CN110258221A - A kind of box frame roadbed - Google Patents
A kind of box frame roadbed Download PDFInfo
- Publication number
- CN110258221A CN110258221A CN201910549508.XA CN201910549508A CN110258221A CN 110258221 A CN110258221 A CN 110258221A CN 201910549508 A CN201910549508 A CN 201910549508A CN 110258221 A CN110258221 A CN 110258221A
- Authority
- CN
- China
- Prior art keywords
- roadbed
- side wall
- bottom plate
- frame
- boxed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000004567 concrete Substances 0.000 claims description 12
- 235000007164 Oryza sativa Nutrition 0.000 claims description 5
- 235000009566 rice Nutrition 0.000 claims description 5
- 240000007594 Oryza sativa Species 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 4
- 239000002689 soil Substances 0.000 description 6
- 238000010586 diagram Methods 0.000 description 5
- 239000000945 filler Substances 0.000 description 5
- 241000209094 Oryza Species 0.000 description 4
- 230000002787 reinforcement Effects 0.000 description 4
- 238000000034 method Methods 0.000 description 2
- 230000009467 reduction Effects 0.000 description 2
- 239000011150 reinforced concrete Substances 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000002266 amputation Methods 0.000 description 1
- 238000009411 base construction Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 238000004062 sedimentation Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 239000000758 substrate Substances 0.000 description 1
- 238000003786 synthesis reaction Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2/00—General structure of permanent way
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C3/00—Foundations for pavings
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
The invention discloses a kind of box frame roadbed, the box frame roadbed includes that the roadbed boxed frame of preset quantity is longitudinally forming, the adjacent roadbed expansion joint that preset length is separated between boxed frame;The roadbed boxed frame includes top plate and bottom plate and at least two side wall panels between the top plate and bottom plate, and upper end, the lower end of the side wall panel are separately connected the top plate and the bottom plate;Cross direction profiles of at least two side wall panels in the top plate or bottom plate, and two adjacent side wall panel interval pre-determined distances;The roadbed further includes the rectangular enclosure of at least one transverse seal surrounded by the top plate, the bottom plate and the side wall panel with boxed frame;The top plate and the bottom plate extend preset length in the outside of the side wall panel, and the development length of the top plate is greater than the extension of the bottom plate.Box frame roadbed of the invention can be reduced high-speed railway subgrade construction cost and reduce cultivated land occupancy area.
Description
Technical field
The present invention relates to railway bed fields, and in particular to a kind of box frame roadbed.
Background technique
With the raising of living standards of the people and the development of railway technology, bullet train and corresponding high-speed railway are increasingly
It is more.
In order to ensure the safety and even running of High Speed Railway Trains, subgrade engineering structure should have enough intensity, steady
Qualitative and durability.Compared to central and west regions, when Eastern Plain area builds high-speed railway, since soil property is softer, subsoil
It is difficult to meet the requirement of settlement control of high-speed railway high standard, it is necessary to carry out stiffening basic ground.Traditional trapezoidal roadbed is general
It is to be filled on subsoil using the filler of a large amount of high standards, substrate takes up a large area and settles and is difficult to meet the requirements.But
Requirement due to high-speed railway to filler is high, and region of no relief shortage of land resource, filler lack very much, considerably increase construction
Cost, every kilometer of comprehensive cost compared with bridge without economic advantages, also as roadbed is wide and largely occupies cultivated land.
Summary of the invention
In view of this, can be reduced high-speed railway subgrade an embodiment of the present invention is intended to provide a kind of box frame roadbed and be constructed into
Sheet and reduction cultivated land occupancy area.
In order to achieve the above objectives, the technical solution of the embodiment of the present invention is achieved in that
The embodiment of the invention provides a kind of roadbed boxed frame, the roadbed boxed frame includes top plate and bottom plate
And at least two side wall panels between the top plate and bottom plate, upper end, the lower end of the side wall panel are separately connected the top plate
With the bottom plate;Cross direction profiles of at least two side wall panels in the top plate or bottom plate, and two adjacent side walls
Plate interval pre-determined distance;The roadbed boxed frame further includes at least one by the top plate, the bottom plate and the side wall
The rectangular enclosure for the transverse seal that plate surrounds;The top plate and the bottom plate extend default length in the outside of the side wall panel
Degree, the development length of the top plate are greater than the extension of the bottom plate.
In above scheme, the roadbed boxed frame further includes tubular pole, and the tubular pole is located at below the bottom plate, described
Tubular pole extends downward preset length from the bottom plate.
In above scheme, the tubular pole is fixed to the bottom plate by raft plate.
In above scheme, the quantity of the side wall panel is two, and the height of the side wall panel is greater than the cross of two side wall panels
To spacing.
In above scheme, the roadbed is poured with boxed frame use ≮ C35 armored concrete.
In above scheme, the transverse width of the side wall panel is 0.4~0.6 meter, the cross of two adjacent side wall panels
It is 4.6~6.5 meters to spacing.
In above scheme, the top plate with a thickness of 0.4~0.6 meter, the top plate extends in the outside of the side wall panel
3.0~3.7 meters;The bottom plate with a thickness of 0.8~1.2 meter, the bottom plate extends 0.9~1.1 in the outside of the side wall panel
Rice.
The embodiment of the invention also provides a kind of box frame roadbed, the box frame roadbed includes that the roadbed of preset quantity is used
Boxed frame is longitudinally forming, the adjacent roadbed expansion joint that preset length is separated between boxed frame;The road
Base boxed frame is any one roadbed boxed frame recited above, and the side wall panel of the roadbed boxed frame is distinguished
Positioned at the centre of two rail on two lines road.
In above scheme, the raft plate is located at the centre of two adjacent roadbed boxed frames, and the raft plate is in longitudinal direction
One end connect a roadbed boxed frame, the other end and be connected to another roadbed boxed frame.
In above scheme, each roadbed is provided with tubular pole, two adjacent roads with the both ends of boxed frame bottom
Tubular pole under base boxed frame is symmetrical with the expansion joint between two roadbed boxed frames, and is fixed on the same raft
On plate.
The roadbed boxed frame and box frame roadbed of the embodiment of the present invention, the roadbed boxed frame include top plate,
Bottom plate and at least two side wall panels between the top plate and bottom plate, upper end, the lower end of the side wall panel are separately connected described
Top plate and the bottom plate;At least two side wall panels the top plate or bottom plate cross direction profiles, and described in adjacent two
Side wall panel interval pre-determined distance;The roadbed boxed frame further includes at least one by the top plate, the bottom plate and described
The rectangular enclosure for the transverse seal that side wall panel surrounds;The top plate and the bottom plate extend in the outside of the side wall panel default
Length, the development length of the top plate are greater than the extension of the bottom plate;As it can be seen that the box frame roadbed of the embodiment of the present invention, passes through
Roadbed replaces filler with boxed frame, can be reduced high-speed railway subgrade construction cost and reduces cultivated land occupancy area.
Other beneficial effects of the embodiment of the present invention will combine specific technical solution furtherly in a specific embodiment
It is bright.
Detailed description of the invention
To describe the technical solutions in the embodiments of the present invention more clearly, make required in being described below to embodiment
Attached drawing makees brief description.It should be appreciated that drawings discussed below is only a part of attached drawing of the embodiment of the present invention, it is right
For those of ordinary skill in the art, without creative efforts, it can also be obtained according to these attached drawings
Its attached drawing.
Fig. 1 is the lateral sectional schematic diagram one of boxed frame in box of embodiment of the present invention frame roadbed;
Fig. 2 is the lateral sectional schematic diagram two of boxed frame in box of embodiment of the present invention frame roadbed;
Fig. 3 is longitudinal composition schematic diagram of box of embodiment of the present invention frame roadbed;
Fig. 4 is the floor map of box of embodiment of the present invention frame roadbed.
Specific embodiment
It should be noted that unless otherwise indicated and being limited, term " connection " should be done extensively in record of the embodiment of the present invention
Reason and good sense solution, for example, it may be electrical connection, the connection being also possible to inside two elements can be directly connected, can also pass through
Intermediary is indirectly connected, and for the ordinary skill in the art, can understand above-mentioned term as the case may be
Concrete meaning.The term " Yi Er third " such as related in the embodiment of the present invention is only the similar object of difference, not generation
Particular sorted of the indicator to object, it is possible to understand that ground, " first second third " can be interchanged specific in the case where permission
Sequence or precedence.
The embodiment of the invention provides a kind of roadbed boxed frame, the roadbed boxed frame includes top plate and bottom plate
And at least two side wall panels between the top plate and bottom plate, upper end, the lower end of the side wall panel are separately connected the top plate
With the bottom plate;Cross direction profiles of at least two side wall panels in the top plate or bottom plate, and two adjacent side walls
Plate interval pre-determined distance;The roadbed boxed frame further includes at least one by the top plate, the bottom plate and the side wall
The rectangular enclosure for the transverse seal that plate surrounds;The top plate and the bottom plate extend default length in the outside of the side wall panel
Degree, the development length of the top plate are greater than the extension of the bottom plate.
In one embodiment, the roadbed boxed frame further includes tubular pole, and the tubular pole is located under the bottom plate
Side, the tubular pole extend downward preset length from the bottom plate.The tubular pole can be directly connected in substratum, substratum
It is chorizon, is commonly called as raw soil layer, compares topsoil, soil is poor, can be further reduced roadbed boxed frame ground
Natural subsidence is preferred embodiment.
In one embodiment, the quantity of the side wall panel is two, and the height of the side wall panel is greater than two side walls
The horizontal spacing of plate.Side wall panel is generally corresponding with rail track, and route generally comprises round-trip two, so two side walls of setting
Plate, it is of course also possible to be arranged more, side wall panel is arranged more, and entire roadbed is more secured with boxed frame.The side wall panel
Height is greater than the horizontal spacing of two side wall panels, and purpose is to increase the roadbed boxed frame in the intensity of vertical direction, is
Preferred embodiment.
In one embodiment, the roadbed is poured with boxed frame use ≮ C35 armored concrete, in this way,
Intensity is higher, and at present for be also a kind of lower-cost mode, be preferred embodiment.
In one embodiment, the transverse width of the side wall panel be 0.4~0.6 meter, be structural strength, cost and from
It is comprehensively considering again as a result, being preferred embodiment;The horizontal spacing of two adjacent side wall panels is 4.6~6.5 meters, this is root
It is arranged according to the line spacing of two railways.
In one embodiment, the top plate with a thickness of 0.4~0.6 meter, be structural strength, cost and self weight synthesis
Consider as a result, being preferred embodiment;The top plate the side wall panel outside extend 3.0~3.7 meters, be structural strength, at
This result comprehensively considered with width of the subgrade surface;The bottom plate with a thickness of 0.8~1.2 meter, be structural strength, cost and self weight
It is comprehensively considering as a result, be preferred embodiment, it is that structure is strong that the bottom plate, which extends 0.9~1.1 meter in the outside of the side wall panel,
The result that degree, cost and self weight comprehensively consider.
In one embodiment, the tubular pole is fixed to the bottom plate by raft plate, and the raft plate is 0.4~0.8 meter
Thick ≮ C35 armored concrete pours;It is the result that structural strength, cost and settlement Control comprehensively consider
The embodiment of the invention also provides a kind of box frame roadbed, the box frame roadbed includes that the roadbed of preset quantity is used
Boxed frame is longitudinally forming, the adjacent roadbed expansion joint that preset length is separated between boxed frame;The road
Base boxed frame is any one roadbed boxed frame recited above, and the side wall panel of the roadbed boxed frame is distinguished
Positioned at the centre of two rail on two lines road.
The box frame roadbed of the embodiment of the present invention, replaces filler with boxed frame by roadbed, can be reduced high-speed railway road
Base construction cost and reduction cultivated land occupancy area.
In one embodiment, the raft plate is located at the centre of two adjacent roadbed boxed frames, the raft plate
Another roadbed boxed frame is connected in longitudinal one roadbed boxed frame of one end connection, the other end.It can effectively control
Settlement of foundation processed, it is ensured that high-speed railway route high stability, high ride.
In one embodiment, each roadbed is provided with tubular pole with the both ends of boxed frame bottom, adjacent
Tubular pole under two roadbed boxed frames is symmetrical with the expansion joint between two roadbed boxed frames, and is fixed on same
On one raft plate.Settlement of foundation can be effectively controlled, it is ensured that high-speed railway route high stability, high ride.
Below in conjunction with drawings and the specific embodiments, the present invention will be described in further detail.It should be appreciated that this place is retouched
It states that specific examples are only used to explain the present invention, is not intended to limit the present invention;Also, the embodiments described below, only
It is a part of the embodiments of the present invention, instead of all the embodiments, those skilled in the art, according to these realities
Example is applied, all other embodiment obtained without creative efforts belongs to the scope of protection of the invention.
Embodiment one
A kind of box frame roadbed is present embodiments provided, the box frame roadbed includes the roadbed box frame of preset quantity
Frame is longitudinally forming, the adjacent roadbed expansion joint that preset length is separated between boxed frame;The roadbed case
Type frame can be shown in fig. 1 or fig. 2, and the side wall panel of roadbed boxed frame is located at two of two lines road
The centre of rail.
As shown in Figure 1, the roadbed boxed frame include top plate 11, bottom plate 12 and be located at the top plate 11, bottom plate 12
Between two side wall panels 13, upper end, the lower end of the side wall panel 13 are separately connected the top plate 11 and the bottom plate 12;Two
The side wall panel 13 is in the cross direction profiles of the top plate 11 or bottom plate 12, and two side wall panels 13 are spaced pre-determined distances;Institute
State the rectangular enclosure that top plate 11, the bottom plate 12 and the side wall panel 13 surround a transverse seal;The top plate 11 and described
Bottom plate 12 extends preset length in the outside of the side wall panel 13, and the development length of the top plate 11 is greater than the bottom plate 12
Extend.
In the present embodiment, the height of the side wall panel 13 is greater than the horizontal spacing of two side wall panels 13.
In the present embodiment, the roadbed is poured with boxed frame use ≮ C35 armored concrete.
In the present embodiment, the transverse width of the side wall panel 13 is 0.5 meter, the transverse direction of the side wall panel 13 of adjacent two
Spacing is 5 meters,
In the present embodiment, the top plate 11 with a thickness of 0.5 meter, the top plate 11 the side wall panel 13 outside extend
3.3 meters, outwardly extending 3.3 meters of top plates can also be referred to as side wing, be intended merely to facilitate description, essence and top plate are one
Body;The bottom plate 12 with a thickness of 1 meter, the bottom plate 12 the side wall panel 13 outside extend 1 meter.
In the present embodiment, the lateral overall width of the roadbed boxed frame includes top plate 11 or bottom plate 12 to two sides
Extension, be 12.6 meters, longitudinal length is 9.92 meters, and the expansion joint between each roadbed boxed frame is 0.1 meter.
As shown in Fig. 2, the roadbed boxed frame further includes tubular pole 21, the tubular pole 21 is located under the bottom plate 12
Side, specifically, the specification of the tubular pole 21 can be according to the engineering geological condition of proposed place foundation soil, through analysis by sedimentation and ground
Base inspection, which is calculated, to be determined, under general geological conditions, the specification of the tubular pole 21 can be by following setting: stake diameter φ=0.5 meter, long
27 meters, 2.0 meters of lateral stake spacing.
In the present embodiment, as shown in Figure 3,4, the tubular pole 21 is fixed to the bottom plate 12, the raft plate by raft plate 22
22 for 0.6 meter thick ≮ C35 armored concrete pours, further include bed course between the raft plate 22 and the tubular pole 21 specifically
(being not shown), the bed course are that 0.2 meter thick of C15 concreting forms, and the bed course and the raft plate 22 are mutual
It is fixed;The bed course connects the bottom plate 12,22 layers of the raft plate connection tubular pole 21.
In the present embodiment, the raft plate 22 is located at the centre of two adjacent roadbed boxed frames, and the raft plate 22 exists
Longitudinal one end connects a roadbed boxed frame, the other end is connected to another roadbed boxed frame.
In the present embodiment, two rows of tubular poles 21 are equipped under each roadbed boxed frame, are separately positioned on the road
The both ends of base boxed frame, the tubular pole 21 under two adjacent roadbed boxed frames is between two roadbed boxed frames
Expansion joint it is symmetrical, and be fixed on the same raft plate 22;Longitudinal stake spacing of tubular pole 21 on the same raft plate 22
It is also 2.0 meters.
It should be noted that the unit of the size marked in Fig. 1-Fig. 4 is millimeter.
In order to better understand box frame roadbed, the work progress of the box frame roadbed, the process packet is described below
Include following steps:
Step 501: tubular pole 21 is inserted on foundation soil.After tubular pole 21 is inserted into predetermined depth, the extra stake of stake top (is revealed
Ground out) amputation;
Step 502: pouring 0.2 meter of thickness C15 concrete cushion at the top of tubular pole 21, the size of the bed course is 8 × 4
Rice, the bed course are evenly arranged on the tubular pole 21, and the bed course is longitudinally evenly distributed in railway, and 0.02 meter is stayed between each bed course
Expansion joint;
Step 503: 0.6 meter of thickness ≮ C35 Reinforced Concrete Raft plate 22, the same institute of the size of raft plate 22 are poured on the bed course
State bed course;
Step 504: roadbed boxed frame is poured on raft plate 22, box frame subgrade construction is completed.
The roadbed boxed frame of above-mentioned steps is prefabricated in advance forms, it is to be understood that can also be with cast in situs, if existing
Field pours, and further includes following steps:
Step 505: pouring the armored concrete of bottom plate 12, and reserve its main reinforcement, main steel in 13 corresponding position of side wall panel
Muscle length in reserve is not less than 1.5 meters, and meets splice requirement;
Step 506: before 12 concrete initial set of bottom plate, pouring the armored concrete of side wall panel 13, and its main reinforcement is stretched
0.2~0.3 meter of top out;
Step 507: after bottom plate 12 and 13 concrete of side wall panel reach design strength, the reinforced concrete for top plate 11 of constructing
Soil, main reinforcement are fixedly connected with the reserved main reinforcement stretched out of side wall panel 13.
Embodiment two
The content of the present embodiment is other than a part is different from embodiment one, remaining content is as in the first embodiment, below only
This part of different content is introduced, schematic diagram is no longer separately shown.
In the present embodiment, the transverse width of the side wall panel 13 is 0.4 meter, the transverse direction of the side wall panel 13 of adjacent two
Spacing is 4.6 meters,
In the present embodiment, the top plate 11 with a thickness of 0.4 meter, the top plate 11 the side wall panel 13 outside extend
3.0 rice;The bottom plate 12 with a thickness of 0.8 meter, the bottom plate 12 the side wall panel 13 outside extend 0.9 meter.
Embodiment three
The content of the present embodiment is other than a part is different from embodiment one, remaining content is as in the first embodiment, below only
This part of different content is introduced, schematic diagram is no longer separately shown.
In the present embodiment, the transverse width of the side wall panel 13 is 0.6 meter, the transverse direction of the side wall panel 13 of adjacent two
Spacing is 6.5 meters.
In the present embodiment, the top plate 11 with a thickness of 0.6 meter, the top plate 11 the side wall panel 13 outside extend
3.7 rice;The bottom plate 12 with a thickness of 1.2 meters, the bottom plate 12 the side wall panel 13 outside extend 1.1 meters.
The foregoing is only a preferred embodiment of the present invention, is not intended to limit the scope of the present invention, it is all
Made any modifications, equivalent replacements, and improvements etc. within the spirit and principles in the present invention, should be included in protection of the invention
Within the scope of.
Claims (10)
1. a kind of roadbed boxed frame, which is characterized in that the roadbed boxed frame includes top plate and bottom plate and is located at described
At least two side wall panels between top plate and bottom plate, upper end, the lower end of the side wall panel are separately connected the top plate and the bottom
Plate;At least two side wall panels are in the cross direction profiles of the top plate or bottom plate, and two adjacent side wall panel intervals are pre-
If distance;The roadbed further includes that at least one is surrounded by the top plate, the bottom plate and the side wall panel with boxed frame
The rectangular enclosure of transverse seal;The top plate and the bottom plate extend preset length, the top in the outside of the side wall panel
The development length of plate is greater than the extension of the bottom plate.
2. roadbed boxed frame according to claim 1, which is characterized in that the roadbed boxed frame further includes pipe
Stake, the tubular pole are located at below the bottom plate, and the tubular pole extends downward preset length from the bottom plate.
3. roadbed boxed frame according to claim 2, which is characterized in that the tubular pole is fixed to described by raft plate
Bottom plate.
4. roadbed boxed frame according to claim 1 or 2, which is characterized in that the quantity of the side wall panel is two,
The height of the side wall panel is greater than the horizontal spacing of two side wall panels.
5. roadbed boxed frame according to claim 3, which is characterized in that the roadbed with boxed frame use ≮
C35 armored concrete pours.
6. roadbed boxed frame according to claim 4, which is characterized in that the transverse width of the side wall panel is 0.4
~0.6 meter, the horizontal spacing of two adjacent side wall panels is 4.6~6.5 meters.
7. roadbed boxed frame according to claim 5, which is characterized in that the top plate with a thickness of 0.4~0.6
Rice, the top plate extend 3.0~3.7 meters in the outside of the side wall panel;The bottom plate with a thickness of 0.8~1.2 meter, the bottom
Plate extends 0.9~1.1 meter in the outside of the side wall panel.
8. a kind of box frame roadbed, which is characterized in that the box frame roadbed includes that the roadbed boxed frame of preset quantity exists
It longitudinally forms, the adjacent roadbed expansion joint that preset length is separated between boxed frame;Roadbed box frame
Frame is the described in any item roadbed boxed frames of claim 1~7, and the side wall panel of roadbed boxed frame is located at
The centre of two rail on two lines road.
9. box frame roadbed according to claim 8, which is characterized in that the box frame roadbed further includes raft plate, described
Raft plate is located at the centre of two adjacent roadbed boxed frames, and the raft plate connects a roadbed box in longitudinal one end
Frame, the other end are connected to another roadbed boxed frame.
10. box frame roadbed according to claim 9, which is characterized in that each roadbed boxed frame bottom
Both ends are provided with tubular pole, and the tubular pole under two adjacent roadbed boxed frames is with stretching between two roadbed boxed frames
Contracting seam is symmetrical, and is fixed on the same raft plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910549508.XA CN110258221A (en) | 2019-06-24 | 2019-06-24 | A kind of box frame roadbed |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910549508.XA CN110258221A (en) | 2019-06-24 | 2019-06-24 | A kind of box frame roadbed |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110258221A true CN110258221A (en) | 2019-09-20 |
Family
ID=67920886
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910549508.XA Pending CN110258221A (en) | 2019-06-24 | 2019-06-24 | A kind of box frame roadbed |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110258221A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111118965A (en) * | 2019-11-03 | 2020-05-08 | 中铁二院工程集团有限责任公司 | Box-type road base end structure and stress concentration adjusting method |
CN111395085A (en) * | 2020-04-29 | 2020-07-10 | 中国铁路经济规划研究院有限公司 | Roadbed transition structure |
CN114541183A (en) * | 2022-01-17 | 2022-05-27 | 中铁工程设计咨询集团有限公司 | Integrated double-layer frame type high-speed rail station widening structure and construction method thereof |
CN115491940A (en) * | 2022-08-22 | 2022-12-20 | 中交第一公路勘察设计研究院有限公司 | Steel-concrete combined structure roadbed for freeway in frozen soil area and construction method |
CN115680005A (en) * | 2022-10-09 | 2023-02-03 | 中交第一公路勘察设计研究院有限公司 | Assembled overhead structure of highway in high-intensity permafrost region and construction method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2749331A1 (en) * | 1996-06-03 | 1997-12-05 | Beauthier Jean Marie | Prefabricated concrete frame forming underpass beneath roads or railways |
CN105951537A (en) * | 2016-04-29 | 2016-09-21 | 中铁第四勘察设计院集团有限公司 | Rib column distributed turnout foundation structure of middle-low speed magnetic levitation low-arranged line |
CN208219303U (en) * | 2018-05-11 | 2018-12-11 | 中铁二院工程集团有限责任公司 | A kind of high-speed railway cast-in-situ bored pile frame-type road structure |
CN208219324U (en) * | 2018-05-11 | 2018-12-11 | 中铁二院工程集团有限责任公司 | A kind of box road structure of high-speed railway cast-in-situ bored pile |
CN210737256U (en) * | 2019-06-24 | 2020-06-12 | 中铁第四勘察设计院集团有限公司 | Box frame and box frame road bed for road bed |
-
2019
- 2019-06-24 CN CN201910549508.XA patent/CN110258221A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2749331A1 (en) * | 1996-06-03 | 1997-12-05 | Beauthier Jean Marie | Prefabricated concrete frame forming underpass beneath roads or railways |
CN105951537A (en) * | 2016-04-29 | 2016-09-21 | 中铁第四勘察设计院集团有限公司 | Rib column distributed turnout foundation structure of middle-low speed magnetic levitation low-arranged line |
CN208219303U (en) * | 2018-05-11 | 2018-12-11 | 中铁二院工程集团有限责任公司 | A kind of high-speed railway cast-in-situ bored pile frame-type road structure |
CN208219324U (en) * | 2018-05-11 | 2018-12-11 | 中铁二院工程集团有限责任公司 | A kind of box road structure of high-speed railway cast-in-situ bored pile |
CN210737256U (en) * | 2019-06-24 | 2020-06-12 | 中铁第四勘察设计院集团有限公司 | Box frame and box frame road bed for road bed |
Non-Patent Citations (1)
Title |
---|
高广运、时刚、冯世进: "《软土地基与深基础工程》", 同济大学出版社, pages: 290 - 292 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111118965A (en) * | 2019-11-03 | 2020-05-08 | 中铁二院工程集团有限责任公司 | Box-type road base end structure and stress concentration adjusting method |
CN111395085A (en) * | 2020-04-29 | 2020-07-10 | 中国铁路经济规划研究院有限公司 | Roadbed transition structure |
CN114541183A (en) * | 2022-01-17 | 2022-05-27 | 中铁工程设计咨询集团有限公司 | Integrated double-layer frame type high-speed rail station widening structure and construction method thereof |
CN115491940A (en) * | 2022-08-22 | 2022-12-20 | 中交第一公路勘察设计研究院有限公司 | Steel-concrete combined structure roadbed for freeway in frozen soil area and construction method |
CN115491940B (en) * | 2022-08-22 | 2024-04-30 | 中交第一公路勘察设计研究院有限公司 | Highway steel-concrete combined structure roadbed in frozen soil area and construction method |
CN115680005A (en) * | 2022-10-09 | 2023-02-03 | 中交第一公路勘察设计研究院有限公司 | Assembled overhead structure of highway in high-intensity permafrost region and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110258221A (en) | A kind of box frame roadbed | |
CN102926299B (en) | Railway elevating and fixing device and railway bridge and culvert construction method adopting railway elevating and fixing device | |
WO2017125028A1 (en) | Rail support beam low track and viaduct transition section structure for medium-low-speed magnetic suspension traffic project | |
CN206219897U (en) | Medium-and low-speed maglev two-wire excavation location pile foundation combined type support rail beam transition section structure | |
CN105821725A (en) | Intra-segment limit structure for bearing-trail beams at double-line section of middle-low speed magnetic levitation traffic engineering low-laying line | |
CN210737256U (en) | Box frame and box frame road bed for road bed | |
CN110258223A (en) | A kind of armored concrete box frame roadbed | |
CN108708290A (en) | The case crane span structure hollow structure and cast-in-situ construction method of minor radius railway curve unit | |
CN210737255U (en) | Box frame and reinforced concrete box frame road bed for road bed | |
CN204174481U (en) | Soft clay area modern tram abutment rebound structure | |
CN110219250A (en) | The continuous combined overhead beam of multilayer | |
CN205603974U (en) | Low circuit single line location support rail girder segment limit structure within a definite time that puts of well low -speed maglev traffic engineering | |
CN206127736U (en) | Moderate -low speed magnetic levitation double -line compound framing formula support rail roof beam transition section structure of location pile foundation that fills | |
CN106283957B (en) | Medium-and low-speed maglev two-wire excavation location pile foundation joist framing type support rail beam transition section structure | |
CN206157485U (en) | Moderate -low speed magnetic levitation single line excavation location pile foundation combined type support rail roof beam transition section structure | |
CN202865708U (en) | Railway aerial fixing device | |
CN106283938A (en) | Medium-and low-speed maglev two-wire excavation location pile foundation is combined framing type support rail girder construction | |
CN205617164U (en) | Low circuit single line location end thorn formula support rail girder segment limit structure within a definite time that puts of well low -speed maglev traffic engineering | |
CN208869876U (en) | Box-structure and a kind of railway high-filled embankment for railway high-filled embankment | |
CN206486798U (en) | The bridgehead structures of overpass above underground rail | |
CN106283952A (en) | Medium-and low-speed maglev two-wire excavation location pile foundation joist framing type support rail girder construction | |
CN106400615A (en) | Medium-low-speed magnetic levitation single line excavation section independent pier column type bearing rail beam transition section structure | |
CN206127740U (en) | Moderate -low speed magnetic levitation single line location supporting beam of pile foundation formula support rail roof beam transition section structure that fills | |
CN206157481U (en) | Compound framing type support rail roof beam transition section structure of moderate -low speed magnetic levitation double -line excavation location pile foundation | |
CN206127744U (en) | Moderate -low speed magnetic levitation single line excavation location supporting beam of pile foundation formula support rail roof beam transition section structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |