the shield The duct worn for prestress wire (3) is preset in column (1).
2. the prefabricated assembled anticollision barrier of science of bridge building according to claim 1, it is characterised in that: the duct is in bow Shape curve is respectively kept with port in the lower end surface at guardrail (1) both ends.
3. the prefabricated assembled anticollision barrier of science of bridge building according to claim 2, it is characterised in that: passed through in the duct Bellows (8) is installed with to be formed, port is stretched out at the both ends of the bellows (8) respectively, and the prestress wire (3) may pass through Bellows (8).
4. the prefabricated assembled anticollision barrier of science of bridge building according to claim 3, it is characterised in that: further include two anchors Have (3), the both ends of prestress wire (3) for being fixed in the cantilever (9) of bridge by the anchorage (3) respectively.
5. the prefabricated assembled anticollision barrier of science of bridge building according to claim 4, it is characterised in that: the anchorage (3) It is fixed on cantilever (9) by anchoring tooth block (7), anchoring tooth block (7) side is type, the section at its both ends is triangular in shape.
6. the prefabricated assembled anticollision barrier of science of bridge building according to claim 5, it is characterised in that: the cantilever (9) Inside also embedded there are two spiral reinforcement (4), the spiral reinforcement (4) is respectively used to be arranged the both ends of bellows (8), the spiral The lower end of reinforcing bar (4) is connected anchorage (3).
7. the prefabricated assembled anticollision barrier of science of bridge building according to claim 6, it is characterised in that: the cantilever (9) Several shear reinforcements (5) are equipped with the end face of guardrail (1) cooperation, the height that the shear reinforcement (5) is exposed is 100 ~ 120mm, the spacing between longitudinally adjacent two shear reinforcements (5) of bridge are 180 ~ 260mm.
8. a kind of construction method of the prefabricated assembled anticollision barrier of science of bridge building as claimed in claim 7, it is characterised in that: packet Include following steps,
S1) precast concrete guardrail (1);
S2 installation spiral reinforcement (4) and shear reinforcement (5) construction) are carried out at cantilever (9) installation guardrail (1) of bridge;
S3) production anchoring tooth block (7);
S4) the brushing adhesive layer (6) on the contact surface of guardrail (1) and cantilever (4);
S5 guardrail (1)) is lifted into installation site, after adhesive layer (6) knot is hard, wears prestress steel twist in bellows (8) Line (8), stretch-draw prestressing force steel strand wires (8) and its both ends are fastened on cantilever (9) with anchorage (3);
S6) to bellows (8) interior mud jacking, installation is completed after to be solidified.
9. construction method according to claim 8, it is characterised in that: the stretch-draw prestressing force of the prestress wire (8) Size is 1339.2MPa ~ 1395MPa, sweep 3000mm.
10. construction method according to claim 9, it is characterised in that: the adhesive layer (6) is epoxy resin mortar layer and its thickness Degree is 4.5 ~ 6.5mm, is greater than 4MPa with Concrete Bond Strength;In the guardrail (1) addition polypropylene fibre or steel fibre and The volume is 0.6 ~ 1.8kg/m3
CN201910587621.7A 2019-07-02 2019-07-02 A kind of science of bridge building prefabricated assembled anticollision barrier and its construction method Pending CN110295543A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910587621.7A CN110295543A (en) 2019-07-02 2019-07-02 A kind of science of bridge building prefabricated assembled anticollision barrier and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910587621.7A CN110295543A (en) 2019-07-02 2019-07-02 A kind of science of bridge building prefabricated assembled anticollision barrier and its construction method

Publications (1)

Publication Number Publication Date
CN110295543A true CN110295543A (en) 2019-10-01

Family

ID=68029818

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910587621.7A Pending CN110295543A (en) 2019-07-02 2019-07-02 A kind of science of bridge building prefabricated assembled anticollision barrier and its construction method

Country Status (1)

Country Link
CN (1) CN110295543A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101644032A (en) * 2009-08-31 2010-02-10 中交通力建设股份有限公司 Beam-removing rib-increasing strengthening construction technology of highway bridge
CN201962850U (en) * 2011-01-04 2011-09-07 山西省第三建筑工程公司 Space unbonded prestressed ring beam
WO2018214518A1 (en) * 2017-05-23 2018-11-29 山东大学 Intelligent, flexible protection device for steel arch in case of tunnel rockfall collapse
CN109208467A (en) * 2017-06-30 2019-01-15 广东工业大学 A kind of precast assembly crash barrier structure
CN109338950A (en) * 2018-11-12 2019-02-15 西安汉河环保科技有限公司 A kind of anticollision barrier construction method for highway
CN210262715U (en) * 2019-07-02 2020-04-07 烟台大学 Bridge engineering is with prefabricated assembled anticollision barrier

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101644032A (en) * 2009-08-31 2010-02-10 中交通力建设股份有限公司 Beam-removing rib-increasing strengthening construction technology of highway bridge
CN201962850U (en) * 2011-01-04 2011-09-07 山西省第三建筑工程公司 Space unbonded prestressed ring beam
WO2018214518A1 (en) * 2017-05-23 2018-11-29 山东大学 Intelligent, flexible protection device for steel arch in case of tunnel rockfall collapse
CN109208467A (en) * 2017-06-30 2019-01-15 广东工业大学 A kind of precast assembly crash barrier structure
CN109338950A (en) * 2018-11-12 2019-02-15 西安汉河环保科技有限公司 A kind of anticollision barrier construction method for highway
CN210262715U (en) * 2019-07-02 2020-04-07 烟台大学 Bridge engineering is with prefabricated assembled anticollision barrier

Similar Documents

Publication Publication Date Title
CN109339828B (en) Tunnel prestress inverted arch structure and construction method thereof
CN210262715U (en) Bridge engineering is with prefabricated assembled anticollision barrier
CN105019365A (en) Structure for rapidly restoring hinge joint of hollow slab bridge and construction method thereof
CN211256531U (en) Shock attenuation assembled steel fiber concrete pavement slab
CN103290786A (en) System and method for rapidly reinforcing railway bridge by external prestressing
CN110700089A (en) Cast-in-place wet joint structure and bridge
CN103306282A (en) Prestressed concrete pile configured with reinforced bars in sections and construction method
CN113062233A (en) Pre-tensioning method prestressed steel plate-concrete reinforcing method for box girder
CN105735099B (en) Construction time uses the simple supported-to-continuous girder bridge and its construction method of external prestressing
CN106087692B (en) A kind of Simply supported non-uniform T negative moment of girder section construction and construction method
CN110485314A (en) Highway T beam spells wide structure and method under a kind of operation state
CN103614975A (en) Shear connector reinforcing method for failed hinge joint of assembly-type hollow slab girder
CN106087694B (en) Assembling steel plate-beams of concrete combined bridge structure and construction method
JP6811678B2 (en) Method of joining concrete structures and concrete members to which continuous fiber reinforced concrete is applied
CN110295543A (en) A kind of science of bridge building prefabricated assembled anticollision barrier and its construction method
CN106087782B (en) A kind of remodeling method of bridge floor floating bowstring arch bridge
JP2000199397A (en) Method of enlarging tunnel for road, highway or expressway without blocking traffic
CN202831388U (en) Small beam high pre-stress pre-cast beam
JPH0959929A (en) Repair and reinforcing method of top of reinforced concrete floor slab
CN209114299U (en) A kind of Single-box multi-chamber box beam bridge
CN108103959B (en) Method for improving shear bearing capacity of hollow slab beam
CN213296883U (en) Prestressed reinforcement laying node
CN114892552A (en) Box girder type bridge reconstruction construction method
CN204590415U (en) A kind of prestressed reinforced concrete construction
CN210482013U (en) Bridge girder

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination