CN110258238A - A kind of laying method of new-old concrete bond intersection - Google Patents

A kind of laying method of new-old concrete bond intersection Download PDF

Info

Publication number
CN110258238A
CN110258238A CN201910386627.8A CN201910386627A CN110258238A CN 110258238 A CN110258238 A CN 110258238A CN 201910386627 A CN201910386627 A CN 201910386627A CN 110258238 A CN110258238 A CN 110258238A
Authority
CN
China
Prior art keywords
section
layer
new
locating slot
slot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910386627.8A
Other languages
Chinese (zh)
Inventor
张国伟
岳跃军
王建
吴文迪
于进
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kunshan Traffic And Navigation Engineering Co Ltd
Original Assignee
Kunshan Traffic And Navigation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kunshan Traffic And Navigation Engineering Co Ltd filed Critical Kunshan Traffic And Navigation Engineering Co Ltd
Priority to CN201910386627.8A priority Critical patent/CN110258238A/en
Publication of CN110258238A publication Critical patent/CN110258238A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/02Arrangement or construction of joints; Methods of making joints; Packing for joints
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C19/00Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving
    • E01C19/12Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving for distributing granular or liquid materials
    • E01C19/16Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving for distributing granular or liquid materials for applying or spreading liquid materials, e.g. bitumen slurries

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Repair (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a kind of laying methods of new-old concrete bond intersection, the weeds waste on two periphery of section one and section is cleared up, expose the road surface of neat and tidy, filling slot will be reserved between section one and section two, the left side in section one is opened up into out locating slot one, the right side opening in section two is set out into locating slot two, locating slot two and locating slot one and is symmetrical arranged with the vertical centerline of filling slot, the surface in section one and section two is fixedly connected to baffle, in the bottom dump asphaltic liquid of filling slot.The present invention, in the step of implementing S1 to S9, also each structure sheaf is vibrated using oscillator, precipitate each asphaltic liquid completely, and by bubble removal therein, it can come into operation after the complete cooled and solidified of each structure sheaf, solve the problem of usually generating sedimentation and deformation between new, old embankment in road surface reconstruction and extension project in actual use, lead to the diseases such as embankment drawing crack, pavement destruction.

Description

A kind of laying method of new-old concrete bond intersection
Technical field
The present invention relates to road engagement technique field, specially a kind of laying method of new-old concrete bond intersection.
Background technique
It improves with the continuous development of society, road Traffic Volume increases, especially the road traffic of the planning and designing of early stage Amount prediction is insufficient, and the road of some early stages construction has not been able to satisfy the demand of the growing volume of traffic more and more, in order to Meet daily use;It needs to carry out old road to build transformation;The transformation on old road is exactly based on existing road, and splicing is new Road increases number of track-lines to improve the traffic current capacity of road, usually produces between new, old embankment in Expressway Extension Project Raw sedimentation and deformation leads to the diseases such as embankment drawing crack, pavement destruction, and improper new-old concrete bond road surface engaging portion handle measure is that disease produces The main reason for raw, thus it is proposed that a kind of laying method of new-old concrete bond intersection.
Summary of the invention
The purpose of the present invention is to provide a kind of laying methods of new-old concrete bond intersection, improve to conventional apparatus, Solves the problems in background technique.
To achieve the above object, the invention provides the following technical scheme: a kind of laying method of new-old concrete bond intersection, packet Section 1, section 22 and connecting plate 7 are included, is included the following steps:
S1: the weeds waste on two periphery of section one and section is cleared up, the road surface of neat and tidy is exposed;
S2: filling slot will be reserved between section one and section two;
S3: the left side in section one is opened up into out locating slot one;
S4: the right side opening in section two is set out into locating slot two, locating slot two and locating slot one with the vertical center of filling slot Line is symmetrical arranged;
S5: the surface in section one and section two is fixedly connected to baffle;
S6: locating slot one and locating slot two are laid in the bottom dump asphaltic liquid of filling slot, and by first layer connecting plate Inner wall in;
S7: after first layer pitch cooled and solidified, then second layer asphaltic liquid is toppled in filling slot, and in second layer pitch Second layer connecting plate is laid with surface on it before liquid cooled and solidified;
S8: after second layer pitch cooled and solidified, the step of repeating S7, completes third layer, drips in the 4th layer and layer 5 The placement of green filling and connecting plate;
S9: layer 6 connecting plate is placed thereon before the uncolled solidification of layer 5 pitch in S8 step, is dripped to this layer After blueness solidification, refill that concrete is placed on it, make the height in concrete and section one and section two quite and by section one and The upper surface in section two connects.
Preferably, irregular protrusion is equipped on the opposite side in the section one and section two.
Preferably, the depth of the filling slot is less than the depth in section one and section two.
Preferably, protrusion also is provided on two inner wall of the locating slot one and locating slot.
Preferably, the quantity of the baffle is two, and two baffles are fixedly arranged on the front and back in section one and section two respectively On side.
Preferably, the height of the baffle upper surface is higher than the height in section one and section two.
Preferably, the connecting plate is V shaped slab, and connecting plate is opening up.
Preferably, in same level, the spacing of two adjacent connecting plates is no more than 30 centimetres.
Preferably, the structure sheaf in the filling slot is no less than three layers.
Preferably, in the vertical direction, the spacing between two adjacent connecting plates is no more than seven centimetres.
Compared with prior art, beneficial effects of the present invention are as follows:
One, the present invention is by raised setting irregular on the opposite side by section one and section two, so that each knot Asphaltic liquid in structure layer can generate bigger contact area with it, to make the pitch after cooled and solidified and section one and section Two connection is stronger.
Two, the present invention is less than the depth in section one and section two by the depth of filling slot, small by the depth of filling slot Depth in section one and section two keeps each structure sheaf and the integraty effect in section one and section two more preferable, in filling slot Structure sheaf be no less than three layers, be no less than three layers by the structure sheaf in filling slot, guarantee road surface when in use, be less prone to disconnected Layer, the problems such as collapsing.
Three, the present invention passes through locating slot two and locating slot by also being provided with protrusion on two inner wall of locating slot one and locating slot Raised setting on one inner wall enables locating slot two and locating slot one and asphaltic liquid to generate bigger contact area, and then produces Raw stronger connection;Connecting plate is placed in two symmetrical locating slots one and locating slot two.
Four, the present invention solves road surface reorganization and expansion in actual use by being used cooperatively between above structure The problem of usually generating sedimentation and deformation between new, old embankment in engineering, lead to the diseases such as embankment drawing crack, pavement destruction.
Detailed description of the invention
Fig. 1 is the top view of structure of the invention;
Fig. 2 is the elevational cross-sectional view of structure of the invention.
In figure: the section 1- one, the section 2- two, 3- filling slot, 4- locating slot one, 5- locating slot two, 6- baffle, 7- connection Plate.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Fig. 1 to Fig. 2 is please referred to, the present invention provides a kind of technical solution: a kind of laying method of new-old concrete bond intersection, packet Section 1, section 22 and connecting plate 7 are included, one of them in section 1, section 22 is old road section, and one is new section, packet Include following steps:
S1: the weeds waste on 22 periphery of section 1 and section is cleared up, the road surface of neat and tidy is exposed.
S2: filling slot 3 will be reserved between section 1 and section 22, will be equipped on the opposite side in section 1 and section 22 Irregular protrusion, by the setting of protrusion irregular on the opposite side in section 1 and section 22, so that in each structure sheaf Asphaltic liquid can generate bigger contact area with it, to make the company of the pitch after cooled and solidified Yu section 1 and section 22 It connects stronger;The depth of filling slot 3 is less than the depth in section 1 and section 22, is less than section by the depth of filling slot 3 1 and section 22 depth, keep each structure sheaf and the integraty effect in section 1 and section 22 more preferable, in filling slot 3 Structure sheaf is no less than three layers, is no less than three layers by the structure sheaf in filling slot 3, guarantees road surface when in use, be less prone to disconnected Layer, the problems such as collapsing;
S3: the left side in section 1 is opened up into out locating slot 1;
S4: the right side opening in section 22 is set out into locating slot 25, locating slot 25 and locating slot 1 are with the vertical of filling slot 3 Center line symmetrical setting also is provided with protrusion on 25 inner wall of locating slot 1 and locating slot, passes through locating slot 25 and locating slot 1 Raised setting on inner wall enables locating slot 25 and locating slot 1 and asphaltic liquid to generate bigger contact area, and then produces Raw stronger connection;Connecting plate 7 is placed in two symmetrical locating slots 1 and locating slot 25;
S5: the surface in section 1 and section 22 is fixedly connected to baffle 6, and the quantity of baffle 6 is two, and two gears Plate 6 is fixedly arranged on respectively on the front and back side in section 1 and section 22, by being symmetrical arranged for two baffles 6, so that each structure The asphaltic liquid of cooled and solidified can be retained in always in filling slot 3 in layer;The height of 6 upper surface of baffle is higher than one 1 He of section The height in section 22 avoids not solidified concrete in the concrete structure of top from overflowing by the setting of height;
S6: locating slot 1 and locating slot are laid in the bottom dump asphaltic liquid of filling slot 3, and by first layer connecting plate 7 In 25 inner wall, connecting plate 7 is V shaped slab, and connecting plate 7 is opening up, and connecting plate 7 is steel construction plate, passes through V shaped slab Setting, can increase the contact area of connecting plate 7 Yu asphaltic liquid, and then each structure sheaf is made to become firmer;Same level On face, the spacing of two adjacent connection plates 7 is no more than 30 centimetres, in the vertical direction, between two adjacent connection plates 7 between Away from being no more than seven centimetres, by the control to upper junction plate 7 quantity in horizontal and vertical direction in filling slot 3, guarantee in filling slot 3 Each structure sheaf has the fastness of enough toughness and connection from both vertically as well as horizontally;
S7: after first layer pitch cooled and solidified, then toppling over second layer asphaltic liquid in filling slot 3, and drips in the second layer Second layer connecting plate 7 is laid with surface on it before green liquid cooled and solidified;
S8: after second layer pitch cooled and solidified, the step of repeating S7, completes third layer, drips in the 4th layer and layer 5 The placement of green filling and connecting plate 7;
S9: layer 6 connecting plate 7 is placed thereon before the uncolled solidification of layer 5 pitch in S8 step, is dripped to this layer It after blueness solidification, refills that concrete is placed on it, makes the height in concrete and section 1 and section 22 quite and by section 1 It is connected with the upper surface in section 22
The laying method of the new-old concrete bond intersection is when implementing, and in the step of implementing S1 to S9, also utilizes oscillator Each structure sheaf is vibrated, precipitates each asphaltic liquid completely, and by bubble removal therein, it is complete to each structure sheaf It can come into operation, be solved in road surface reconstruction and extension project in actual use usually on new, old road after full cooled and solidified The problem of generating sedimentation and deformation between dike, leading to the diseases such as embankment drawing crack, pavement destruction.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (10)

1. a kind of laying method of new-old concrete bond intersection, it is characterised in that: including section one (1), section two (2) and connecting plate (7), include the following steps:
S1: the weeds waste in section one (1) and section two (2) periphery is cleared up, the road surface of neat and tidy is exposed;
S2: filling slot (3) will be reserved between section one (1) and section two (2);
S3: locating slot one (4) will be opened up out on the left of section one (1);
S4: the right side opening in section two (2) is set out into locating slot two (5), locating slot two (5) and locating slot one (4) with filling slot (3) Vertical centerline be symmetrical arranged;
S5: the surface in section one (1) and section two (2) is fixedly connected to baffle (6);
S6: locating slot one (4) and positioning are laid in the bottom dump asphaltic liquid of filling slot (3), and by first layer connecting plate (7) In the inner wall of slot two (5);
S7: second layer asphaltic liquid is toppled over after first layer pitch cooled and solidified, then in filling slot (3), and in second layer pitch Second layer connecting plate (7) are laid with surface on it before liquid cooled and solidified;
S8: after second layer pitch cooled and solidified, the step of repeating S7, completes third layer, pitch in the 4th layer and layer 5 Filling and the placement of connecting plate (7);
S9: layer 6 connecting plate (7) are placed thereon, to this layer of pitch before the uncolled solidification of layer 5 pitch in S8 step It after solidification, refills that concrete is placed on it, makes the height in concrete and section one (1) and section two (2) quite and by section The upper surface in one (1) and section two (2) connects.
2. a kind of laying method of new-old concrete bond intersection according to claim 1, it is characterised in that: the section one (1) and on the opposite side in section two (2) it is equipped with irregular protrusion.
3. a kind of laying method of new-old concrete bond intersection according to claim 1, it is characterised in that: the filling slot (3) depth is less than the depth in section one (1) and section two (2).
4. a kind of laying method of new-old concrete bond intersection according to claim 1, it is characterised in that: the locating slot one (4) and on locating slot two (5) inner wall it also is provided with protrusion.
5. a kind of laying method of new-old concrete bond intersection according to claim 1, it is characterised in that: the baffle (6) Quantity be two, and two baffles (6) are fixedly arranged on respectively on the front and back side in section one (1) and section two (2).
6. a kind of laying method of new-old concrete bond intersection according to claim 1, it is characterised in that: the baffle (6) The height of upper surface is higher than the height in section one (1) and section two (2).
7. a kind of laying method of new-old concrete bond intersection according to claim 1, it is characterised in that: the connecting plate It (7) is V shaped slab, and connecting plate (7) is opening up.
8. a kind of laying method of new-old concrete bond intersection according to claim 1, it is characterised in that: same level On, the spacing of two adjacent connection plates (7) is no more than 30 centimetres.
9. a kind of laying method of new-old concrete bond intersection according to claim 1, it is characterised in that: the filling slot (3) structure sheaf in is no less than three layers.
10. a kind of laying method of new-old concrete bond intersection according to claim 1, it is characterised in that: in vertical direction On, the spacing between two adjacent connecting plates (7) is no more than seven centimetres.
CN201910386627.8A 2019-05-09 2019-05-09 A kind of laying method of new-old concrete bond intersection Pending CN110258238A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910386627.8A CN110258238A (en) 2019-05-09 2019-05-09 A kind of laying method of new-old concrete bond intersection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910386627.8A CN110258238A (en) 2019-05-09 2019-05-09 A kind of laying method of new-old concrete bond intersection

Publications (1)

Publication Number Publication Date
CN110258238A true CN110258238A (en) 2019-09-20

Family

ID=67914522

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910386627.8A Pending CN110258238A (en) 2019-05-09 2019-05-09 A kind of laying method of new-old concrete bond intersection

Country Status (1)

Country Link
CN (1) CN110258238A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113026473A (en) * 2021-03-24 2021-06-25 上海瀛盛市政工程有限公司 Road widening construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08165608A (en) * 1994-12-12 1996-06-25 Daijiro Numa Joint material for concrete product or the like, and connecting construction method for concrete product or the like
CN101591882A (en) * 2009-06-29 2009-12-02 邢台路桥建设总公司 Stress absorption band and job practices thereof
CN105507109A (en) * 2016-01-14 2016-04-20 郑州大学 Damaged concrete pavement panel reinforcing structure and method
CN105839489A (en) * 2016-05-18 2016-08-10 山东省交通规划设计院 New and used pavement splicing structure and construction method for ultrahigh section in highway extension project
CN108824117A (en) * 2018-07-20 2018-11-16 四川瑞通工程建设集团有限公司 A kind of asphalt pavement pit repairing construction technology

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08165608A (en) * 1994-12-12 1996-06-25 Daijiro Numa Joint material for concrete product or the like, and connecting construction method for concrete product or the like
CN101591882A (en) * 2009-06-29 2009-12-02 邢台路桥建设总公司 Stress absorption band and job practices thereof
CN105507109A (en) * 2016-01-14 2016-04-20 郑州大学 Damaged concrete pavement panel reinforcing structure and method
CN105839489A (en) * 2016-05-18 2016-08-10 山东省交通规划设计院 New and used pavement splicing structure and construction method for ultrahigh section in highway extension project
CN108824117A (en) * 2018-07-20 2018-11-16 四川瑞通工程建设集团有限公司 A kind of asphalt pavement pit repairing construction technology

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113026473A (en) * 2021-03-24 2021-06-25 上海瀛盛市政工程有限公司 Road widening construction method

Similar Documents

Publication Publication Date Title
AU607007B2 (en) Frames for constructing pavement boards
CN205934629U (en) Wide structure of increasing is pieced together to existing barricade section road bed
CN110258238A (en) A kind of laying method of new-old concrete bond intersection
CN107152036A (en) A kind of pipe gallery and its construction method
CN108004866A (en) A kind of precast concrete road system and construction method
CN215052148U (en) A kind of guarantee that meets the rapid flood discharge requirement in the river course leads to the urinal
CN113215995B (en) Method for constructing bridge road in narrow space
CN217758136U (en) Rubble laying device for railway construction
CN107938612B (en) A kind of mud-rock flow gravity type blocking dam group based on waste and old Container Reconstruction
CN208009193U (en) A kind of highway engineering assembling type steel reinforced concrete gutter structure
CN207552830U (en) A kind of Anti-settling device of highway subgrade
CN108677980A (en) Upstream cofferdam heightening method and structure with traffic function
CN208121502U (en) Based on the reserved displacement cast-in-place curb stone structure of modular indwelling groove mould asphalt concrete pavement
CN105297875B (en) Construction method of integrated catchwater
CN213389548U (en) Settlement-preventing roadbed for deep soft soil high fill
CN213358194U (en) Permeable pavement structure
CN208717941U (en) A kind of no toe board buttress type road shoulder retaining wall structure
CN209412844U (en) A kind of assembled resin concrete drainage ditch
CN208280000U (en) Attachment device for bridges and culverts and roadbed
CN112813844A (en) Access-protecting passage meeting rapid flood discharge requirement in river channel and construction method
CN211227948U (en) Prefabricated water-permeable base layer block for laying green path drift diameter
CN210134293U (en) Horizontal lattice type prefabricated assembly segment and high-speed railway foundation assembled by same
CN209066442U (en) A kind of inverse construction joint structure for building construction of deep basal pit
CN216041218U (en) Side slope lattice beam structure
CN220978069U (en) Building rubbish recycling landscaping pile reinforcement

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190920

RJ01 Rejection of invention patent application after publication