CN110241980A - A kind of metal lagging adds flexible waterproof sheet Double-layer roof system - Google Patents

A kind of metal lagging adds flexible waterproof sheet Double-layer roof system Download PDF

Info

Publication number
CN110241980A
CN110241980A CN201910493229.6A CN201910493229A CN110241980A CN 110241980 A CN110241980 A CN 110241980A CN 201910493229 A CN201910493229 A CN 201910493229A CN 110241980 A CN110241980 A CN 110241980A
Authority
CN
China
Prior art keywords
layer
roof system
double
waterproof
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910493229.6A
Other languages
Chinese (zh)
Inventor
李俊瑾
田晶
秦凯
黄墨
宋罕伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Center International Group Co Ltd
Original Assignee
Center International Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Center International Group Co Ltd filed Critical Center International Group Co Ltd
Priority to CN201910493229.6A priority Critical patent/CN110241980A/en
Publication of CN110241980A publication Critical patent/CN110241980A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
    • E04D13/16Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure
    • E04D13/1606Insulation of the roof covering characterised by its integration in the roof structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D3/00Roof covering by making use of flat or curved slabs or stiff sheets
    • E04D3/02Roof covering by making use of flat or curved slabs or stiff sheets of plane slabs, slates, or sheets, or in which the cross-section is unimportant
    • E04D3/16Roof covering by making use of flat or curved slabs or stiff sheets of plane slabs, slates, or sheets, or in which the cross-section is unimportant of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D3/00Roof covering by making use of flat or curved slabs or stiff sheets
    • E04D3/36Connecting; Fastening
    • E04D3/361Connecting; Fastening by specially-profiled marginal portions of the slabs or sheets

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

The invention discloses a kind of Double-layer roof systems, the system includes successively from top to bottom sheet metal assemblies, splash guard, every acoustical absorption heat preserving plate, purlin and main support, it is equipped at intervals with multiple support posts in the main support, is formed between the purlin and the support post and is detachably fixed connection;The support post sequentially passes through described every acoustical absorption heat preserving plate and splash guard, the upper end forms a fixed connection with the sheet metal assemblies, described formed between acoustical absorption heat preserving plate and the purlin is detachably fixed connection, forms waterproof sealing structure between the support post and the splash guard.The present invention is in the case where Roof system is provided with metal lagging, promote the moulding applicability of Roof system, make entire Roof system that there is better stability, combine the basic functional requirement such as waterproof, heat preservation, durability, for this purpose, the present invention, which provides a kind of metal lagging, adds flexible waterproof sheet Double-layer roof system.

Description

A kind of metal lagging adds flexible waterproof sheet Double-layer roof system
Technical field
The present invention relates to roofing system with lightweight steel structure field, in particular to a kind of metal lagging adds flexible waterproof sheet bilayer room Plane system is mainly used in when roof curved surface is complex, curvature is larger, and the gradient is relatively slow, and when outer layer is metal lagging such as What solves the technical problems such as wind resistance, waterproof and the durability of Roof system.
Background technique
Large-scale large span public building main structure mostly uses steel structural form to be built at present, in enclosed structure system In system, the general moulding of roofing is complicated, therefore mostly uses the preferable metal Roof system of lighter in weight, appearance.
Doubling plate metal Roof system is a kind of more common Roof system of current lightweight steel construction public building, construction There are many types for way, and common way is the Roof system that standing-seam roofing adds metal lagging, as shown in Figure 1;Roofing The specific connection structure of plate is as shown in Figure 2.Metal lagging and its keel are fixed on strip metal splash guard by fixing clamp, Two waterproof layers 8, insulating layer, vapour barrier, sound absorbing layer, dust-proof layer, die mould steel sole plate, secondary purlin are successively laid under metal splash guard Item, main purlin or main steel construction.This construction way can solve the functions such as beauty, waterproof, heat preservation, sound insulation, the sound-absorbing of roofing and want It asks.
Standing-seam splash guard 7 includes plate face 71, first panel rib 72 and second panel rib 73, is easy in application process There is following situations:
(1) complex three-dimensional curved surface biggish for curvature, strip metal splash guard are difficult to accomplish smooth laying, many times It is during installation, by artificially deforming laying completion by force, therefore when expanding with heat and contract with cold, it is broken to occur drawing crack because of being obstructed Bad situation.
(2) the strip metal splash guard in this system and between fixing seat for hold tightly lock seaming connection, it is biggish in wind load Coastal typhoon region, roof boarding is also easy to produce deformation under negative Action of Wind pressure, leads to the first panel rib between plate face and fixing seat 9 72, second panel rib 73 opens, and roof boarding is fallen off from fixing seat, and generation wind lifts and leakage accident, such as Fig. 3, Fig. 4 institute Show.
(3) the strip metal splash guard in this system is free extension system, when decorative panel, the sun is arranged in splash guard top When the auxiliary facilities such as energy plate, a stable base cannot be provided for the facility on top.The temperature of roof boarding is flexible to be will lead to Card rib snapped-in position changes, and then decorative panel or other auxiliary facility wind resistances is caused to take off ability decline or even structure occur Drawing crack, extruding etc. destroy.
Summary of the invention
It is an object of the invention to solve to promote Roof system in the case where Roof system is provided with metal lagging Moulding applicability makes entire Roof system have better stability, combines the basic function such as waterproof, heat preservation, durability It can require, for this purpose, the present invention, which provides a kind of metal lagging, adds flexible waterproof sheet Double-layer roof system.
It is adopted the following technical scheme that
A kind of Double-layer roof system, the system include successively from top to bottom sheet metal assemblies, splash guard, every acoustical absorption heat preserving Plate, purlin and main support are equipped at intervals with multiple support posts in the main support, are formed between the purlin and the support post It is detachably fixed connection;The support post sequentially passes through described every acoustical absorption heat preserving plate and splash guard, the upper end and described Sheet metal assemblies form a fixed connection, and described formed between acoustical absorption heat preserving plate and the purlin is detachably fixed connection, the branch Waterproof sealing structure is formed between support column and the splash guard.
The sheet metal assemblies and the splash guard form a gap, and the sheet metal assemblies include being located at metal lagging With decoration board keel, the metal lagging is fixed on the decoration board keel, and the decoration board keel and the support are vertical Column is fixedly connected.
It is open design that adjacent two metal lagging, which is formed by plate stitch,.
The splash guard includes upper layer flexible waterproof sheet, lower layer's flexible waterproof sheet and steel plate screed-coat, described Lower layer's flexible waterproof sheet forms a fixed connection with the steel plate screed-coat, and the upper layer flexible waterproof sheet is solid by bonding Due on lower layer's flexible waterproof sheet;The steel plate screed-coat forms removable with the upper plane every acoustical absorption heat preserving plate It unloads and is fixedly connected.
It is described to include upper profiled sheet, push shape steel plate and positioned at the upper profiled sheet and down-pressing type every acoustical absorption heat preserving plate Insulating layer, vapor barrier layer, sound absorbing layer and dust-proof layer between steel plate;The upper profiled sheet is fixed on the upper surface of the purlin, The down-pressing type Interal fixation is in the lower surface of the purlin.
Sound-absorption hole is distributed on the pushing shape steel plate.
The support post includes steel pipe post, column end plate, otic placode, upper layer waterproof roll sleeve, lower layer's waterproof roll Sleeve, anchor ear and sealing material, the column end plate are set to the upper end of the steel pipe post, the column end plate and the dress Plaque keel form a fixed connection;The otic placode is set to the lower part of the steel pipe post, is formed detachably with the purlin It is fixedly connected, lower layer's waterproof roll sleeve is placed on the steel pipe post, the lower end of lower layer's waterproof roll sleeve The open end of lower layer's flexible waterproof sheet is placed on its inside;The upper layer waterproof roll sleeve is placed on the lower layer The outside of waterproof roll sleeve, the lower end of the upper layer waterproof roll sleeve is by the opening end cap of the upper layer flexible waterproof sheet Side disposed within;The sealing material is set to the upper end of the upper layer waterproof roll sleeve, lower layer's waterproof roll sleeve Upper end and the steel pipe post between, and the sealing material, upper layer waterproof roll sleeve, lower layer are prevented by the anchor ear Water coil sleeve is anchored on the steel pipe post.
The connector of two adjacent flexible waterproof sheets is tightly connected by hot air welding.
The insulating layer and sound absorbing layer are all made of blanket of glass wool, and the density of material is 12~48kg/m3, the dust-proof layer Using non-woven fabrics or glass wool cloth.
Adhering and sealing adhesive tape on the overlap joint end face of the vapor barrier layer, and the faying surface shape with another adjacent vapor barrier layer At the connection that is bonded and sealed.
Technical solution of the present invention has the advantages that
A. the support post that the present invention is directly born in main support by root is consolidated the sheet metal assemblies for being located at top layer It is fixed, the rigidity of metal roofing board is improved, Wind-Pressure Resistance ability is stronger.Splash guard uses two sheets of flexible waterproof roll simultaneously, can increase Add the durable years of lower layer's waterproof layer, and reduce the initial leakage hidden trouble as caused by installation quality problem, and has excellent Watertightness and air-tightness.
B. upper layer flexible waterproof sheet and lower layer's flexible waterproof sheet can reach good wind resistance by reasonably fixing Energy.
C. metal lagging is directly fixed on decoration board keel, and decoration board keel is fixed on the support for being pierced by roofing waterproofing plate Column, support post are directly fixed on main structure or purlins, and base is firm, safer.
D. the steel plate and profiled sheet used in the Roof system serves not only as the support of waterproof layer, due to its quality Greatly, and overlap joint connects, and without gap, and can play good sound insulation effect.
Detailed description of the invention
It, below will be to needed in specific embodiment in order to illustrate more clearly of the specific embodiment of the invention Attached drawing is briefly described, it should be apparent that, the accompanying drawings in the following description is some embodiments of the present invention, for this field For those of ordinary skill, without creative efforts, it is also possible to obtain other drawings based on these drawings.
Fig. 1 is the structural schematic diagram that provided standing-seam roofing adds metal lagging in the prior art;
Fig. 2 is the attachment structure schematic diagram between standing seam roof slabs and fixing seat in Fig. 1;
Fig. 3 is that the standing seam roof slabs in Fig. 2 are deformed schematic diagram by negative wind pressure;
Fig. 4 is that the rib of slab of the standing seam roof slabs in Fig. 3 opens the schematic diagram that falls off under negative Action of Wind pressure;
Fig. 5 is that metal lagging provided by the present invention adds flexible waterproof sheet Double-layer roof system structural schematic diagram (horizontal To);
Fig. 6 is that metal lagging provided by the present invention adds flexible waterproof sheet Double-layer roof system structural schematic diagram (vertical To);
Fig. 7 is the decorative panel spine support pillar construction schematic diagram in Fig. 5.
Description of symbols:
1- sheet metal assemblies
11- metal lagging, 12- decorate board keel
2- splash guard
The upper layer 21- flexible waterproof sheet, 22- lower layer flexible waterproof sheet
23- steel plate screed-coat
3- is every acoustical absorption heat preserving plate
The upper profiled sheet of 31-, 32- push shape steel plate, 33- insulating layer
34- vapor barrier layer, 35- sound absorbing layer, 36- dust-proof layer
4- purlin;The main support of 5-
6- support post
61- steel pipe post, 62- column end plate, the upper layer 63- otic placode 64- waterproof roll sleeve
65- lower layer waterproof roll sleeve, 66- anchor ear, 67- sealing material
7- standing-seam splash guard;
71- plate face, 72- first panel rib, 73- second panel rib
Bis- waterproof layer of 8-;9- fixing seat.
Specific embodiment
Technical solution of the present invention is clearly and completely described below in conjunction with attached drawing, it is clear that described implementation Example is a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiment of the present invention, ordinary skill people Member's every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
As shown in Figure 5 and Figure 6, the present invention provides a kind of Double-layer roof system, the system from top to bottom successively includes Sheet metal assemblies 1, splash guard 2, every acoustical absorption heat preserving plate 3, purlin 4 and it is main support 5, it is described it is main support 5 on be equipped at intervals with multiple Column 6 is supportted, is formed between the purlin 4 and the support post 6 and is detachably fixed connection;The support post 6 sequentially passes through institute State every acoustical absorption heat preserving plate 3 and splash guard 2, the upper end forms a fixed connection with the sheet metal assemblies 1, described every sound-absorbing It is formed between insulation board 3 and the purlin 4 and is detachably fixed connection, form waterproof between the support post 6 and the splash guard 2 Sealing structure.
As shown in fig. 7, the sheet metal assemblies 1 form a gap with the splash guard 2, the sheet metal assemblies 1 include Positioned at metal lagging 11 and decoration board keel 12, the metal lagging 11 is fixed on the decoration board keel 12, described Decoration board keel 12 is fixedly connected with the support post 6.It is unlimited that adjacent two metal lagging 11, which is formed by plate stitch, Structure.
The splash guard 2 includes upper layer flexible waterproof sheet 21, lower layer's flexible waterproof sheet 22 and steel plate screed-coat 23, lower layer's flexible waterproof sheet 22 by special washer and screw be fixed on the steel plate screed-coat 23, and meet Wind resistance requirement;The upper layer flexible waterproof sheet 21 is by being adhesively fixed on lower layer's flexible waterproof sheet 22;Institute It states steel plate screed-coat 23 and is detachably fixed with the upper plane formation every acoustical absorption heat preserving plate 3 and is connect.Adjacent flexible water The connector of coiled material is tightly connected by hot air welding.Two layers of waterproof roll is arranged in the present invention, can increase the durable of lower layer's waterproof layer The time limit, and reduce the initial leakage hidden trouble as caused by installation quality problem.And there is excellent watertightness and air-tightness.
It is described to include upper profiled sheet 31, push shape steel plate 32 and positioned at the upper profiled sheet 31 every acoustical absorption heat preserving plate 3 And push insulating layer 33, vapor barrier layer 34, sound absorbing layer 35 and the dust-proof layer 36 between shape steel plate 32;The upper profiled sheet 31 is fixed In the upper surface of the purlin 4, the lower surface for pushing shape steel plate 32 and being fixed on the purlin 4 by tapping screw.It is described It pushes and sound-absorption hole is distributed on shape steel plate 32, there is sound absorption function and indoor decorative effect, 32 support of pushing shape steel plate is protected Warm layer 33, vapor barrier layer 34, the weight of sound absorbing layer 35, dust-proof layer 36.
The support post 6 includes steel pipe post 61, column end plate 62, otic placode 63, upper layer waterproof roll sleeve 64, lower layer Waterproof roll sleeve 65, anchor ear 66 and sealing material 67, the column end plate 62 are set to the upper end of the steel pipe post 61, The column end plate 62 forms a fixed connection with the decoration board keel 12;The otic placode 63 is set to the steel pipe post 61 Lower part, be detachably fixed and connect with the purlin 4 formation, lower layer's waterproof roll sleeve 65 is placed on the steel pipe and stands On column 61, the open end of lower layer's flexible waterproof sheet 22 is placed on it by the lower end of lower layer's waterproof roll sleeve 65 Inside;The upper layer waterproof roll sleeve 64 is placed on the outside of lower layer's waterproof roll sleeve 65, the upper layer waterproof roll The open end of the upper layer flexible waterproof sheet 21 is placed on its inside by the lower end of material sleeve 64;The sealing material 67 is set It is placed in the upper end of the upper layer waterproof roll sleeve 64, the upper end of lower layer's waterproof roll sleeve 65 and the steel pipe post 61 Between, and it is by the anchor ear 66 that the sealing material 67, upper layer waterproof roll sleeve 64, lower layer's waterproof roll sleeve 65 is tight It is fixed on the steel pipe post 61.
The connector of two adjacent flexible waterproof sheets is tightly connected by hot air welding.
The insulating layer 33 and sound absorbing layer 35 are all made of blanket of glass wool, and the density of material is 12~48kg/m3, described Dust-proof layer 36 uses non-woven fabrics or glass wool cloth.
Adhering and sealing adhesive tape on the overlap joint end face of the vapor barrier layer 34, and the overlap joint with another adjacent vapor barrier layer 34 Face forms the connection that is bonded and sealed.
Obviously, the above embodiments are merely examples for clarifying the description, and does not limit the embodiments.It is right For those of ordinary skill in the art, can also make on the basis of the above description it is other it is various forms of variation or It changes.There is no necessity and possibility to exhaust all the enbodiments.And it is extended from this it is obvious variation or Variation is still in the protection scope of this invention.

Claims (10)

1. a kind of Double-layer roof system, the system from top to bottom successively include sheet metal assemblies (1), splash guard (2), every sound-absorbing Insulation board (3), purlin (4) and main support (5), which is characterized in that be equipped at intervals with multiple support posts on the main support (5) (6), the purlin (4) is detachably fixed with formation between the support post (6) and connect;The support post (6) sequentially passes through It is described every acoustical absorption heat preserving plate (3) and splash guard (2), the upper end forms a fixed connection with the sheet metal assemblies (1), described It is formed to be detachably fixed between acoustical absorption heat preserving plate (3) and the purlin (4) and be connect, the support post (6) and the splash guard (2) waterproof sealing structure is formed between.
2. Double-layer roof system according to claim 1, which is characterized in that the sheet metal assemblies (1) and the waterproof Plate (2) forms a gap, and the sheet metal assemblies (1) include positioned at metal lagging (11) and decorating board keel (12), described Metal lagging (11) is fixed on the decoration board keel (12), the decoration board keel (12) and the support post (6) It is fixedly connected.
3. Double-layer roof system according to claim 2, which is characterized in that adjacent two metal lagging (11) institute shape At plate stitch be open design.
4. Double-layer roof system according to claim 1, which is characterized in that the splash guard (2) includes upper layer flexibility Waterproof roll (21), lower layer's flexible waterproof sheet (22) and steel plate screed-coat (23), lower layer's flexible waterproof sheet (22) It forms a fixed connection with the steel plate screed-coat (23), the upper layer flexible waterproof sheet (21) is by being adhesively fixed in described On lower layer's flexible waterproof sheet (22);The steel plate screed-coat (23) is formed with the upper plane every acoustical absorption heat preserving plate (3) It is detachably fixed connection.
5. Double-layer roof system according to claim 4, which is characterized in that it is described every acoustical absorption heat preserving plate (3) include upper pressure Shape steel plate (31) pushes shape steel plate (32) and is located at the upper profiled sheet (31) and pushes the insulating layer between shape steel plate (32) (33), vapor barrier layer (34), sound absorbing layer (35) and dust-proof layer (36);The upper profiled sheet (31) is fixed on the purlin (4) Upper surface, the lower surface for pushing shape steel plate (32) and being fixed on the purlin (4).
6. Double-layer roof system according to claim 5, which is characterized in that suction is distributed on the pushing shape steel plate (32) Sound hole.
7. Double-layer roof system according to claim 5, which is characterized in that the support post (6) includes steel pipe post (61), column end plate (62), otic placode (63), upper layer waterproof roll sleeve (64), lower layer's waterproof roll sleeve (65), anchor ear (66) With sealing material (67), the column end plate (62) is set to the upper end of the steel pipe post (61), the column end plate (62) It forms a fixed connection with the decoration board keel (12);The otic placode (63) is set to the lower part of the steel pipe post (61), It is formed to be detachably fixed with the purlin (4) and be connect, lower layer's waterproof roll sleeve (65) is placed on the steel pipe post (61) on, the open end of lower layer's flexible waterproof sheet (22) is placed on by the lower end of lower layer's waterproof roll sleeve (65) Its inside;The upper layer waterproof roll sleeve (64) is placed on the outside of lower layer's waterproof roll sleeve (65), the upper layer The open end of the upper layer flexible waterproof sheet (21) is placed on its inside by the lower end of waterproof roll sleeve (64);The sealing Material (67) be set to the upper end of the upper layer waterproof roll sleeve (64), lower layer's waterproof roll sleeve (65) upper end and Between the steel pipe post (61), and pass through the anchor ear (66) for the sealing material (67), upper layer waterproof roll sleeve (64), lower layer's waterproof roll sleeve (65) is anchored on the steel pipe post (61).
8. according to any Double-layer roof system of claim 5-7, which is characterized in that two adjacent flexible waterproof sheets Connector is tightly connected by hot air welding.
9. Double-layer roof system according to claim 8, which is characterized in that the insulating layer (33) and sound absorbing layer (35) are equal Using blanket of glass wool, the density of material is 12~48kg/m3, the dust-proof layer (36) is using non-woven fabrics or glass wool cloth.
10. Double-layer roof system according to claim 9, which is characterized in that on the overlap joint end face of the vapor barrier layer (34) Adhering and sealing adhesive tape, and be bonded and sealed and connect with the formation of the faying surface of another adjacent vapor barrier layer (34).
CN201910493229.6A 2019-06-06 2019-06-06 A kind of metal lagging adds flexible waterproof sheet Double-layer roof system Pending CN110241980A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910493229.6A CN110241980A (en) 2019-06-06 2019-06-06 A kind of metal lagging adds flexible waterproof sheet Double-layer roof system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910493229.6A CN110241980A (en) 2019-06-06 2019-06-06 A kind of metal lagging adds flexible waterproof sheet Double-layer roof system

Publications (1)

Publication Number Publication Date
CN110241980A true CN110241980A (en) 2019-09-17

Family

ID=67886373

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910493229.6A Pending CN110241980A (en) 2019-06-06 2019-06-06 A kind of metal lagging adds flexible waterproof sheet Double-layer roof system

Country Status (1)

Country Link
CN (1) CN110241980A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111042418A (en) * 2019-11-18 2020-04-21 中铁六局集团有限公司 Hyperbolic roof and building
CN111042416A (en) * 2019-11-18 2020-04-21 中铁六局集团有限公司 Roofing with decorative board
CN111042417A (en) * 2019-11-18 2020-04-21 中铁六局集团有限公司 Metal roof

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB167517A (en) * 1920-02-19 1921-07-19 Cammell Laird And Company Ltd Improvements in the method of and in means for securing in position and strengthening sheet metal cover-plates for casings, such as refrigerating chamber insulating casings and the like
JPH06100065A (en) * 1992-09-17 1994-04-12 Kawasaki Steel Corp Method for packing coil of metal sheet
JPH08112371A (en) * 1994-10-17 1996-05-07 Kiyuudenkou:Kk Ceiling-installed fire hydrant
JP2005090076A (en) * 2003-09-17 2005-04-07 Tajima Roofing Co Ltd Waterproofing membrane rise end section protection structure and back-up material attached protection metal fitting
CN1793540A (en) * 2005-12-26 2006-06-28 蔡伯中 Thermal insulation aluminium light wall
CN102409816A (en) * 2011-12-02 2012-04-11 哈尔滨工业大学空间钢结构幕墙有限公司 Double-layer waterproof heat-preserving fireproof metal roof
CN102518266A (en) * 2011-11-30 2012-06-27 哈尔滨工业大学空间钢结构幕墙有限公司 Waterproof thermal-insulated metal roof
CN202324396U (en) * 2011-11-30 2012-07-11 哈尔滨工业大学空间钢结构幕墙有限公司 Waterproof heat-insulating metal roof
CN104153519A (en) * 2014-09-03 2014-11-19 孟涛 Solar integrated roof
CN205742778U (en) * 2016-05-11 2016-11-30 新疆金桥金新型建材有限公司 A kind of flexible waterproof sheet roof lightning system metal support
CN107143098A (en) * 2017-07-12 2017-09-08 天元建设集团有限公司 A kind of secondary waterproof structure of metal roof and construction method
KR101812265B1 (en) * 2016-08-30 2017-12-26 한미기초기술 주식회사 A Foundation Method Of Continuous and Cut Off wall By Overlap Casing

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB167517A (en) * 1920-02-19 1921-07-19 Cammell Laird And Company Ltd Improvements in the method of and in means for securing in position and strengthening sheet metal cover-plates for casings, such as refrigerating chamber insulating casings and the like
JPH06100065A (en) * 1992-09-17 1994-04-12 Kawasaki Steel Corp Method for packing coil of metal sheet
JPH08112371A (en) * 1994-10-17 1996-05-07 Kiyuudenkou:Kk Ceiling-installed fire hydrant
JP2005090076A (en) * 2003-09-17 2005-04-07 Tajima Roofing Co Ltd Waterproofing membrane rise end section protection structure and back-up material attached protection metal fitting
CN1793540A (en) * 2005-12-26 2006-06-28 蔡伯中 Thermal insulation aluminium light wall
CN102518266A (en) * 2011-11-30 2012-06-27 哈尔滨工业大学空间钢结构幕墙有限公司 Waterproof thermal-insulated metal roof
CN202324396U (en) * 2011-11-30 2012-07-11 哈尔滨工业大学空间钢结构幕墙有限公司 Waterproof heat-insulating metal roof
CN102409816A (en) * 2011-12-02 2012-04-11 哈尔滨工业大学空间钢结构幕墙有限公司 Double-layer waterproof heat-preserving fireproof metal roof
CN104153519A (en) * 2014-09-03 2014-11-19 孟涛 Solar integrated roof
CN205742778U (en) * 2016-05-11 2016-11-30 新疆金桥金新型建材有限公司 A kind of flexible waterproof sheet roof lightning system metal support
KR101812265B1 (en) * 2016-08-30 2017-12-26 한미기초기술 주식회사 A Foundation Method Of Continuous and Cut Off wall By Overlap Casing
CN107143098A (en) * 2017-07-12 2017-09-08 天元建设集团有限公司 A kind of secondary waterproof structure of metal roof and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111042418A (en) * 2019-11-18 2020-04-21 中铁六局集团有限公司 Hyperbolic roof and building
CN111042416A (en) * 2019-11-18 2020-04-21 中铁六局集团有限公司 Roofing with decorative board
CN111042417A (en) * 2019-11-18 2020-04-21 中铁六局集团有限公司 Metal roof

Similar Documents

Publication Publication Date Title
CN103711262B (en) A kind of curved surface aluminum-magnesium-manganese alloy roof plate system construction method
CN110241980A (en) A kind of metal lagging adds flexible waterproof sheet Double-layer roof system
CN102409815B (en) Double-layer waterproof thermal insulation metal roof
CN102409814B (en) Double-layer waterproof noise-reducing heat-preserving sound-absorbing metal roof
CN203113630U (en) Upright overlock roof system
CN106677439A (en) Hidden button type super-long metal roof standing seam and construction method thereof
CN210263651U (en) Metal decorative plate and flexible waterproof coiled material double-layer roof system
CN202347747U (en) Double-layer waterproof and heat-insulating metal roof
CN207700486U (en) A kind of stainless steel continuously welds the ridge structure of Roof system
CN202347748U (en) Double-layer waterproof, heat-insulating and fireproof metal roof
CN208039635U (en) A kind of wind resistance waterproof roof boarding with sound-absorbing structure
CN206495424U (en) A kind of concealed fastener type overlength metal Roof standing-seam
CN211548448U (en) Waterproof construction at concrete wall and various steel roof boarding position of connecting
CN213868597U (en) Green energy-saving environment-friendly metal roof enclosure system
CN200958267Y (en) Roof waterproof system
CN210086662U (en) Novel wind-resistant metal roof system
CN111042417A (en) Metal roof
CN217000543U (en) Cornice type skylight and roof waterproof structure
CN113833326A (en) Steel construction factory building with heat preservation function
JP2913268B2 (en) Vertical roofing exterior structure and construction method
CN211597398U (en) Shingle roofing
CN219794363U (en) Ridge structure of heavy grade metal roof
CN216893196U (en) Metal roof expansion joint node
JPH04357245A (en) Roof
CN215484132U (en) High-performance sound insulation metal roof structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination