CN110260721A - Marl stratum high pressure pneumatic component method within the scope of railway protective - Google Patents
Marl stratum high pressure pneumatic component method within the scope of railway protective Download PDFInfo
- Publication number
- CN110260721A CN110260721A CN201910606975.1A CN201910606975A CN110260721A CN 110260721 A CN110260721 A CN 110260721A CN 201910606975 A CN201910606975 A CN 201910606975A CN 110260721 A CN110260721 A CN 110260721A
- Authority
- CN
- China
- Prior art keywords
- fracturing device
- fracturing
- ball valve
- pipe
- marl
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F42—AMMUNITION; BLASTING
- F42B—EXPLOSIVE CHARGES, e.g. FOR BLASTING, FIREWORKS, AMMUNITION
- F42B3/00—Blasting cartridges, i.e. case and explosive
- F42B3/04—Blasting cartridges, i.e. case and explosive for producing gas under pressure
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F42—AMMUNITION; BLASTING
- F42D—BLASTING
- F42D1/00—Blasting methods or apparatus, e.g. loading or tamping
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F42—AMMUNITION; BLASTING
- F42D—BLASTING
- F42D3/00—Particular applications of blasting techniques
- F42D3/04—Particular applications of blasting techniques for rock blasting
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Filling Or Discharging Of Gas Storage Vessels (AREA)
Abstract
The invention discloses a kind of marl stratum high pressure pneumatic component methods within the scope of railway protective; it is related to the technical field of blast working; it solves existing explosive blasting and generates significant shock; it seriously affects construction safety and is easy the problem of impacting to railway use, its key points of the technical solution are that the following steps are included: a. is assembled;B. it inflates;C. it drills;D. explosion;E. it recycles, liquid carbon dioxide is under conditions of quickly heating suddenly, sharply rapid expanding, the mode for generating greater impact power carries out explosion, the vibration of generation is faint when carrying out explosion, it is not easy to generate destruction to the stratum of surrounding, can greatly guarantees construction safety and be not easy to impact the normal use of railway.
Description
Technical field
The present invention relates to the technical fields of blast working, more specifically, it is related to plaster within the scope of a kind of railway protective
Rock stratum high pressure pneumatic component method.
Background technique
When carrying out blast working within the scope of railway protective, in order to guarantee not cause to damage and do not influence on railway
The normal use of railway, all can strict control explosion influence that stratum is generated, needs are to adopting when carrying out blast working
The equivalent of explosive carries out stringent control.
When carrying out blast working in marl stratum within the scope of railway protective, marl is one kind between carbonic acid
The rock of excessive type between rock salt and clay rock, is made of clay particle and carbonate particle, is in particle or pureed structure;
Usually marl all refer to mixed by flour sand and mud grade carbonate with clay mineral form a kind of it is loose, soft, frangible compared with
New sedimentary rock;Because of the characteristic of marl itself, in process that blast working is carried out in the marl stratum, hold very much
The case where vibration generated when easily because of explosive blasting causes stratum large area to be collapsed;This can cause greatly the safety of construction
It influences, and because is to be very easy to impact the normal use of railway and may be to iron within the scope of railway protective
Road damages, and needs a kind of to complete explosion again and will not generate the blasting method of significant shock now.
Summary of the invention
In view of the deficiencies of the prior art, the present invention intends to providing within the scope of a kind of railway protective marl
Layer high pressure pneumatic component method, under conditions of quickly heating suddenly, sharply rapid expanding, generates larger liquid carbon dioxide
The mode of impact force carries out explosion, and the vibration of generation is faint when carrying out explosion, it is not easy to generate to the stratum of surrounding broken
It is bad, it can greatly guarantee construction safety and be not easy to impact the normal use of railway.
To achieve the above object, the present invention provides the following technical scheme that marl stratum within the scope of a kind of railway protective
High pressure pneumatic component method, comprising the following steps:
A. assemble: by conducting wire from liquid storage pipe carve characters one end protrude into then from the liquid storage pipe other end stretch out;Level pressure is sheared into piece later
It loads onto gasket and links together with the conducting wire of heating device, level pressure shears one end of piece protrusion inwardly, then pulls out and adds
Thermal, so that level pressure shears piece completely into liquid storage pipe;Release pipe is first manually tightened later, then tightens filling valve again;
Then release pipe and filling valve are tightened using changer respectively, resistance is measured later, normal resistance value is the Europe 1-2
Nurse;
B. it inflates: fracturing device being inflated, carbon dioxide is filled into fracturing device, test the leakproofness of fracturing device later,
The filling valve of fracturing device and release pipe are respectively put into water when test, it is ensured that without a large amount of bubbles;
C. drill: drilling is constructed using down-the-hole drill, drilling it is deep-controlled in 1-3m, drilling arrangement uses "-" type
Formula;
D. explosion: more fracturing devices are sequentially inserted into blast hole, are carried out after then connecting the conducting wire of more fracturing devices
Explosion;
E. it recycles: the fracturing device of the recycling after explosion is transported to operation room, be filled with valve and release pipe is backed out, will cause later
The residue inside device is split to clean out;When carrying out filling valve and release pipe disassembly, dismantled using changer.
By using above-mentioned technical proposal, by being heated to liquid carbon dioxide, so that increased pressure causes 20MPa-
60MPa, the carbon dioxide of high pressure can rapidly be converted into gaseous state, and more than 600 times of volume expansion, the gas expansion energy of abrupt release
Make the rock mass fracturing on drill point periphery, a large amount of heat can be absorbed in the process of liquid carbon dioxide volume expansion, it is calm to reduce
The heat of surrounding rock body, and it is pneumatic when using low-pressure pneumatic, carbon dioxide explosion more many safely than conventional blast
It is the process of volume expansion, so the vibration generated in the moment for carrying out explosion is minimum, it is not easy to be generated to the stratum of surrounding broken
It is bad, it can greatly guarantee construction safety and be not easy to impact the normal use of railway.
The present invention is further arranged to: being needed to be prepared work before the step a, is checked inflating machine and changer is
No there are failures, and provide 380V alternating current for inflating machine and changer, and whether check has enough liquid in fluid reservoir
Carbon dioxide checks whether the corresponding consumptive material of fracturing device is sufficient;Then the works such as multimeter, pliers, spanner and interior hexagonal are checked
Whether complete have.
By using above-mentioned technical proposal, check equipment with the presence or absence of failure and check it is complete when consumptive material and tool,
It can guarantee going on smoothly for work progress, prevent from influencing construction because of the equipment fault either shortage of consumptive material and tool
It is normally carried out.
The present invention is further arranged to: in the step a, when conducting wire is passed through liquid storage pipe, first being put fracturing device liquid storage pipe
On display rack, iron wire is inserted into liquid storage pipe, and makes one end of iron wire buckle from one end that liquid storage pipe is carved characters
It stretches out, then catches on the conducting wire of heating device with one end of iron wire buckle and pull iron wire, so that conducting wire is from the another of liquid storage pipe
It is stretched out in one end.
By using above-mentioned technical proposal, conducting wire is pulled to pass through in liquid storage pipe by the iron wire of buckle, it can be to leading
Line guides, and enables conducting wire to pass through liquid storage pipe more convenient.
The present invention is further arranged to: in the step a, when tightening to release pipe and filling valve, first by hand
The fracturing device that work is twisted is placed on changer jaw, and is filled with one, valve and is inserted into dismounting in front;It pins and clamps button to pressure
Power, which rises to unclamp after 10MPa or more, clamps button, when then pinning fastening buttons pressure being made to rise to 10MPa, decontrols tight
Gu button;Then fracturing device is turned around, repeated presses clamp button and fastening buttons, so that pressure is risen to 10MPa respectively.
By using above-mentioned technical proposal, by controlling the range of pressure, release pipe and filling valve can either be tightened, again
It can prevent the helicitic texture for excessively tightening and destroying junction.
The present invention is further arranged to: in the step b, being deflated, will entirely be managed before working for the first time daily
Evacuating pipeline, when exhaust, first open inlet ball valve and vent ball valve in filling station, release button are then pressed, until vent ball valve
After spraying continuously white gas, vent ball valve is closed.
By using above-mentioned technical proposal, deflation processing is all carried out before working for the first time daily, can prevent from having in pipeline
Other remaining gases, so that carbon dioxide gas can be full of in pipeline.
The present invention is further arranged to: in the step b, inflation when, first carries out washing pipe, washes Guan Shixian for fracturing device
It is placed in filling station to hole is filled well, tightens clamping bar and be filled with valve with allen wrench and open, then open fracturing device
Corresponding ball valve closes the ball valve of no fracturing device, after pressing release button, closes inlet ball valve and then opens outlet ball
Valve releases the carbon dioxide in fracturing pipe, closes vent ball valve after releasing most, repeats two to three times.
By using above-mentioned technical proposal, other purge of gas in the liquid storage pipe of fracturing device can be done by washing pipe
Only, so that only storing carbon dioxide in the liquid storage pipe of fracturing device.
The present invention is further arranged to: in the step b, when being inflated, first being closed inlet ball valve, is then pressed pressurization
Button waits fracturing device machine full of after to be automatically closed, after machine stops, with allen wrench by the filling valve of fracturing device
It closes, is then shut off inlet ball valve, then open vent ball valve and release excessive gas.
The present invention is further arranged to: in the step d, when carrying out explosion, first being caused first fracturing device and second
It splits device first to connect, is then plugged bolt, the plug of first fracturing device is cut short, and the conducting wire of two fracturing devices is entangled in
Together, it is twined with insulating tape, later connects conehead later;Connect two fracturing devices are inserted into blast hole,
Insertion before first lifting rod is inserted into the release pipe of second fracturing device so that second fracturing device will not directly hang in it is quick-fried
In holes, facilitate the connection for carrying out third root fracturing device and second fracturing device, by third root fracturing device and second fracturing device
It connects, in the release pipe of second lifting rod insertion third root fracturing device, then extracts first lifting rod, later will
Fracturing device is put into hole, is sequentially completed the connection to subsequent fracturing device later.
By using above-mentioned technical proposal, fracturing device is limited using pull rod, next fracturing device can connected
When, prevent previous fracturing device from falling in blast hole.
In conclusion the present invention has the advantages that compared with the prior art
1, the present invention carries out explosion by the way of carbon dioxide explosion, and liquid carbon dioxide is in the condition quickly heated suddenly
Under, sharply rapid expanding, the mode for generating greater impact power carry out explosion, and the vibration of generation is faint when carrying out explosion,
It is not easy to generate destruction to the stratum of surrounding, can greatly guarantees construction safety and be not easy to make the normal use of railway
At influence;
2, the present invention limits the fracturing device being put into blast hole by using lifting rod, can be in next of connection
When fracturing device, prevent previous fracturing device from falling in blast hole.
Detailed description of the invention
Fig. 1 is the axonometric drawing of the fracturing device of embodiment.
Specific embodiment
Embodiment: a kind of marl stratum high pressure pneumatic component method within the scope of railway protective, comprising the following steps:
A. it preparation: checks that inflating machine and changer whether there is failure, and provides 380V friendship for inflating machine and changer
Whether galvanic electricity, checking has enough liquid carbon dioxides in fluid reservoir, checks whether the corresponding consumptive material of fracturing device is sufficient, such as
Heating rod, rupture disk and gasket;Then check whether the tools such as multimeter, pliers, spanner and interior hexagonal are complete;
B. it assembles: conducting wire being protruded into and then stretched out from the liquid storage pipe other end from liquid storage pipe one end of carving characters, first by fracturing device when operation
Liquid storage pipe is placed on display rack, and iron wire is inserted into liquid storage pipe, and one end of iron wire buckle is carved characters from liquid storage pipe
One end in stretch out, then catch on the conducting wire of heating device with one end of iron wire buckle and pull iron wire, so that conducting wire is from storage
It is stretched out in the other end of liquid pipe;Level pressure shearing piece is loaded into gasket later and is connected to one with the conducting wire of heating device
It rises, it should be noted that one end of level pressure shearing piece protrusion is inwardly, then pulls out heating device, so that level pressure shears piece completely into storage
In liquid pipe;First tighten later release pipe, then tighten filling valve again, be tightened to when being tightened can not turn for
Only;Then release pipe and filling valve are tightened using changer respectively, the fracturing device being twisted by hand is first placed on dismounting when tightening
On machine jaw, and it is filled with one, valve and is inserted into dismounting in front;It pins to clamp after button to pressure rises to 10MPa or more and unclamp
Button is clamped, when then pinning fastening buttons pressure being made to rise to 10MPa, decontrols fastening buttons;Then fracturing device is turned around,
Repeated presses clamp button and fastening buttons, so that pressure is risen to 10MPa respectively;To which fracturing as shown in Figure 1 will be assembled into
Device;Resistance is measured later, normal resistance value is 1-2 ohm;
C. it inflates: deflating before working for the first time daily, entire pipeline is emptied, when exhaust first opens in filling station
Inlet ball valve and vent ball valve, then press release button, after vent ball valve sprays continuously white gas, close
Vent ball valve;Then fracturing device is inflated again, inflation when first carries out washing pipe, washes Guan Shixian and is placed on fracturing device and fills
To hole is filled well on platform, tightens clamping bar and be filled with valve with allen wrench and open, then open corresponding to fracturing device
Ball valve closes the ball valve of no fracturing device, after pressing release button, closes inlet ball valve and then opens vent ball valve, by fracturing
Carbon dioxide in pipe is released, and closes vent ball valve after releasing most, repeats two to three times;Then carbon dioxide is filled
Into fracturing device, inlet ball valve is first closed when filling, then presses pressurization button, and fracturing device machine full of after is waited to close automatically
It closes, after machine stops, the filling valve of fracturing device is closed with allen wrench, is then shut off inlet ball valve, then open outlet
Ball valve releases excessive gas;The leakproofness for testing fracturing device later, by the filling valve of fracturing device and release pipe difference when test
Into the water, it is ensured that without a large amount of bubbles;
D. drill: drilling is constructed using down-the-hole drill, drilling it is deep-controlled in 1-3m, drilling arrangement uses "-" type
Formula;
E. explosion: more fracturing devices are sequentially inserted into blast hole, are carried out after then connecting the conducting wire of more fracturing devices
Explosion;When specific operation, first first fracturing device and second fracturing device are first connected, is then plugged bolt, by first
The plug of fracturing device is cut short, and twines, the conducting wire tangle up of two fracturing devices later by conehead with insulating tape later
In connection;Connect two fracturing devices are inserted into blast hole, lifting rod is first inserted into second fracturing device before insertion
Release pipe in so that second fracturing device will not directly be hung in blast hole, facilitate and carry out third root fracturing device and second
The connection of root fracturing device connects third root fracturing device and second fracturing device, and second lifting rod insertion third root is caused
It splits in the release pipe of device, then extracts first lifting rod, fracturing device is put into hole later, is sequentially completed later to subsequent
The connection of fracturing device;
F. it recycles: the fracturing device of the recycling after explosion is transported to operation room, be filled with valve and release pipe is backed out, will cause later
The residue inside device is split to clean out;When carrying out filling valve and release pipe disassembly, dismantled using changer.
The above is only a preferred embodiment of the present invention, protection scope of the present invention is not limited merely to above-mentioned implementation
Example, all technical solutions belonged under thinking of the present invention all belong to the scope of protection of the present invention.It should be pointed out that for the art
Those of ordinary skill for, several improvements and modifications without departing from the principles of the present invention, these improvements and modifications
It should be regarded as protection scope of the present invention.
Claims (8)
1. a kind of marl stratum high pressure pneumatic component method within the scope of railway protective, it is characterised in that: the following steps are included:
A. assemble: by conducting wire from liquid storage pipe carve characters one end protrude into then from the liquid storage pipe other end stretch out;Level pressure is sheared into piece later
It loads onto gasket and links together with the conducting wire of heating device, level pressure shears one end of piece protrusion inwardly, then pulls out and adds
Thermal, so that level pressure shears piece completely into liquid storage pipe;Release pipe is first manually tightened later, then tightens filling valve again;
Then release pipe and filling valve are tightened using changer respectively, resistance is measured later, normal resistance value is the Europe 1-2
Nurse;
B. it inflates: fracturing device being inflated, carbon dioxide is filled into fracturing device, test the leakproofness of fracturing device later,
The filling valve of fracturing device and release pipe are respectively put into water when test, it is ensured that without a large amount of bubbles;
C. drill: drilling is constructed using down-the-hole drill, drilling it is deep-controlled in 1-3m, drilling arrangement uses "-" type
Formula;
D. explosion: more fracturing devices are sequentially inserted into blast hole, are carried out after then connecting the conducting wire of more fracturing devices
Explosion;
E. it recycles: the fracturing device of the recycling after explosion is transported to operation room, be filled with valve and release pipe is backed out, will cause later
The residue inside device is split to clean out;When carrying out filling valve and release pipe disassembly, dismantled using changer.
2. marl stratum high pressure pneumatic component method within the scope of railway protective according to claim 1, it is characterised in that:
It needs to be prepared work before the step a, checks that inflating machine and changer whether there is failure, and for inflating machine and tear open
Installation provides 380V alternating current, and whether check has enough liquid carbon dioxides in fluid reservoir, checks the corresponding consumption of fracturing device
Whether material is sufficient;Then check whether the tools such as multimeter, pliers, spanner and interior hexagonal are complete.
3. marl stratum high pressure pneumatic component method within the scope of railway protective according to claim 1, it is characterised in that:
In the step a, when conducting wire is passed through liquid storage pipe, first fracturing device liquid storage pipe is placed on display rack, iron wire is inserted into liquid storage
In pipe, and one end of iron wire buckle is stretched out from one end that liquid storage pipe is carved characters, is then hooked with one end of iron wire buckle
Firmly the conducting wire of heating device and iron wire is pulled, so that conducting wire stretches out in the other end of liquid storage pipe.
4. marl stratum high pressure pneumatic component method within the scope of railway protective according to claim 1, it is characterised in that:
In the step a, when tightening to release pipe and filling valve, the fracturing device being twisted by hand is first placed on changer jaw
On, and be filled with one, valve and be inserted into dismounting in front;Release clamping after clamping button to pressure rises to 10MPa or more is pinned to press
Button when then pinning fastening buttons pressure being made to rise to 10MPa, decontrols fastening buttons;Then fracturing device is turned around, repetition is pressed
Pressure clamps button and fastening buttons, so that pressure is risen to 10MPa respectively.
5. marl stratum high pressure pneumatic component method within the scope of railway protective according to claim 1, it is characterised in that:
It in the step b, deflates before working for the first time daily, entire pipeline is emptied, when exhaust first opens in filling station
Inlet ball valve and vent ball valve, then press release button, until vent ball valve sprays continuously after white gas, close
Close vent ball valve.
6. marl stratum high pressure pneumatic component method within the scope of railway protective according to claim 1, it is characterised in that:
In the step b, inflation when, first carries out washing pipe, washes Guan Shixian and fracturing device is placed in filling station to hole is filled well, tighten
Clamping bar and with allen wrench be filled with valve open, then open fracturing device corresponding to ball valve, closing there is no fracturing device
Ball valve, after pressing release button, close inlet ball valve then open vent ball valve, by fracturing pipe carbon dioxide release,
Vent ball valve is closed after releasing most, repeats two to three times.
7. marl stratum high pressure pneumatic component method within the scope of railway protective according to claim 1, it is characterised in that:
In the step b, when being inflated, inlet ball valve is first closed, then presses pressurization button, waits fracturing device machine full of after
It is automatically closed, after machine stops, the filling valve of fracturing device is closed with allen wrench, is then shut off inlet ball valve, then beat
Vent ball valve is opened to release excessive gas.
8. marl stratum high pressure pneumatic component method within the scope of railway protective according to claim 1, it is characterised in that:
In the step d, when carrying out explosion, first first fracturing device and second fracturing device is first connected, are then plugged bolt, it will
The plug of first fracturing device is cut short, and by the conducting wire tangle up of two fracturing devices, is twined later with insulating tape, later
Conehead is connected;Connect two fracturing devices are inserted into blast hole, lifting rod is first inserted into second before insertion
In the release pipe of fracturing device, so that second fracturing device will not directly be hung in blast hole, facilitates and carry out third root fracturing device
With the connection of second fracturing device, third root fracturing device and second fracturing device are connected, by second lifting rod insertion the
In the release pipe of three fracturing devices, first lifting rod is then extracted, fracturing device is put into hole later, is sequentially completed later
Connection to subsequent fracturing device.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910606975.1A CN110260721A (en) | 2019-07-06 | 2019-07-06 | Marl stratum high pressure pneumatic component method within the scope of railway protective |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910606975.1A CN110260721A (en) | 2019-07-06 | 2019-07-06 | Marl stratum high pressure pneumatic component method within the scope of railway protective |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110260721A true CN110260721A (en) | 2019-09-20 |
Family
ID=67924778
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910606975.1A Pending CN110260721A (en) | 2019-07-06 | 2019-07-06 | Marl stratum high pressure pneumatic component method within the scope of railway protective |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110260721A (en) |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2010019085A1 (en) * | 2008-08-11 | 2010-02-18 | Thoernqvist Milana Kirsanova | Gas generator for splitting and destructing materials, ignition unit and composition for use in gas generators for splitting and destructing materials |
CN105201481A (en) * | 2015-10-17 | 2015-12-30 | 山西晋煤集团技术研究院有限责任公司 | Liquid CO2 phase transition multipoint fracturing and permeability increasing method |
CN105401930A (en) * | 2015-09-02 | 2016-03-16 | 煤科集团沈阳研究院有限公司 | Carbon dioxide phase change coal seam fracturing device and utilization method |
CN105604550A (en) * | 2016-03-14 | 2016-05-25 | 山东名世矿业机械有限公司 | Carbon dioxide fracturer |
CN205718701U (en) * | 2016-04-25 | 2016-11-23 | 永州市鑫东森机械装备有限公司 | Connect the carbon dioxide fracturing device attachment means of quick change soon |
CN106351659A (en) * | 2016-10-13 | 2017-01-25 | 山东名世矿业机械有限公司 | Carbon dioxide cracking device |
CN107063009A (en) * | 2016-08-26 | 2017-08-18 | 中国铁建大桥工程局集团有限公司 | A kind of micro- blasting technology that shakes of subway two-wire longspan tunnel |
CN208443267U (en) * | 2018-07-11 | 2019-01-29 | 安徽理工大学 | A kind of explosion carbon dioxide fracturing device |
-
2019
- 2019-07-06 CN CN201910606975.1A patent/CN110260721A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2010019085A1 (en) * | 2008-08-11 | 2010-02-18 | Thoernqvist Milana Kirsanova | Gas generator for splitting and destructing materials, ignition unit and composition for use in gas generators for splitting and destructing materials |
CN105401930A (en) * | 2015-09-02 | 2016-03-16 | 煤科集团沈阳研究院有限公司 | Carbon dioxide phase change coal seam fracturing device and utilization method |
CN105201481A (en) * | 2015-10-17 | 2015-12-30 | 山西晋煤集团技术研究院有限责任公司 | Liquid CO2 phase transition multipoint fracturing and permeability increasing method |
CN105604550A (en) * | 2016-03-14 | 2016-05-25 | 山东名世矿业机械有限公司 | Carbon dioxide fracturer |
CN205718701U (en) * | 2016-04-25 | 2016-11-23 | 永州市鑫东森机械装备有限公司 | Connect the carbon dioxide fracturing device attachment means of quick change soon |
CN107063009A (en) * | 2016-08-26 | 2017-08-18 | 中国铁建大桥工程局集团有限公司 | A kind of micro- blasting technology that shakes of subway two-wire longspan tunnel |
CN106351659A (en) * | 2016-10-13 | 2017-01-25 | 山东名世矿业机械有限公司 | Carbon dioxide cracking device |
CN208443267U (en) * | 2018-07-11 | 2019-01-29 | 安徽理工大学 | A kind of explosion carbon dioxide fracturing device |
Non-Patent Citations (1)
Title |
---|
唐鹏春 等: "浅谈路改工程中二氧化碳爆破技术", 《中国新技术新产品》 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107063009A (en) | A kind of micro- blasting technology that shakes of subway two-wire longspan tunnel | |
CN212291344U (en) | Emergency leakage blocking device for hazardous chemical tank truck | |
CN106969911A (en) | A kind of locomotive brake hose test device | |
CN110260721A (en) | Marl stratum high pressure pneumatic component method within the scope of railway protective | |
CN112253398B (en) | Automatic internal gas emission method for single pile foundation of offshore wind turbine generator system | |
CN108105524B (en) | Inflatable pipeline plugging tool with pressure relief structure | |
CN206012565U (en) | A kind of inflating and tire-patching device and its Multifunctional inflating joint | |
CN104608893B (en) | Irregular hole leaking stoppage device | |
JPH0249137A (en) | Method and apparatus for testing pressure for pipe segment | |
CN108302279B (en) | Temporary emergency pipeline quick plugging equipment and construction method thereof | |
CN109552591A (en) | A kind of aerostatics fast aeration method and device | |
CN104213848B (en) | A kind of arc sealing device and using method for pipeline with pressure or drilling rod perforate | |
CN113295051A (en) | Air energy expansion rock fracturing system and use method thereof | |
CN206804286U (en) | A kind of locomotive brake hose test device | |
CN2099236U (en) | Inflatable rubber bag for pipe sealing | |
CN208653744U (en) | A kind of artesian well temporary leaking water device | |
CN210291075U (en) | Safe convenient GIS equipment inflation connecting device | |
CN112432049A (en) | Celebration palace lantern fills gassing device fast | |
CN210324794U (en) | Transformer capsule type conservator exhaust training auxiliary equipment | |
CN209249239U (en) | A kind of main transformer spray test oil electrical equipment and instrument and meter protective device | |
CN208616171U (en) | Gasbag-type leak stoppage device peculiar to vessel | |
CN205592561U (en) | A pressure testing head for liner hanger | |
CN110644493A (en) | Boulder excavation method and boulder excavation device | |
CN110906160A (en) | Oil-immersed transformer pillow type capsule automatic inflation device | |
CN104565810A (en) | General type SF6-gas filling device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190920 |