CN110172871A - Plateau Permafrost Regions High Speed Railway Subgrade and its construction method - Google Patents

Plateau Permafrost Regions High Speed Railway Subgrade and its construction method Download PDF

Info

Publication number
CN110172871A
CN110172871A CN201910502181.0A CN201910502181A CN110172871A CN 110172871 A CN110172871 A CN 110172871A CN 201910502181 A CN201910502181 A CN 201910502181A CN 110172871 A CN110172871 A CN 110172871A
Authority
CN
China
Prior art keywords
stake
groove
shaped supporting
high speed
supporting board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910502181.0A
Other languages
Chinese (zh)
Inventor
王多青
李成
张文忠
张然
王平
田龙飞
王飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Survey and Design Institute Group Ltd
Original Assignee
China Railway First Survey and Design Institute Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Survey and Design Institute Group Ltd filed Critical China Railway First Survey and Design Institute Group Ltd
Priority to CN201910502181.0A priority Critical patent/CN110172871A/en
Publication of CN110172871A publication Critical patent/CN110172871A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • E01B1/001Track with ballast
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2/00General structure of permanent way
    • E01B2/003Arrangement of tracks on bridges or in tunnels
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2/00General structure of permanent way
    • E01B2/006Deep foundation of tracks
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D1/00Bridges in general
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/06Arrangement, construction or bridging of expansion joints
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/08Damp-proof or other insulating layers; Drainage arrangements or devices ; Bridge deck surfacings
    • E01D19/086Drainage arrangements or devices
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • E01D19/103Parapets, railings ; Guard barriers or road-bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/35Foundations formed in frozen ground, e.g. in permafrost soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to Plateau Permafrost Regions High Speed Railway Subgrade and its construction methods, the road structure bottom is stake, and stake top is the groove-shaped supporting board of armored concrete, and groove-shaped supporting board includes the floor of bottom plate and two sides, it is equipped with graded broken stone on bottom plate, track structure is set on graded broken stone;Stake is mechanical hole perfusion post, and elongated arrangement of reinforcement, stake bottom gos deep into ever-frozen ground, bar dowel is added near frozen soil natural permafrost table.The present invention applies Permafrost Area pile foundation computational theory, it fully considers and freezes and melt two states, the pile foundation support board structure of design had both solved the technical problems such as Permafrost Area subgrade settlement, frost heave, cracking, inhomogeneous deformation, roadbed earthwork exploitation, railway land occupation can be reduced again, facilitate wild animal normal pass, provides technological approaches and method for Permafrost Area high speed railway construction.

Description

Plateau Permafrost Regions High Speed Railway Subgrade and its construction method
Technical field
The present invention relates to a kind of roadbeds, and in particular to a kind of Plateau Permafrost Regions High Speed Railway Subgrade and its construction Method.
Background technique
High-speed railway subgrade is subject to the basis of track structure and train load, is the important component of railway engineering, It is the key project for guaranteeing train high speed, safety, comfortable operating system.Subgrade engineering should also have in addition to should have basic function There are enough intensity, rigidity, stability and durability, guarantee that roadbed is smooth, guarantees railway basis safety steady in a long-term.High-speed iron Road post-construction settlement of subgrade control standard is shown in Table 1.
The soil body is to generate thaw collapse, frost heave and bad jelly containing the basic place that ice is that ever-frozen ground is different from other class ground The basic place of native phenomenon.Often there is Thick Underground Ice and hight-ice-content permafrost near ever-frozen ground natural permafrost table, due to It is buried shallowly, and the influence of the natural factors such as climate, ecology, microrelief, hydrologic condition and various human activities is easy to melt, The permafrost protections technologies such as existing slabstone air cooling, ventilation duct, heat pipe are difficult to ensure that thaw collapse, frost-heaving deformation do not occur for ever-frozen ground, It is unable to satisfy the requirement of high-speed railway sedimentation techniques standard.
Summary of the invention
The object of the present invention is to provide a kind of Plateau Permafrost Regions High Speed Railway Subgrade and its construction methods, meet Plateau Permafrost Regions use demand.
The technical scheme adopted by the invention is as follows:
Plateau Permafrost Regions High Speed Railway Subgrade, it is characterised in that:
The road structure bottom is stake, and stake top is the groove-shaped supporting board of armored concrete, and groove-shaped supporting board includes bottom plate and two sides Floor is equipped with graded broken stone on bottom plate, track structure is arranged on graded broken stone;
Stake is mechanical hole perfusion post, and elongated arrangement of reinforcement, stake bottom gos deep into ever-frozen ground, bar dowel is added near frozen soil natural permafrost table.
On the bottom plate of groove-shaped supporting board, graded broken stone two sides be arranged facilities network column.
On the bottom plate of groove-shaped supporting board, cable trough is set on the outside of facilities network column.
Upright railing is provided on the floor of groove-shaped supporting board two sides.
Outside drain hole is provided on the floor of groove-shaped supporting board.
Stake is directly rigidly connected with groove-shaped supporting board, stake top insert plate bottom.
Groove-shaped supporting board end is taken and is put on the bracket of abutment end face setting by the road structure and bridge joint.
The expansion joint of 3cm, filled and process rubber slab in expansion joint are reserved between groove-shaped supporting board end and abutment tail.
The construction method of Plateau Permafrost Regions High Speed Railway Subgrade, it is characterised in that:
The following steps are included:
Step 1: pile driving construction:
(1) drilling construction of every pile is carried out continuously, and promotes drill bit when shutting down for some reason, has the drilling machine of drilling rod, by drill bit lift-off hole Bottom 5m or more, other drilling machines propose drill bit outside hole;
(2) after pore-forming reaches design altitude, hole quality and the heavy quarrel situation of bottom hole are checked;It is timely entered after passed examination Next process;Stake bottom is reported when existing containing native ice sheet by construction program in time;
(3) it is carried out continuously when casting concrete;Safeguard measure is taken in aperture, prevents aperture loosened soil from falling into hole;
(4) molding temperature is not higher than 10 DEG C when concreting;
(5) after pile foundation construction, the processing of pile foundation anti-freeze expansion is carried out by design requirement, and be monitored to stake week ground temperature;
(6) after pile driving construction is completed 28 days, pile quality detection is carried out to whole foundation piles using low strain reflected wave method, and according to setting Meter requires to carry out foundation pile loading test, to examine its bearing capacity;
Step 2: groove-shaped supporting board construction:
(1) plate is poured using the lower concrete segmentation of the heat of hydration, and pre-buried railing bolt when pouring reserves drain hole;
(2) to reduce concrete shrinkage, the match ratio of concrete, early stage small using heat of hydration low-shrinkage as far as possible are reasonably adjusted High-strength cement reduces cement consumption, reduces the ratio of mud, and reinforces wet curing work;
(3) in concreting, chance rain and snow weather must not be soaked before masking measure, concrete should be taken to be not up to final set;
(4) longitudinally reinforced reinforcing bar is arranged in the construction joint position of continuous slab, and stiffener quantity is the 50% of longitudinal reinforcement, and reinforcing bar is straight The same longitudinal reinforcement of diameter, stiffener are inserted into two sides concrete depth and are not less than 1m;
(5) longitudinal reinforcement uses flash-butt welding in plate, and strength of welded joint is not less than the tensile strength of reinforcing bar itself;Welding connects Head is located to meet with stresses and smaller part and mutually stagger, and the welding point of longitudinal reinforcement is not more than the 50% of longitudinal reinforcement quantity;It is same Root reinforcing bar sets connector less;
(6) it after plate construction, is covered in time, moisturizing, insulated curing 1~2 month;When using covering and heat insulating, template is outer and coagulation The insulating layer of native surface covering, newly-laid concrete surface spreads layer of plastic film;
(7) it after curing period, to avoid the exposure of its long-time, is influenced by temperature change, plate face covering is not less than the wheat of 5cm thickness Grass is protected.
The invention has the following advantages that
1, pile foundation support board structure applies Permafrost Area pile foundation computational theory, fully considers and freezes and melt two states, solves The technical problems such as permafrost area embankment of having determined sedimentation, frost heave, cracking and inhomogeneous deformation, it is ensured that high-speed railway high speed, peace Entirely, it comfortably runs.
2, pile foundation construction uses churning driven dry method hole creating technology, and speed of fulfiling hole is fast, hole wall rule, the thermal agitation to frozen soil It is small, frozen soil environment is disturbed less, the construction quality of drilled pile bored concrete pile can be increased substantially;Due to there is no mud, also subtract significantly Few pollution to environment, favorable environment protection.
3, the conventional thought that roadbed is continuous band-shaped entity structure object is breached, roadbed earthwork exploitation is greatly lowered, subtracts Few railway land occupation takes soil site, is conducive to protection of permafrost area vegetation, environmental protection.
4, space is conducive to wild animal normal pass, migrates, multiplies and lives between stake, is conducive to ecological environmental protection.
Detailed description of the invention
Fig. 1 is cross-sectional view of the present invention;
Fig. 2 is front elevation of the present invention.
In figure, 1- facilities network column, 2- railing, 3- cable trough, 4- drain hole, 5- graded broken stone, 6- groove-shaped supporting board, 7- Stake, 8- bracket, 9- abutment.
Specific embodiment
The present invention will be described in detail With reference to embodiment.
The present invention relates to a kind of Plateau Permafrost Regions High Speed Railway Subgrade, the road structure bottom is stake 7, stake Top is the groove-shaped supporting board 6 of armored concrete, and groove-shaped supporting board 6 includes the floor of bottom plate and two sides, is equipped with graded broken stone 5 on bottom plate Track structure is arranged on graded broken stone 5 in (mixing 5% cement);Stake 7 is mechanical hole perfusion post, and elongated arrangement of reinforcement, the ratio of reinforcement is no less than 0.6%, stake diameter 1m, 4.6~5m of lateral stake spacing, 5~7m of longitudinal stake spacing, pore-forming use rotary drilling rig dry method pore-forming technique, stake Basis considers to freeze and melt two states, and there are certain degrees of safety.Foundation soil within the scope of 1.5 times of natural permafrost table depth Disregard freezing force or frictional force, disregards freezing force containing native ice sheet.Stake bottom must not be placed in containing on native ice sheet.Stake bottom is deeply frozen for many years Soil adds bar dowel, separately according to engineering geological condition when frozen soil natural permafrost table is nearby hight-ice-content permafrost to resist soil The lifting by frost power that frost heave generates.Stake 7 is directly rigidly connected with groove-shaped supporting board 6, stake top insert plate bottom 0.1m.
6 thickness 1.0m of groove-shaped supporting board, width is according to classification of track, main track number, line spacing, Widening on Curve, shoulder width, electricity The factors such as cable slot, contact net pillar types and type of foundation, which calculate, to be determined.
On the bottom plate of groove-shaped supporting board 6,5 two sides of graded broken stone be arranged facilities network column 1.On the bottom plate of groove-shaped supporting board 6, basis Cable trough 3 is set on the outside of net column 1.Upright railing 2 is provided on the floor of 6 two sides of groove-shaped supporting board.The floor of groove-shaped supporting board 6 On be provided with outside drain hole 4.
6 end of groove-shaped supporting board is taken and is put on the bracket 8 of 9 end face of abutment setting by the road structure and bridge joint.Slot The expansion joint of 3cm, filled and process rubber slab in expansion joint are reserved between 9 tail of 6 end of type supporting plate and abutment.
Work progress of the invention are as follows:
1, it rather fills out when arranging drilling construction place and does not dig as far as possible, reduce the thermal agitation to original place table foundation soil.
2, pore-forming uses " dry method " pore-forming technique, should not take band drilling mud practice.Steel pile casting it is embedding using pressurization, hammering or Vibratory drilling method, casing bottom should be placed in Upper Limit of Permafrost or less not less than 0.5 m.
3, drilled pile construction
(1) drilling construction of every pile should be carried out continuously, and drill bit should be promoted for some reason by shutting down, and had the drilling machine of drilling rod, should be mentioned drill bit From bottom hole 5m or more, other drilling machines should propose drill bit outside hole.
(2) after pore-forming reaches design altitude, situations such as being cut that should sink to hole quality and bottom hole is checked;After passed examination Next process should be timely entered, the intermittent time is unsuitable too long.Stake bottom should be reported in time when existing containing native ice sheet by construction program.
(3) it should be carried out continuously when casting concrete;Aperture should take safeguard measure, prevent aperture loosened soil from falling into hole.
(4) molding temperature should not be higher than 10 DEG C when concreting.
(5) after pile foundation construction, the processing of pile foundation anti-freeze expansion is carried out by design requirement, and should supervise to stake week ground temperature It surveys.
(6) after pile driving construction is completed 28 days, pile quality detection, and root are carried out to whole foundation piles using low strain reflected wave method Foundation pile loading test is carried out according to design requirement, to examine its bearing capacity.
4, groove-shaped supporting board is constructed
(1) plate is poured using the lower concrete segmentation of the heat of hydration.Pre-buried railing bolt when pouring reserves drain hole.
(2) to reduce concrete shrinkage, the match ratio of concrete should be reasonably adjusted, uses heat of hydration low-shrinkage small as far as possible Early stage high-strength cement, reduce cement consumption, reduce the ratio of mud, and reinforce wet curing work.
(3) in concreting, chance rain and snow weather must not be soaked before masking measure, concrete should be taken to be not up to final set.
(4) longitudinally reinforced reinforcing bar is arranged in the construction joint position of continuous slab, and stiffener quantity is the 50% of longitudinal reinforcement, steel The same longitudinal reinforcement of muscle diameter, stiffener are inserted into two sides concrete depth and are not less than 1m.
(5) longitudinal reinforcement uses flash-butt welding in plate, and strength of welded joint is not less than the tensile strength of reinforcing bar itself;Weldering Connector should be located to meet with stresses and smaller part and mutually stagger, and the welding point of longitudinal reinforcement should not exceed longitudinal reinforcement quantity 50%;Same root reinforcing bar Ying Shaoshe connector.
(6) it after plate construction, should be covered in time, moisturizing, insulated curing 1~2 month.When using covering and heat insulating, outside template With the insulating layer of concrete surface covering, the material of dampness should not be used, it also should not be by the direct bedding of thermal insulation material in tide Wet concrete surface, newly-laid concrete surface should spread layer of plastic film.
(7) it after curing period, to avoid the exposure of its long-time, is influenced by temperature change, plate face covering is thick not less than 5cm Wheat straw protected.
The contents of the present invention are not limited to cited by embodiment, and those of ordinary skill in the art are by reading description of the invention And to any equivalent transformation that technical solution of the present invention is taken, all are covered by the claims of the invention.

Claims (9)

1. Plateau Permafrost Regions High Speed Railway Subgrade, it is characterised in that:
The road structure bottom is stake (7), and stake top is the groove-shaped supporting board (6) of armored concrete, and groove-shaped supporting board (6) includes bottom plate With the floor of two sides, it is equipped with graded broken stone (5) on bottom plate, track structure is arranged on (5) in graded broken stone;
Stake (7) is mechanical hole perfusion post, and elongated arrangement of reinforcement, stake bottom gos deep into ever-frozen ground, short steel is added near frozen soil natural permafrost table Muscle.
2. Plateau Permafrost Regions High Speed Railway Subgrade according to claim 1, it is characterised in that:
On the bottom plate of groove-shaped supporting board (6), graded broken stone (5) two sides setting facilities network column (1).
3. Plateau Permafrost Regions High Speed Railway Subgrade according to claim 2, it is characterised in that:
Cable trough (3) are set on the bottom plate of groove-shaped supporting board (6), on the outside of facilities network column (1).
4. Plateau Permafrost Regions High Speed Railway Subgrade according to claim 3, it is characterised in that:
Upright railing (2) are provided on the floor of groove-shaped supporting board (6) two sides.
5. Plateau Permafrost Regions High Speed Railway Subgrade according to claim 4, it is characterised in that:
Outside drain hole (4) are provided on the floor of groove-shaped supporting board (6).
6. Plateau Permafrost Regions High Speed Railway Subgrade according to claim 5, it is characterised in that:
Stake (7) and groove-shaped supporting board (6) are directly rigidly connected, stake top insert plate bottom.
7. Plateau Permafrost Regions High Speed Railway Subgrade according to claim 6, it is characterised in that:
Groove-shaped supporting board (6) end is taken and is put on the bracket (8) of abutment (9) end face setting by the road structure and bridge joint.
8. Plateau Permafrost Regions High Speed Railway Subgrade according to claim 7, it is characterised in that:
The expansion joint of 3cm, filled and process rubber slab in expansion joint are reserved between groove-shaped supporting board (6) end and abutment (9) tail.
9. the construction method of Plateau Permafrost Regions High Speed Railway Subgrade, it is characterised in that:
The following steps are included:
Step 1: pile driving construction:
(1) drilling construction of every pile is carried out continuously, and promotes drill bit when shutting down for some reason, has the drilling machine of drilling rod, by drill bit lift-off hole Bottom 5m or more, other drilling machines propose drill bit outside hole;
(2) after pore-forming reaches design altitude, hole quality and the heavy quarrel situation of bottom hole are checked;It is timely entered after passed examination Next process;Stake bottom is reported when existing containing native ice sheet by construction program in time;
(3) it is carried out continuously when casting concrete;Safeguard measure is taken in aperture, prevents aperture loosened soil from falling into hole;
(4) molding temperature is not higher than 10 DEG C when concreting;
(5) after pile foundation construction, the processing of pile foundation anti-freeze expansion is carried out by design requirement, and be monitored to stake week ground temperature;
(6) after pile driving construction is completed 28 days, pile quality detection is carried out to whole foundation piles using low strain reflected wave method, and according to setting Meter requires to carry out foundation pile loading test, to examine its bearing capacity;
Step 2: groove-shaped supporting board construction:
(1) plate is poured using the lower concrete segmentation of the heat of hydration, and pre-buried railing bolt when pouring reserves drain hole;
(2) to reduce concrete shrinkage, the match ratio of concrete, early stage small using heat of hydration low-shrinkage as far as possible are reasonably adjusted High-strength cement reduces cement consumption, reduces the ratio of mud, and reinforces wet curing work;
(3) in concreting, chance rain and snow weather must not be soaked before masking measure, concrete should be taken to be not up to final set;
(4) longitudinally reinforced reinforcing bar is arranged in the construction joint position of continuous slab, and stiffener quantity is the 50% of longitudinal reinforcement, and reinforcing bar is straight The same longitudinal reinforcement of diameter, stiffener are inserted into two sides concrete depth and are not less than 1m;
(5) longitudinal reinforcement uses flash-butt welding in plate, and strength of welded joint is not less than the tensile strength of reinforcing bar itself;Welding connects Head is located to meet with stresses and smaller part and mutually stagger, and the welding point of longitudinal reinforcement is not more than the 50% of longitudinal reinforcement quantity;It is same Root reinforcing bar sets connector less;
(6) it after plate construction, is covered in time, moisturizing, insulated curing 1~2 month;When using covering and heat insulating, template is outer and coagulation The insulating layer of native surface covering, newly-laid concrete surface spreads layer of plastic film;
(7) it after curing period, to avoid the exposure of its long-time, is influenced by temperature change, plate face covering is not less than the wheat of 5cm thickness Grass is protected.
CN201910502181.0A 2019-06-11 2019-06-11 Plateau Permafrost Regions High Speed Railway Subgrade and its construction method Pending CN110172871A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910502181.0A CN110172871A (en) 2019-06-11 2019-06-11 Plateau Permafrost Regions High Speed Railway Subgrade and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910502181.0A CN110172871A (en) 2019-06-11 2019-06-11 Plateau Permafrost Regions High Speed Railway Subgrade and its construction method

Publications (1)

Publication Number Publication Date
CN110172871A true CN110172871A (en) 2019-08-27

Family

ID=67698104

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910502181.0A Pending CN110172871A (en) 2019-06-11 2019-06-11 Plateau Permafrost Regions High Speed Railway Subgrade and its construction method

Country Status (1)

Country Link
CN (1) CN110172871A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110820731A (en) * 2019-12-05 2020-02-21 东莞嘉誉诚建设基础工程有限公司 Construction process of cast-in-situ bored pile

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4407747A1 (en) * 1994-03-08 1995-11-09 Porr Technobau Ag Train rail track securing system
RU2052007C1 (en) * 1988-02-29 1996-01-10 Петр Степанович Лобов Railway track and method for its construction
KR20060073731A (en) * 2004-12-24 2006-06-29 한국철도기술연구원 Amethod for solidification of railroad bridge and public works-connection part
KR101062732B1 (en) * 2011-01-21 2011-09-06 주식회사 서현기술단 Freeze prevention structure for rail roadbed and this construction technique
CN105544311A (en) * 2016-01-17 2016-05-04 中铁二院工程集团有限责任公司 Water-rich foundation frost-heaving-resistant ballastless track embankment structure
CN106283956A (en) * 2016-09-15 2017-01-04 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev two-wire excavation location pile foundation combined type support rail beam transition section structure
CN210238157U (en) * 2019-06-11 2020-04-03 中铁第一勘察设计院集团有限公司 Plateau permafrost region high-speed railway roadbed structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2052007C1 (en) * 1988-02-29 1996-01-10 Петр Степанович Лобов Railway track and method for its construction
DE4407747A1 (en) * 1994-03-08 1995-11-09 Porr Technobau Ag Train rail track securing system
KR20060073731A (en) * 2004-12-24 2006-06-29 한국철도기술연구원 Amethod for solidification of railroad bridge and public works-connection part
KR101062732B1 (en) * 2011-01-21 2011-09-06 주식회사 서현기술단 Freeze prevention structure for rail roadbed and this construction technique
CN105544311A (en) * 2016-01-17 2016-05-04 中铁二院工程集团有限责任公司 Water-rich foundation frost-heaving-resistant ballastless track embankment structure
CN106283956A (en) * 2016-09-15 2017-01-04 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev two-wire excavation location pile foundation combined type support rail beam transition section structure
CN210238157U (en) * 2019-06-11 2020-04-03 中铁第一勘察设计院集团有限公司 Plateau permafrost region high-speed railway roadbed structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郑翔: "多年冻土地区桥梁桩基础施工技术", 《西部探矿工程》, no. 09, pages 167 - 169 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110820731A (en) * 2019-12-05 2020-02-21 东莞嘉誉诚建设基础工程有限公司 Construction process of cast-in-situ bored pile

Similar Documents

Publication Publication Date Title
CN107503257B (en) One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
CN206902479U (en) Ballastless track roadbed Deformation control is worn under a kind of aqueduct with repairing structure
CN102071607A (en) Railroad bed repair method without affecting existing running conditions
CN207109475U (en) It is close to mountain high-filled subgrade stabilization and Deformation control structure
CN109736141A (en) The anti-freeze expansion structural body and paving method of Railway Roadbed in Permafrost Regions
CN109236367A (en) A kind of tunnel structure and its frozen construction method with antiseepage drain function
CN101768960B (en) Bored concrete pile construction method of permafrost layer
CN210238157U (en) Plateau permafrost region high-speed railway roadbed structure
CN208982109U (en) A kind of tunnel structure with antiseepage drain function
CN110172871A (en) Plateau Permafrost Regions High Speed Railway Subgrade and its construction method
CN208293317U (en) A kind of Plateau Permafrost Areas high-speed railway cutting water blocking discharge structure
CN110454189A (en) A kind of river tunnel Xia Chuan construction technology
CN103866788B (en) A kind of method of pillar abutment scarp slope barricadeization transformation
Zheng et al. Study on cause analysis and treatment measures of lining cracking and ballast bed freezing at tunnel portal in seasonally-frozen regions
CN110273435A (en) A kind of construction of city open trench tunnel
CN109750568A (en) A kind of road structure and its construction method with pile foundation bent cap
CN102587399B (en) Salivary flow ice prevention and management structure in cold zone
CN205576638U (en) Consolidate roadbed structure who handles newly -built railway karst foundation
CN209324377U (en) Ledge method tunneling subway station arch springing ruggedized construction
CN207295348U (en) Railway karst ground treatment anti-pollution structure near a kind of I grade of potable water source district
CN110857543B (en) Replacement method for railway roadbed filling
Allenby et al. The use of jacked-box tunnelling under a live motorway
Lunardi et al. Brenner base tunnel & Isarco River underpass section: Several technical and operational solutions
Zhang et al. Construction technology of the freezing method for the connecting-passage in the subway
Zhu et al. Treatment of collapsible loess foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination