CN110208729A CN201910570851.2A CN201910570851A CN110208729A CN 110208729 A CN110208729 A CN 110208729A CN 201910570851 A CN201910570851 A CN 201910570851A CN 110208729 A CN110208729 A CN 110208729A
Authority
CN
China
Prior art keywords
electric energy
key
energy meter
combined floodgate
controller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910570851.2A
Other languages
Chinese (zh)
Inventor
尹家悦
肖勇
张乐平
胡珊珊
罗鸿轩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CSG Electric Power Research Institute
China Southern Power Grid Co Ltd
Research Institute of Southern Power Grid Co Ltd
Original Assignee
China Southern Power Grid Co Ltd
Research Institute of Southern Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Southern Power Grid Co Ltd, Research Institute of Southern Power Grid Co Ltd filed Critical China Southern Power Grid Co Ltd
Priority to CN201910570851.2A priority Critical patent/CN110208729A/en
Publication of CN110208729A publication Critical patent/CN110208729A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R35/00Testing or calibrating of apparatus covered by the other groups of this subclass
    • G01R35/04Testing or calibrating of apparatus covered by the other groups of this subclass of instruments for measuring time integral of power or current
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01HELECTRIC SWITCHES; RELAYS; SELECTORS; EMERGENCY PROTECTIVE DEVICES
    • H01H13/00Switches having rectilinearly-movable operating part or parts adapted for pushing or pulling in one direction only, e.g. push-button switch
    • H01H13/02Details
    • H01H13/12Movable parts; Contacts mounted thereon
    • H01H13/14Operating parts, e.g. push-button

Abstract

The invention discloses a kind of key combined floodgate detection methods of electric energy meter, comprising steps of S1: controller drives mandril to press combined floodgate key by motor;S2: controller judges whether receiver receives predetermined switching signal, if so, step S4 is turned to, if it is not, turning to step S3;S3: controller judgement does not receive whether the duration of predetermined switching signal is more than the predetermined time, if turning to step S4, turns to step S2 if not;S4: controller drives mandril to be detached from combined floodgate key by motor.Mandril can be made to stretch out by driving part by controller and press electric energy meter key, judged whether to complete closing operation by the signal of signal receiver, and retract mandril automatically when closing operation is completed, reduce fault caused by human factor.Can also by the multiple objects of the communication modes Parallel Control such as USB deconcentrator, thus conveniently realize at the same high-volume electric energy meter detection process needed for closing operation, operating efficiency and accuracy can be improved more significantly.

Description

The key combined floodgate detection method of electric energy meter
Technical field
The present invention relates to a kind of key of electric energy measuring equipment detection technique field more particularly to electric energy meter combined floodgate detection sides Method.
Background technique
Intelligent electric energy meter has for the function that progress key combined floodgate restores under electric energy meter alarm and overdraw state, is carrying out It is extraneous to carry out combined floodgate behaviour by long-pressing intelligent electric energy meter key and intelligent electric energy meter during electric energy meter takes control Function detection Make, including warning function restores guarantor's electricity condition, overdraw functional rehabilitation is had good luck.
For confirmation intelligent electric energy meter warning function, overdraw function whether meet associated specifications requirement, need to its into Row detection.When detection, by the key on long-pressing intelligent electric energy meter to issue it is clear and melodious " rub-a-dub " combined floodgate sound, can be realized and intelligence Electric energy meter carries out the manual operation of combined floodgate telegram in reply.Take the detection of control function for electric energy meter, now still manually pressing electric energy meter is pressed The mode that key extremely closes a floodgate.
In the detection of high-volume electric energy meter, need manually to press one by one, detection efficiency is low;And due to the electricity of different manufacturers production Can table size it is different, disunity the time required to electric energy meter closes a floodgate is not closed a floodgate inside electric energy meter and is stopped there are long-pressing key press time is short Human operational error caused by only pressing.
Summary of the invention
The object of the present invention is to provide a kind of electric energy meter key combined floodgate detection methods, and high-volume electric energy meter can be realized automatically Required button operation when detection improves detection efficiency, reduces human operational error.
To achieve the above object, the present invention provides a kind of key combined floodgate detection methods of electric energy meter, comprising the following steps:
S1: controller drives mandril to press combined floodgate key by motor;
S2: controller judges whether receiver receives predetermined switching signal, if so, step S4 is turned to, if it is not, turning to step S3;
S3: controller judgement does not receive whether the duration of predetermined switching signal is more than the predetermined time, if turning to Step S4 turns to step S2 if not;
S4: controller drives mandril to be detached from combined floodgate key by motor.
Preferably, in step s 2, the predetermined switching signal includes the vibration letter by vibrating and sound transducer acquires Number and voice signal, by judging whether scheduled vibration signal and sound with the vibration and the controller that connect of sound transducer Whether signal receives.
Preferably, the vibration frequency of the vibration signal is 1000Hz-3000Hz, and the decibels of the voice signal are 20-60。
Preferably, in step s3, the predetermined time is 15 seconds.
Preferably, further comprising the steps of before step S1:
S0: adjusting the position of mandril, it is made to be directed at combined floodgate key.
The key combined floodgate detection method of electric energy meter provided by the present invention, can make to push up by controller by driving part Bar stretches out and presses electric energy meter key, judges whether to complete closing operation by the signal of signal receiver, and in closing operation Automatically mandril is retracted when completion, reduces fault caused by human factor.The parallel connection of the communication modes such as USB deconcentrator can also be passed through Control multiple objects, thus conveniently realize and meanwhile high-volume electric energy meter detection process needed for closing operation, can be more Operating efficiency and accuracy are improved significantly.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this The embodiment of invention for those of ordinary skill in the art without creative efforts, can also basis The attached drawing of offer obtains other attached drawings.
Fig. 1 is the structural schematic diagram using the system of method provided by the present invention;
Fig. 2 for a kind of specific embodiment institute providing method of the invention work flow diagram.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Core of the present invention is to provide a kind of electric energy meter key combined floodgate detection method, and the inspection of high-volume electric energy meter can be realized automatically Required button operation when survey improves detection efficiency, reduces human operational error.
Fig. 1 and Fig. 2 are please referred to, Fig. 1 is the structural schematic diagram using the system of method provided by the present invention;Fig. 2 is this hair A kind of work flow diagram of bright specific embodiment institute providing method.
System using method provided by the present invention includes hold assembly 2, and hold assembly 2 is for enabling the detection system Clamp electric energy meter;Hold assembly 2 can be the clamping plate with certain elasticity, be arranged in parallel in the left and right sides.
Detection panel 1 is equipped between two hold assemblies 2, detection panel 1 is irony panel or the face of other suitable materials Plate, it is vertically arranged, form frame-shaped construction with the hold assembly 2 of its two sides, wherein two hold assemblies 2 substantially with 1 phase of detection panel Vertically.
Two hold assemblies 2 can be similarly irony component or the component of other suitable materials, San Zheke with detection panel 1 To be integrally formed.Certainly, even if three is that irony component is not meant as cannot having other except the irony as main part Material.
Detection panel 1 has the detection window for making mandril 3 be directed at electric energy meter key.
At least one hold assembly 2 can open up screw hole, be provided with the fastening screw 4 matched;Fastening screw 4 and folder It is perpendicular to hold component 2.In this way, the combination of product and electric energy meter can be made more stable by screwing fastening screw 4.
Detection panel 1, which is installed, simultaneously supports mandril 3, and mandril 3 is also connect with driving part (such as motor 7), and can be It is extended and retracted under the action of driving part perpendicular to detection panel 1.
It should be pointed out that detection panel 1 and mandril 3 are flexibly connected with which kind of specific structure realization, and non-present invention Improvement, a very known rod piece is how to be flexibly connected (such as to slide with a plate to those skilled in the art The cooperation of bar and slide opening);Mandril 3 and driving part are driven reciprocating motion ability with what which kind of specific connection type realized mandril 3 The technical staff in domain is equally known (such as rack-and-pinion), and the prior art of the detail with reference maturation of these connection relationships is It can.Main improvement of the invention is to combine these common mechanical structures, and makes these knots in specific technology scene Structure is combined into whole to generation technology effect.
The detection system further includes signal receiver, and signal receiver completes signal for receiving scheduled feed motion; The signal receiver can be vibration and sound receiver 5, other receivers can also be selected according to the difference of determination strategy, but Vibration and sound receiver 5 can usually be selected.
Above-mentioned motor 7 (or other driving parts) and vibration and sound receiver 5 (or other signal receivers) with control 6 signal of device connection processed;It is wirelessly connected, or is connected by USB data line.
Based on above structure, the key of electric energy meter provided by the present invention closes a floodgate, and detection method includes the following steps:
Step S1: controller 6 drives mandril 3 to press combined floodgate key by motor 7.
Motor 7 replace with other common drivings lose it is also possible.
In addition, it is optional, can also have before step S1:
Step S0: the position of adjustment mandril 3 makes it be directed at combined floodgate key.The concrete mode of adjustment and corresponding machinery Structure setting is the prior art, and the application repeats no more.
Step S2: controller 6 judges whether receiver receives predetermined switching signal, if so, step S4 is turned to, if it is not, turning To step S3.
When signal receiver selects vibration and sound receiver 5, received with vibration signal and voice signal to complete touching Hair.
Wherein, the vibration frequency of the vibration signal can be selected as 1000Hz-3000Hz, the decibels of the voice signal It can be selected as 20-60.
Step S3: the judgement of controller 6 does not receive whether the duration of predetermined switching signal is more than the predetermined time, if Step S4 is turned to, turns to step S2 if not;
The predetermined time can be selected as 15 seconds
S4: controller drives mandril to be detached from combined floodgate key by motor.
The key combined floodgate detection method of electric energy meter provided by the present invention, can make to push up by controller by driving part Bar stretches out and presses electric energy meter key, judges whether to complete closing operation by the signal of signal receiver, and in closing operation Automatically mandril is retracted when completion, reduces fault caused by human factor.The parallel connection of the communication modes such as USB deconcentrator can also be passed through Control multiple objects, thus conveniently realize and meanwhile high-volume electric energy meter detection process needed for closing operation, can be more Operating efficiency and accuracy are improved significantly.
Each embodiment in this specification is described in a progressive manner, the highlights of each of the examples are with other The difference of embodiment, the same or similar parts in each embodiment may refer to each other.
The key combined floodgate detection method of electric energy meter provided by the present invention is described in detail above.It is used herein A specific example illustrates the principle and implementation of the invention, and the above embodiments are only used to help understand Method and its core concept of the invention.It should be pointed out that for those skilled in the art, not departing from this , can be with several improvements and modifications are made to the present invention under the premise of inventive principle, these improvement and modification also fall into the present invention In scope of protection of the claims.

Claims (5)

1. a kind of key combined floodgate detection method of electric energy meter, which comprises the following steps:
S1: controller drives mandril to press combined floodgate key by motor;
S2: controller judges whether receiver receives predetermined switching signal, if so, step S4 is turned to, if it is not, turning to step S3;
S3: controller judgement does not receive whether the duration of predetermined switching signal is more than the predetermined time, if turning to step S4 turns to step S2 if not;
S4: controller drives mandril to be detached from combined floodgate key by motor.
2. the key combined floodgate detection method of electric energy meter as described in claim 1, which is characterized in that
In step s 2, the predetermined switching signal includes the vibration signal harmony message by vibrating and sound transducer acquires Number, judge whether scheduled vibration signal and voice signal are equal by the controller connecting with the vibration and sound transducer It receives.
3. the key combined floodgate detection method of electric energy meter as claimed in claim 2, which is characterized in that
The vibration frequency of the vibration signal is 1000Hz-3000Hz, and the decibels of the voice signal are 20-60.
4. the key combined floodgate detection method of electric energy meter as described in any one of claims 1-3, which is characterized in that
In step s3, the predetermined time is 15 seconds.
5. the key combined floodgate detection method of electric energy meter as described in any one of claims 1-3, which is characterized in that
It is further comprising the steps of before step S1:
S0: adjusting the position of mandril, it is made to be directed at combined floodgate key.
CN201910570851.2A 2019-06-27 2019-06-27 The key combined floodgate detection method of electric energy meter Pending CN110208729A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910570851.2A CN110208729A (en) 2019-06-27 2019-06-27 The key combined floodgate detection method of electric energy meter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910570851.2A CN110208729A (en) 2019-06-27 2019-06-27 The key combined floodgate detection method of electric energy meter

Publications (1)

Publication Number Publication Date
CN110208729A true CN110208729A (en) 2019-09-06

Family

ID=67795218

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910570851.2A Pending CN110208729A (en) 2019-06-27 2019-06-27 The key combined floodgate detection method of electric energy meter

Country Status (1)

Country Link
CN (1) CN110208729A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201149617Y (en) * 2008-01-11 2008-11-12 莱芜供电公司 Portable load instrument for measurement specially
CN202110274U (en) * 2011-05-24 2012-01-11 北京市电力公司 Association test tool for meter switch
CN104483653A (en) * 2015-01-04 2015-04-01 潍坊五洲浩特电气有限公司 Automatic detection system and method for intelligent electric energy meter motherboard
CN206250136U (en) * 2016-12-05 2017-06-13 威胜电气有限公司 The pattern switching mechanism of the external breaker of electric energy meter
CN108107401A (en) * 2017-12-20 2018-06-01 宁波三星医疗电气股份有限公司 A kind of uncap detection method and intelligent meter based on intelligent meter
CN108535639A (en) * 2018-03-27 2018-09-14 江苏卡欧万泓电子有限公司 A kind of method of automatic detection intelligent electric meter relay switching on

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201149617Y (en) * 2008-01-11 2008-11-12 莱芜供电公司 Portable load instrument for measurement specially
CN202110274U (en) * 2011-05-24 2012-01-11 北京市电力公司 Association test tool for meter switch
CN104483653A (en) * 2015-01-04 2015-04-01 潍坊五洲浩特电气有限公司 Automatic detection system and method for intelligent electric energy meter motherboard
CN206250136U (en) * 2016-12-05 2017-06-13 威胜电气有限公司 The pattern switching mechanism of the external breaker of electric energy meter
CN108107401A (en) * 2017-12-20 2018-06-01 宁波三星医疗电气股份有限公司 A kind of uncap detection method and intelligent meter based on intelligent meter
CN108535639A (en) * 2018-03-27 2018-09-14 江苏卡欧万泓电子有限公司 A kind of method of automatic detection intelligent electric meter relay switching on

Similar Documents

Publication Publication Date Title
CN103376411B (en) The device in mobile terminal, inverter state reported to the police and the device analyzing motor status
DE69723423T2 (en) Diagnostics of a capacitive pressure transducer in a process transmitter, operated solely by a loop current
EP1715603A3 (en) Apparatus and method for controlling electric appliances using broadcast wave, and apparatus and method for controlling home network
CN101947111B (en) Electrocardio-analog device and electrocardio-analog method for outputting polarization voltage signal
CN110208729A (en) The key combined floodgate detection method of electric energy meter
WO2017045980A1 (en) Communication unit for an electrical machine tool, electrical machine tool system and method
CN204333559U (en) A kind of wire harness Auto-mounting and drawing force testing device
CN105336150A (en) Sound wave based remote control method and system
CN207964483U (en) A kind of electromagnetic type is drawn, pressure turns round Microsecond grade synchronization combining dynamic load experimental provision
CN203279078U (en) Automatic detection device for production of television board
TW200632753A (en) Control unit for contact screen
CN110187205A (en) Screen method for detecting operation state, device and digital signage
CN202466183U (en) Voice alarm system for lace dyeing machine
CN205988293U (en) A kind of anti-pinch warning system for CT scan bed
CN205051878U (en) Test fixture and test system
CN210775697U (en) General frequency converter detection equipment
CN102609230B (en) Method and system for realizing consistent starting of display units on video wall
CN208188978U (en) A kind of operation base station alarm system for unmanned boat
CN208174006U (en) A kind of easy-to-mount mounting device and electricity box
EP2091164A3 (en) Radio receiving apparatus and output restoring method
CN105068021A (en) Switching mode power supply offline fault detection device and system
CN103191862A (en) Device and method for controlling screening times for soil aggregate water-stability measuring device
CN2893720Y (en) Phase angle monitoring instrument
CN104329779B (en) Gateway controller and control system of air conditioning unit
CN205787053U (en) A kind of regulated power supply monitoring alarm based on pulse frequency conversion

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190906

RJ01 Rejection of invention patent application after publication