CN110182700A - GIS metal can dismantling device - Google Patents
GIS metal can dismantling device Download PDFInfo
- Publication number
- CN110182700A CN110182700A CN201910466609.0A CN201910466609A CN110182700A CN 110182700 A CN110182700 A CN 110182700A CN 201910466609 A CN201910466609 A CN 201910466609A CN 110182700 A CN110182700 A CN 110182700A
- Authority
- CN
- China
- Prior art keywords
- positioning
- crossbeam
- plate
- hole
- inserted link
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000002184 metal Substances 0.000 title claims abstract description 19
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims abstract description 28
- 238000009434 installation Methods 0.000 claims abstract description 27
- 230000001360 synchronised effect Effects 0.000 claims description 4
- 238000000034 method Methods 0.000 description 6
- 238000010586 diagram Methods 0.000 description 5
- 238000012423 maintenance Methods 0.000 description 4
- 229910018503 SF6 Inorganic materials 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 230000008092 positive effect Effects 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
- SFZCNBIFKDRMGX-UHFFFAOYSA-N sulfur hexafluoride Chemical compound FS(F)(F)(F)(F)F SFZCNBIFKDRMGX-UHFFFAOYSA-N 0.000 description 1
- 229960000909 sulfur hexafluoride Drugs 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/12—Slings comprising chains, wires, ropes, or bands; Nets
- B66C1/18—Band-type slings
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C25/00—Cranes not provided for in groups B66C17/00 - B66C23/00
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C5/00—Base supporting structures with legs
- B66C5/02—Fixed or travelling bridges or gantries, i.e. elongated structures of inverted L or of inverted U shape or tripods
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66D—CAPSTANS; WINCHES; TACKLES, e.g. PULLEY BLOCKS; HOISTS
- B66D3/00—Portable or mobile lifting or hauling appliances
- B66D3/12—Chain or like hand-operated tackles with or without power transmission gearing between operating member and lifting rope, chain or cable
- B66D3/16—Chain or like hand-operated tackles with or without power transmission gearing between operating member and lifting rope, chain or cable operated by an endless chain passing over a pulley or a sprocket
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Load-Engaging Elements For Cranes (AREA)
Abstract
A kind of GIS metal can dismantling device, including two gantry cranes arranged side by side, each gantry crane includes crossbeam, it is equipped with column vertically at the end positions of crossbeam, the bottom of each column is fixedly connected with pedestal, in the bottom of the crossbeam, there are two chain blocks for installation, and two chain blocks are between two columns.To overcome operating space encountered in current dismounting operation link limited, easily accidentally touch the security risk that neighbouring electrical equipment causes, the uncontrollable problem of precision of equipment installation, it realizes the control accurate of GIS tank body dismounting link, and then facilitates the service work of safe and efficient, high quality completion GIS device.
Description
Technical field
The present invention relates to station fixture technology field, specifically a kind of GIS metal can dismantling device.
Background technique
GIS is the abbreviation of gas insulated metal-enclosed switchgear, i.e. " gas-insulated metal envelope
Close switchgear ", with putting into operation on a large scale for super-pressure sulfur hexafluoride GIS substation, the GIS device meeting in actual moving process
Occur such as internal discharge, gas leakage situations such as, this just needs to disassemble the abutted flange of GIS fault gas chamber, then to GIS failure at
It is overhauled, is again restored the GIS plenum interior of dismantling after maintenance, finally the flange of gas chamber dock tight
Gu GIS shell need to mostly be lifted by crane by crane when dismantling GIS gas chamber flange at present, then by the tight of mutual disassembly's flange
Fixing bolt separates flange face by mobile pull with manpower of crane suspension centre, but since crane volume is excessive, use environment is just
It is limited by very large, and distance and direction are inconvenient to accurately be adjusted during crane handling, easily accidentally meet other
Equipment is also easy to scratch electrically setting inside flange face even damage using manpower dragging etc. there are biggish security risk
It is standby, it is time-consuming and laborious also to lose more than gain, certain trouble is brought to the upkeep operation of GIS substation.
Summary of the invention
To solve the above problems, the purpose of the present invention is to provide a kind of GIS metal can dismantling device, to overcome at present
Operating space encountered in dismounting operation link is limited, easily accidentally touches the security risk that neighbouring electrical equipment causes, equipment installation
The uncontrollable problem of precision, realizes the control accurate of GIS tank body dismounting link, and then facilitates safe and efficient, high quality complete
At the service work of GIS device.
The technical solution adopted by the present invention to solve the technical problems is:
A kind of GIS metal can dismantling device, including two gantry cranes arranged side by side, each gantry crane is equal
Include crossbeam, is equipped with column vertically at the end positions of crossbeam, the bottom of each column is fixedly connected with pedestal, in institute
The bottom installation of crossbeam is stated there are two chain block, two chain blocks between two columns, described two chain blocks
Chain bottom end connects same U-shaped suspender belt jointly, is set side by side on the top of the crossbeam there are two traversing adjustment plate, each traversing tune
Whole plate is arranged along the length direction of crossbeam, and the strip being arranged along its length is offered in the two sides of traversing adjustment plate
Hole is fitted with screw rod in the strip hole, and screw rod is vertically arranged and passes through strip hole, positioned at traversing adjustment plate two sides
Nut is equipped on screw rod, the diameter of the nut is greater than the width of strip hole, screw rod can be located in any position of strip hole
It sets, is fixedly connected with mounting base in two screw rod upper ends of described the same side, mounting base is equipped with hand-rail type jack, described
The upper end of two hand-rail type jack connects supporting plate jointly, and supporting plate is arranged along the length direction of crossbeam, on the supporting plate also side by side
Equipped with two declining lugs for placing metal can.
The column includes the cylindrical bar and square column of mutual sheathing, and cylindrical bar is located inside square column and energy edge moves down thereon
Dynamic, the bottom of cylindrical bar and the upper end of square column offer the first through hole matched, grafting locating rod in perforative first through hole
Cylindrical bar and square column can be positioned, connecting plate is equipped between the cylindrical bar and crossbeam, the bottom of crossbeam is equipped with along its length
The sliding rail of direction arrangement, is respectively mounted baffle at the end positions of sliding rail, and it is sliding that first matched with sliding rail is offered on connecting plate
The bottom of slot, connecting plate is connected by shaft with cylindrical bar, hound is additionally provided between the connecting plate and cylindrical bar, tiltedly
One end of strut is fixed on cylindrical bar, horizontal on the other end of hound to be equipped with positioning plate, installs positioning and locking on positioning plate
Device, positioning and locking device can be fixed on the slide rail by hound and connecting plate, are also provided on the lateral surface of the square column
The through groove matched with hound.The positioning and locking device includes installation set, and installation set is vertically arranged in the bottom of positioning plate,
Inserted link is fitted in installation set, the bottom end of inserted link stretches out installation set and connects pull ring, on the inserted link in installation set
Equipped with positioning convex platform, the positioning convex platform is located in the mounting groove in installation set, and spring, the bullet are also equipped in mounting groove
Spring is located at the periphery of boss bottom, inserted link, and spring has the tendency that making always the upper end of inserted link to stretch out positioning plate, corresponds to inserted link
Upper end position, offer the second through-hole matched with inserted link on connecting plate and sliding rail, inserted link can protrude into the second through-hole will
Positioning plate and connecting plate are fixed on the slide rail.Bearing base, each bearing base are hinged at the end positions of each pedestal
On be respectively provided with sliding sleeve, offer second sliding slot on the side of bearing base and pedestal, the sliding sleeve is matched with second sliding slot, sliding
Set can slide on bearing base and pedestal along second sliding slot, offer first on the two sides of bearing base and pedestal articulated position
Positioning screw hole is equipped with the first positioning thread insert corresponding with two the first positioning screw hole positions, each first positioning on sliding sleeve
The first positioning bolt is respectively mounted in swivel nut, the first positioning bolt can protrude into the first positioning screw hole, thus by sliding sleeve by bearing base
It is connected as one with pedestal.Hinged first connecting rod on the sliding sleeve, hinged second connecting rod on column, second connecting rod
It is sleeved in first connecting rod, the second positioning screw hole is offered in the second connecting rod, is equipped on first connecting rod and matches therewith
The second swivel nut and the second positioning bolt closed, the second positioning bolt can protrude into the second positioning screw hole, by first connecting rod and the
Two connecting rods are connected as one.Synchronous belt is installed between the handle shaft of described two hand-rail type jack.
The positive effect of the present invention is: a kind of GIS metal can dismantling device of the present invention, the body of integral device
Product is smaller, can use in narrow space, improves the use scope of its maintenance, is equipped with chain block on dismantling device
With the equidistant regulating device of hand-rail type jack, while reducing operator's labor intensity, moreover it is possible to guarantee in disassembly process
Installation accuracy between flange, and whole operation process will not be occurred between two gantry cranes of dismantling device
It accidentally touches electrical equipment and bring security risk, adds bearing base on pedestal, the stability and load-bearing energy of integral device can be improved
Power, and single unit system can also carry out assembling-disassembling foldable storage in non-use, to reduce its memory space, convenient for transfer fortune
Defeated, furthermore the present invention also has many advantages, such as compact-sized, easy to assemble, easy access maintenance.
Detailed description of the invention
Fig. 1 is three dimensional structure diagram of the invention;
Fig. 2 is the main view of gantry crane in the present invention;
Fig. 3 is the left view of Fig. 2;
Fig. 4 is the partial enlarged view of I in Fig. 2;
Fig. 5 is sectional view along A-A in Fig. 4;
Fig. 6 is the partial enlarged view of II in Fig. 2;
Fig. 7 is the structural schematic diagram of positioning and locking device;
Fig. 8 is that pedestal adds structural schematic diagram after bearing base;
Fig. 9 is the status diagram of bearing base folding storage;
Figure 10 is the storage schematic diagram of the present invention in the non-use state.
Traversing 7 strip hole of adjustment plate, 8 screw rod 9 of 1 crossbeam, 2 column, 3 pedestal, 4 chain block 5U type suspender belt 6 in figure
15 square column of nut 10 mounting base, 11 hand-rail type jack, 12 supporting plate, 13 declining lug, 14 cylindrical bar, 16 first through hole 17
24 through groove of locating rod 18 connecting plate, 19 sliding rail, 20 baffle, 21 first sliding groove, 22 hound, 23 positioning plate, 25 installation set 26
29 mounting groove of inserted link 27 pull ring, 28 positioning convex platform, 30 33 sliding sleeve of spring 31 second through-hole, 32 bearing base, 34 second sliding slot
35 first positioning screw hole, 36 first 37 first positioning bolt of positioning thread insert, 38 first connecting rod, 39 second connecting rod 40 second
41 second 42 second positioning bolt of swivel nut of positioning screw hole, 43 synchronous belt.
Specific embodiment
A kind of GIS metal can dismantling device of the present invention, as shown in Figure 1, including two gantry arranged side by side
Crane, the both ends of Awaiting Overhaul GIS gas chamber are located in each gantry crane the dismounting operation that can be attached flange,
As shown in Fig. 2, each gantry crane includes crossbeam 1, it is equipped with column 2 vertically at the end positions of crossbeam 1, each
The bottom of column 2 is fixedly connected with pedestal 3, and in the bottom of the crossbeam 1, there are two chain block 4, two chain blocks 4 for installation
Between two columns 2, the chain bottom end of described two chain blocks 4 connects same U-shaped suspender belt 5, the U-shaped suspender belt 5 jointly
For fixing and promoting the GIS gas chamber shell lower than 1 position of crossbeam, and the position of gas chamber end face of flange is adjusted by operator
It sets, in order to improve the efficiency of flange dismounting operation.
For being more than that crossbeam 1 highly locates the dismounting of GIS gas chamber, as shown in figure 4, being equipped with side by side on the top of the crossbeam 1
Two traversing adjustment plates 6, each traversing adjustment plate 6 is arranged along the length direction of crossbeam 1, as shown in figure 5, in traversing adjustment plate
6 two sides offer the strip hole 7 being arranged along its length, and screw rod 8, screw rod 8 are fitted in the strip hole 7
It is vertically arranged and is passed through strip hole 7, nut 9, the diameter of the nut 9 are equipped on the screw rod 8 of traversing 6 two sides of adjustment plate
Greater than the width of strip hole 7, screw rod 8 can be located on any position of strip hole 7.Two screw rods 8 in described the same side
Upper end is fixedly connected with mounting base 10, and mounting base 10 is equipped with hand-rail type jack 11, described two hand-rail type jack 11
Upper end connects supporting plate 12 jointly, and supporting plate 12 is arranged along the length direction of crossbeam 1, is also equipped with side by side on the supporting plate 12 and places metal
Two declining lugs 13 of tank body.Height and position is more than the GIS gas chamber of crossbeam 1, and the dismounting that flange is attached to it will incite somebody to action
It is placed between two declining lugs 13 of supporting plate 12 and is positioned, if wanting to adjust position of the supporting plate 12 on 1 length direction of crossbeam
It sets, then the nut 9 on two sides screw rod 8 should be unscrewed, while the mounting base 10 of mobile two sides is to suitable position and then by nut
9 screw, that is, can reach adjustment supporting plate 12 and the thereon purpose of GIS gas chamber shell lateral position.And for supporting plate 12 and its
Adjustment of the upper GIS gas chamber shell in height distance, can be completed by the hand-rail type jack 11 of two sides, i.e., time saving and energy saving,
It also assures Adjustment precision, improves operating efficiency.
Preferably, in order to keep single unit system easy to disassemble and folding storage, as shown in figure 3, the column 2 includes mutually covering
The cylindrical bar 14 and square column 15 of dress, cylindrical bar 14 are located at 15 inside of square column and can move up and down along it.The bottom of cylindrical bar 14 and
The upper end of square column 15 offers the first through hole 16 matched, and when gantry crane is in running order, perforative first is logical
Grafting locating rod 17 can position cylindrical bar 14 and square column 15 in hole 16, and the square column 15 of the stretching of cylindrical bar 14 at this time reaches specified height
Degree.
Furthermore as shown in fig. 6, being additionally provided with connecting plate 18 between the cylindrical bar 14 and crossbeam 1, the bottom of crossbeam 1 is equipped with
The sliding rail 19 arranged along its length is respectively mounted baffle 20 at the end positions of sliding rail 19, offered on connecting plate 18 with it is sliding
The bottom of the first sliding groove 21 that rail 19 matches, connecting plate 18 is connected by shaft with cylindrical bar 14, and cylindrical bar 14 can be opposite
Connecting plate 18 rotates, and cylindrical bar 14 and square column 15 can be driven by connecting plate 18 and be relatively moved on sliding rail 19.Described
Hound 22 is additionally provided between connecting plate 18 and cylindrical bar 14, hound 22, which plays, to be reinforced connecting between connecting plate 18 and cylindrical bar 14
The effect of intensity is connect, one end of hound 22 is fixed on cylindrical bar 14, horizontal on the other end of hound 22 to be equipped with positioning plate
23, positioning and locking device is installed on positioning plate 23, hound 22 and connecting plate 18 can be fixed on sliding rail 19 by positioning and locking device
On, when being guaranteed at working condition, cylindrical bar 14 will not rotate, cylindrical bar 14, square column 15 and connecting plate 18 and sliding rail
19 in relatively fixed state, it is ensured that the stability of single unit system under working condition, above-mentioned positioning and locking device can be existing
Bolt fastener or fastening screw.For the ease of dismounting storage, it is also provided on the lateral surface of the square column 15 and diagonal brace
The through groove 24 that bar 22 matches.
Preferably, as shown in fig. 7, positioning and locking device herein may include installation set 25, installation set 25 is vertically arranged
In the bottom of positioning plate 23, inserted link 26 is fitted in installation set 25, the bottom end of inserted link 26 is stretched out installation set 25 and connected
Pull ring 27, the inserted link 26 in installation set 25 are equipped with positioning convex platform 28, and the positioning convex platform 28 is located in installation set 25
In mounting groove 29, spring 30 is also equipped in mounting groove 29, the spring 30 is located at the periphery of 28 bottom of boss, inserted link 26,
And spring 30 has the tendency that so that the upper end of inserted link 26 is stretched out positioning plate 23 is connecting corresponding to the upper end position of inserted link 26 always
The second through-hole 31 matched with inserted link 26 is offered on plate 18 and sliding rail 19, inserted link 26 can protrude into the second through-hole 31 for positioning plate
23 and connecting plate 18 be fixed on sliding rail 19.
It is first when needing to store gantry crane under tooling state shown in Fig. 2 for off working state shown in Fig. 10
First operator removes chain block 4, pulls the pull ring 27 of two sides, separates inserted link 26 with the second through-hole 31, positioning plate 23, oblique
Strut 22 and cylindrical bar 14 are no longer fixed with sliding rail 19, rotate cylindrical bar 14 later, and hound 22 is made to be located at the outer of cylindrical bar 14
Side position makes the cylindrical bar 14 of two sides after, unclamps pull ring 27, again consolidates the hound 22 of two sides and 19 phase of sliding rail
It is fixed, to prevent from generating sliding under receiving state, locating rod 17 is finally pulled out, cylindrical bar 14 is fallen into square column 15, corresponding oblique
Strut 22 is fallen into through groove 24, not only reduces the height of single unit system, due also to restriction of the through groove 24 to hound 22, into one
Step prevents the rotation between cylindrical bar 14 and connecting plate 18, and stowing operation is simple and easy to do, substantially reduces storage and transportation space, also exists
It ensure that the stability of single unit system under receiving state to a certain extent.
Preferably, in order to improve the load-bearing capacity and stability of single unit system, as shown in figure 8, the two of each pedestal 3
It is hinged with bearing base 32 at end position, is respectively provided with sliding sleeve 33, the side of bearing base 32 and pedestal 3 on each bearing base 32
On offer second sliding slot 34, the sliding sleeve 33 is matched with second sliding slot 34, and sliding sleeve 33 can be along second sliding slot 34 in load-bearing
It is slided on seat 32 and pedestal 3.The first positioning screw hole 35 is offered on the two sides of 3 articulated position of bearing base 32 and pedestal, it is sliding
The first positioning thread insert 36 corresponding with two 35 positions of the first positioning screw hole, each first positioning thread insert 36 are installed on set 33
It is inside respectively mounted the first positioning bolt 37, the first positioning bolt 37 can protrude into the first positioning screw hole 35, to will be held by sliding sleeve 33
Weight seat 32 and pedestal 3 are connected as one.The setting of bearing base 32 increases the contact area between gantry crane and ground,
It ensure that stability of the GIS gas chamber in lifting process to a certain extent.
Preferably, in order to further ensure it is in running order when, bonding strength between pedestal 3 and column 2, such as Fig. 8
It is shown, hinged first connecting rod 38 on the sliding sleeve 33, hinged second connecting rod 39 on column 2,39 sets of second connecting rod
In first connecting rod 38, the second positioning screw hole 40 is offered in the second connecting rod 39, be equipped on first connecting rod 38 with
The second swivel nut 41 matched and the second positioning bolt 42, the second positioning bolt 42 can protrude into the second positioning screw hole 40, will
First connecting rod 38 and the second connecting rod 39 are connected as one.First connecting rod 38, the second connecting rod 39, pedestal 3 and column 2 it
Between form stable triangular support structure, it can be ensured that stability when work to avoid device and the security risks such as topple, protects
Demonstrate,prove the personal safety of operator.
When the device for having added bearing base 32 and first connecting rod 38, the second connecting rod 39 needs to store, such as Fig. 9 institute
Show, rotate the first positioning bolt 37 and the second positioning bolt 42 first, positions it with the first positioning screw hole 35 and second respectively
Screw hole 40 separates, and then moves to sliding sleeve 33 at 2 position of column along second sliding slot 34, the second connecting rod 39 protrudes into the first company at this time
In extension bar 38, finally bearing base 32 is rotated inward along articulated shaft to pedestal 3, as shown in figure 9, reducing to a certain extent
The space integrally stored, easy to carry and transfer transport use.
Preferably, adjusting of the personnel to supporting plate 12 in the height direction for ease of operation, as shown in figure 4, described two
Synchronous belt 43 is installed between the handle shaft of hand-rail type jack 11, rotates the tune of wherein any one hand-rail type jack 11
Handle is saved, another hand-rail type jack 11 can be driven to carry out real-time synchronization adjusting, simplifies the adjusting step in short transverse
Suddenly, operating efficiency is improved.
Above-mentioned GIS metal can dismantling device is light adjustable, and stability and intensity are reliable, be more suitable in small space into
The lifting disassembling operations of row GIS device, significantly reduce task difficulty, improve operating efficiency, reduce GIS gas chamber tank body
The offset distance of installation installs firm, the rework rate after reducing maintenance operation, avoids the mistake of equipment near in installation process
Phenomenon is touched, while the requirement after single unit system storage to storage space is also smaller, easy to carry and transfer transport.
Technical solution of the present invention is not restricted in the range of embodiment of the present invention.The not detailed description of the present invention
Technology contents be well-known technique.
Claims (6)
1. a kind of GIS metal can dismantling device, it is characterised in that: including two gantry cranes arranged side by side, Mei Gelong
Door crane includes crossbeam (1), is equipped with column (2) vertically at the end positions of crossbeam (1), each column (2)
Bottom is fixedly connected with pedestal (3), and in the bottom of the crossbeam (1), there are two chain block (4), two chain blocks for installation
(4) between two columns (2), the chain bottom end of described two chain blocks (4) connects same U-shaped suspender belt (5) jointly, in institute
The top for stating crossbeam (1) is set side by side there are two traversing adjustment plate (6), and each traversing adjustment plate (6) is along the length side of crossbeam (1)
To setting, the strip hole (7) being arranged along its length is offered in the two sides of traversing adjustment plate (6), in the strip hole
(7) it is fitted with screw rod (8) in, screw rod (8) is vertically arranged and passes through strip hole (7), is located at traversing adjustment plate (6) two sides
It is equipped on screw rod (8) nut (9), the diameter of the nut (9) is greater than the width of strip hole (7), can be located in screw rod (8)
It on any position of strip hole (7), is fixedly connected with mounting base (10), installs in two screw rod (8) upper ends of described the same side
Seat (10) is equipped with hand-rail type jack (11), and the upper end of described two hand-rail type jack (11) connects supporting plate (12) jointly,
Supporting plate (12) is arranged along the length direction of crossbeam (1), and two for being also equipped with placement metal can on the supporting plate (12) side by side incline
Oblique convex block (13).
2. a kind of GIS metal can dismantling device according to claim 1, it is characterised in that: the column (2) includes phase
The cylindrical bar (14) and square column (15) being mutually set with, cylindrical bar (14) are located at square column (15) inside and can move up and down along it, cylinder
The bottom of bar (14) and the upper end of square column (15) offer the first through hole (16) matched, perforative first through hole (16) interpolation
Cylindrical bar (14) and square column (15) can be positioned by connecing locating rod (17), the company of being equipped between the cylindrical bar (14) and crossbeam (1)
Fishplate bar (18), the bottom of crossbeam (1) are equipped with the sliding rail (19) arranged along its length, pacify at the end positions of sliding rail (19)
It fills baffle (20), offers the first sliding groove (21) matched with sliding rail (19), the bottom of connecting plate (18) on connecting plate (18)
It is connected by shaft with cylindrical bar (14), hound (22) is additionally provided between the connecting plate (18) and cylindrical bar (14),
One end of hound (22) is fixed on cylindrical bar (14), horizontal on the other end of hound (22) to be equipped with positioning plate (23), fixed
Positioning and locking device is installed on position plate (23), hound (22) and connecting plate (18) can be fixed on sliding rail by positioning and locking device
(19) on, the through groove (24) matched with hound (22) is also provided on the lateral surface of the square column (15).
3. a kind of GIS metal can dismantling device according to claim 2, it is characterised in that: the positioning and locking device
Including installation set (25), installation set (25) is vertically arranged in the bottom of positioning plate (23), is fitted in installation set (25)
Inserted link (26), the bottom end of inserted link (26) are stretched out installation set (25) and are connected pull ring (27), the inserted link being located in installation set (25)
(26) positioning convex platform (28) are equipped with, the positioning convex platform (28) is located at the mounting groove (29) in installation set (25) Nei, is installing
It is also equipped with spring (30) in slot (29), the spring (30) is located at the periphery of boss (28) bottom, inserted link (26), and spring
(30) have the tendency that making the upper end of inserted link (26) to stretch out positioning plate (23) always, correspond to the upper end position of inserted link (26), even
The second through-hole (31) matched with inserted link (26) is offered on fishplate bar (18) and sliding rail (19), it is logical that inserted link (26) can protrude into second
Positioning plate (23) and connecting plate (18) are fixed on sliding rail (19) by hole (31).
4. a kind of GIS metal can dismantling device according to claim 1, it is characterised in that: each pedestal (3)
It is hinged with bearing base (32), is respectively provided with sliding sleeve (33) on each bearing base (32), bearing base (32) and pedestal at end positions
(3) it is offered on side second sliding slot (34), the sliding sleeve (33) matches with second sliding slot (34), and sliding sleeve (33) can edge
Second sliding slot (34) is slided on bearing base (32) and pedestal (3), on the two sides of bearing base (32) and pedestal (3) articulated position
It offers the first positioning screw hole (35), corresponding with two the first positioning screw hole (35) positions is equipped on sliding sleeve (33)
One positioning thread insert (36), each first positioning thread insert (36) is interior to be respectively mounted the first positioning bolt (37), the first positioning bolt (37)
It can protrude into the first positioning screw hole (35), to be connected as one bearing base (32) and pedestal (3) by sliding sleeve (33).
5. a kind of GIS metal can dismantling device according to claim 4, it is characterised in that: cut with scissors on the sliding sleeve (33)
It connects first connecting rod (38), hinged second connecting rod (39) on column (2), second connecting rod (39) is sleeved on the first connection
In bar (38), offered in the second connecting rod (39) the second positioning screw hole (40), first connecting rod is equipped with phase therewith on (38)
The second swivel nut (41) and the second positioning bolt (42) of cooperation, the second positioning bolt (42) can protrude into the second positioning screw hole (40)
It is interior, first connecting rod (38) and the second connecting rod (39) are connected as one.
6. a kind of GIS metal can dismantling device according to claim 1, it is characterised in that: described two hand-rail types thousand
Synchronous belt (43) are installed between the handle shaft on jin top (11).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910466609.0A CN110182700B (en) | 2019-05-31 | 2019-05-31 | GIS metal tank body disassembling tool |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910466609.0A CN110182700B (en) | 2019-05-31 | 2019-05-31 | GIS metal tank body disassembling tool |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110182700A true CN110182700A (en) | 2019-08-30 |
CN110182700B CN110182700B (en) | 2024-05-10 |
Family
ID=67719249
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910466609.0A Active CN110182700B (en) | 2019-05-31 | 2019-05-31 | GIS metal tank body disassembling tool |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110182700B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110355507A (en) * | 2019-09-02 | 2019-10-22 | 菏泽京九特种汽车有限公司 | Planer-type welding robot |
CN110844821A (en) * | 2019-11-23 | 2020-02-28 | 施伟 | Multifunctional construction operation platform for comprehensive pipe rack |
CN111346317A (en) * | 2020-03-31 | 2020-06-30 | 国网河南省电力公司南阳供电公司 | Safety belt hanging device for maintenance of isolating switch |
CN116040495A (en) * | 2023-02-01 | 2023-05-02 | 菲尔森智能装备(江苏)有限公司 | Crane portal frame |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20100183372A1 (en) * | 2009-01-08 | 2010-07-22 | Coleman Michael J | Pipe support system and method for use in underground pipe ramming |
CN203602256U (en) * | 2013-10-16 | 2014-05-21 | 国家电网公司 | Hoisting portal frame |
CN104405957A (en) * | 2014-11-20 | 2015-03-11 | 兖州煤业股份有限公司 | Mounting vehicle for mine overhead pipeline |
CN204211387U (en) * | 2014-06-29 | 2015-03-18 | 上海梅山钢铁股份有限公司 | A kind of hanger device |
CN206188296U (en) * | 2016-10-11 | 2017-05-24 | 杭州锦昌起重机械有限公司 | Longmen hand -drive block |
CN210419034U (en) * | 2019-05-31 | 2020-04-28 | 国家电网有限公司 | GIS metal can body assembly and disassembly tools |
-
2019
- 2019-05-31 CN CN201910466609.0A patent/CN110182700B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20100183372A1 (en) * | 2009-01-08 | 2010-07-22 | Coleman Michael J | Pipe support system and method for use in underground pipe ramming |
CN203602256U (en) * | 2013-10-16 | 2014-05-21 | 国家电网公司 | Hoisting portal frame |
CN204211387U (en) * | 2014-06-29 | 2015-03-18 | 上海梅山钢铁股份有限公司 | A kind of hanger device |
CN104405957A (en) * | 2014-11-20 | 2015-03-11 | 兖州煤业股份有限公司 | Mounting vehicle for mine overhead pipeline |
CN206188296U (en) * | 2016-10-11 | 2017-05-24 | 杭州锦昌起重机械有限公司 | Longmen hand -drive block |
CN210419034U (en) * | 2019-05-31 | 2020-04-28 | 国家电网有限公司 | GIS metal can body assembly and disassembly tools |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110355507A (en) * | 2019-09-02 | 2019-10-22 | 菏泽京九特种汽车有限公司 | Planer-type welding robot |
CN110844821A (en) * | 2019-11-23 | 2020-02-28 | 施伟 | Multifunctional construction operation platform for comprehensive pipe rack |
CN111346317A (en) * | 2020-03-31 | 2020-06-30 | 国网河南省电力公司南阳供电公司 | Safety belt hanging device for maintenance of isolating switch |
CN116040495A (en) * | 2023-02-01 | 2023-05-02 | 菲尔森智能装备(江苏)有限公司 | Crane portal frame |
Also Published As
Publication number | Publication date |
---|---|
CN110182700B (en) | 2024-05-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110182700A (en) | GIS metal can dismantling device | |
CN103777122B (en) | Withstand voltage testing system and assembly method thereof | |
CN105109530A (en) | Multifunctional trolley for electric power construction site operation | |
CN205855930U (en) | A kind of power supply station electric power overhaul platform | |
CN210419034U (en) | GIS metal can body assembly and disassembly tools | |
CN110905387A (en) | Portable operation of ascending a height maintenance ladder | |
CN209375075U (en) | A kind of electric power GIS equipment bus tube supporting device | |
CN207108176U (en) | Wind-driven generator and its instrument conveying device | |
CN207230092U (en) | Height-adjustable door frame and Coal Transport equipment | |
CN215516507U (en) | Splicing movable type transportation lifting platform | |
CN205724585U (en) | Multi-function overhaul platform | |
CN212426086U (en) | Quick mounting device for middle and small sleeves of blast furnace tuyere | |
CN204482046U (en) | A kind of box emergency base station | |
CN208762095U (en) | A kind of capacitor replacement platform | |
CN209213815U (en) | Steam generator vertical support anchoring rod assembles bracket | |
CN204675782U (en) | A kind of lifting work platform | |
CN203967573U (en) | A kind of replacing current transformer Portable handcart | |
CN104417499B (en) | For dismounting the supporting arrangement of non-penetrating broken bridge of car | |
CN202729628U (en) | Hoisting device | |
CN101615766A (en) | A kind of novel ladder that is used for the repairing high-voltage breaker operation | |
CN203705595U (en) | Voltage withstanding test system | |
CN207149989U (en) | Transformer changes auxiliary conditioning unit in high-tension switch cabinet | |
CN208413748U (en) | A kind of folding end carriage jacking apparatus | |
CN206734655U (en) | A kind of aircraft back antenna removable component | |
CN209261184U (en) | A kind of construction operation platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |