CN110276560A - Blocking management system construction method - Google Patents

Blocking management system construction method Download PDF

Info

Publication number
CN110276560A
CN110276560A CN201910577735.3A CN201910577735A CN110276560A CN 110276560 A CN110276560 A CN 110276560A CN 201910577735 A CN201910577735 A CN 201910577735A CN 110276560 A CN110276560 A CN 110276560A
Authority
CN
China
Prior art keywords
index
unit
rule
management system
system construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910577735.3A
Other languages
Chinese (zh)
Inventor
龚量亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Information Technology Co Ltd Clip
Original Assignee
Chongqing Information Technology Co Ltd Clip
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Information Technology Co Ltd Clip filed Critical Chongqing Information Technology Co Ltd Clip
Priority to CN201910577735.3A priority Critical patent/CN110276560A/en
Publication of CN110276560A publication Critical patent/CN110276560A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to be specially adapted for management, the data processing system of supervision or method and technology field, specially a kind of blocking management system construction method, comprising the following steps: indicator rule screening step obtains index creation rule according to index demand;Unit rules screening step filters out unit creation rule according to functional requirement;Unit foundation step creates regular constructing function unit according to unit creation rule, index;System construction step constructs enterprise management system according to several functional units.Using this programme, enables to enterprise's rapid deployment and implement management system.

Description

Blocking management system construction method
Technical field
The present invention relates to be specially adapted for management, the data processing system of supervision or method and technology field, specially one kind Blocking management system construction method.
Background technique
For any one enterprise, it is all vital for managing, by between management coordination technology and market Relationship, by management so that enterprise efficiency is promoted.If an enterprise is without the management system of complete science, its institute face What is faced is exactly personnel's confusion, and system is indefinite, the cost of product, quality and a series of problems such as supply and marketing is unstable, and these Problem finally only results in the failure of enterprise.Therefore for enterprise, it is necessary first to be exactly a complete management system.
Existing enterprise management system is mostly that enterprise and software supplier develop cooperatively, is provided demand by enterprise and is thought Method, software supplier are suitable for a set of enterprise management system of the enterprise according to the exploitation of the demand and idea of enterprise.But this The building of the enterprise management system of sample has the following problems:
1. duration is used in deployment and implementation.Enterprise needs to propose demand, and software supplier needs and enterprise confirms demand, then It is developed, trial operation system is needed after exploitation, also needed training enterprise staff using the system, usually develop the management of an enterprise The period of system is to differ for six months to 1 year.
Information island.Required between enterprise's difference column it is different, due to according to function, business scenario or operating process not Together, the enterprise management system developed is divided into different systems, such as ERP, MRP, PLM, OA etc. causes data among systems to be handed over Mutual and difficult communication.
Summary of the invention
The invention is intended to provide a kind of blocking management system construction method, enables to enterprise's rapid deployment and implement pipe Reason system.
The present invention provides base case: blocking management system construction method includes the following steps,
Indicator rule screening step obtains index creation rule according to index demand;
Unit rules screening step filters out unit creation rule according to functional requirement;
Unit foundation step creates regular constructing function unit according to unit creation rule, index.
Noun illustrates: functional requirement is the function that company manager needs or desired enterprise management system is realized;Index needs Asking as company manager is to reach index set by functional requirement;Unit creation rule is preset according to index constructing function The rule of unit;Index creation rule is the preset rule that index is generated according to parameter.
The working principle and beneficial effect of base case: functional requirement and index demand are specified by company manager, institute's structure The enterprise management system built more meets the demand of company manager, so that the experience sense of company manager is more preferable.Each function list Member realize a function, and can independent operating, unit creation rule and index creation rule be system developer it is preset, By directly creating regular constructing function unit according to unit creation rule, index, building difficulty is small, and deployment time is short.Pass through Staff's upload parameter just can generate index, realize correlation function, give training without carrying out to staff, implement letter It is single.Regular constructing function unit is created by existing unit creation rule and index, enables enterprise's rapid deployment and reality Apply management system.
Further, the indicator rule screening step specifically includes following steps,
S101 obtains the index demand of company manager;
S102, index creation rule needed for creating Rules Filterings from several indexs preset in database according to index demand Then.
Beneficial effect;Under different function demand, required index is also different.Selecting index by company manager needs It asks, different index demand its parameter differences, corresponding index creation rule is also different, obtains index according to specific needs and creates Rule, such as index demand are production cost, then the parameter obtained may include human cost, material cost etc., right The index creation rule answered generates index demand for the cumulative parameter obtained.In another example specific needs are single products cost, then There are two types of corresponding index creation rules, first is that then index creation rule is in the case where having generated production cost Production is obtained, production cost is divided by production, second is that in the case where not generating production cost, then index To obtain human cost, material cost and production, first add up creation rule every cost, then accumulation result is in production Total amount.Index creation rule is preset in the database by system developer in advance, calls directly index creation rule therein, contracting Short deployment time.
It is further, further comprising the steps of,
Parameter configuration step adjusts index creation rule according to specified parameter;
The unit foundation step creates regular constructing function unit according to index adjusted.
Beneficial effect;Since index creation rule is default in the database, fixation is output and input, can not be pasted completely Close the demand of company manager.Such as index creation rule is three inputs, it is cumulative to be exported, but company manager Demand be four input.Therefore by parameter configuration step adjust index creation rule, by three input be adjusted to four it is defeated Enter.
Further, the parameter configuration step specifically includes following steps,
Parameters acquiring procedure obtains the specified parameter of company manager;
Rule step obtains the index creation rule filtered out;
Index selection step obtains index demand;
Rule adjustment step, according to index demand, specified parameter adjustment index creation rule.
Beneficial effect;Specified parameter representative input, index demand represent output, create according to adjustment index is output and input Rule, with index needed for generating company manager.
Further, the indicator rule screening step specifically includes following steps,
S201 obtains the index demand of company manager;
S202 obtains index creation rule, and index creation rule is by user setting.
The utility model has the advantages that type and quantity are fixed since default index in the database creates rule, only based on Rule, therefore the creation of preset index is regular and is unsatisfactory for whole demands, for company manager, there are specific demands, therefore Rule by obtaining company manager's self-setting creates rule as index.
It is further, further comprising the steps of,
System construction step constructs enterprise management system according to several functional units.
Beneficial effect;Since an enterprise possesses each department, each plate, various functional requirements, according to multiple functions Demand or multiple columns construct multiple functional units, enterprise management system are constructed further according to multiple functional units, to realize enterprise Information mutual communication between each column of industry.
Further, the system construction step specifically includes following steps,
Unit obtaining step obtains several functional units;
Unit relating module is followed successively by functional unit and establishes connection, constructs enterprise management system.
Beneficial effect;It is followed successively by between functional unit and establishes connection, the connection between all functional units, which is established, to be completed When, that is, it represents enterprise management system building and completes, enterprise can come into operation the system.
Further, the unit foundation step specifically includes following steps,
Base rule obtaining step obtains several base rules,
Base rule combination step, according to index demand and functional requirement from several base rules select base rule into Row combination producing unit creation rule;
Unit generation step creates regular constructing function according to index demand, functional requirement, unit creation rule, index Unit.
Noun explanation: base rule is preset basic function, just can generation unit creation rule by combination foundation rule Then.
The utility model has the advantages that default base rule, company manager is by way of calling base rule to be combined or arrange in pairs or groups Just the unit creation rule needed for oneself can be generated.Company manager is in the light of actual conditions composed unit creation rule, portion It is short to affix one's name to the time, and the enterprise management system finally constituted more meets the demand of enterprise.
Further, the base rule is the preset general basic function of developer.
The utility model has the advantages that default basic function, is similar to template or tool, calling directly just can be used, easy to operate, be used It is convenient.
Further, the unit foundation step is specifically further comprising the steps of,
Regular configuration step, unit creation rule includes several standard indexs and standard feature, is selected according to standard index Specified index, selects specified function according to standard feature, creates rule according to the unit that specified index and specified functional configuration generate Then;
In unit generation step, regular constructing function unit is created according to the unit postponed.
The utility model has the advantages that specified function and specified index are obtained, the unit generated according to specified function and specified index allocation Creation rule, the i.e. type output and input and quantity of configuration unit creation rule, so that the enterprise management system of creation is just In enterprise carry out using.
Detailed description of the invention
Fig. 1 is the logic diagram that invention unit management system constructs system embodiment one;
Fig. 2 is the flow chart of invention unit management system construction method embodiment one;
Fig. 3 is the flow chart of invention unit management system construction method embodiment two.
Specific embodiment
It is further described below by specific embodiment:
Embodiment one
Blocking management system construction method of the invention is illustrated in order to clearer, and a kind of list is also disclosed in the present embodiment Memberization management system constructs system, and as shown in Fig. 1, including background server and management end, background server include that demand obtains Modulus block, index creation module, unit creation module, system building module and database.Several units are stored in database Creation rule, several indexs creation rule, unit creation rule is according to the building unit of index construction unit rule, index wound Rule is built as according to the rule of parameter generation index.
Management end for obtaining functional requirement and specific needs, and is sent to background server.Wherein functional requirement and refer to Determine demand to be determined by company manager, for example, functional requirement be cost management, index demand be same day totle drilling cost, single products at Originally, the exceeded item of cost.
Index creation module for receiving index demand, and obtains index creation rule according to index demand from database Then (index creation rule at this time includes an output and several inputs, and output is index demand, and input is acquisition parameter), and It is sent to unit creation module.When index demand is same day totle drilling cost, index creation rule is to ask according to several inputs are accumulative With exported, output be the same day totle drilling cost.
Demand obtains module, needs summing target demand for receive capabilities, and according to functional requirement and index demand from number According to filtering out in library, unit creation is regular, and is sent to unit creation module.
Unit creation module is used for receiving unit creation rule, index creation rule, and creates rule according to unit, refers to Mark creates regular constructing function unit, and functional unit is for constructing enterprise management system.
System constructs module, the connection for establishing between several functional units.It establishes and contacts for several functional units, structure At enterprise management system needed for company manager.
Blocking management system construction method based on above system, as shown in Fig. 2, comprising the following steps:
Indicator rule screening step obtains the index demand of company manager's setting, and according to index demand from database In filter out index creation rule.It is to reach index set by functional requirement that i.e. index demand, which is company manager, index wound Building rule is the preset rule that index is generated according to parameter.
Unit rules screening step obtains the functional requirement of company manager's setting, and according to functional requirement from database In filter out unit creation rule.I.e. functional requirement is the function that company manager needs or desired enterprise management system is realized, Unit creation rule is the preset rule according to index constructing function unit.
Unit foundation step creates regular constructing function unit according to unit creation rule, index.Unit creation rule and Index creation rule is directly acquired from database, thus shortens deployment time, since functional requirement and index demand are by enterprise Manager's setting, the functional unit of building meet the needs of company manager.
System construction step constructs enterprise management system according to several functional units.Due to enterprise possess numerous plates or Process, company manager determine functional unit also just have it is multiple, such as according to different departments distinguish, then can construct research and development pipe The functional units such as reason, supply of material management, production management, sales management, divide according to process, then can construct store keeping, production pipe The functional units such as reason, assembling management, quality management, Package Management.It establishes and contacts for several functional units, constitute company manager Required enterprise management system.
Specifically, indicator rule screening step the following steps are included:
S101 obtains the index demand of company manager;
S102, index creation rule needed for creating Rules Filterings from several indexs preset in database according to index demand Then
Specifically, system construction step includes the following steps,
Unit obtaining step obtains several functional units;
Unit relating module is followed successively by functional unit and establishes connection, constructs enterprise management system.
Embodiment two
Since index creation rule is preset by system developer, in order to meet most of enterprise demand, index creation rule It is then only capable of optimized integration function, needs enterprise to be voluntarily adjusted in the place of some details, to adapt to the reality of enterprise itself Border situation.
The present embodiment and embodiment one the difference is that: blocking management system constructs the background server of system also Including rule adjustment module.
Index creation module, for index creation rule to be sent to management end and rule adjustment module.
Management end for showing that index creation rule is checked for company manager, and obtains specified parameter, and after being sent to Platform server.Company manager checks index creation rule by management end, and when needing to adjust index creation rule, acquisition refers to Determine parameter, such as index creation rule is exported for cumulative human cost, material cost, basic cost three, still The demand of company manager is cumulative human cost, material cost, basic cost, other costs four inputs, then needs to obtain at this time Fetching determines parameter, i.e., specified parameter is human cost, material cost, basic cost, other costs.
Rule adjustment module, for receiving index demand, specified parameter and index creation rule, and according to index demand, Specified parameter adjustment index creation rule, and it is sent to unit creation module.
Blocking management system construction method based on above system, it is as shown in Fig. 3, further comprising the steps of,
Parameter configuration step obtains specified parameter, index creation rule is adjusted according to specified parameter, to meet business administration The demand of person.
Unit foundation step creates regular constructing function unit according to unit creation rule, index adjusted.
Specifically, parameter configuration step the following steps are included:
Parameters acquiring procedure obtains the specified parameter of company manager;
Rule step obtains the index creation rule filtered out;
Index selection step obtains index demand;
Rule adjustment step, according to index demand, specified parameter adjustment index creation rule.
Embodiment three
Each enterprise is unique, so its demand is also different, and preset index in database Creation rule is only capable of optimized integration function, and some specific demands of enterprise can not achieve.Therefore, enterprise can be to voluntarily Setting target creation rule, so that the enterprise management system finally constructed more meets the demand of enterprise.
The present embodiment and embodiment two the difference is that: blocking management system constructs the background server of system also Module, unit configuration module are obtained including rule acquisition module, unit rules, is also preset with several base rules in database.
Management end for obtaining index creation rule, and is sent to background server.Index creation rule by enterprise voluntarily Setting, more meets the demand of company manager.
Rule acquisition module for receiving index creation rule, and is sent to unit creation module.
Unit rules obtain module, for transferred from database several base rules be sent to management end for manager into Row combination (or collocation or setting), and several base rule generation units for the combination selected according to the manager that management end is fed back Creation rule, and it is sent to unit configuration module.
Unit configuration module, being used for receiving unit creation rule, (unit creation at this time is regular including several inputs and defeated Out, i.e. standard index and standard feature), and unit creation rule is sent to management end and selectes standard index and mark for manager Quasi- function, and using the standard index of feedback as specified index, and using the standard feature of feedback as specified function, according to specified The unit that function and specified index allocation generate creates rule, and is sent to unit creation module.
Blocking management system construction method based on above system, specifically, indicator rule screening step is following step It is rapid:
S201 obtains the index demand of company manager;
S202 obtains index creation rule, and index creation rule is by user setting.
Specifically, unit foundation step includes the following steps,
Base rule obtaining step, obtains several base rules, and base rule is the preset general basic letter of developer Number.
Base rule combination step, according to index demand and functional requirement from several base rules select base rule into Row combination producing unit creation rule.
Regular configuration step, unit creation rule includes several standard indexs and standard feature, is selected according to standard index Specified index, selects specified function according to standard feature, creates rule according to the unit that specified index and specified functional configuration generate Then.
Unit generation step creates rule according to index demand, functional requirement, with unit creation rule, the index postponed Constructing function unit.
What has been described above is only an embodiment of the present invention, and the common sense such as well known specific structure and characteristic are not made herein in scheme Excessive description, technical field that the present invention belongs to is all before one skilled in the art know the applying date or priority date Ordinary technical knowledge can know the prior art all in the field, and have using routine experiment hand before the date The ability of section, one skilled in the art can improve and be implemented in conjunction with self-ability under the enlightenment that the application provides This programme, some typical known features or known method should not become one skilled in the art and implement the application Obstacle.It should be pointed out that for those skilled in the art, without departing from the structure of the invention, can also make Several modifications and improvements out, these also should be considered as protection scope of the present invention, these all will not influence the effect that the present invention is implemented Fruit and patent practicability.The scope of protection required by this application should be based on the content of the claims, the tool in specification The records such as body embodiment can be used for explaining the content of claim.

Claims (10)

1. blocking management system construction method, it is characterised in that: include the following steps,
Indicator rule screening step obtains index creation rule according to index demand;
Unit rules screening step filters out unit creation rule according to functional requirement;
Unit foundation step creates regular constructing function unit according to unit creation rule, index.
2. blocking management system construction method according to claim 1, it is characterised in that: the indicator rule screening step Suddenly following steps are specifically included,
S101 obtains the index demand of company manager;
S102, index creation rule needed for creating Rules Filterings from several indexs preset in database according to index demand.
3. blocking management system construction method according to claim 1, it is characterised in that: it is further comprising the steps of,
Parameter configuration step adjusts index creation rule according to specified parameter;
The unit foundation step creates regular constructing function unit according to index adjusted.
4. blocking management system construction method according to claim 3, it is characterised in that: the parameter configuration step tool Body includes the following steps,
Parameters acquiring procedure obtains the specified parameter of company manager;
Rule step obtains the index creation rule filtered out;
Index selection step obtains index demand;
Rule adjustment step, according to index demand, specified parameter adjustment index creation rule.
5. described in any item blocking management system construction methods according to claim 1, it is characterised in that: the indicator rule Screening step specifically includes following steps,
S201 obtains the index demand of company manager;
S202 obtains index creation rule, and index creation rule is by user setting.
6. blocking management system construction method according to claim 1, it is characterised in that: it is further comprising the steps of,
System construction step constructs enterprise management system according to several functional units.
7. blocking management system construction method according to claim 6, it is characterised in that: the system construction step tool Body includes the following steps,
Unit obtaining step obtains several functional units;
Unit relating module is followed successively by functional unit and establishes connection, constructs enterprise management system.
8. blocking management system construction method according to claim 1, it is characterised in that: the unit foundation step tool Body includes the following steps,
Base rule obtaining step obtains several base rules,
Base rule combination step selectes base rule from several base rules according to index demand and functional requirement and carries out group Close generation unit creation rule;
Unit generation step creates regular constructing function unit according to index demand, functional requirement, unit creation rule, index.
9. blocking management system construction method according to claim 8, it is characterised in that: the base rule is exploitation The preset general basic function of person.
10. blocking management system construction method according to claim 9, it is characterised in that: the unit foundation step It is specific further comprising the steps of,
Regular configuration step, unit creation rule include several standard indexs and standard feature, are selected according to standard index specified Index, selects specified function according to standard feature, creates rule according to the unit that specified index and specified functional configuration generate;
In unit generation step, regular constructing function unit is created according to the unit postponed.
CN201910577735.3A 2019-06-28 2019-06-28 Blocking management system construction method Pending CN110276560A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910577735.3A CN110276560A (en) 2019-06-28 2019-06-28 Blocking management system construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910577735.3A CN110276560A (en) 2019-06-28 2019-06-28 Blocking management system construction method

Publications (1)

Publication Number Publication Date
CN110276560A true CN110276560A (en) 2019-09-24

Family

ID=67962619

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910577735.3A Pending CN110276560A (en) 2019-06-28 2019-06-28 Blocking management system construction method

Country Status (1)

Country Link
CN (1) CN110276560A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0947916A1 (en) * 1996-10-30 1999-10-06 Information System Development Institute Software producing method, processor, processing method and recording medium
CN102609259A (en) * 2012-02-03 2012-07-25 中国人民解放军63928部队 Architecture design and evaluation method for basic software platform
CN105608254A (en) * 2015-12-15 2016-05-25 宁波力芯科信息科技有限公司 Automated design method and platform oriented to intelligent hardware system development
CN107590638A (en) * 2017-07-28 2018-01-16 中车工业研究院有限公司 Match the acquisition methods and relevant device of the track traffic product model of user's request
CN109408039A (en) * 2018-09-30 2019-03-01 昆明理工大学 A kind of Optimal Configuration Method of scientific and technological resources services component

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0947916A1 (en) * 1996-10-30 1999-10-06 Information System Development Institute Software producing method, processor, processing method and recording medium
CN102609259A (en) * 2012-02-03 2012-07-25 中国人民解放军63928部队 Architecture design and evaluation method for basic software platform
CN105608254A (en) * 2015-12-15 2016-05-25 宁波力芯科信息科技有限公司 Automated design method and platform oriented to intelligent hardware system development
CN107590638A (en) * 2017-07-28 2018-01-16 中车工业研究院有限公司 Match the acquisition methods and relevant device of the track traffic product model of user's request
CN109408039A (en) * 2018-09-30 2019-03-01 昆明理工大学 A kind of Optimal Configuration Method of scientific and technological resources services component

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李婷: "基于SMDA的企业应用定制技术研究", 《中国优秀硕士学位论文全文数据库》 *

Similar Documents

Publication Publication Date Title
US7505998B2 (en) Apparatuses and methods for dynamic creation of phase Gantt charts
US6615182B1 (en) System and method for defining the organizational structure of an enterprise in a performance evaluation system
US20080091496A1 (en) Method and system for delivering and executing best practices in oilfield development projects
US6604084B1 (en) System and method for generating an evaluation in a performance evaluation system
US7945522B2 (en) Match-based employment system and method
US6901426B1 (en) System and method for providing access privileges for users in a performance evaluation system
US20140075342A1 (en) Collaborative on-line design landscape design tool
US20110145284A1 (en) Presenting skills distribution data for a business enterprise
US20040001103A1 (en) Modeling business objects
CN104956330A (en) Workload distribution with resource awareness
US20160055504A1 (en) Systems and methods of simulating user intuition of business relationships using biographical imagery
US20080288320A1 (en) Actionable business plan creation and execution
CN109377195A (en) Project development management method and device
Ackermann et al. Managing corporate knowledge experiences with SODA and V· I· S· A
CN111047282A (en) Method and device for executing approval process
WO2009017395A1 (en) Actionable business intelligence system and method
US20030050829A1 (en) Method and system for collecting and distributing data evaluating the job performances of short term job contractors through a computer controlled centralized database
CN109657908A (en) A kind of visiting method, system and computer readable storage medium
CN110276560A (en) Blocking management system construction method
CN114092061A (en) Visual project progress management system and method
CN110276561A (en) Information management system based on cloud platform
CN110276562A (en) Blocking management system constructs system and construction method
CN110288254A (en) Blocking management system based on cloud platform
DE112020004753T5 (en) RGB network and devices
JP2004145591A (en) System and method for distributing production capacity

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190924

RJ01 Rejection of invention patent application after publication