- CN110242323A CN110242323A CN201910588771.XA CN201910588771A CN110242323A CN 110242323 A CN110242323 A CN 110242323A CN 201910588771 A CN201910588771 A CN 201910588771A CN 110242323 A CN110242323 A CN 110242323A
- Authority
- CN
- China
- Prior art keywords
- section
- jurisdiction
- ontology
- prefabricated
- duct piece
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/08—Lining with building materials with preformed concrete slabs
- E21D11/083—Methods or devices for joining adjacent concrete segments
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/08—Lining with building materials with preformed concrete slabs
- E21D11/086—Methods of making concrete lining segments
Abstract
The invention discloses a kind of design methods of side steel concrete shield duct piece, the basic figure of the shield duct piece selected first according to tunnel design carries out the prefabricated of section of jurisdiction ontology, during the section of jurisdiction ontology is prefabricated, the circumferential interface of ontology and the pre-buried stainless steel angle in intrados junction in section of jurisdiction, the shape of the stainless steel angle and the circumferential interface of section of jurisdiction ontology and intrados shape are adapted;Section of jurisdiction ontology after the completion of prefabricated enters tunnel installation, after end to be installed and slip casting are stablized, corner weldering is carried out to the pre-buried stainless steel connecting sewing of adjacent section of jurisdiction ontology joining place, to ensure that the sealed connection between the ontology of section of jurisdiction.The invention has the advantages that effect is similar to reinforced concrete segment and clean steel section of jurisdiction, but compared with reinforced concrete segment, eliminates rubber water-proof, water-stagnating effect is more preferable, and the tunnel structure durability of lining cutting is higher.Meanwhile the design method is easy to operate, the shield duct piece suitable for various types.
Description
Technical field
The present invention relates to tunnel shield duct pieces, more particularly, to the design method of side steel concrete shield duct piece.
Background technique
Using the tunnel of shield formula tunneler construction, the general carry out lining cutting for using prefabricated reinforced concrete section of jurisdiction is special
Clean steel section of jurisdiction can also be used in hole section.With the appearance of great burying, long range tunnel, the structure stress condition of tunnel is more and more multiple
It is miscellaneous, therefore, high security, high usability, high application property, high-environmental, high maintenance and high-durability shield duct piece structure
It is core strategy and the only way of sustainable development of the following Structural Engineering development.Currently, shield duct piece has clean steel section of jurisdiction
And reinforced concrete segment.Clean steel section of jurisdiction is mainly characterized by that intensity is high, ductility is good, light-weight, but overall stiffness is small, corrosion-resistant
Property is poor, cost is higher;When tunnel lining is installed, the linking seam between adjacent section of jurisdiction needs that rubber is arranged reinforced concrete segment
Sealing rod is come the sealing for meeting tunnel or only slurry requirement, and rubber water-proof item is easy aging, greatly affected the later period of tunnel
Safe handling.
Summary of the invention
It is an object of that present invention to provide a kind of design methods of side steel concrete shield duct piece.
To achieve the above object, the present invention takes following technical proposals:
The design method of steel concrete shield duct piece in side of the present invention, the shield duct piece selected first according to tunnel design are basic
Figure carries out the prefabricated of section of jurisdiction ontology, during the section of jurisdiction ontology is prefabricated, the circumferential interface and inner arc of ontology in section of jurisdiction
Face junction is pre-buried with a thickness of 5mm ~ 10mm, the stainless steel angle that One-sided Widths are 5cm ~ 15cm, the shape of the stainless steel angle
The circumferential interface and intrados shape of shape and section of jurisdiction ontology are adapted;Section of jurisdiction ontology after the completion of prefabricated enters tunnel installation,
After end to be installed and slip casting are stablized, corner weldering is carried out to the pre-buried stainless steel connecting sewing of adjacent section of jurisdiction ontology joining place,
To ensure that the sealed connection between the ontology of section of jurisdiction.
The invention has the advantages that effect is similar to reinforced concrete segment and clean steel section of jurisdiction, but with reinforced concrete segment phase
Than eliminating rubber water-proof, water-stagnating effect is more preferable, and the tunnel structure durability of lining cutting is higher.Meanwhile the design method operation letter
It is single, the shield duct piece suitable for various types.
Detailed description of the invention
Fig. 1 is the side steel concrete shield duct piece axonometric drawing implemented according to the method for the present invention.
Fig. 2 is the structural schematic diagram that the adjacent pre-buried stainless steel connecting sewing of section of jurisdiction ontology joining place implements corner weldering.
Specific embodiment
As shown in Figure 1, 2, the design method of steel concrete shield duct piece in side of the present invention, is selected according to tunnel design first
The basic figure of fixed shield duct piece carries out the prefabricated of section of jurisdiction ontology, in the ontology prefabrication process of section of jurisdiction, the circumferential rank of ontology in section of jurisdiction
Junction 1 and 2 junction of intrados are pre-buried with a thickness of 5mm ~ 10mm, the stainless steel angle 3 that One-sided Widths are 5cm ~ 15cm, stainless steel
The shape of angle bar 3 and the circumferential interface of section of jurisdiction ontology and intrados shape are adapted;Section of jurisdiction ontology after the completion of prefabricated enters
After tunnel installation, end to be installed and slip casting are stablized, side is carried out to 3 connecting sewing of pre-buried stainless steel of adjacent section of jurisdiction ontology joining place
Fillet welding 4, to ensure that the sealed connection between the ontology of section of jurisdiction.
Claims (1)
1. a kind of design method of side steel concrete shield duct piece, it is characterised in that: the shield selected first according to tunnel design
The basic figure in section of jurisdiction carries out the prefabricated of section of jurisdiction ontology, during the section of jurisdiction ontology is prefabricated, the circumferential linking of ontology in section of jurisdiction
Face and intrados junction are pre-buried with a thickness of 5mm ~ 10mm, the stainless steel angle that One-sided Widths are 5cm ~ 15cm, the stainless steel
The shape of angle bar and the circumferential interface of section of jurisdiction ontology and intrados shape are adapted;Section of jurisdiction ontology after the completion of prefabricated enters tunnel
After hole installation, end to be installed and slip casting are stablized, corner is carried out to the pre-buried stainless steel connecting sewing of adjacent section of jurisdiction ontology joining place
Weldering.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910588771.XA CN110242323A (en) | 2019-07-02 | 2019-07-02 | The design method of side steel concrete shield duct piece |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910588771.XA CN110242323A (en) | 2019-07-02 | 2019-07-02 | The design method of side steel concrete shield duct piece |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110242323A true CN110242323A (en) | 2019-09-17 |
Family
ID=67890620
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910588771.XA Withdrawn CN110242323A (en) | 2019-07-02 | 2019-07-02 | The design method of side steel concrete shield duct piece |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110242323A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111335920A (en) * | 2020-03-26 | 2020-06-26 | 中铁第四勘察设计院集团有限公司 | Construction method of shield tunnel |
CN113586083A (en) * | 2021-08-19 | 2021-11-02 | 北京隧盾市政建设有限公司 | Segment caulking plugging structure and plugging process |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2395032Y (en) * | 1999-09-28 | 2000-09-06 | 成保才 | Hollow pipe sheet for channel |
JP3918648B2 (en) * | 2002-06-13 | 2007-05-23 | 清水建設株式会社 | Tunnel impermeable structure and steel box segment |
CN104481553A (en) * | 2014-09-18 | 2015-04-01 | 黄河勘测规划设计有限公司 | Water stop method for contact part of shield segment and cast-in-place concrete |
CN105114100A (en) * | 2015-06-25 | 2015-12-02 | 同济大学 | Corner reinforcing member of shield tunnel duct piece and application method thereof |
-
2019
- 2019-07-02 CN CN201910588771.XA patent/CN110242323A/en not_active Withdrawn
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2395032Y (en) * | 1999-09-28 | 2000-09-06 | 成保才 | Hollow pipe sheet for channel |
JP3918648B2 (en) * | 2002-06-13 | 2007-05-23 | 清水建設株式会社 | Tunnel impermeable structure and steel box segment |
CN104481553A (en) * | 2014-09-18 | 2015-04-01 | 黄河勘测规划设计有限公司 | Water stop method for contact part of shield segment and cast-in-place concrete |
CN105114100A (en) * | 2015-06-25 | 2015-12-02 | 同济大学 | Corner reinforcing member of shield tunnel duct piece and application method thereof |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111335920A (en) * | 2020-03-26 | 2020-06-26 | 中铁第四勘察设计院集团有限公司 | Construction method of shield tunnel |
CN113586083A (en) * | 2021-08-19 | 2021-11-02 | 北京隧盾市政建设有限公司 | Segment caulking plugging structure and plugging process |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201972269U (en) | Prefabricated reinforcing steel bar concrete shear wall | |
CN110242323A (en) | The design method of side steel concrete shield duct piece | |
CN209100050U (en) | A kind of prefabricated lining segment of self waterproofing shield tunnel | |
CN206956685U (en) | A kind of tunnel multi-purpose type sealing fixing device | |
CN101487290A (en) | Construction method for construction floating window | |
CN105114100B (en) | The corner angle strenthening member of duct pieces of shield tunnel and its application method | |
CN209760300U (en) | Steel shell pre-member of double-steel shell concrete immersed tube tunnel | |
CN101812871B (en) | Method for horizontally connecting precast concrete members | |
CN203452271U (en) | Tie bar connecting structure of profile steel reinforced concrete beam | |
CN205224288U (en) | Connection node of reinforced concrete superposed beam and steel pipe column | |
CN201460220U (en) | Single-head split bolt for underground continuous wall inner lining wall shuttering erection | |
CN202181907U (en) | Tenon-free pipe curtain structure | |
CN209637770U (en) | A kind of metro shield section of jurisdiction | |
CN204059840U (en) | A kind of dry-hang keel installation structure | |
CN204151835U (en) | The vertical piece structure of connection of the basement wall and cast-in-place buttress | |
CN201972271U (en) | Novel precast reinforced concrete shear wall | |
CN210087338U (en) | Side steel concrete shield segment | |
CN209308695U (en) | A kind of compound tunnel segment structure of Mechanical Method service channel portal fringing | |
CN212177148U (en) | Symmetrical horseshoe-shaped assembled concrete tunnel | |
CN205171661U (en) | A core section of thick bamboo | |
CN205152917U (en) | Hydraulic tunnel concrete lining section and steel pipe linkage segment structure | |
CN204646267U (en) | A kind of corrugated steel Tunnel structure | |
CN206289875U (en) | A kind of reinforcing bar cylinder button coupling arrangement | |
CN201461702U (en) | Circumferential and longitudinal segment fastener | |
CN203559432U (en) | Underground powerhouse vault |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20190917 |